TDOT contract CN261051 bid tabulation
The slope stabilization on s.r. 116 near l.m. 0.9. Let by Tennessee DOT on May 8, 2026, Anderson County. 4 bids received; low bid $998,692 by J. Hill Excavating, LLC.
- Owner
- Tennessee DOT
- Letting
- 08 MAY 2026
- Pay items
- 47
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | J. Hill Excavating, LLC | $998,692 | Low |
| 2 | Advanced Grading Worx LLC | $1,014,880 | +2.0% |
| 3 | Rogers Group, Inc. | $1,097,000 | +10% |
| 4 | Adams Contracting, LLC | $1,279,514 | +28% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. J. Hill Excavating, LLC | 2. Advanced Grading Worx LLC | 3. Rogers Group, Inc. | 4. Adams Contracting, LLC |
|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $40,600 | $20,000 | $25,000 | $15,000 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $54,750 | $124,000 | $65,000 | $75,000 |
| 3 | Road & drainage excavation (unclassified) (203-01) | CY | 694 | $60.00 | $50.00 | $80.00 | $75.00 |
| 4 | Borrow excavation (graded solid rock) (203-02.01) | TON | 1,665 | $65.75 | $62.25 | $60.00 | $70.00 |
| 5 | Construction of haul road (203-50) | LS | 1 | $225,500 | $214,200 | $290,416 | $350,000 |
| 6 | Brooming & degrassing shoulders (208-01.05) | LM | 0.20 | $3,500.00 | $10,000 | $1,200.00 | $5,000.00 |
| 7 | Temporary silt fence (with backing) (209-08.02) | LF | 750 | $8.00 | $7.50 | $7.00 | $5.00 |
| 8 | Enhanced rock check dam (209-08.08) | EACH | 2 | $1,250.00 | $1,000.00 | $650.00 | $825.00 |
| 9 | Mineral aggregate, type A base, grading D (303-01) | TON | 64 | $95.00 | $100.00 | $100.00 | $100.00 |
| 10 | Mineral aggregate (size 57) (303-10.01) | TON | 9 | $94.55 | $100.00 | $70.00 | $100.00 |
| 11 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01) | TON | 4 | $965.00 | $845.00 | $845.00 | $848.00 |
| 12 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 3 | $1,256.00 | $1,081.00 | $1,081.00 | $848.00 |
| 13 | Bituminous material for prime coat (PC) (402-01) | TON | 1 | $1,655.00 | $1,360.00 | $1,360.00 | $2,720.00 |
| 14 | Bituminous material for tack coat (TC) (403-01) | TON | 1 | $1,250.00 | $980.00 | $980.00 | $109.00 |
| 15 | Acs mix(PG64-22) grading D (411-01.10) | TON | 40 | $645.00 | $480.00 | $480.00 | $517.00 |
| 16 | Scoring for rumble stripe (non-continuous) (4IN width) (411-12.04) | LM | 0.20 | $5,500.00 | $20,000 | $5,400.00 | $48,200 |
| 17 | Cold planing bituminous pavement (415-01.02) | SY | 1,045 | $18.65 | $12.00 | $12.00 | $24.00 |
| 18 | Retaining wall (wall 1) (604-07.01) | SF | 585 | $190.00 | $190.00 | $200.00 | $225.00 |
| 19 | 30" concrete pipe culvert (class IV) (607-06.03) | LF | 48 | $248.00 | $250.00 | $500.00 | $325.00 |
| 20 | 30" concrete pipe culvert (class IV) trenchless (607-06.10) | LF | 25 | $1,655.00 | $2,000.00 | $3,100.00 | $2,400.00 |
| 21 | Manholes, > 8' - 12' depth (611-01.03) | EACH | 1 | $16,750 | $15,000 | $35,000 | $20,000 |
| 22 | Class A concrete (pipe endwalls) (611-07.01) | CY | 4.10 | $3,200.00 | $2,000.00 | $3,250.00 | $1,500.00 |
| 23 | Steel bar reinforcement (pipe endwalls) (611-07.02) | LB | 136 | $13.65 | $5.00 | $2.50 | $5.00 |
| 24 | W beam GR (type 2) MASH TL-3 (long post) (705-06.02) | LF | 242 | $39.45 | $29.00 | $31.00 | $32.00 |
| 25 | Tangent energy absorbing term MASH TL-3 (705-06.20) | EACH | 2 | $5,355.00 | $3,200.00 | $3,400.00 | $3,480.00 |
| 26 | Thrie beam bridge transition MASH TL-3 (705-06.25) | EACH | 2 | $3,850.00 | $2,500.00 | $2,700.00 | $2,720.00 |
| 27 | High-visibility construction fence (707-08.11) | LF | 390 | $6.90 | $6.00 | $5.00 | $2.00 |
| 28 | Machined rip-rap (class A-3) (709-05.05) | TON | 50 | $98.50 | $100.00 | $85.00 | $100.00 |
| 29 | Machined rip-rap (class A-1) (709-05.06) | TON | 45 | $97.85 | $100.00 | $90.00 | $100.00 |
| 30 | 36IN single slope concrete barrier wall (711-05.69) | LF | 90 | $160.85 | $300.00 | $155.00 | $165.00 |
| 31 | Traffic control (712-01) | LS | 1 | $38,750 | $21,000 | $25,000 | $135,000 |
| 32 | Portable barrier rail (MASH TL-3) (712-02.10) | LF | 450 | $60.00 | $100.00 | $64.00 | $39.00 |
| 33 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 1 | $8,300.00 | $6,000.00 | $10,000 | $12,600 |
| 34 | Flexible drums (channelizing) (712-04.01) | EACH | 13 | $45.00 | $40.00 | $15.00 | $43.50 |
| 35 | Barrier rail delineator (712-04.50) | EACH | 18 | $17.45 | $13.00 | $16.00 | $14.50 |
| 36 | Signs (construction) (712-06) | SF | 250 | $12.00 | $7.85 | $6.00 | $8.75 |
| 37 | Removable pavement marking line (712-09.01) | LF | 2,000 | $7.00 | $2.75 | $4.50 | $3.00 |
| 38 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 785 | $10.55 | $3.65 | $9.00 | $4.00 |
| 39 | Removable pavement marking (stop line) (712-09.04) | LF | 22 | $33.55 | $22.00 | $34.00 | $22.00 |
| 40 | Removable black-out tape (6") (712-09.30) | LF | 800 | $10.45 | $4.00 | $9.00 | $4.50 |
| 41 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 6 | $175.35 | $100.00 | $160.00 | $109.00 |
| 42 | Removal of snowplowable reflective marker (716-01.30) | EACH | 6 | $70.00 | $25.00 | $56.50 | $27.50 |
| 43 | Painted pavement marking (6" line) (716-05.20) | LM | 0.30 | $4,900.00 | $4,500.00 | $3,950.00 | $4,890.00 |
| 44 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 0.30 | $16,056 | $10,000 | $13,500 | $10,900 |
| 45 | Mobilization (717-01) | LS | 1 | $60,000 | $85,000 | $85,000 | $100,000 |
| 46 | Temporary traffic signal system (730-40) | EACH | 1 | $25,000 | $24,000 | $12,000 | $26,000 |
| 47 | Geotextile (type III)(erosion control) (740-10.03) | SY | 194 | $5.05 | $8.00 | $6.00 | $4.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of May 8, 2026. Compiled by Mirage Metrics.