TDOT contract CN264903 bid tabulation
The construction of a multimodal path along s.r. 211 from samaria bend road (l.m. 0.47) to horner road (l.m. 1.09) in dyersburg. Let by Tennessee DOT on June 26, 2026, Dyer County. 2 bids received; low bid $2,063,677 by Ford Construction Company.
- Owner
- Tennessee DOT
- Letting
- 26 JUN 2026
- Pay items
- 70
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ford Construction Company | $2,063,677 | Low |
| 2 | Adams Contracting, LLC | $2,449,957 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ford Construction Company | 2. Adams Contracting, LLC |
|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $46,000 | $50,000 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $9,000.00 | $15,000 |
| 3 | Removal of pipe (24" CMP ,sta. 15+00.00) (202-02.01) | LF | 196 | $45.00 | $50.00 |
| 4 | Removal of pipe (size 24" CMP,sta. 17+00.00) (202-02.02) | LF | 163 | $45.00 | $50.00 |
| 5 | Removal of pipe (size 24" CMP,sta. 19+22.00) (202-02.03) | LF | 45 | $45.00 | $50.00 |
| 6 | Removal of pipe (size 24" CMP,sta. 19+22.00) (202-02.04) | LF | 49 | $45.00 | $50.00 |
| 7 | Removal of rigid pavement, sidewalk, etc. (202-03) | SY | 6,114 | $32.50 | $35.00 |
| 8 | Removal of structures (sign and post at tract 6) (202-04.01) | LS | 1 | $1,560.00 | $3,500.00 |
| 9 | Road & drainage excavation (unclassified) (203-01) | CY | 899 | $28.00 | $55.00 |
| 10 | Borrow excavation (unclassified) (203-03) | CY | 1,540 | $31.00 | $90.00 |
| 11 | Placing and spreading topsoil (203-04) | CY | 200 | $21.00 | $37.00 |
| 12 | Water (203-06) | MG | 50 | $34.00 | $73.00 |
| 13 | Furnishing & spreading topsoil (203-07) | CY | 200 | $39.00 | $100.00 |
| 14 | Flowable fill (general) (204-06.01) | CY | 7 | $650.00 | $585.00 |
| 15 | Brooming & degrassing shoulders (208-01.05) | LM | 1.30 | $5,500.00 | $2,000.00 |
| 16 | Filter sock (12 inch) (209-03.21) | LF | 2,190 | $5.50 | $6.25 |
| 17 | Sediment removal (209-05) | CY | 24 | $60.00 | $10.00 |
| 18 | Enhanced rock check dam (209-08.08) | EACH | 3 | $1,100.00 | $850.00 |
| 19 | Sandbags (209-09.01) | BAG | 860 | $6.00 | $5.00 |
| 20 | Curb inlet protection (type 4) (209-09.43) | EACH | 7 | $425.00 | $525.00 |
| 21 | Catch basin protection (type A) (209-40.30) | EACH | 4 | $575.00 | $625.00 |
| 22 | Catch basin filter assembly(type 1) (209-40.41) | EACH | 4 | $800.00 | $875.00 |
| 23 | Mineral aggregate, type A base, grading D (303-01) | TON | 2,780 | $55.00 | $58.00 |
| 24 | Mineral aggregate (size 57) (303-10.01) | TON | 40 | $60.00 | $75.00 |
| 25 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01) | TON | 56 | $304.43 | $370.00 |
| 26 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 625 | $267.00 | $155.00 |
| 27 | Bituminous material for tack coat (TC) (403-01) | TON | 5 | $1,200.00 | $1,250.00 |
| 28 | Saw cutting asphalt pavement (407-20.05) | LF | 3,277 | $8.00 | $4.00 |
| 29 | Acs mix(PG64-22) grading D (411-01.10) | TON | 1,200 | $232.00 | $175.00 |
| 30 | Cold planing bituminous pavement (415-01.01) | TON | 1,345 | $25.00 | $55.00 |
| 31 | 18" concrete pipe culvert (class III) (607-03.02) | LF | 875 | $180.00 | $150.00 |
| 32 | 24" concrete pipe culvert (class III) (607-05.02) | LF | 534 | $190.00 | $160.00 |
| 33 | 36" concrete pipe culvert (class III) (607-07.02) | LF | 20 | $360.00 | $400.00 |
| 34 | Junction box, type 1 (611-02.10) | EACH | 3 | $7,000.00 | $8,000.00 |
| 35 | 18IN endwall (side drain) (611-07.31) | EACH | 3 | $4,300.00 | $3,900.00 |
| 36 | 24IN endwall (side drain) (611-07.32) | EACH | 1 | $6,000.00 | $5,400.00 |
| 37 | 18IN endwall (cross drain) 3:1 (611-07.54) | EACH | 1 | $1,800.00 | $3,000.00 |
| 38 | Catch basins, type 12, > 4' - 8' depth (611-12.02) | EACH | 7 | $8,700.00 | $12,000 |
| 39 | Catch basins, type 42, 0' - 4' depth (611-42.01) | EACH | 1 | $8,400.00 | $6,200.00 |
| 40 | Catch basins, type 42, > 4' - 8' depth (611-42.02) | EACH | 1 | $12,900 | $13,000 |
| 41 | Concrete curb (702-01) | CY | 60 | $1,170.00 | $925.00 |
| 42 | Concrete combined curb & gutter (702-03) | CY | 51 | $1,400.00 | $765.00 |
| 43 | Portable barrier rail delineator (705-04.50) | EACH | 90 | $10.00 | $11.00 |
| 44 | High-visibility construction fence (707-08.11) | LF | 875 | $2.50 | $2.75 |
| 45 | Markers (concrete R.O.W. posts) (708-02.01) | EACH | 5 | $400.00 | $500.00 |
| 46 | Machined rip-rap (class A-3) (709-05.05) | TON | 375 | $61.00 | $70.00 |
| 47 | Machined rip-rap (class A-1) (709-05.06) | TON | 197 | $61.00 | $70.00 |
| 48 | Traffic control (712-01) | LS | 1 | $37,000 | $250,000 |
| 49 | Portable barrier rail (MASH TL-3) (712-02.10) | LF | 1,800 | $25.00 | $18.25 |
| 50 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 12 | $4,000.00 | $4,700.00 |
| 51 | Flexible drums (channelizing) (712-04.01) | EACH | 125 | $35.00 | $36.00 |
| 52 | Signs (construction) (712-06) | SF | 788 | $6.00 | $7.00 |
| 53 | Temporary barricades (type III) (712-07.03) | LF | 500 | $15.00 | $16.00 |
| 54 | Arrow board (type C) (712-08.03) | EACH | 2 | $1,785.00 | $1,800.00 |
| 55 | "U" section steel posts (713-11.01) | LB | 198 | $5.00 | $6.00 |
| 56 | Flat sheet aluminum signs (0.080" thick) (713-13.02) | SF | 31 | $18.00 | $19.00 |
| 57 | Removal of signs, posts and footings (713-15) | LS | 1 | $100.00 | $550.00 |
| 58 | Plastic pavement marking (stop line) (716-02.05) | LF | 76 | $30.00 | $32.00 |
| 59 | Plastic pavement marking (longitudinal cross-walk) (716-02.09) | LF | 338 | $52.00 | $55.00 |
| 60 | Painted pavement marking (6" line) (716-05.20) | LM | 2 | $3,000.00 | $3,200.00 |
| 61 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 2.70 | $11,500 | $12,000 |
| 62 | Mobilization (717-01) | LS | 1 | $80,000 | $240,000 |
| 63 | Temporary traffic signal system (730-40.02) | LS | 1 | $79,500 | $100,000 |
| 64 | Geotextile (type III)(erosion control) (740-10.03) | SY | 1,580 | $6.00 | $3.50 |
| 65 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 3,064 | $6.00 | $3.75 |
| 66 | Temporary sediment tube check dam (740-11.06) | EACH | 10 | $300.00 | $330.00 |
| 67 | Temporary seeding (with mulch) (801-01.07) | UNIT | 30 | $33.00 | $40.00 |
| 68 | Seeding (without mulch) (801-02) | UNIT | 18 | $45.00 | $75.00 |
| 69 | Water (seeding & sodding) (801-03) | MG | 8 | $100.00 | $135.00 |
| 70 | Erosion control blanket (type III) (805-12.03) | SY | 1,000 | $2.50 | $4.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of June 26, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.