TDOT contract CNZ018 bid tabulation
The miscellaneous safety improvements including signals on hamilton church road from east of u.s. 41 (u.s. 70s, s.r. 1) to west of calumet drive in nashville. Let by Tennessee DOT on February 7, 2025, Davidson County. 3 bids received; low bid $895,817 by Capital City Construction Services, LLC.
- Owner
- Tennessee DOT
- Letting
- 07 FEB 2025
- Pay items
- 74
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Capital City Construction Services, LLC | $895,817 | Low |
| 2 | Taggart Constructors, LLC | $929,000 | +4.0% |
| 3 | Civil Constructors, LLC | $934,441 | +4.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Capital City Construction Services, LLC | 2. Taggart Constructors, LLC | 3. Civil Constructors, LLC |
|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $10,714 | $45,000 | $12,970 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $10,024 | $18,247 | $16,500 |
| 3 | Removal of pipe (18" CMP, sta. 61+45) (202-02.01) | LF | 17 | $147.42 | $82.00 | $37.00 |
| 4 | Removal of asphalt pavement (202-03.01) | SY | 200 | $50.12 | $69.00 | $22.20 |
| 5 | Removal of structures (endwalls, sta. 61+51 & 62+79) (202-04.01) | LS | 1 | $5,012.14 | $10,010 | $1,960.00 |
| 6 | Removal of structures (partial, wingwalls, sta. 52+56.50) (202-04.02) | LS | 1 | $20,049 | $20,000 | $943.00 |
| 7 | Road & drainage excavation (unclassified) (203-01) | CY | 425 | $55.58 | $110.00 | $69.50 |
| 8 | Borrow excavation (unclassified) (203-03) | CY | 795 | $73.98 | $56.00 | $25.00 |
| 9 | Placing and spreading topsoil (203-04) | CY | 190 | $52.76 | $87.00 | $53.00 |
| 10 | Water (203-06) | MG | 2 | $714.29 | $390.00 | $15.00 |
| 11 | Flowable fill (general) (204-06.01) | CY | 40 | $786.00 | $320.00 | $439.00 |
| 12 | Sediment removal (209-05) | CY | 7 | $198.42 | $33.50 | $102.00 |
| 13 | Temporary silt fence (with backing) (209-08.02) | LF | 200 | $6.47 | $7.00 | $4.70 |
| 14 | Rock check dam (209-08.07) | EACH | 12 | $926.32 | $990.00 | $817.00 |
| 15 | Enhanced rock check dam (209-08.08) | EACH | 5 | $926.32 | $990.00 | $1,080.00 |
| 16 | Curb inlet protection (type 2) (209-09.41) | EACH | 4 | $205.26 | $220.00 | $119.00 |
| 17 | Catch basin filter assembly(type 6) (209-40.46) | EACH | 1 | $789.47 | $830.00 | $685.00 |
| 18 | Catch basin filter assembly(type 7) (209-40.47) | EACH | 1 | $789.47 | $830.00 | $685.00 |
| 19 | Mineral aggregate, type A base, grading D (303-01) | TON | 400 | $71.98 | $75.00 | $94.50 |
| 20 | Granular backfill (roadway) (303-01.01) | TON | 400 | $56.39 | $47.50 | $50.50 |
| 21 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 3 | $384.95 | $730.00 | $1,880.00 |
| 22 | Saw cutting asphalt pavement (407-20.05) | LF | 905 | $7.27 | $6.00 | $3.75 |
| 23 | Acs mix(PG64-22) grading D (411-01.10) | TON | 14 | $835.10 | $730.00 | $669.00 |
| 24 | Class A concrete (roadway) (604-01.01) | CY | 23 | $3,007.00 | $1,770.00 | $2,450.00 |
| 25 | Steel bar reinforcement (roadway) (604-01.02) | LB | 4,212 | $5.52 | $1.70 | $2.50 |
| 26 | Box tube safety rail (604-01.20) | LF | 75 | $306.74 | $340.00 | $308.00 |
| 27 | 18" concrete pipe culvert (class III) (607-03.02) | LF | 178 | $144.58 | $150.00 | $315.00 |
| 28 | 18" corrugated metal pipe culvert (607-37.02) | LF | 26 | $157.84 | $150.00 | $202.00 |
| 29 | 24" corrugated metal pipe culvert (607-37.03) | LF | 24 | $170.57 | $170.00 | $237.00 |
| 30 | 24" pipe culvert (side drain) (607-39.03) | LF | 24 | $170.57 | $170.00 | $205.00 |
| 31 | Corrugated metal pipe arch (size equiv. 24" round) (607-40.04) | LF | 54 | $178.80 | $170.00 | $160.00 |
| 32 | Junction box, type 2 (611-02.11) | EACH | 1 | $10,012 | $5,910.00 | $7,300.00 |
| 33 | Class A concrete (pipe endwalls) (611-07.01) | CY | 3 | $3,613.57 | $3,420.00 | $2,950.00 |
| 34 | Steel bar reinforcement (pipe endwalls) (611-07.02) | LB | 86 | $3.14 | $3.00 | $8.30 |
| 35 | Catch basins, type 12, > 4' - 8' depth (611-12.02) | EACH | 1 | $23,263 | $6,730.00 | $9,500.00 |
| 36 | Catch basins, type 14, > 4' - 8' depth (611-14.02) | EACH | 1 | $27,191 | $13,100 | $15,170 |
| 37 | Concrete sidewalk (4 ") (701-01.01) | SF | 4,146 | $6.84 | $9.75 | $13.60 |
| 38 | Concrete driveway (701-02) | SF | 405 | $10.53 | $13.00 | $22.30 |
| 39 | Concrete curb ramp (701-02.03) | SF | 264 | $10.53 | $35.50 | $44.00 |
| 40 | Concrete combined curb & gutter (702-03) | CY | 58 | $578.95 | $680.00 | $1,010.00 |
| 41 | High-visibility construction fence (707-08.11) | LF | 100 | $2.84 | $3.00 | $2.20 |
| 42 | Machined rip-rap (class B) (709-05.08) | TON | 59 | $98.41 | $73.00 | $102.00 |
| 43 | Machined rip-rap (class C) (709-05.09) | TON | 34 | $98.41 | $73.00 | $118.00 |
| 44 | Traffic control (712-01) | LS | 1 | $67,632 | $80,000 | $71,820 |
| 45 | Temporary flexible tubular delineator (712-04.10) | EACH | 30 | $70.53 | $56.00 | $50.50 |
| 46 | Signs (construction) (712-06) | SF | 320 | $8.58 | $15.50 | $8.80 |
| 47 | Arrow board (type C) (712-08.03) | EACH | 2 | $1,263.16 | $2,810.00 | $2,510.00 |
| 48 | Street name sign (rigid 0.100IN thick (713-14.21) | SF | 18 | $47.37 | $88.00 | $98.00 |
| 49 | Changeable message sign unit (713-16.01) | EACH | 2 | $6,315.79 | $9,880.00 | $8,230.00 |
| 50 | Plastic pavement marking (stop line) (716-02.05) | LF | 44 | $26.32 | $30.00 | $31.50 |
| 51 | Plastic pavement marking (longitudinal cross-walk) (716-02.09) | LF | 65 | $42.11 | $60.00 | $56.50 |
| 52 | Removal of pavement marking (cross-walk) (716-08.03) | LF | 18 | $31.58 | $30.00 | $31.50 |
| 53 | Removal of pavement marking (stop line) (716-08.05) | LF | 48 | $10.53 | $15.00 | $15.10 |
| 54 | Mobilization (717-01) | LS | 1 | $44,500 | $46,000 | $66,450 |
| 55 | Removal of signal equipment (730-01.02) | EACH | 1 | $3,157.89 | $12,000 | $6,180.00 |
| 56 | Signal head assembly (130 with backplate) (730-02.09) | EACH | 5 | $1,326.32 | $1,460.00 | $1,640.00 |
| 57 | Signal head assembly (150 A2H with backplate) (730-02.17) | EACH | 1 | $2,273.68 | $1,410.00 | $2,840.00 |
| 58 | Install pull box (type B) (730-03.21) | EACH | 2 | $1,052.63 | $2,010.00 | $2,250.00 |
| 59 | Signal cable - 5 conductor (730-08.02) | LF | 224 | $2.11 | $2.00 | $2.25 |
| 60 | Signal cable - 7 conductor (730-08.03) | LF | 132 | $2.63 | $2.40 | $2.65 |
| 61 | Signal cable - 12 conductor (730-08.05) | LF | 310 | $2.89 | $2.70 | $3.00 |
| 62 | Signal cable - 2 conductor shielded (730-08.08) | LF | 489 | $2.37 | $1.60 | $1.75 |
| 63 | Conduit 2" diameter (PVC schedule 40) (730-12.02) | LF | 109 | $23.16 | $62.00 | $69.00 |
| 64 | Conduit 2" diameter (directional bore) (730-12.23) | LF | 250 | $84.21 | $39.50 | $44.00 |
| 65 | Vehicle detector (radar - stop line) (730-13.12) | EACH | 3 | $11,011 | $9,830.00 | $11,010 |
| 66 | Vehicle detector (radar - advance) (730-13.13) | EACH | 2 | $11,011 | $13,920 | $15,590 |
| 67 | Modify cabinet (install new equipment and timings) (730-15.11) | EACH | 1 | $1,263.16 | $2,130.00 | $2,390.00 |
| 68 | Pedestal pole (type A) (730-23.28) | EACH | 2 | $3,684.21 | $3,120.00 | $3,490.00 |
| 69 | Cantilever signal support (2 @ 30' & 40') (730-23.70) | EACH | 1 | $44,926 | $48,160 | $53,940 |
| 70 | Countdown ped SGNL head W/audible pushbutton & 15IN sign (730-26.11) | EACH | 3 | $1,957.89 | $1,990.00 | $2,230.00 |
| 71 | Temporary sediment tube 12IN (740-11.02) | LF | 1,375 | $3.89 | $4.20 | $3.15 |
| 72 | Water (seeding & sodding) (801-03) | MG | 1 | $168.42 | $180.00 | $314.00 |
| 73 | Sodding (new sod) (803-01) | SY | 1,225 | $6.42 | $8.00 | $6.60 |
| 74 | (18" RCP 22.5 degree elbow) (920-10.05) | LS | 1 | $1,002.43 | $6,750.00 | $4,860.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of February 7, 2025. Compiled by Mirage Metrics.