TDOT contract CNZ019 bid tabulation
The construction of a concrete box beam bridge on lawrenceburg highway over tennessee southern railroad (l.m. 3.18), including grading, drainage, and paving. Let by Tennessee DOT on March 21, 2025, Maury County. 4 bids received; low bid $2,550,110 by Dement Construction Group, LLC.
- Owner
- Tennessee DOT
- Letting
- 21 MAR 2025
- Pay items
- 71
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Dement Construction Group, LLC | $2,550,110 | Low |
| 2 | Jones Bros. Contractors, LLC | $2,916,404 | +14% |
| 3 | Bell & Associates Construction, LLC | $3,142,827 | +23% |
| 4 | Capital City Construction Services, LLC | $3,745,728 | +47% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Dement Construction Group, LLC | 2. Jones Bros. Contractors, LLC | 3. Bell & Associates Construction, LLC | 4. Capital City Construction Services, LLC |
|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $25,000 | $25,000 | $30,000 | $29,135 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $223,000 | $75,000 | $206,000 | $125,718 |
| 3 | Removal of structures and obstructions (202-01) | LS | 1 | $5,000.00 | $5,000.00 | $20,000 | $28,257 |
| 4 | Road & drainage excavation (unclassified) (203-01) | CY | 856 | $30.00 | $45.00 | $35.00 | $27.72 |
| 5 | Borrow excavation (unclassified) (203-03) | CY | 1,164 | $40.00 | $55.00 | $50.00 | $88.67 |
| 6 | Water (203-06) | MG | 14 | $10.00 | $2.00 | $150.00 | $33.33 |
| 7 | Furnishing & spreading topsoil (203-07) | CY | 370 | $55.00 | $50.00 | $70.00 | $69.37 |
| 8 | Construction of haul road (203-50) | LS | 1 | $110,040 | $10,000 | $165,000 | $58,333 |
| 9 | Sediment removal (209-05) | CY | 38 | $30.00 | $15.00 | $75.00 | $78.05 |
| 10 | Temporary silt fence (with backing) (209-08.02) | LF | 526 | $5.90 | $5.50 | $6.00 | $5.53 |
| 11 | Temporary silt fence (without backing) (209-08.03) | LF | 935 | $2.50 | $2.00 | $2.25 | $2.11 |
| 12 | Enhanced rock check dam (209-08.08) | EACH | 2 | $880.00 | $1,400.00 | $850.00 | $789.47 |
| 13 | Mineral aggregate, type A base, grading D (303-01) | TON | 1,368 | $49.00 | $49.00 | $55.00 | $44.80 |
| 14 | Mineral aggregate (size 57) (303-10.01) | TON | 785 | $45.00 | $45.00 | $80.00 | $68.86 |
| 15 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 279 | $185.00 | $185.00 | $200.00 | $236.84 |
| 16 | Bituminous material for prime coat (PC) (402-01) | TON | 4 | $1,800.00 | $1,800.00 | $2,000.00 | $1,263.16 |
| 17 | Aggregate for cover material (PC) (402-02) | TON | 14 | $85.00 | $85.00 | $95.00 | $252.63 |
| 18 | Bituminous material for tack coat (TC) (403-01) | TON | 1 | $1,800.00 | $1,800.00 | $2,000.00 | $905.26 |
| 19 | Acs mix(PG64-22) grading D (411-01.10) | TON | 172 | $216.00 | $216.00 | $230.00 | $357.89 |
| 20 | 18" pipe culvert (side drain) (607-39.02) | LF | 94 | $70.00 | $100.00 | $50.00 | $121.44 |
| 21 | Concrete driveway (701-02) | SF | 3,051 | $10.00 | $11.00 | $11.00 | $14.98 |
| 22 | Guardrail transition 27IN to 31IN (705-02.10) | EACH | 2 | $188.00 | $100.00 | $210.00 | $197.89 |
| 23 | Guardrail terminal (type-in-line) (705-04.05) | EACH | 2 | $1,063.00 | $1,500.00 | $1,200.00 | $1,118.95 |
| 24 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 663 | $29.81 | $30.50 | $33.00 | $31.38 |
| 25 | Thrie beam bridge transition MASH TL-2 (705-06.26) | EACH | 4 | $1,091.00 | $2,750.00 | $1,100.00 | $1,148.42 |
| 26 | Guardrail removed (706-01) | LF | 986 | $5.15 | $1.00 | $5.10 | $5.42 |
| 27 | Radius rail (706-06.03) | LF | 50 | $36.13 | $37.50 | $40.00 | $38.03 |
| 28 | Rounded end element (706-10.26) | EACH | 2 | $125.00 | $50.00 | $140.00 | $131.58 |
| 29 | High-visibility construction fence (707-08.11) | LF | 380 | $2.60 | $3.00 | $1.90 | $1.84 |
| 30 | Machined rip-rap (class A-3) (709-05.05) | TON | 362 | $65.00 | $61.00 | $65.00 | $62.77 |
| 31 | Machined rip-rap (class A-1) (709-05.06) | TON | 180 | $65.00 | $61.00 | $65.00 | $62.86 |
| 32 | Traffic control (712-01) | LS | 1 | $11,850 | $11,000 | $25,000 | $110,632 |
| 33 | Flexible drums (channelizing) (712-04.01) | EACH | 15 | $31.00 | $31.00 | $33.00 | $32.63 |
| 34 | Warning lights (type A) (712-05.01) | EACH | 4 | $20.00 | $20.00 | $22.00 | $21.05 |
| 35 | Signs (construction) (712-06) | SF | 51 | $7.50 | $7.50 | $10.00 | $7.89 |
| 36 | Temporary barricades (type III) (712-07.03) | LF | 40 | $30.00 | $30.00 | $32.00 | $31.58 |
| 37 | Removal of signs, posts and footings (713-15) | LS | 1 | $150.00 | $100.00 | $500.00 | $250.00 |
| 38 | Changeable message sign unit (713-16.01) | EACH | 4 | $5,950.00 | $5,950.00 | $5,950.00 | $16,579 |
| 39 | Signs (S3-1, 36" X 36", sign and support) (713-16.20) | EACH | 1 | $350.00 | $300.00 | $300.00 | $315.79 |
| 40 | Painted pavement marking (contrast 6" line) (716-05.12) | LM | 0.15 | $10,000 | $20,000 | $10,500 | $10,526 |
| 41 | Spray thermo PVMT MRKNG (60 mil) (6IN line) (716-13.02) | LM | 0.70 | $10,000 | $3,200.00 | $10,500 | $10,526 |
| 42 | Mobilization (717-01) | LS | 1 | $273,000 | $288,000 | $300,000 | $169,000 |
| 43 | Geogrid reinforcement type 2 (740-07.04) | SY | 267 | $6.00 | $2.48 | $6.50 | $5.00 |
| 44 | Geotextile (type III)(erosion control) (740-10.03) | SY | 549 | $5.00 | $7.15 | $6.50 | $3.55 |
| 45 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 3,331 | $5.00 | $4.95 | $1.50 | $1.58 |
| 46 | Temporary sediment tube 18IN (740-11.03) | LF | 200 | $4.40 | $4.00 | $5.00 | $4.74 |
| 47 | Temporary sediment tube check dam (740-11.06) | EACH | 10 | $192.00 | $250.00 | $650.00 | $631.58 |
| 48 | Temporary mulch (801-01.65) | UNIT | 20 | $29.00 | $50.00 | $11.00 | $10.53 |
| 49 | Seeding (without mulch) (801-02) | UNIT | 18 | $48.00 | $50.00 | $48.00 | $45.26 |
| 50 | Water (seeding & sodding) (801-03) | MG | 8 | $150.00 | $75.00 | $210.00 | $210.53 |
| 51 | Sodding (new sod) (803-01) | SY | 175 | $6.20 | $7.50 | $8.50 | $7.89 |
| 52 | Erosion control blanket (type I) (805-12.01) | SY | 1,881 | $1.40 | $1.25 | $2.75 | $2.63 |
| 53 | Removal of structures (exist. BR. no. 60-2733-3.18) (202-04.01) | LS | 1 | $242,500 | $640,000 | $350,000 | $541,667 |
| 54 | Dry excavation (bridges) (204-02.01) | CY | 586 | $50.00 | $45.00 | $45.00 | $46.75 |
| 55 | Rock excavation (bridges) (204-04.01) | CY | 8 | $100.00 | $100.00 | $55.00 | $297.81 |
| 56 | Rock drilling (bridges) (204-05) | LF | 48 | $50.00 | $30.00 | $35.00 | $83.33 |
| 57 | Granular backfill (bridges) (303-01.02) | TON | 42 | $40.00 | $45.00 | $100.00 | $149.58 |
| 58 | Epoxy coated reinforcing steel (604-02.03) | LB | 30,481 | $1.76 | $1.50 | $2.00 | $2.18 |
| 59 | Class A concrete (bridges) (604-03.01) | CY | 177 | $1,000.00 | $1,500.00 | $2,400.00 | $2,806.20 |
| 60 | Steel bar reinforcement (bridges) (604-03.02) | LB | 40,369 | $1.63 | $1.50 | $1.50 | $1.81 |
| 61 | Class D concrete (bridge deck) (604-03.09) | CY | 129 | $1,850.00 | $1,500.00 | $2,000.00 | $2,500.00 |
| 62 | Applied texture finish (new structures) (604-04.01) | SY | 735 | $10.50 | $10.50 | $11.00 | $24.17 |
| 63 | Bridge deck grooving (mechanical) (604-05.31) | SY | 432 | $9.26 | $16.64 | $13.00 | $15.43 |
| 64 | Steel piles (10 inch) (606-02.03) | LF | 497 | $60.00 | $70.00 | $70.00 | $98.31 |
| 65 | Pile tips (steel piles, 10 inch) (606-02.06) | EACH | 14 | $300.00 | $100.00 | $200.00 | $331.67 |
| 66 | Prestressed concrete box beam (24" X 36") (615-02.19) | LF | 553 | $550.00 | $680.00 | $685.00 | $591.14 |
| 67 | Conc parapet single slope (STD-1-1SS) (620-05.01) | LF | 348 | $150.00 | $150.00 | $150.00 | $204.69 |
| 68 | Temporary shoring (621-05.02) | LS | 1 | $150,000 | $215,000 | $115,000 | $500,000 |
| 69 | Chain-link fence (bridges) (707-07.01) | SF | 1,985 | $29.00 | $29.00 | $32.50 | $31.29 |
| 70 | 6" perforated pipe with vertical drain system (710-09.01) | LF | 114 | $50.00 | $60.00 | $25.00 | $5.00 |
| 71 | 6" pipe underdrain (710-09.02) | LF | 36 | $15.00 | $20.00 | $20.00 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of March 21, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.