TDOT contract CNZ211 bid tabulation

The installation of rock buttresses on s.r. 31 near l.m. 5.54, including grading, drainage, and paving. Let by Tennessee DOT on August 15, 2025, Hancock County. 2 bids received; low bid $4,438,015 by Wright Brothers Civil Construction, LLC.

Owner
Tennessee DOT
Letting
15 AUG 2025
Pay items
77
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Wright Brothers Civil Construction, LLC$4,438,015Low
2Baker's Construction Services, Inc.$5,515,266+24%
TDOT contract CNZ211: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Wright Brothers Civil Construction, LLC2. Baker's Construction Services, Inc.
1Construction stakes, lines and grades (105-01)LS1$18,500$150,000
2Clearing and grubbing (201-01)LS1$85,000$450,000
3Removal of curb (along eastbound SR-31) (202-08.10)LF624$69.00$52.00
4Road & drainage excavation (unclassified) (203-01)CY9,101$46.60$35.00
5Borrow excavation (graded solid rock) (203-02.01)TON18,103$73.50$96.00
6Water (203-06)MG2$26.70$18.25
7Furnishing & spreading topsoil (203-07)CY514$58.00$90.00
8Construction of haul road (203-50)LS1$300,000$796,667
9Bedding material (pipe) class B (204-07)CY80$112.00$120.00
1012" temporary slope drain (209-02.05)LF565$22.60$53.95
11Sediment removal (209-05)CY62$38.40$100.00
12Rock check dam (209-08.07)EACH62$1,100.00$1,233.38
13Enhanced rock check dam (209-08.08)EACH16$1,600.00$1,771.00
14Sandbags (209-09.01)BAG141$17.00$35.00
15Sediment filter bag(15' X 10') (209-09.04)EACH2$670.00$1,265.00
16Polyethylene sheeting (6 mil. minimum) (209-20.03)SY32$17.00$18.98
17Mineral aggregate, type A base, grading D (303-01)TON779$61.00$90.00
18Mineral aggregate (size 57) (303-10.01)TON50$62.00$90.00
19Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01)TON254$254.00$240.35
20Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON57$374.00$353.90
21Bituminous material for prime coat (PC) (402-01)TON4$1,600.00$1,477.35
22Aggregate for cover material (PC) (402-02)TON14$570.00$249.17
23Bituminous material for tack coat (TC) (403-01)TON5$1,100.00$1,102.50
24Acs mix(PG64-22) grading D (411-01.10)TON570$235.00$224.91
25Scoring for rumble stripe (non-continuous) (8IN width) (411-12.03)LM1$11,000$1,919.24
26Cold planing bituminous pavement (415-01.02)SY9,584$4.65$4.41
27Structural steel (602-01)LB4,834$2.30$14.00
28Class A concrete (roadway) (604-01.01)CY2$1,550.00$2,616.35
2960" minimum ID pipe to slip line 72" pipe (607-65.71)LF239$1,775.00$935.00
30Class A concrete (pipe endwalls) (611-07.01)CY27$1,775.00$2,249.23
31Steel bar reinforcement (pipe endwalls) (611-07.02)LB1,764$4.80$6.90
3236" temporary drainage pipe (621-03.05)LF333$98.00$169.03
33Portable barrier rail delineator (705-04.50)EACH40$29.00$27.56
34W beam GR (type 2) MASH TL-3 (705-06.01)LF37.50$35.00$33.07
35W beam GR (type 2) MASH TL-3 (long post) (705-06.02)LF1,087$41.00$38.59
36GR terminal (in-inline) MASH TL-3 (705-06.11)EACH1$1,400.00$1,323.00
37Tangent energy absorbing term MASH TL-3 (705-06.20)EACH3$4,100.00$3,858.75
38GR terminal (energy absorbing) MASH TL-2 (705-06.30)EACH1$4,000.00$3,748.50
39Guardrail removed (706-01)LF1,019$3.50$10.00
40Radius rail (706-06.03)LF25$52.00$49.61
41Machined rip-rap (class A-3) (709-05.05)TON100$80.00$91.65
42Machined rip-rap (class A-1) (709-05.06)TON438$86.00$92.34
43Machined rip-rap (class C) (709-05.09)TON103$87.00$97.00
44Traffic control (712-01)LS1$60,000$78,918
45Portable barrier rail, reduced deflection (MASH TL-3) (712-02.12)LF2,200$147.00$91.04
46Temporary work zone crash cushion (MASH TL-3) (712-02.60)EACH11$13,000$8,419.83
47Flexible drums (channelizing) (712-04.01)EACH405$42.00$48.00
48Barrier rail delineator (712-04.50)EACH40$16.00$19.24
49Warning lights (type C) (712-05.03)EACH40$32.00$30.87
50Signs (construction) (712-06)SF281$8.75$10.19
51Temporary barricades (type III) (712-07.03)LF240$18.65$24.62
52Removable pavement marking (8" barrier line) (712-09.02)LF3,000$4.65$4.37
53Removable pavement marking (6" line) (712-09.08)LF3,000$3.80$3.98
54Removable black-out tape (6") (712-09.30)LF3,000$3.80$4.43
55Removable black-out tape (8IN) (712-09.31)LF3,000$4.65$4.74
56Sign post delineation enhancement (713-02.21)LF8$8.15$7.72
57Perforated/knockout square tube post (713-11.02)LB101$6.00$5.68
58P post slip base (713-11.21)EACH1$700.00$661.50
59Flat sheet aluminum signs (0.080" thick) (713-13.02)SF7$19.45$18.42
60Flat sheet aluminum signs (0.100" thick) (713-13.03)SF9$21.00$19.85
61Removal of signs, posts and footings (713-15)LS1$291.00$2,175.76
62Temporary raised pavement marker,yellow (716-01.07)EACH90$17.50$15.50
63Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21)EACH30$58.25$107.53
64Removal of snowplowable reflective marker (716-01.30)EACH30$17.50$31.63
65Painted pavement marking (8" barrier line) (716-05.02)LF6,810$0.60$0.51
66Painted pavement marking (6" line) (716-05.20)LM4$2,100.00$1,296.63
67Removal of pavement marking (line) (716-08.01)LF20,430$1.15$0.74
68Removal of pavement marking (8" barrier line) (716-08.02)LF6,810$1.15$0.82
69Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM2$8,700.00$7,906.25
70Mobilization (717-01)LS1$362,000$349,753
71Geotextile (type III)(erosion control) (740-10.03)SY366$4.15$5.44
72Geotextile (type IV)(stabilization) (740-10.04)SY4,109$4.25$5.44
73Temporary sediment tube 24IN (740-11.05)LF3,423$6.20$8.00
74Seeding (without mulch) (801-02)UNIT37$87.75$35.27
75Temporary seeding (without mulch) (801-02.08)UNIT37$48.10$50.00
76Water (seeding & sodding) (801-03)MG4$291.00$78.82
77Erosion control blanket (type II) (805-12.02)SY4,077$2.15$2.34
TDOT contract CNZ211: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of August 15, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy