TDOT contract CNZ243 bid tabulation
The drainage improvements on s.r. 74 (spring place road) from l.m. 11.15 to l.m. 11.80) in cleveland. Let by Tennessee DOT on July 25, 2025, Bradley County. 4 bids received; low bid $1,572,428 by APAC-Atlantic, Inc..
- Owner
- Tennessee DOT
- Letting
- 25 JUL 2025
- Pay items
- 66
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | APAC-Atlantic, Inc. | $1,572,428 | Low |
| 2 | Summers-Taylor, Inc. | $2,168,079 | +38% |
| 3 | Wright Brothers Civil Construction, LLC | $2,198,035 | +40% |
| 4 | Eclipse Companies,LLC | $3,535,526 | +125% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. APAC-Atlantic, Inc. | 2. Summers-Taylor, Inc. | 3. Wright Brothers Civil Construction, LLC | 4. Eclipse Companies,LLC |
|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $9,599.04 | $9,830.00 | $9,900.00 | $54,885 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $32,400 | $33,000 | $83,000 | $55,595 |
| 3 | Removal of structures and obstructions (202-01.01) | LS | 1 | $5,334.60 | $6,920.00 | $1,700.00 | $10,923 |
| 4 | Removal of pipe (24" CMP sta. 127+44.74 LT. SR-74) (202-02.01) | LF | 232 | $13.19 | $100.00 | $37.20 | $41.50 |
| 5 | Removal of pipe (36" RCP sta. 131+86.36 LT. SR-74) (202-02.02) | LF | 30 | $14.81 | $138.00 | $39.10 | $78.50 |
| 6 | Removal of pipe (26" RCP sta. 134+21.11 LT. SR-74) (202-02.03) | LF | 16 | $14.79 | $248.00 | $47.20 | $55.50 |
| 7 | Removal of pipe (24" RCP sta. 134+56.22 LT. SR-74) (202-02.04) | LF | 27 | $14.83 | $147.00 | $42.70 | $61.00 |
| 8 | Removal of pipe (24" CMP sta. 135+22.24 LT. SR-74) (202-02.05) | LF | 106 | $13.19 | $93.50 | $39.20 | $50.00 |
| 9 | Removal of pipe (36" CMP sta. 136+07.72 LT. SR-74) (202-02.06) | LF | 63 | $13.21 | $154.00 | $35.50 | $60.00 |
| 10 | Removal of pipe (36" CMP sta. 136+91.91 LT. SR-74) (202-02.07) | LF | 59 | $13.21 | $107.00 | $37.90 | $51.00 |
| 11 | Removal of pipe (18" CMP sta. 137+61.96 LT. SR-74) (202-02.08) | LF | 42 | $13.19 | $126.00 | $37.80 | $49.00 |
| 12 | Removal of pipe (24" CMP sta. 137+62.53 LT. SR-74) (202-02.09) | LF | 41 | $13.22 | $129.00 | $38.70 | $49.50 |
| 13 | Removal of curb (mountable concrete curb) (202-08.10) | LF | 242 | $6.68 | $13.00 | $35.40 | $16.50 |
| 14 | Road & drainage excavation (unclassified) (203-01) | CY | 28,096 | $12.68 | $20.30 | $22.00 | $35.50 |
| 15 | Placing and spreading topsoil (203-04) | CY | 1,400 | $5.14 | $17.50 | $20.60 | $12.00 |
| 16 | Sediment removal (209-05) | CY | 103 | $37.29 | $38.00 | $36.80 | $42.00 |
| 17 | Temporary silt fence (with backing) (209-08.02) | LF | 1,030 | $4.86 | $6.40 | $5.05 | $16.50 |
| 18 | Rock check dam (209-08.07) | EACH | 1 | $2,160.00 | $719.00 | $2,300.00 | $1,077.50 |
| 19 | Enhanced rock check dam (209-08.08) | EACH | 7 | $1,026.00 | $912.00 | $1,100.00 | $1,040.50 |
| 20 | Filter sock check dam (209-08.09) | EACH | 2 | $864.00 | $332.00 | $900.00 | $935.50 |
| 21 | Detention pond outlet structure (descr.) (209-20.20) | EACH | 1 | $8,279.45 | $20,800 | $13,700 | $7,125.50 |
| 22 | Catch basin protection (type D) (209-40.33) | EACH | 6 | $405.00 | $359.00 | $423.00 | $200.50 |
| 23 | Catch basin filter assembly(type 3) (209-40.43) | EACH | 2 | $729.00 | $923.00 | $760.00 | $166.00 |
| 24 | Temporary diversion channel (209-65.03) | LF | 90 | $41.99 | $408.00 | $14.45 | $40.00 |
| 25 | Temporary in stream diversion (209-65.04) | LF | 840 | $18.84 | $51.00 | $126.00 | $47.50 |
| 26 | Mineral aggregate, type A base, grading D (303-01) | TON | 171 | $68.24 | $209.00 | $61.25 | $60.50 |
| 27 | Mineral aggregate (size 57) (303-10.01) | TON | 206 | $52.56 | $81.00 | $60.75 | $59.50 |
| 28 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 115 | $197.18 | $261.00 | $236.00 | $950.00 |
| 29 | Bituminous material for prime coat (PC) (402-01) | TON | 0.60 | $3,676.05 | $928.00 | $1,400.00 | $3,560.00 |
| 30 | Aggregate for cover material (PC) (402-02) | TON | 2.40 | $665.64 | $912.00 | $825.00 | $251.00 |
| 31 | Bituminous material for tack coat (TC) (403-01) | TON | 0.10 | $1,080.00 | $995.00 | $900.00 | $34,702 |
| 32 | Acs mix(PG64-22) grading D (411-01.10) | TON | 66 | $270.16 | $386.00 | $349.00 | $1,034.50 |
| 33 | 30" concrete pipe culvert (class III) (607-06.02) | LF | 60 | $248.26 | $310.00 | $184.00 | $188.50 |
| 34 | 30" concrete pipe culvert (class IV) (607-06.03) | LF | 420 | $159.82 | $286.00 | $186.00 | $178.50 |
| 35 | 36" concrete pipe culvert (class III) (607-07.02) | LF | 23 | $240.25 | $330.00 | $217.00 | $222.50 |
| 36 | 36" concrete pipe culvert (class IV) (607-07.03) | LF | 222 | $238.24 | $267.00 | $219.00 | $206.00 |
| 37 | 38"X 24" horizontal oval concrete pipe culvert (607-16.04) | LF | 58 | $295.97 | $324.00 | $233.00 | $408.00 |
| 38 | 24" folded PVC pipe liner (607-67.11) | LF | 142 | $540.00 | $536.00 | $600.00 | $1,243.50 |
| 39 | 36" folded PVC pipe liner (607-67.13) | LF | 607 | $648.00 | $644.00 | $700.00 | $1,243.50 |
| 40 | Class A concrete (pipe endwalls) (611-07.01) | CY | 9 | $2,360.46 | $2,920.00 | $3,200.00 | $2,753.00 |
| 41 | Steel bar reinforcement (pipe endwalls) (611-07.02) | LB | 314 | $5.90 | $3.50 | $4.45 | $27.50 |
| 42 | 30IN endwall (side drain) (611-07.33) | EACH | 4 | $4,543.68 | $12,700 | $8,000.00 | $9,510.50 |
| 43 | 36IN endwall (side drain) (611-07.34) | EACH | 1 | $14,202 | $16,400 | $10,100 | $10,723 |
| 44 | 30IN endwall (cross drain) 6:1 (611-07.62) | EACH | 4 | $10,932 | $9,600.00 | $8,000.00 | $4,225.50 |
| 45 | Catch basins, type 42, > 4' - 8' depth (611-42.02) | EACH | 1 | $6,075.18 | $5,820.00 | $9,600.00 | $4,910.50 |
| 46 | Concrete curb (702-01.02) | LF | 242 | $24.21 | $33.00 | $44.30 | $61.00 |
| 47 | High-visibility construction fence (707-08.11) | LF | 957 | $2.16 | $4.00 | $2.25 | $11.00 |
| 48 | Machined rip-rap (class A-3) (709-05.05) | TON | 50 | $98.61 | $76.00 | $69.75 | $73.50 |
| 49 | Machined rip-rap (class A-1) (709-05.06) | TON | 308 | $70.69 | $97.00 | $74.50 | $66.00 |
| 50 | Machined rip-rap (class B) (709-05.08) | TON | 227 | $75.12 | $98.00 | $78.50 | $104.00 |
| 51 | Machined rip-rap (class C) (709-05.09) | TON | 86 | $98.61 | $95.00 | $78.50 | $174.00 |
| 52 | Traffic control (712-01) | LS | 1 | $1,296.00 | $59,200 | $74,700 | $152,389 |
| 53 | Flexible drums (channelizing) (712-04.01) | EACH | 60 | $37.80 | $40.00 | $42.90 | $42.00 |
| 54 | Warning lights (type C) (712-05.03) | EACH | 30 | $37.80 | $40.00 | $33.80 | $42.00 |
| 55 | Signs (construction) (712-06) | SF | 279 | $8.10 | $8.60 | $9.90 | $11.50 |
| 56 | Arrow board (type C) (712-08.03) | EACH | 2 | $2,136.24 | $2,250.00 | $1,100.00 | $1,676.00 |
| 57 | Changeable message sign unit (713-16.01) | EACH | 2 | $1,144.80 | $4,250.00 | $5,100.00 | $11,336 |
| 58 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 0.10 | $13,500 | $16,585 | $13,900 | $102,975 |
| 59 | Mobilization (717-01) | LS | 1 | $113,524 | $116,000 | $147,500 | $228,806 |
| 60 | Geotextile (type III)(erosion control) (740-10.03) | SY | 689 | $4.45 | $4.00 | $4.15 | $5.50 |
| 61 | Temporary sediment tube 18IN (740-11.03) | LF | 3,468 | $5.02 | $5.30 | $5.25 | $6.00 |
| 62 | Seeding (with mulch) (801-01) | UNIT | 50 | $51.84 | $58.00 | $54.00 | $1,979.00 |
| 63 | Temporary seeding (with mulch) (801-01.07) | UNIT | 93 | $44.28 | $45.00 | $46.20 | $1,886.50 |
| 64 | Natve seed MX final stablizatn of slopes (801-01.38) | UNIT | 1 | $1,080.00 | $276.00 | $1,100.00 | $8,786.00 |
| 65 | Water (seeding & sodding) (801-03) | MG | 119 | $135.00 | $100.00 | $141.00 | $14.00 |
| 66 | Sodding (new sod) (803-01) | SY | 10,400 | $6.48 | $7.00 | $6.75 | $5.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of July 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way