TDOT contract CNZ243 bid tabulation

The drainage improvements on s.r. 74 (spring place road) from l.m. 11.15 to l.m. 11.80) in cleveland. Let by Tennessee DOT on July 25, 2025, Bradley County. 4 bids received; low bid $1,572,428 by APAC-Atlantic, Inc..

Owner
Tennessee DOT
Letting
25 JUL 2025
Pay items
66
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1APAC-Atlantic, Inc.$1,572,428Low
2Summers-Taylor, Inc.$2,168,079+38%
3Wright Brothers Civil Construction, LLC$2,198,035+40%
4Eclipse Companies,LLC$3,535,526+125%
TDOT contract CNZ243: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. APAC-Atlantic, Inc.2. Summers-Taylor, Inc.3. Wright Brothers Civil Construction, LLC4. Eclipse Companies,LLC
1Construction stakes, lines and grades (105-01)LS1$9,599.04$9,830.00$9,900.00$54,885
2Clearing and grubbing (201-01)LS1$32,400$33,000$83,000$55,595
3Removal of structures and obstructions (202-01.01)LS1$5,334.60$6,920.00$1,700.00$10,923
4Removal of pipe (24" CMP sta. 127+44.74 LT. SR-74) (202-02.01)LF232$13.19$100.00$37.20$41.50
5Removal of pipe (36" RCP sta. 131+86.36 LT. SR-74) (202-02.02)LF30$14.81$138.00$39.10$78.50
6Removal of pipe (26" RCP sta. 134+21.11 LT. SR-74) (202-02.03)LF16$14.79$248.00$47.20$55.50
7Removal of pipe (24" RCP sta. 134+56.22 LT. SR-74) (202-02.04)LF27$14.83$147.00$42.70$61.00
8Removal of pipe (24" CMP sta. 135+22.24 LT. SR-74) (202-02.05)LF106$13.19$93.50$39.20$50.00
9Removal of pipe (36" CMP sta. 136+07.72 LT. SR-74) (202-02.06)LF63$13.21$154.00$35.50$60.00
10Removal of pipe (36" CMP sta. 136+91.91 LT. SR-74) (202-02.07)LF59$13.21$107.00$37.90$51.00
11Removal of pipe (18" CMP sta. 137+61.96 LT. SR-74) (202-02.08)LF42$13.19$126.00$37.80$49.00
12Removal of pipe (24" CMP sta. 137+62.53 LT. SR-74) (202-02.09)LF41$13.22$129.00$38.70$49.50
13Removal of curb (mountable concrete curb) (202-08.10)LF242$6.68$13.00$35.40$16.50
14Road & drainage excavation (unclassified) (203-01)CY28,096$12.68$20.30$22.00$35.50
15Placing and spreading topsoil (203-04)CY1,400$5.14$17.50$20.60$12.00
16Sediment removal (209-05)CY103$37.29$38.00$36.80$42.00
17Temporary silt fence (with backing) (209-08.02)LF1,030$4.86$6.40$5.05$16.50
18Rock check dam (209-08.07)EACH1$2,160.00$719.00$2,300.00$1,077.50
19Enhanced rock check dam (209-08.08)EACH7$1,026.00$912.00$1,100.00$1,040.50
20Filter sock check dam (209-08.09)EACH2$864.00$332.00$900.00$935.50
21Detention pond outlet structure (descr.) (209-20.20)EACH1$8,279.45$20,800$13,700$7,125.50
22Catch basin protection (type D) (209-40.33)EACH6$405.00$359.00$423.00$200.50
23Catch basin filter assembly(type 3) (209-40.43)EACH2$729.00$923.00$760.00$166.00
24Temporary diversion channel (209-65.03)LF90$41.99$408.00$14.45$40.00
25Temporary in stream diversion (209-65.04)LF840$18.84$51.00$126.00$47.50
26Mineral aggregate, type A base, grading D (303-01)TON171$68.24$209.00$61.25$60.50
27Mineral aggregate (size 57) (303-10.01)TON206$52.56$81.00$60.75$59.50
28Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON115$197.18$261.00$236.00$950.00
29Bituminous material for prime coat (PC) (402-01)TON0.60$3,676.05$928.00$1,400.00$3,560.00
30Aggregate for cover material (PC) (402-02)TON2.40$665.64$912.00$825.00$251.00
31Bituminous material for tack coat (TC) (403-01)TON0.10$1,080.00$995.00$900.00$34,702
32Acs mix(PG64-22) grading D (411-01.10)TON66$270.16$386.00$349.00$1,034.50
3330" concrete pipe culvert (class III) (607-06.02)LF60$248.26$310.00$184.00$188.50
3430" concrete pipe culvert (class IV) (607-06.03)LF420$159.82$286.00$186.00$178.50
3536" concrete pipe culvert (class III) (607-07.02)LF23$240.25$330.00$217.00$222.50
3636" concrete pipe culvert (class IV) (607-07.03)LF222$238.24$267.00$219.00$206.00
3738"X 24" horizontal oval concrete pipe culvert (607-16.04)LF58$295.97$324.00$233.00$408.00
3824" folded PVC pipe liner (607-67.11)LF142$540.00$536.00$600.00$1,243.50
3936" folded PVC pipe liner (607-67.13)LF607$648.00$644.00$700.00$1,243.50
40Class A concrete (pipe endwalls) (611-07.01)CY9$2,360.46$2,920.00$3,200.00$2,753.00
41Steel bar reinforcement (pipe endwalls) (611-07.02)LB314$5.90$3.50$4.45$27.50
4230IN endwall (side drain) (611-07.33)EACH4$4,543.68$12,700$8,000.00$9,510.50
4336IN endwall (side drain) (611-07.34)EACH1$14,202$16,400$10,100$10,723
4430IN endwall (cross drain) 6:1 (611-07.62)EACH4$10,932$9,600.00$8,000.00$4,225.50
45Catch basins, type 42, > 4' - 8' depth (611-42.02)EACH1$6,075.18$5,820.00$9,600.00$4,910.50
46Concrete curb (702-01.02)LF242$24.21$33.00$44.30$61.00
47High-visibility construction fence (707-08.11)LF957$2.16$4.00$2.25$11.00
48Machined rip-rap (class A-3) (709-05.05)TON50$98.61$76.00$69.75$73.50
49Machined rip-rap (class A-1) (709-05.06)TON308$70.69$97.00$74.50$66.00
50Machined rip-rap (class B) (709-05.08)TON227$75.12$98.00$78.50$104.00
51Machined rip-rap (class C) (709-05.09)TON86$98.61$95.00$78.50$174.00
52Traffic control (712-01)LS1$1,296.00$59,200$74,700$152,389
53Flexible drums (channelizing) (712-04.01)EACH60$37.80$40.00$42.90$42.00
54Warning lights (type C) (712-05.03)EACH30$37.80$40.00$33.80$42.00
55Signs (construction) (712-06)SF279$8.10$8.60$9.90$11.50
56Arrow board (type C) (712-08.03)EACH2$2,136.24$2,250.00$1,100.00$1,676.00
57Changeable message sign unit (713-16.01)EACH2$1,144.80$4,250.00$5,100.00$11,336
58Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM0.10$13,500$16,585$13,900$102,975
59Mobilization (717-01)LS1$113,524$116,000$147,500$228,806
60Geotextile (type III)(erosion control) (740-10.03)SY689$4.45$4.00$4.15$5.50
61Temporary sediment tube 18IN (740-11.03)LF3,468$5.02$5.30$5.25$6.00
62Seeding (with mulch) (801-01)UNIT50$51.84$58.00$54.00$1,979.00
63Temporary seeding (with mulch) (801-01.07)UNIT93$44.28$45.00$46.20$1,886.50
64Natve seed MX final stablizatn of slopes (801-01.38)UNIT1$1,080.00$276.00$1,100.00$8,786.00
65Water (seeding & sodding) (801-03)MG119$135.00$100.00$141.00$14.00
66Sodding (new sod) (803-01)SY10,400$6.48$7.00$6.75$5.50
TDOT contract CNZ243: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of July 25, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy