TDOT contract CNZ244 bid tabulation

The culvert repair including retaining walls on u.s. 41 (u.s. 64, s.r. 2, lee highway) at l.m. 17.25. Let by Tennessee DOT on July 25, 2025, Marion County. 2 bids received; low bid $882,882 by APAC-Atlantic, Inc..

Owner
Tennessee DOT
Letting
25 JUL 2025
Pay items
72
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1APAC-Atlantic, Inc.$882,882Low
2J. Hill Excavating, LLC$1,252,318+42%
TDOT contract CNZ244: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. APAC-Atlantic, Inc.2. J. Hill Excavating, LLC
1Construction stakes, lines and grades (105-01)LS1$8,800.00$49,000
2Clearing and grubbing (201-01)LS1$15,728$63,750
3Removal of pipe (66" CMP) (202-01.13)LF140$83.15$126.00
4Removal of structures & obstructions (CB, sta. 13+39.03 off. 32.5') (202-01.56)LS1$7,881.04$6,900.00
5Road & drainage excavation (unclassified) (203-01)CY2,443$36.33$43.50
6Placing and spreading topsoil (203-04)CY85$39.43$39.75
7Furnishing & spreading topsoil (203-07)CY50$208.44$90.00
8Foundation fill material (204-08)CY3$1,006.73$117.00
918" temporary slope drain (209-02.07)LF96$22.58$41.25
10Stream mitigation - articulated concrete mat (209-03.53)SY660$69.33$285.00
11Sediment removal (209-05)CY13$76.16$25.00
12Temporary silt fence (with backing) (209-08.02)LF244$6.05$12.00
13Sandbags (209-09.01)BAG360$31.39$15.65
14Sediment filter bag(15' X 10') (209-09.04)EACH4$2,605.54$2,100.00
15Polyethylene sheeting (6 mil. minimum) (209-20.03)SY32$50.60$20.00
16Temporary in stream diversion (209-65.04)LF222$7.56$105.00
17Granular backfill (roadway) (303-01.01)TON99$66.77$85.00
18Mineral aggregate (size 57) (303-10.01)TON145$66.78$88.00
19Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON96$251.00$345.00
20Bituminous material for prime coat (PC) (402-01)TON0.30$4,371.60$5,650.00
21Bituminous material for tack coat (TC) (403-01)TON3$825.00$2,100.00
22Saw cutting asphalt pavement (407-20.05)LF150$13.20$23.75
23Acs mix(PG64-22) grading D (411-01.10)TON437$171.47$280.00
24Cold planing bituminous pavement (415-01.02)SY5,488$3.51$7.55
25Structural steel (602-01)LB180.50$5.50$27.00
26Class A concrete (roadway) (604-01.01)CY13$5,044.00$2,600.00
27Steel bar reinforcement (roadway) (604-01.02)LB2,550$5.50$3.45
28Retaining wall (R1, sta. 13+00.39 to sta. 13+33.46 RT) (604-07.01)SF155$286.49$260.00
29Retaining wall (R2, sta. 13+46.30 to sta. 13+72.10 RT) (604-07.02)SF134$329.99$278.50
3042" temporary drainage pipe (621-03.06)LF40$204.25$120.00
31Temporary shoring (621-05.02)LS1$47,667$10,000
32Earth pad for type 38 GR end treatment (705-04.09)EACH1$1,980.00$1,895.00
33W beam GR (type 2) MASH TL-3 (long post) (705-06.02)LF196$38.50$52.00
34GR terminaltrailing end (type 13) MASH TL-3 (705-06.10)EACH1$1,980.00$2,275.00
35GR terminal (in-inline) MASH TL-3 (705-06.11)EACH2$1,760.00$2,125.00
36Tangent energy absorbing term MASH TL-3 (705-06.20)EACH1$3,850.00$3,855.00
37Radius rail (706-06.03)LF60$55.00$49.00
38Rounded end element (706-10.26)EACH1$165.00$380.00
39Chain link fence (6 foot) (707-01.11)LF130$42.90$45.00
40End & corner post assembly(chain-link fence 6') (707-01.12)EACH2$1,650.00$2,500.00
41Removal of fence (tract 1) (707-06.01)LF130$28.56$15.00
42Removal and reset fence (tract 1) (707-06.03)LF130$28.56$45.00
43High-visibility construction fence (707-08.11)LF43$9.35$8.00
44Machined rip-rap (class A-3) (709-05.05)TON50$82.32$88.00
45Machined rip-rap (class A-1) (709-05.06)TON23$88.92$90.00
46Machined rip-rap (class B) (709-05.08)TON16$149.16$102.00
47Traffic control (712-01)LS1$2,200.00$85,500
48Interconnected portable barrier rail (712-02.02)LF290$47.95$89.00
49Temporary work zone crash cushion (MASH TL-3) (712-02.60)EACH2$7,150.00$11,250
50Flexible drums (channelizing) (712-04.01)EACH100$41.80$43.00
51Signs (construction) (712-06)SF269$9.19$10.00
52Temporary barricades (type III) (712-07.03)LF20$17.60$20.00
53Arrow board (type C) (712-08.03)EACH2$550.00$1,230.00
54Removable pavement marking (8" barrier line) (712-09.02)LF4,500$4.95$6.15
55Removable pavement marking (stop line) (712-09.04)LF40$27.50$25.00
56Removable black-out tape (6") (712-09.30)LF2,500$10.45$5.45
57Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21)EACH55$55.00$112.00
58Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22)EACH10$55.00$114.00
59Plastic pavement marking(channelization striping) (716-02.04)SY130$30.25$35.00
60Plastic pavement marking (stop line) (716-02.05)LF55$13.20$19.00
61Plastic pavement marking (turn lane arrow) (716-02.06)EACH2$192.50$380.00
62Plastic pavement marking (8IN line) (716-02.12)LM0.10$13,750$13,000
63Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM1$9,625.00$8,200.00
64Mobilization (717-01)LS1$111,127$105,000
65Modification of existing traffic signal equipment (730-01.04)LS1$14,410$15,500
66Geotextile (type III)(erosion control) (740-10.03)SY240$6.18$7.00
67Temporary sediment tube 18IN (740-11.03)LF619$6.05$7.77
68Temporary seeding (with mulch) (801-01.07)UNIT9$93.50$235.00
69Natve seed MX final stablizatn of slopes (801-01.38)UNIT14$192.50$246.00
70Temporary mulch (801-01.65)UNIT1$1,100.00$127.55
71Water (seeding & sodding) (801-03)MG2$220.00$118.00
72Erosion control blanket (type II) (805-12.02)SY800$1.76$3.48
TDOT contract CNZ244: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of July 25, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy