FDOT contract T4702 bid tabulation
SR 7 (US 441) AT LAKE WORTH RD. Let by Florida DOT on August 27, 2025, Palm Beach, District 4. 8 bids received; low bid $3,408,647 by The Stout Group LLC.
- Owner
- Florida DOT
- Letting
- 27 AUG 2025
- Pay items
- 141
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | The Stout Group LLC | $3,408,647 | Low |
| 2 | Ohla USA Inc | $3,415,198 | 0.0% |
| 3 | General Asphalt Company, LLC | $3,453,411 | +1.0% |
| 4 | Florida Engineering & Development Corp | $3,554,681 | +4.0% |
| 5 | Carr Construction, LLC | $3,578,204 | +5.0% |
| 6 | Ranger Construction Industries, Inc. | $3,579,817 | +5.0% |
| 7 | Roadway Construction, LLC | $3,741,314 | +10% |
| 8 | Halley Engineering Contractors, Inc. | $3,989,477 | +17% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. The Stout Group LLC | 2. Ohla USA Inc | 3. General Asphalt Company, LLC | 4. Florida Engineering & Development Corp | 5. Carr Construction, LLC | 6. Ranger Construction Industries, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $330,000 | $340,000 | $300,000 | $355,284 | $248,000 | $546,100 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $300,000 | $180,000 | $475,000 | $325,803 | $121,700 | $247,445 |
| 0015 | Traffic control officer (0102-14) | HR | 184 | $90.00 | $75.00 | $88.00 | $88.17 | $100.00 | $90.92 |
| 0020 | Work zone sign (0102-60) | ED | 8,134 | $0.19 | $0.21 | $0.23 | $0.22 | $0.23 | $0.25 |
| 0025 | Temporary barrier, F&I, free standing (0102-71-16) | LF | 840 | $48.00 | $42.00 | $1.10 | $43.26 | $42.00 | $47.75 |
| 0030 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 9,656 | $0.10 | $0.10 | $0.13 | $0.12 | $0.10 | $0.10 |
| 0035 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 10,872 | $0.04 | $0.05 | $0.07 | $0.06 | $0.10 | $0.06 |
| 0040 | Arrow board / advance warning arrow panel (0102-76) | ED | 350 | $5.00 | $4.50 | $5.50 | $5.15 | $5.00 | $5.12 |
| 0045 | Temporary crash cushion, redirective option (0102-89-1) | LO | 2 | $1,500.00 | $1,050.00 | $951.50 | $890.95 | $1,050.00 | $3,162.00 |
| 0050 | Portable changeable message sign, temporary (0102-99) | ED | 904 | $9.00 | $9.00 | $10.95 | $10.25 | $9.00 | $10.25 |
| 0055 | Temporary signalization and maintenance, intersection (0102-104) | ED | 212 | $32.40 | $23.00 | $35.64 | $33.37 | $12.25 | $47.73 |
| 0060 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 212 | $31.20 | $44.00 | $34.32 | $32.14 | $12.25 | $23.86 |
| 0065 | Type III barricade (0102-115) | ED | 424 | $0.75 | $0.25 | $0.35 | $0.33 | $0.30 | $0.30 |
| 0070 | Sediment barrier (0104-10-3) | LF | 2,251 | $8.00 | $5.00 | $1.10 | $2.71 | $5.40 | $3.55 |
| 0075 | Floating turbidity barrier (0104-11) | LF | 42 | $35.00 | $35.00 | $22.00 | $70.56 | $1,131.00 | $30.42 |
| 0080 | Inlet protection system (0104-18) | EACH | 6 | $200.00 | $1,200.00 | $181.50 | $124.26 | $597.00 | $328.70 |
| 0085 | Litter removal (0107-1) | ACRE | 20.68 | $1.00 | $100.00 | $1.10 | $35.60 | $326.00 | $331.00 |
| 0090 | Mowing (0107-2) | ACRE | 15.50 | $1.00 | $100.00 | $1.10 | $56.80 | $408.00 | $280.70 |
| 0095 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $20,000 | $9,300.00 | $1.10 | $1,545.00 | $7,300.00 | $3,410.00 |
| 0100 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $105,000 | $350,000 | $92,499 | $112,526 | $50,953 | $27,600 |
| 0105 | Removal of existing concrete (0110-4-10) | SY | 654 | $25.00 | $50.00 | $27.50 | $45.66 | $52.00 | $32.42 |
| 0110 | Tree protection barrier (0110-21) | LF | 180 | $15.00 | $12.00 | $11.00 | $9.34 | $8.70 | $2.30 |
| 0115 | Tree root and branch pruning (0110-22) | EACH | 4 | $650.00 | $4,000.00 | $1,870.00 | $5,150.00 | $1,304.00 | $852.50 |
| 0120 | Regular excavation (0120-1) | CY | 855 | $55.00 | $50.00 | $92.62 | $138.11 | $35.00 | $23.80 |
| 0125 | Embankment (0120-6) | CY | 988 | $65.00 | $25.00 | $44.55 | $63.94 | $35.00 | $37.50 |
| 0130 | Type B stabilization (0160-4) | SY | 2,130 | $25.00 | $18.00 | $17.60 | $19.47 | $37.50 | $28.32 |
| 0135 | Optional base, base group 01 (0285-701) | SY | 475 | $55.00 | $31.00 | $39.05 | $28.79 | $55.00 | $47.05 |
| 0140 | Optional base, base group 02 (0285-702) | SY | 87 | $55.00 | $60.00 | $40.70 | $110.38 | $55.00 | $219.10 |
| 0145 | Optional base, base group 09 (0285-709) | SY | 888 | $83.00 | $47.00 | $48.40 | $99.85 | $55.00 | $37.80 |
| 0150 | Optional base, base group 10 (0285-710) | SY | 772 | $90.00 | $48.00 | $87.73 | $118.88 | $55.00 | $77.82 |
| 0155 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 18,382 | $3.50 | $6.00 | $4.12 | $4.94 | $7.70 | $5.25 |
| 0160 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 149.40 | $210.00 | $200.00 | $322.19 | $375.95 | $338.00 | $379.00 |
| 0165 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 1,650.50 | $230.00 | $175.00 | $212.94 | $249.26 | $225.00 | $209.50 |
| 0170 | Miscellaneous asphalt (0339-1) | TN | 28.60 | $350.00 | $315.00 | $495.00 | $353.35 | $100.00 | $494.35 |
| 0175 | Inlets, curb, type P-5, <10' (0425-1351) | EACH | 1 | $16,000 | $11,000 | $15,400 | $9,227.27 | $14,000 | $15,910 |
| 0180 | Inlets, curb, type P-5, >10' (0425-1352) | EACH | 2 | $19,000 | $11,000 | $16,500 | $14,437 | $14,500 | $16,500 |
| 0185 | Inlets, curb, type J-5, <10' (0425-1451) | EACH | 2 | $17,000 | $11,000 | $19,800 | $10,967 | $18,000 | $20,455 |
| 0190 | Inlets, curb, type J-5, >10' (0425-1452) | EACH | 1 | $21,000 | $11,000 | $20,900 | $22,305 | $19,000 | $21,600 |
| 0195 | Inlets, curb, type J-6, <10' (0425-1461) | EACH | 1 | $17,000 | $11,000 | $20,350 | $11,171 | $18,500 | $21,023 |
| 0200 | Inlets, DT bot, type C,<10' (0425-1521) | EACH | 1 | $15,000 | $11,000 | $6,600.00 | $7,572.48 | $6,000.00 | $6,820.00 |
| 0205 | Inlets, closed flume (0425-1910) | EACH | 1 | $20,000 | $18,000 | $9,900.00 | $8,751.85 | $9,000.00 | $10,228 |
| 0210 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 280 | $200.00 | $300.00 | $154.00 | $131.79 | $135.00 | $153.42 |
| 0215 | French drain, 24" (0443-70-4) | LF | 449 | $350.00 | $400.00 | $357.50 | $202.70 | $325.00 | $369.35 |
| 0220 | Concrete curb & gutter, type E (0520-1-7) | LF | 2,453 | $33.00 | $50.00 | $39.60 | $66.21 | $145.00 | $44.20 |
| 0225 | Traffic separator concrete- type IV, 6' wide (0520-5-42) | LF | 15 | $250.00 | $415.00 | $275.00 | $293.75 | $227.00 | $113.65 |
| 0230 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 499 | $90.00 | $140.00 | $85.97 | $89.41 | $150.00 | $108.40 |
| 0235 | Detectable warnings (0527-2) | SF | 112 | $40.00 | $70.00 | $39.60 | $40.63 | $30.00 | $56.82 |
| 0240 | Guardrail -roadway, general (0536-1-1) | LF | 939 | $28.81 | $29.00 | $29.15 | $28.79 | $28.00 | $24.95 |
| 0245 | Rub rail for guardrail, single sided rub rail (0536-5-1) | LF | 163 | $15.25 | $16.00 | $17.60 | $12.48 | $12.00 | $17.60 |
| 0250 | Pipe rail for guardrail (0536-6) | LF | 189 | $24.25 | $19.00 | $27.50 | $22.70 | $22.00 | $21.10 |
| 0255 | Guardrail end treatment- trailing anchorage (0536-85-20) | EACH | 6 | $1,675.00 | $1,400.00 | $1,870.00 | $1,626.97 | $1,580.00 | $1,503.00 |
| 0260 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 3 | $3,850.00 | $3,200.00 | $3,630.00 | $3,579.73 | $3,500.00 | $3,462.00 |
| 0265 | Guardrail end treatment- type CRT (0536-85-26) | EACH | 1 | $2,190.00 | $3,200.00 | $4,180.00 | $4,368.16 | $4,250.00 | $3,500.00 |
| 0270 | Performance turf, sod (0570-1-2) | SY | 5,167 | $12.00 | $5.00 | $3.47 | $3.71 | $10.00 | $6.27 |
| 0275 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 1.36 | $1,800.00 | $1,840.00 | $1,925.00 | $1,802.50 | $1,401.00 | $1,575.00 |
| 0280 | Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102) | GM | 0.03 | $2,000.00 | $2,300.00 | $2,933.70 | $2,747.20 | $2,160.00 | $1,592.00 |
| 0285 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 1,096 | $2.00 | $1.80 | $1.87 | $1.75 | $1.10 | $1.25 |
| 0290 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 105 | $3.00 | $1.98 | $1.98 | $1.85 | $1.60 | $1.76 |
| 0295 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 349 | $4.00 | $2.05 | $2.09 | $1.96 | $2.00 | $2.30 |
| 0300 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 0.81 | $1,000.00 | $530.00 | $550.00 | $515.00 | $648.00 | $720.00 |
| 0305 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.33 | $1,000.00 | $725.00 | $770.00 | $721.01 | $704.00 | $771.00 |
| 0310 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 2 | $100.00 | $50.00 | $49.50 | $46.35 | $100.00 | $114.00 |
| 0315 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 31 | $50.00 | $38.00 | $38.50 | $36.05 | $35.00 | $39.80 |
| 0320 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 0.47 | $1,800.00 | $1,900.00 | $1,925.00 | $1,802.50 | $1,406.00 | $1,593.00 |
| 0325 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 5 | $3.00 | $1.70 | $1.76 | $1.65 | $1.60 | $1.76 |
| 0330 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.11 | $1,800.00 | $722.00 | $770.00 | $720.97 | $681.00 | $770.00 |
| 0335 | Partnering, DO not bid (0999-16) | LS | 1 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 |
| 0340 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0345 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 7 | $480.00 | $625.00 | $649.59 | $597.40 | $480.00 | $546.00 |
| 0350 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 2 | $1,600.00 | $1,700.00 | $2,079.57 | $2,472.00 | $1,600.00 | $1,819.00 |
| 0355 | Single column ground sign assembly, remove (0700-1600) | EACH | 8 | $65.00 | $65.00 | $55.00 | $46.35 | $65.00 | $74.00 |
| 0360 | Multi-column ground sign assembly, F&I ground mount, 30.0 SF (0700-2113) | EACH | 1 | $6,500.00 | $4,560.00 | $7,205.15 | $8,497.50 | $6,500.00 | $7,387.00 |
| 0365 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 1 | $1,250.00 | $750.00 | $1,320.00 | $2,317.50 | $1,250.00 | $1,421.00 |
| 0370 | Sign panel, furnish & install overhead mount, 31-50 SF (0700-3204) | EACH | 4 | $3,384.21 | $3,300.00 | $3,722.63 | $3,347.50 | $3,311.00 | $4,057.00 |
| 0375 | Sign panel, relocate, 21-30 SF (0700-3503) | EACH | 1 | $400.00 | $2,560.00 | $874.72 | $1,957.00 | $400.00 | $455.00 |
| 0380 | Sign panel, remove, 31-50 SF (0700-3604) | EACH | 4 | $250.00 | $255.00 | $605.00 | $2,987.00 | $1,683.00 | $1,142.05 |
| 0385 | Overhead static sign furnish & install, cantilever, 40 FT (0700-4113) | EACH | 1 | $130,000 | $125,000 | $133,232 | $124,754 | $133,000 | $115,552 |
| 0390 | Overhead static sign shallow foundation removal, cantilever (0700-4611) | EACH | 1 | $10,000 | $12,750 | $7,920.44 | $7,416.41 | $8,332.00 | $18,205 |
| 0395 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 2 | $90.00 | $130.00 | $165.00 | $206.00 | $90.00 | $103.00 |
| 0400 | Tubular marker, 36" white post (0704-1-3) | EACH | 1 | $165.00 | $275.00 | $264.00 | $257.50 | $170.00 | $187.50 |
| 0405 | Tubular marker, 36" yellow (0704-1-4) | EACH | 5 | $175.00 | $275.00 | $264.00 | $257.50 | $175.00 | $199.00 |
| 0410 | Object marker, type 2 (0705-10-2) | EACH | 12 | $130.00 | $125.00 | $275.64 | $123.60 | $130.00 | $148.00 |
| 0415 | Raised pavement marker, type B (0706-1-3) | EACH | 419 | $4.00 | $4.40 | $4.57 | $4.27 | $4.00 | $4.55 |
| 0420 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 28 | $20.00 | $5.30 | $5.50 | $5.15 | $5.60 | $6.37 |
| 0425 | Painted pavement markings, surface (0710-90) | LS | 1 | $8,200.00 | $9,225.00 | $9,590.90 | $8,980.57 | $8,200.00 | $9,320.00 |
| 0430 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 1,096 | $3.20 | $3.15 | $3.25 | $3.04 | $3.20 | $3.64 |
| 0435 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 105 | $4.95 | $4.70 | $4.87 | $4.56 | $5.00 | $5.62 |
| 0440 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 349 | $5.80 | $6.25 | $6.49 | $6.08 | $6.00 | $6.59 |
| 0445 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.33 | $2,900.00 | $2,400.00 | $2,475.00 | $2,317.50 | $2,918.00 | $3,216.00 |
| 0450 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 2 | $120.00 | $69.00 | $71.50 | $66.95 | $120.00 | $137.00 |
| 0455 | Thermoplastic, standard, arrow (0711-11170) | EACH | 31 | $68.00 | $53.00 | $55.00 | $51.50 | $70.00 | $77.27 |
| 0460 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 5 | $4.95 | $4.75 | $4.87 | $4.56 | $5.00 | $5.62 |
| 0465 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.11 | $2,900.00 | $2,317.00 | $2,475.00 | $2,317.52 | $3,080.00 | $3,208.00 |
| 0470 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 912 | $12.50 | $16.15 | $16.72 | $15.66 | $12.50 | $14.20 |
| 0475 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 6 | $215.00 | $222.00 | $231.00 | $216.30 | $215.00 | $244.35 |
| 0480 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 6 | $120.00 | $93.00 | $95.70 | $89.61 | $120.00 | $136.40 |
| 0485 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 1.36 | $6,500.00 | $5,325.00 | $5,571.50 | $5,216.95 | $5,204.00 | $5,870.00 |
| 0490 | Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102) | GM | 0.03 | $5,200.00 | $5,700.00 | $7,429.40 | $6,956.80 | $7,800.00 | $8,864.00 |
| 0495 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 0.81 | $5,200.00 | $1,300.00 | $1,393.70 | $1,305.00 | $2,020.00 | $2,245.00 |
| 0500 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.47 | $5,200.00 | $5,200.00 | $5,571.50 | $4,951.92 | $5,222.00 | $5,934.36 |
| 0505 | Green-colored pavement markings, bike lane (0714-10) | SF | 1,021 | $7.15 | $9.20 | $9.52 | $8.91 | $7.20 | $8.12 |
| 0510 | Pull & splice box, F&I, 17" X 30" cover size (0635-2-14) | EACH | 9 | $1,200.00 | $2,500.00 | $1,320.00 | $1,236.00 | $2,720.00 | $1,643.00 |
| 0515 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 2,943 | $5.00 | $2.69 | $5.50 | $5.15 | $3.20 | $3.02 |
| 0520 | Lighting conductors, remove & dispose, contractor owns (0715-1-60) | LF | 1,692 | $1.70 | $1.00 | $1.87 | $1.75 | $0.40 | $1.25 |
| 0525 | Luminaire & bracket arm- aluminum, furnish & install new luminaire and arm on new/existing pole (0715-5-31) | EACH | 4 | $1,180.00 | $3,900.00 | $1,298.00 | $1,215.40 | $1,919.00 | $1,448.87 |
| 0530 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 4 | $542.00 | $850.00 | $596.20 | $558.26 | $1,186.00 | $915.00 |
| 0535 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 1,247 | $38.70 | $61.00 | $42.57 | $39.86 | $49.25 | $26.10 |
| 0540 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 1 | $28,800 | $18,000 | $31,680 | $29,664 | $39,370 | $23,387 |
| 0545 | Signal cable, remove- intersection (0632-7-6) | PI | 1 | $2,160.00 | $3,250.00 | $2,376.00 | $2,224.80 | $2,606.00 | $4,807.00 |
| 0550 | Span wire assembly, F&I, two point, box or drop box (0634-4153) | PI | 1 | $32,533 | $16,750 | $35,787 | $33,509 | $17,887 | $13,080 |
| 0555 | Pull & splice box, F&I, 17" X 30" cover size (0635-2-14) | EACH | 35 | $1,066.70 | $2,450.00 | $1,173.37 | $1,098.70 | $2,410.00 | $1,643.00 |
| 0560 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 1 | $4,386.90 | $7,200.00 | $4,825.59 | $4,518.51 | $6,713.00 | $2,966.00 |
| 0565 | Electrical power service, F&I, underground, meter not required (0639-1123) | AS | 1 | $2,840.20 | $4,000.00 | $3,124.22 | $2,925.41 | $6,025.00 | $2,387.00 |
| 0570 | Electrical service wire, & install (0639-2-1) | LF | 299 | $7.70 | $6.75 | $8.47 | $7.93 | $10.50 | $11.95 |
| 0575 | Electrical service wire, (0639-2-6) | LF | 140 | $1.90 | $2.70 | $2.09 | $1.96 | $2.60 | $2.85 |
| 0580 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 1 | $2,346.80 | $2,100.00 | $2,581.48 | $2,417.20 | $2,371.00 | $1,802.00 |
| 0585 | Prestressed concrete pole, complete pole removal- pole 30' and greater (0641-2-80) | EACH | 4 | $12,481 | $29,000 | $13,729 | $12,855 | $11,490 | $23,012 |
| 0590 | Aluminum signals pole, (0646-1-11) | EACH | 7 | $2,593.50 | $3,850.00 | $2,852.85 | $2,671.31 | $3,367.00 | $2,620.00 |
| 0595 | Aluminum signals pole, remove (0646-1-60) | EACH | 4 | $300.10 | $875.00 | $330.11 | $309.10 | $652.00 | $478.00 |
| 0600 | Steel strain pole, F&I, type PS- X (0649-1-17) | EACH | 4 | $56,696 | $5,700.00 | $62,365 | $58,397 | $75,372 | $82,728 |
| 0605 | Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14) | AS | 30 | $2,057.50 | $2,400.00 | $2,263.25 | $2,119.23 | $2,452.00 | $1,995.00 |
| 0610 | Vehicular traffic signal, furnish & install aluminum, 5 section cluster, 1 way (0650-1-19) | AS | 2 | $3,237.50 | $3,880.00 | $3,561.25 | $3,334.63 | $3,528.00 | $3,114.00 |
| 0615 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 8 | $986.80 | $1,050.00 | $1,085.48 | $1,016.40 | $1,165.00 | $1,114.00 |
| 0620 | Loop detector inductive, F&I, type 9 (0660-1109) | EACH | 11 | $380.10 | $800.00 | $418.11 | $391.50 | $805.00 | $1,143.00 |
| 0625 | Loop assembly, F&I, type F (0660-2106) | AS | 20 | $2,000.10 | $2,520.00 | $2,200.11 | $2,060.10 | $2,175.00 | $2,841.00 |
| 0630 | Vehicle detection system- microwave, furnish & install cabinet equipment (0660-3-11) | EACH | 1 | $10,800 | $14,500 | $10,831 | $10,142 | $9,100.00 | $14,100 |
| 0635 | Vehicle detection system- microwave, furnish & install, above ground equipment (0660-3-12) | EACH | 1 | $13,440 | $18,000 | $14,215 | $13,311 | $11,300 | $17,500 |
| 0640 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 8 | $220.10 | $440.00 | $242.11 | $226.70 | $351.00 | $421.00 |
| 0645 | Traffic controller assembly, F&I, NEMA W/standard lock, 1 preemption (0670-5161) | AS | 1 | $71,850 | $69,000 | $62,920 | $58,916 | $62,578 | $55,341 |
| 0650 | Traffic controller assembly, remove controller with (0670-5600) | AS | 1 | $480.10 | $2,100.00 | $528.00 | $494.50 | $978.00 | $1,250.00 |
| 0655 | ITS CCTV camera, non- pressurized, IP, high definition (0682-1173) | EACH | 1 | $6,954.00 | $10,800 | $7,649.40 | $7,162.62 | $5,800.00 | $9,000.00 |
| 0660 | Managed field ethernet switch, furnish & install (0684-1-1) | EACH | 1 | $4,200.00 | $6,000.00 | $4,620.00 | $4,326.00 | $3,800.00 | $5,785.00 |
| 0665 | Remote power management rpmu, furnish and install (0685-2-1) | EACH | 1 | $8,333.70 | $1,500.00 | $9,167.07 | $8,583.71 | $2,045.00 | $1,240.00 |
| 0670 | Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201) | EACH | 10 | $606.70 | $1,500.00 | $667.37 | $624.90 | $1,095.00 | $870.00 |
| 0675 | Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22) | EACH | 4 | $2,853.50 | $5,312.00 | $3,138.85 | $2,939.11 | $8,586.00 | $4,926.15 |
| 0680 | Fiber optic cable, F&I, underground,13-48 fibers (0633-1122) | LF | 900 | $4.50 | $6.10 | $4.95 | $4.64 | $3.80 | $7.33 |
| 0685 | Fiber optic connection, install, splice (0633-2-31) | EACH | 96 | $52.80 | $72.00 | $58.08 | $54.38 | $45.00 | $68.20 |
| 0690 | Fiber optic connection hardware, F&I, splice (0633-3-11) | EACH | 2 | $1,470.00 | $2,150.00 | $1,617.00 | $1,514.10 | $1,360.00 | $2,103.00 |
| 0695 | Fiber optic connection hardware, F&I, splice tray (0633-3-12) | EACH | 8 | $60.00 | $79.50 | $66.00 | $61.80 | $50.00 | $73.86 |
| 0700 | Pull & splice box, F&I, 17" X 30" cover size (0635-2-14) | EACH | 6 | $1,122.10 | $2,700.00 | $1,234.31 | $1,155.76 | $3,023.00 | $1,643.00 |
| 0705 | Pull & splice box, F&I, 30" X 48" cover size (0635-2-15) | EACH | 2 | $4,954.90 | $6,225.00 | $5,450.39 | $5,103.55 | $5,281.00 | $3,915.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of August 27, 2025. Compiled by Mirage Metrics.