FDOT contract T4745 bid tabulation
SR 882 FOREST HILL BLVD) FROM E OF LAKE CLARKE DR TO US1 (DIXIE HWY). Let by Florida DOT on July 29, 2026, Palm Beach, District 4. 6 bids received; low bid $5,317,094 by Florida Engineering & Development Corp.
- Owner
- Florida DOT
- Letting
- 29 JUL 2026
- Pay items
- 192
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Florida Engineering & Development Corp | $5,317,094 | Low |
| 2 | The Stout Group LLC | $5,422,489 | +2.0% |
| 3 | Ranger Construction Industries, Inc. | $5,788,888 | +9.0% |
| 4 | Community Asphalt Corp. | $5,797,094 | +9.0% |
| 5 | Sice Inc | $5,889,874 | +11% |
| 6 | Aum Construction Inc. | $5,999,000 | +13% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Florida Engineering & Development Corp | 2. The Stout Group LLC | 3. Ranger Construction Industries, Inc. | 4. Community Asphalt Corp. | 5. Sice Inc | 6. Aum Construction Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $267,938 | $275,000 | $325,000 | $375,000 | $237,189 | $300,000 |
| 0010 | Mobilization (0101-1) | LS | 1 | $262,857 | $275,000 | $245,000 | $200,000 | $313,996 | $250,000 |
| 0015 | Maintenance of traffic (0102-1) | DA | 1 | $214,105 | $270,000 | $362,500 | $250,000 | $128,711 | $210,000 |
| 0020 | Maintenance of traffic (0102-1) | DA | 1 | $213,928 | $270,000 | $294,500 | $200,000 | $157,313 | $170,000 |
| 0025 | Special detour- temporary pavement (0102-2200) | SY | 1 | $3,757.18 | $16,000 | $6,596.74 | $1.00 | $10,437 | $25,000 |
| 0030 | Special detour- temporary earthwork/base (0102-2300) | CY | 1 | $5,426.54 | $15,000 | $5,560.00 | $1.00 | $10,564 | $24,155 |
| 0035 | Commercial material for temporary driveway maintenance (0102-3) | CY | 30.10 | $189.04 | $35.00 | $365.50 | $250.00 | $451.46 | $200.00 |
| 0040 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $2,344.04 | $3,500.00 | $2,300.00 | $1.00 | $2,807.02 | $32,000 |
| 0045 | Traffic control officer (0102-14) | HR | 624 | $86.29 | $90.00 | $85.30 | $90.00 | $111.11 | $75.00 |
| 0050 | Work zone sign (0102-60) | ED | 19,584 | $0.20 | $0.19 | $0.23 | $0.20 | $0.22 | $0.25 |
| 0055 | Business sign (0102-61) | EACH | 5 | $37.56 | $45.00 | $42.10 | $37.00 | $52.63 | $60.00 |
| 0060 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 350 | $39.59 | $39.00 | $51.20 | $0.13 | $58.98 | $55.00 |
| 0065 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 25,880 | $0.10 | $0.15 | $0.11 | $0.10 | $0.13 | $0.20 |
| 0070 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 13,530 | $0.05 | $0.10 | $0.06 | $0.05 | $0.07 | $0.15 |
| 0075 | Arrow board / advance warning arrow panel (0102-76) | ED | 1,159 | $5.08 | $5.00 | $5.70 | $5.00 | $5.67 | $6.00 |
| 0080 | Temporary raised/retroreflective pavement marker, type B (0102-78-2) | EACH | 1,265 | $4.06 | $5.00 | $4.55 | $4.00 | $5.85 | $5.25 |
| 0085 | Portable changeable message sign, temporary (0102-99) | ED | 1,468 | $10.15 | $10.00 | $11.35 | $10.00 | $10.64 | $12.00 |
| 0090 | Temporary signalization and maintenance, intersection (0102-104) | ED | 1,936 | $7.81 | $8.00 | $9.40 | $10.00 | $22.27 | $12.00 |
| 0095 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 1,936 | $7.81 | $8.00 | $9.40 | $10.00 | $22.27 | $12.00 |
| 0100 | Existing ITS maintenance (0102-112) | DA | 242 | $160.23 | $160.00 | $154.60 | $150.00 | $146.20 | $125.00 |
| 0105 | Sediment barrier (0104-10-3) | LF | 595 | $3.24 | $6.00 | $6.85 | $18.00 | $5.85 | $5.00 |
| 0110 | Inlet protection system (0104-18) | EACH | 28 | $161.97 | $150.00 | $190.00 | $450.00 | $233.92 | $150.00 |
| 0115 | Litter removal (0107-1) | ACRE | 53.80 | $112.05 | $5.00 | $73.90 | $25.00 | $100.18 | $25.00 |
| 0120 | Mowing (0107-2) | ACRE | 37.42 | $181.53 | $5.00 | $96.70 | $52.00 | $144.03 | $50.00 |
| 0125 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $11,624 | $15,000 | $13,000 | $75,000 | $16,608 | $25,000 |
| 0130 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $11,624 | $15,000 | $13,000 | $50,000 | $16,608 | $15,000 |
| 0135 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $38,203 | $10,000 | $21,900 | $150,000 | $35,147 | $15,000 |
| 0140 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $29,677 | $30,000 | $40,800 | $108,175 | $35,147 | $30,000 |
| 0145 | Selective clearing and areas with trees to remain (0110-2-2) | ACRE | 0.10 | $16,485 | $100,000 | $38,700 | $71,513 | $55,307 | $200,000 |
| 0150 | Removal of existing concrete (0110-4-10) | SY | 1,810 | $35.79 | $30.00 | $22.00 | $27.54 | $47.24 | $35.00 |
| 0155 | Tree protection barrier (0110-21) | LF | 785 | $11.43 | $6.00 | $13.65 | $10.00 | $8.77 | $12.00 |
| 0160 | Tree root and branch pruning (0110-22) | EACH | 19 | $3,553.30 | $550.00 | $3,980.00 | $3,500.00 | $4,327.49 | $4,000.00 |
| 0165 | Regular excavation (0120-1) | CY | 1,410 | $50.35 | $30.00 | $40.15 | $47.46 | $89.45 | $70.00 |
| 0170 | Embankment (0120-6) | CY | 402 | $90.94 | $30.00 | $16.40 | $91.81 | $68.22 | $130.00 |
| 0175 | Regular excavation (3-R projects only) (0120-71) | LS | 1 | $1,012.44 | $5,000.00 | $3,300.00 | $10,000 | $543.13 | $5,000.00 |
| 0180 | Type B stabilization (0160-4) | SY | 1,684 | $23.00 | $15.00 | $27.55 | $1.00 | $7.47 | $32.00 |
| 0185 | Optional base, base group 06 (0285-706) | SY | 596 | $27.62 | $40.00 | $31.90 | $50.00 | $41.01 | $43.00 |
| 0190 | Optional base, base group 11 (0285-711) | SY | 844 | $62.73 | $60.00 | $46.25 | $50.00 | $59.49 | $90.00 |
| 0195 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 20,131 | $3.81 | $3.00 | $4.72 | $2.00 | $2.61 | $4.50 |
| 0200 | Milling existing asphalt pavement, 1 1/4" avg depth (0327-70-12) | SY | 22,075 | $3.55 | $2.90 | $3.23 | $2.00 | $2.61 | $4.75 |
| 0205 | Milling existing asphalt pavement, 3/4" avg depth (0327-70-19) | SY | 186 | $3.55 | $20.00 | $2.42 | $20.00 | $2.61 | $45.00 |
| 0210 | Superpave asphaltic conc, traffic B (0334-1-12) | TN | 204.80 | $236.32 | $200.00 | $375.25 | $195.00 | $395.05 | $330.00 |
| 0215 | Asphalt concrete friction course,traffic B, FC-9.5, PG 76-22 (0337-7-80) | TN | 3,297.10 | $219.09 | $215.00 | $196.50 | $199.00 | $285.77 | $245.00 |
| 0220 | Inlets, barrier wall, rigid, curb & gutter, <=10' (0425-1881) | EACH | 2 | $7,319.45 | $15,000 | $9,550.00 | $12,171 | $8,187.13 | $13,000 |
| 0225 | Inlets, closed flume (0425-1910) | EACH | 1 | $9,510.51 | $13,000 | $12,100 | $14,188 | $5,847.95 | $14,500 |
| 0230 | Manhole, adjust (0425-5) | EACH | 2 | $1,781.36 | $900.00 | $909.75 | $1,200.00 | $1,754.39 | $1,500.00 |
| 0235 | Manhole, adjust, utilities (0425-5-1) | EACH | 15 | $948.27 | $900.00 | $966.50 | $1,200.00 | $1,754.39 | $1,500.00 |
| 0240 | Valve boxes, adjust (0425-6) | EACH | 36 | $843.43 | $700.00 | $881.25 | $1,200.00 | $1,169.59 | $1,000.00 |
| 0245 | Pipe culvert,optional material,round, 24"S/CD (0430-175124) | LF | 9 | $401.19 | $1,200.00 | $1,140.00 | $225.00 | $526.32 | $575.00 |
| 0250 | Pipe culvert,optional material,other-elip/arch, (0430-175218) | LF | 7 | $391.76 | $1,500.00 | $682.25 | $460.00 | $701.75 | $575.00 |
| 0255 | Pipe culvert, opt material, shape - elip/arch, 42"S/CD (0430-175242) | LF | 4 | $1,000.44 | $3,000.00 | $2,740.00 | $1,200.00 | $1,169.59 | $1,450.00 |
| 0260 | Mitered end section, optional round, 24" CD (0430-982129) | EACH | 1 | $5,109.60 | $8,000.00 | $4,550.00 | $2,500.00 | $4,678.36 | $11,000 |
| 0265 | Mitered end section, optional - elliptical / arch, 18" CD (0430-982625) | EACH | 1 | $5,544.12 | $8,000.00 | $4,320.00 | $2,400.00 | $4,678.36 | $10,000 |
| 0270 | Mitered end section, optional - elliptical / arch, 42" CD (0430-982640) | EACH | 1 | $10,000 | $10,000 | $13,100 | $6,400.00 | $8,187.13 | $17,250 |
| 0275 | Concrete curb & gutter, type E (0520-1-7) | LF | 308 | $36.50 | $40.00 | $72.20 | $66.75 | $31.58 | $55.00 |
| 0280 | Concrete curb & gutter, type F (0520-1-10) | LF | 1,383 | $42.05 | $43.00 | $73.00 | $100.00 | $31.58 | $57.00 |
| 0285 | Concrete curb, type D (0520-2-4) | LF | 49 | $47.07 | $25.00 | $25.95 | $68.00 | $60.88 | $35.00 |
| 0290 | Shoulder concrete barrier, 38" or 44" height (0521-72-40) | LF | 260 | $327.60 | $450.00 | $405.75 | $552.00 | $374.27 | $450.00 |
| 0295 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 408 | $52.06 | $63.00 | $76.40 | $150.42 | $76.18 | $85.00 |
| 0300 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 1,024 | $71.75 | $78.00 | $94.30 | $171.79 | $108.57 | $105.00 |
| 0305 | Concrete ditch pavement, non reinforced, 4" (0524-1-2) | SY | 23 | $65.62 | $63.00 | $130.80 | $238.47 | $143.86 | $150.00 |
| 0310 | Pavers, architectural, remove existing and reinstall (0526-1101) | SY | 130 | $103.70 | $95.00 | $113.70 | $280.12 | $473.68 | $100.00 |
| 0315 | Detectable warnings (0527-2) | SF | 555 | $36.29 | $35.00 | $44.55 | $44.06 | $46.21 | $45.00 |
| 0320 | Performance turf, sod (0570-1-2) | SY | 2,856 | $3.30 | $8.00 | $8.55 | $10.00 | $5.56 | $15.00 |
| 0325 | Irrigation system- modify existing system (0590-70-5) | LS | 1 | $25,914 | $50,000 | $29,000 | $30,000 | $29,854 | $30,000 |
| 0330 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 1.35 | $2,131.98 | $1,600.00 | $2,380.00 | $2,089.09 | $1,871.35 | $2,750.00 |
| 0335 | Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102) | GM | 0.15 | $2,842.61 | $1,800.00 | $3,120.00 | $2,745.10 | $2,105.26 | $3,650.00 |
| 0340 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 413 | $1.52 | $2.00 | $1.71 | $1.50 | $2.34 | $2.00 |
| 0345 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 185 | $1.62 | $3.00 | $1.82 | $1.60 | $3.51 | $2.10 |
| 0350 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 767 | $1.73 | $4.00 | $1.93 | $1.70 | $4.68 | $2.25 |
| 0355 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 0.18 | $558.39 | $1,000.00 | $625.50 | $550.00 | $1,169.59 | $1,000.00 |
| 0360 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.10 | $701.24 | $1,000.00 | $738.50 | $649.48 | $1,169.59 | $2,000.00 |
| 0365 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 37 | $45.69 | $85.00 | $51.20 | $45.00 | $99.42 | $60.00 |
| 0370 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 54 | $40.61 | $45.00 | $45.50 | $40.00 | $52.63 | $55.00 |
| 0375 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 0.52 | $2,131.99 | $1,600.00 | $2,350.00 | $2,067.57 | $1,871.35 | $2,750.00 |
| 0380 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 139 | $1.62 | $3.00 | $1.82 | $1.60 | $3.51 | $3.00 |
| 0385 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.05 | $710.67 | $1,000.00 | $707.50 | $622.22 | $1,169.59 | $3,000.00 |
| 0390 | Partnering, DO not bid (0999-16) | LS | 1 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 |
| 0395 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $23,842 | $23,842 | $23,842 | $23,842 | $23,842 | $23,842 |
| 0400 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $36,079 | $36,079 | $36,079 | $36,079 | $36,079 | $36,079 |
| 0405 | Local agency initial amount (DO not bid) (0999-26) | LS | 1 | $2,190.00 | $2,190.00 | $2,190.00 | $2,190.00 | $2,190.00 | $2,190.00 |
| 0410 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 48 | $583.76 | $575.00 | $622.00 | $552.45 | $672.51 | $800.00 |
| 0415 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 3 | $2,436.55 | $2,400.00 | $1,480.00 | $1,311.84 | $2,807.02 | $2,500.00 |
| 0420 | Single column ground sign assembly, remove (0700-1600) | EACH | 48 | $35.53 | $35.00 | $131.90 | $117.12 | $40.94 | $50.00 |
| 0425 | Sign panel, furnish & install overhead mount, 12-20 SF (0700-3202) | EACH | 4 | $1,725.89 | $1,700.00 | $2,070.00 | $1,834.45 | $1,988.30 | $1,200.00 |
| 0430 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 1 | $35.53 | $35.00 | $395.50 | $351.35 | $40.94 | $100.00 |
| 0435 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 9 | $101.52 | $100.00 | $127.10 | $111.00 | $116.96 | $150.00 |
| 0440 | Raised pavement marker, type B (0706-1-3) | EACH | 1,160 | $4.06 | $5.00 | $4.55 | $4.00 | $5.85 | $5.25 |
| 0445 | Painted pavement markings, surface (0710-90) | LS | 1 | $15,085 | $20,000 | $16,900 | $14,859 | $23,392 | $20,000 |
| 0450 | Painted pavement markings, surface (0710-90) | LS | 1 | $8,122.84 | $10,000 | $9,100.00 | $8,001.00 | $11,696 | $10,500 |
| 0455 | Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102) | GM | 0.09 | $6,649.18 | $7,500.00 | $7,000.00 | $6,157.18 | $8,771.93 | $8,500.00 |
| 0460 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 1,091 | $2.94 | $4.00 | $3.30 | $2.90 | $4.68 | $3.75 |
| 0465 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 532 | $4.44 | $5.00 | $4.97 | $4.37 | $5.85 | $5.75 |
| 0470 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 1,599 | $5.89 | $6.00 | $6.60 | $5.80 | $7.02 | $7.60 |
| 0475 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.23 | $1,870.04 | $3,500.00 | $2,040.00 | $1,793.10 | $4,093.57 | $3,000.00 |
| 0480 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 64 | $115.74 | $250.00 | $129.60 | $114.00 | $292.40 | $150.00 |
| 0485 | Thermoplastic, standard, arrow (0711-11170) | EACH | 88 | $51.78 | $90.00 | $58.00 | $51.00 | $105.26 | $67.00 |
| 0490 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 280 | $4.44 | $5.00 | $4.97 | $4.37 | $5.85 | $5.70 |
| 0495 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.04 | $1,870.00 | $3,500.00 | $1,750.00 | $1,535.00 | $4,093.57 | $5,000.00 |
| 0500 | Thermoplastic, preformed, white, solid, 12" for crosswalk (0711-14123) | LF | 1,975 | $7.51 | $10.00 | $8.40 | $7.40 | $11.70 | $9.60 |
| 0505 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 2,227 | $15.03 | $16.00 | $16.85 | $14.80 | $18.71 | $19.00 |
| 0510 | Thermoplastic, preformed, white with black contrast on concrete pavement, message symbol (0711-14560) | EACH | 6 | $1,561.42 | $800.00 | $1,750.00 | $1,538.00 | $935.67 | $2,000.00 |
| 0515 | Thermoplastic, preformed, white with black contrast, arrow on concrete surface (0711-14570) | EACH | 6 | $703.55 | $700.00 | $788.00 | $693.00 | $818.71 | $900.00 |
| 0520 | Thermoplastic, preformed, color route shield (0711-14660) | EACH | 12 | $1,858.88 | $3,500.00 | $2,080.00 | $1,831.00 | $4,093.57 | $2,400.00 |
| 0525 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 3.40 | $4,979.69 | $5,000.00 | $5,570.00 | $4,899.24 | $5,847.95 | $6,375.00 |
| 0530 | Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102) | GM | 0.11 | $6,639.56 | $5,500.00 | $7,180.00 | $6,310.53 | $6,432.75 | $8,500.00 |
| 0535 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 1.56 | $1,245.69 | $3,000.00 | $1,390.00 | $1,226.21 | $3,508.77 | $1,600.00 |
| 0540 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 2.40 | $4,416.24 | $5,000.00 | $4,930.00 | $4,339.11 | $5,847.95 | $5,660.00 |
| 0545 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 0.82 | $1,104.57 | $3,000.00 | $1,240.00 | $1,088.00 | $3,508.77 | $1,500.00 |
| 0550 | Permanent tape, white, solid, 6" for concrete bridges (0713-103101) | GM | 0.09 | $45,685 | $30,000 | $49,500 | $43,548 | $35,088 | $58,500 |
| 0555 | Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181) | GM | 0.11 | $11,421 | $10,000 | $12,000 | $10,514 | $11,696 | $14,625 |
| 0560 | Permanent tape, yellow, solid, for concrete bridges (0713-103201) | GM | 0.09 | $45,685 | $30,000 | $49,500 | $43,548 | $35,088 | $58,500 |
| 0565 | Preformed/permanent tape, remove (0713-107) | SF | 2,454 | $2.54 | $2.50 | $2.84 | $2.50 | $2.92 | $3.25 |
| 0570 | Conduit, furnish & install, open trench (0630-2-11) | LF | 1,852 | $14.79 | $15.00 | $20.10 | $18.78 | $21.21 | $20.00 |
| 0575 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 1,853 | $31.52 | $32.00 | $27.25 | $25.43 | $47.00 | $30.00 |
| 0580 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 50 | $1,357.41 | $1,500.00 | $882.50 | $824.00 | $1,283.92 | $1,500.00 |
| 0585 | Electrical power service, F&I, underground, meter furnished by power company (0639-1121) | AS | 1 | $5,824.05 | $5,900.00 | $7,370.00 | $6,885.35 | $4,711.70 | $7,500.00 |
| 0590 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 3 | $5,824.05 | $5,900.00 | $4,600.00 | $4,292.66 | $4,711.70 | $7,500.00 |
| 0595 | Electrical power service, remove underground (0639-1620) | AS | 1 | $585.60 | $600.00 | $527.50 | $492.47 | $1,010.53 | $750.00 |
| 0600 | Electrical service wire, & install (0639-2-1) | LF | 709 | $9.72 | $10.00 | $15.25 | $14.26 | $15.17 | $15.00 |
| 0605 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 1 | $2,484.74 | $2,500.00 | $2,440.00 | $2,278.29 | $3,171.95 | $2,000.00 |
| 0610 | Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60) | EACH | 1 | $780.80 | $800.00 | $1,050.00 | $984.93 | $673.68 | $750.00 |
| 0615 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 14,049 | $2.86 | $3.00 | $2.87 | $2.68 | $2.75 | $3.00 |
| 0620 | Lighting conductors, remove & dispose, contractor owns (0715-1-60) | LF | 5,564 | $0.39 | $0.50 | $0.98 | $0.91 | $1.75 | $0.20 |
| 0625 | Luminaire & bracket arm- aluminum, furnish & install new luminaire and arm on new/existing pole (0715-5-31) | EACH | 6 | $2,441.15 | $2,500.00 | $2,680.00 | $2,503.24 | $1,851.46 | $1,200.00 |
| 0630 | Luminaire & bracket arm, luminaire and arm; pole remains (0715-5-51) | EACH | 7 | $390.41 | $400.00 | $435.25 | $406.32 | $224.56 | $250.00 |
| 0635 | Load center, F&I, secondary voltage (0715-7-11) | EACH | 4 | $15,330 | $16,000 | $18,900 | $17,658 | $12,456 | $18,000 |
| 0640 | Load center, remove, primary voltage (0715-7-42) | EACH | 1 | $1,171.21 | $1,200.00 | $1,120.00 | $1,046.94 | $1,932.16 | $750.00 |
| 0645 | Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211) | EACH | 2 | $1,598.99 | $1,600.00 | $2,140.00 | $1,997.74 | $1,350.53 | $1,250.00 |
| 0650 | Light pole complete, F&I, standard pole standard foundation, 30' mounting height, 8' arm length (0715-61111) | EACH | 11 | $8,976.65 | $9,000.00 | $9,360.00 | $8,737.56 | $8,915.44 | $7,300.00 |
| 0655 | Light pole complete, F&I, standard pole standard foundation, 30' mounting height, 10' arm length (0715-61121) | EACH | 1 | $8,353.13 | $8,400.00 | $9,510.00 | $8,879.28 | $7,813.72 | $7,400.00 |
| 0660 | Light pole complete, F&I, standard pole standard foundation, 30' mounting height, 15' arm length (0715-61152) | EACH | 1 | $8,504.00 | $8,600.00 | $7,750.00 | $7,238.96 | $6,521.64 | $7,500.00 |
| 0665 | Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 10' arm length (0715-61321) | EACH | 7 | $9,566.97 | $9,600.00 | $11,300 | $10,510 | $9,352.78 | $9,000.00 |
| 0670 | Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 15' arm length (0715-61352) | EACH | 3 | $9,717.85 | $9,800.00 | $9,500.00 | $8,870.06 | $7,853.64 | $9,200.00 |
| 0675 | Light pole complete, remove pole and foundation (0715-69000) | EACH | 8 | $780.80 | $800.00 | $1,050.00 | $984.93 | $1,550.88 | $1,500.00 |
| 0680 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 34 | $820.86 | $850.00 | $1,010.00 | $939.10 | $987.08 | $750.00 |
| 0685 | Conduit, furnish & install, open trench (0630-2-11) | LF | 103 | $24.43 | $25.00 | $14.65 | $13.70 | $23.25 | $30.00 |
| 0690 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 2,526 | $35.39 | $40.00 | $28.60 | $26.73 | $59.32 | $60.00 |
| 0695 | Conduit, furnish & install, aboveground (0630-2-14) | LF | 147 | $47.04 | $50.00 | $46.05 | $42.99 | $77.79 | $70.00 |
| 0700 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 4 | $9,047.45 | $9,500.00 | $13,400 | $12,486 | $15,506 | $20,000 |
| 0705 | Signal cable, remove- intersection (0632-7-6) | PI | 3 | $1,366.41 | $1,400.00 | $1,650.00 | $1,539.65 | $2,021.05 | $500.00 |
| 0710 | Fiber optic cable, F&I, underground,2-12 fibers (0633-1121) | LF | 112 | $4.29 | $5.00 | $3.82 | $3.57 | $3.92 | $4.50 |
| 0715 | Fiber optic connection, install, splice (0633-2-31) | EACH | 4 | $64.09 | $65.00 | $56.70 | $52.94 | $58.48 | $65.00 |
| 0720 | Fiber optic connection hardware, F&I, splice enclosure (0633-3-11) | EACH | 1 | $1,570.27 | $1,600.00 | $1,790.00 | $1,669.43 | $1,432.75 | $1,600.00 |
| 0725 | Fiber optic connection hardware, F&I, splice tray (0633-3-12) | EACH | 1 | $70.50 | $71.00 | $87.20 | $81.46 | $64.33 | $100.00 |
| 0730 | Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16) | EACH | 1 | $2,877.77 | $3,000.00 | $2,140.00 | $1,993.57 | $2,625.73 | $3,000.00 |
| 0735 | Fiber optic cable locator (0633-6) | DA | 242 | $160.23 | $160.00 | $158.20 | $147.74 | $146.20 | $50.00 |
| 0740 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 1 | $2,333.87 | $2,500.00 | $2,410.00 | $2,251.77 | $3,465.16 | $2,500.00 |
| 0745 | Pull & splice box, F&I, 17" X 30" cover size (0635-2-14) | EACH | 68 | $1,555.75 | $1,600.00 | $1,570.00 | $1,465.86 | $2,518.16 | $1,800.00 |
| 0750 | Pull & splice box, install (0635-2-30) | EACH | 1 | $1,055.12 | $1,100.00 | $977.25 | $912.44 | $2,350.88 | $1,200.00 |
| 0755 | Junction box, furnish & install, aerial (0635-3-11) | EACH | 2 | $962.79 | $1,000.00 | $706.75 | $659.87 | $1,169.59 | $1,500.00 |
| 0760 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 3 | $5,412.58 | $5,500.00 | $4,180.00 | $3,906.90 | $4,336.26 | $7,500.00 |
| 0765 | Electrical power service, remove underground (0639-1620) | AS | 3 | $488.00 | $500.00 | $527.50 | $492.47 | $1,595.32 | $750.00 |
| 0770 | Electrical service wire, & install (0639-2-1) | LF | 276 | $9.72 | $10.00 | $15.25 | $14.26 | $12.91 | $10.00 |
| 0775 | Electrical service wire, (0639-2-6) | LF | 49 | $0.40 | $0.50 | $0.97 | $0.90 | $2.34 | $1.00 |
| 0780 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 3 | $2,484.74 | $2,500.00 | $2,440.00 | $2,278.29 | $3,171.95 | $2,500.00 |
| 0785 | Prestressed concrete pole, complete pole removal- pole 30' and greater (0641-2-80) | EACH | 7 | $8,390.51 | $8,500.00 | $3,690.00 | $3,441.56 | $8,187.13 | $2,000.00 |
| 0790 | Aluminum signals pole, (0646-1-11) | EACH | 16 | $2,290.20 | $2,300.00 | $3,060.00 | $2,855.24 | $1,927.76 | $1,800.00 |
| 0795 | Aluminum signals pole, furnish install pedestrian detector post (0646-1-12) | EACH | 1 | $2,224.37 | $2,300.00 | $2,320.00 | $2,167.51 | $1,117.23 | $1,500.00 |
| 0800 | Aluminum signals pole, remove (0646-1-60) | EACH | 4 | $488.00 | $500.00 | $527.75 | $492.72 | $505.26 | $500.00 |
| 0805 | Steel mast arm assembly, and install, single arm 50' (0649-21-6) | EACH | 1 | $69,306 | $70,000 | $78,900 | $73,662 | $60,291 | $72,000 |
| 0810 | Steel mast arm assembly, and install, double arm 50'-40' (0649-21-8) | EACH | 1 | $96,541 | $97,000 | $115,800 | $108,079 | $82,303 | $102,000 |
| 0815 | Steel mast arm assembly, and install, single arm 60' (0649-21-10) | EACH | 1 | $75,441 | $76,000 | $88,500 | $82,637 | $68,217 | $80,000 |
| 0820 | Steel mast arm assembly, and install, double arm 60'-40' (0649-21-12) | EACH | 1 | $101,207 | $102,000 | $117,600 | $109,811 | $80,339 | $102,000 |
| 0825 | Steel mast arm assembly, and install, single arm 70' (0649-21-15) | EACH | 1 | $93,424 | $94,000 | $98,500 | $91,976 | $72,066 | $90,000 |
| 0830 | Steel mast arm assembly, and install, single arm 78' (0649-21-21) | EACH | 1 | $113,319 | $115,000 | $122,400 | $114,269 | $89,421 | $105,000 |
| 0835 | Steel mast arm assembly, remove, deep foundation- bolt on attachment (0649-26-5) | EACH | 1 | $16,934 | $17,000 | $16,100 | $15,043 | $8,880.38 | $5,000.00 |
| 0840 | Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14) | AS | 27 | $1,653.85 | $1,700.00 | $2,550.00 | $2,376.96 | $1,670.76 | $1,900.00 |
| 0845 | Vehicular traffic signal, furnish & install aluminum, 4 section, 1 way (0650-1-16) | AS | 1 | $1,970.68 | $2,000.00 | $2,920.00 | $2,727.96 | $1,939.44 | $2,500.00 |
| 0850 | Vehicular traffic signal, furnish & install aluminum, 5 section cluster, 1 way (0650-1-19) | AS | 2 | $2,697.80 | $2,800.00 | $4,310.00 | $4,024.47 | $2,632.22 | $3,500.00 |
| 0855 | Vehicular traffic signal, remove- poles to remain (0650-1-60) | AS | 6 | $292.80 | $300.00 | $428.50 | $400.12 | $505.26 | $500.00 |
| 0860 | Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109) | EACH | 6 | $728.03 | $800.00 | $543.75 | $507.71 | $702.99 | $650.00 |
| 0865 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 16 | $967.84 | $1,000.00 | $1,130.00 | $1,058.02 | $1,017.29 | $1,500.00 |
| 0870 | Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60) | AS | 4 | $195.20 | $200.00 | $254.10 | $237.24 | $449.12 | $500.00 |
| 0875 | Loop detector inductive, F&I, type 9 (0660-1109) | EACH | 12 | $550.22 | $600.00 | $768.00 | $717.00 | $1,086.67 | $650.00 |
| 0880 | Loop assembly, F&I, type F (0660-2106) | AS | 78 | $1,769.93 | $1,800.00 | $538.75 | $503.07 | $1,722.81 | $1,800.00 |
| 0885 | Vehicle detection system- furnish & install cabinet equipment (0660-4-11) | EACH | 1 | $20,513 | $21,000 | $28,700 | $26,760 | $19,481 | $19,500 |
| 0890 | Vehicle detection system- furnish & install above ground equipment (0660-4-12) | EACH | 2 | $4,850.48 | $5,000.00 | $7,610.00 | $7,105.94 | $4,367.57 | $5,500.00 |
| 0895 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 17 | $411.03 | $500.00 | $714.25 | $714.58 | $587.13 | $300.00 |
| 0900 | Pedestrian detector, furnish & install, accessible (0665-1-12) | EACH | 1 | $1,632.56 | $1,700.00 | $2,480.00 | $2,316.54 | $1,647.33 | $1,200.00 |
| 0905 | Pedestrian detector, remove- pole/pedestal to remain (0665-1-60) | EACH | 5 | $97.60 | $100.00 | $142.30 | $132.85 | $336.84 | $100.00 |
| 0910 | Traffic controller assembly, F&I, NEMA W/standard lock, 2 preemption (0670-5162) | AS | 1 | $72,550 | $73,000 | $98,100 | $91,566 | $70,135 | $75,000 |
| 0915 | Traffic controller assembly, remove controller with (0670-5600) | AS | 1 | $1,366.41 | $1,400.00 | $2,000.00 | $1,867.26 | $1,887.72 | $750.00 |
| 0920 | Traffic controller, modify (0671-2-40) | EACH | 3 | $1,904.50 | $2,000.00 | $3,800.00 | $3,545.55 | $421.05 | $2,500.00 |
| 0925 | Traffic signal controller cabinet, adjust/modify (0676-1500) | EACH | 3 | $1,904.50 | $2,000.00 | $2,520.00 | $2,349.29 | $673.68 | $5,000.00 |
| 0930 | ITS CCTV camera, non- pressurized, IP, high definition (0682-1173) | EACH | 2 | $6,402.87 | $6,500.00 | $12,500 | $11,698 | $6,264.49 | $6,500.00 |
| 0935 | Managed field ethernet switch, furnish & install (0684-1-1) | EACH | 1 | $3,713.69 | $3,800.00 | $4,350.00 | $4,062.96 | $3,368.09 | $4,500.00 |
| 0940 | Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201) | EACH | 11 | $1,105.22 | $1,200.00 | $1,100.00 | $1,025.68 | $931.62 | $1,200.00 |
| 0945 | Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22) | EACH | 7 | $4,525.71 | $4,600.00 | $5,840.00 | $5,453.12 | $3,734.40 | $3,500.00 |
| 0950 | Relocate trees and palms, palms, <10.0" DBH, <14.0' of clear trunk (0581-1271) | EACH | 3 | $1,522.84 | $2,500.00 | $1,710.00 | $1,500.00 | $1,754.39 | $3,000.00 |
| 0955 | Relocate trees and palms, tree, 8.1" to 14.0" DBH (0581-1340) | EACH | 3 | $20,305 | $2,500.00 | $22,700 | $20,000 | $23,392 | $25,000 |
| 0960 | Relocate trees and palms, tree, 14.1" to 16.0" DBH (0581-1350) | EACH | 1 | $20,305 | $3,500.00 | $22,700 | $20,000 | $23,392 | $25,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of July 29, 2026. Compiled by Mirage Metrics.