FDOT contract T5888 bid tabulation
SR 50 / SR 33 FROM CR 565 (VILLA CITY RD) TO 2ND AVE. Let by Florida DOT on June 10, 2026, Lake, District 5. 8 bids received; low bid $26,833,115 by C.W. Roberts Contracting, Inc..
- Owner
- Florida DOT
- Letting
- 10 JUN 2026
- Pay items
- 227
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | C.W. Roberts Contracting, Inc. | $26,833,115 | Low |
| 2 | Watson Civil Construction, Inc. | $27,726,804 | +3.0% |
| 3 | Cone & Graham, Inc. | $29,138,500 | +9.0% |
| 4 | De Moya Contracting LLC | $30,607,382 | +14% |
| 5 | Hubbard Construction Company | $30,857,858 | +15% |
| 6 | Ranger Construction Industries, Inc. | $31,394,556 | +17% |
| 7 | Atlantic Civil Constructors Corp | $34,664,306 | +29% |
| 8 | Cathcart Construction Company - Florida, LLC | $42,834,356 | +60% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. C.W. Roberts Contracting, Inc. | 2. Watson Civil Construction, Inc. | 3. Cone & Graham, Inc. | 4. De Moya Contracting LLC | 5. Hubbard Construction Company | 6. Ranger Construction Industries, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $1,660,000 | $2,700,000 | $2,910,000 | $3,000,000 | $3,050,000 | $2,890,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $466,000 | $771,000 | $798,000 | $900,000 | $2,200,000 | $945,168 |
| 0015 | Special detour- temporary pavement (0102-2200) | SY | 1 | $237,000 | $403,000 | $500,000 | $250,000 | $1,010,404 | $286,000 |
| 0016 | Special detour- temporary earthwork/base (0102-2300) | CY | 1 | $461,000 | $165,000 | $155,000 | $125,000 | $686,200 | $294,000 |
| 0020 | Traffic control officer (0102-14) | HR | 2,840 | $97.00 | $110.00 | $90.00 | $90.00 | $90.00 | $96.40 |
| 0025 | Work zone sign (0102-60) | ED | 19,457 | $0.25 | $0.33 | $0.22 | $0.22 | $0.22 | $0.25 |
| 0030 | Business sign (0102-61) | EACH | 600 | $0.40 | $1.00 | $0.35 | $35.00 | $0.35 | $0.40 |
| 0035 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 6,850 | $45.30 | $43.00 | $42.00 | $41.00 | $42.70 | $47.65 |
| 0040 | Temporary barrier, relocate, low profile concrete (0102-71-23) | LF | 3,300 | $19.00 | $18.00 | $9.00 | $17.00 | $17.71 | $10.20 |
| 0045 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 267,885 | $0.12 | $0.16 | $0.11 | $0.11 | $0.11 | $0.10 |
| 0050 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 20,904 | $0.10 | $0.15 | $0.10 | $0.10 | $0.10 | $0.10 |
| 0055 | Temporary separator, F&I remove (0102-75-1) | LF | 1,090 | $19.00 | $17.50 | $32.00 | $16.95 | $18.17 | $19.20 |
| 0060 | Arrow board / advance warning arrow panel (0102-76) | ED | 1,258 | $6.00 | $7.50 | $5.25 | $5.25 | $5.25 | $5.95 |
| 0065 | Portable changeable message sign, temporary (0102-99) | ED | 3,878 | $12.00 | $15.00 | $11.00 | $11.00 | $11.00 | $12.50 |
| 0070 | Temporary signalization and maintenance, intersection (0102-104) | ED | 134 | $20.00 | $95.00 | $71.00 | $71.00 | $25.48 | $20.40 |
| 0075 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 134 | $160.00 | $95.00 | $71.00 | $71.00 | $18.21 | $10.20 |
| 0080 | Type III barricade (0102-115) | ED | 11,475 | $0.35 | $0.45 | $0.30 | $0.30 | $0.30 | $0.35 |
| 0085 | Sediment barrier (0104-10-3) | LF | 16,495 | $6.25 | $1.40 | $3.75 | $3.30 | $2.57 | $1.95 |
| 0090 | Floating turbidity barrier (0104-11) | LF | 839 | $12.00 | $10.50 | $15.00 | $13.00 | $13.14 | $13.60 |
| 0095 | Inlet protection system (0104-18) | EACH | 48 | $160.00 | $135.00 | $130.00 | $180.00 | $627.38 | $170.10 |
| 0100 | Litter removal (0107-1) | ACRE | 557.88 | $23.00 | $22.00 | $100.00 | $30.00 | $21.64 | $22.70 |
| 0105 | Mowing (0107-2) | ACRE | 515.96 | $70.00 | $66.00 | $105.00 | $35.00 | $64.92 | $68.10 |
| 0110 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $1,933,971 | $815,000 | $1,500,000 | $1,500,000 | $547,956 | $692,000 |
| 0115 | Removal of existing concrete (0110-4-10) | SY | 6,745 | $44.65 | $26.00 | $23.00 | $55.00 | $15.76 | $10.30 |
| 0120 | Mailbox, F&I single (0110-7-1) | EACH | 21 | $330.00 | $320.00 | $350.00 | $250.00 | $350.00 | $624.00 |
| 0125 | Regular excavation (0120-1) | CY | 135,625 | $5.10 | $5.50 | $7.15 | $10.00 | $7.16 | $4.75 |
| 0130 | Subsoil excavation (0120-4) | CY | 30,874 | $18.30 | $14.00 | $22.00 | $25.00 | $15.15 | $12.90 |
| 0135 | Embankment (0120-6) | CY | 117,680 | $3.15 | $3.50 | $11.10 | $15.00 | $5.71 | $1.55 |
| 0140 | Type B stabilization (0160-4) | SY | 77,160 | $9.60 | $11.00 | $8.75 | $15.00 | $10.26 | $6.40 |
| 0145 | Optional base, base group 01 (0285-701) | SY | 8,516 | $9.15 | $14.00 | $12.40 | $20.00 | $11.86 | $8.65 |
| 0150 | Optional base, base group 04 (0285-704) | SY | 3,231 | $13.60 | $16.50 | $17.20 | $20.00 | $12.98 | $13.80 |
| 0155 | Optional base, base group 06 (0285-706) | SY | 105 | $47.00 | $35.00 | $27.50 | $30.00 | $39.24 | $40.15 |
| 0160 | Optional base, base group 09 (0285-709) | SY | 17,094 | $18.25 | $19.50 | $20.50 | $30.00 | $21.09 | $23.70 |
| 0165 | Optional base, base group 12 (0285-712) | SY | 33,625 | $18.85 | $22.50 | $23.00 | $30.00 | $20.24 | $24.30 |
| 0170 | Optional base, base group 15 (0285-715) | SY | 15,162 | $61.80 | $78.50 | $78.00 | $60.00 | $91.25 | $76.50 |
| 0175 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 23,013 | $4.25 | $5.55 | $5.30 | $5.00 | $6.40 | $6.70 |
| 0180 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 10,808 | $9.15 | $12.20 | $11.70 | $5.00 | $7.55 | $3.40 |
| 0190 | Superpave asphaltic conc, traffic B (0334-1-12) | TN | 839.40 | $140.00 | $165.00 | $158.50 | $200.00 | $244.00 | $208.10 |
| 0195 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 788.70 | $157.70 | $186.00 | $178.50 | $200.00 | $244.00 | $215.00 |
| 0200 | Superpave asphaltic conc, traffic E (0334-1-15) | TN | 12,878.80 | $128.40 | $152.00 | $146.00 | $170.00 | $205.00 | $198.25 |
| 0205 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 556.90 | $215.50 | $248.00 | $238.00 | $240.00 | $284.00 | $210.20 |
| 0210 | Asphalt concrete friction course,traffic E, FC-12.5, PG (0337-7-88) | TN | 6,853.10 | $173.15 | $204.00 | $196.00 | $240.00 | $226.00 | $202.25 |
| 0215 | Concrete class NS, gravity index 400-011 (0400-0-11) | CY | 164.30 | $1,380.00 | $990.00 | $880.00 | $900.00 | $848.63 | $1,030.00 |
| 0225 | Inlets, curb, type 9, J bot, <10' (0425-1203) | EACH | 1 | $8,500.00 | $8,200.00 | $10,300 | $15,000 | $7,993.72 | $22,000 |
| 0230 | Inlets, curb, type P-1, <10' (0425-1311) | EACH | 56 | $8,200.00 | $8,100.00 | $9,030.00 | $9,000.00 | $7,542.74 | $15,200 |
| 0235 | Inlets, curb type P-1, >10' (0425-1312) | EACH | 2 | $11,700 | $10,300 | $14,300 | $13,000 | $9,320.58 | $19,000 |
| 0240 | Inlets, curb, type P-2, <10' (0425-1321) | EACH | 8 | $9,100.00 | $8,900.00 | $10,125 | $10,500 | $8,913.96 | $17,000 |
| 0245 | Inlets, curb, type P-3, <10' (0425-1331) | EACH | 18 | $7,700.00 | $8,000.00 | $9,800.00 | $9,000.00 | $7,741.22 | $17,500 |
| 0250 | Inlets, curb, type P-4, <10' (0425-1341) | EACH | 9 | $8,600.00 | $8,700.00 | $10,650 | $9,000.00 | $8,259.32 | $18,700 |
| 0255 | Inlets, curb, type P-4, >10' (0425-1342) | EACH | 2 | $9,900.00 | $10,300 | $12,825 | $15,000 | $9,393.34 | $23,400 |
| 0260 | Inlets, curb, type P-5, <10' (0425-1351) | EACH | 11 | $7,600.00 | $7,300.00 | $8,500.00 | $9,000.00 | $7,441.37 | $12,800 |
| 0265 | Inlets, curb, type P-6, <10' (0425-1361) | EACH | 1 | $7,200.00 | $8,300.00 | $11,184 | $10,000 | $8,104.58 | $15,300 |
| 0270 | Inlets, curb type J-1, <10' (0425-1411) | EACH | 25 | $13,200 | $10,700 | $13,050 | $11,000 | $9,984.56 | $19,400 |
| 0275 | Inlets, curb, type J-1, >10' (0425-1412) | EACH | 22 | $17,100 | $14,500 | $17,000 | $13,000 | $12,638 | $25,600 |
| 0280 | Inlets, curb, type J-2, <10' (0425-1421) | EACH | 4 | $14,700 | $11,000 | $12,500 | $15,000 | $10,901 | $22,300 |
| 0285 | Inlets, curb, type J-3, <10' (0425-1431) | EACH | 4 | $19,700 | $13,000 | $17,000 | $18,000 | $12,482 | $26,600 |
| 0290 | Inlets, curb, type J-4, <10' (0425-1441) | EACH | 2 | $18,100 | $14,000 | $17,000 | $20,000 | $13,130 | $32,900 |
| 0295 | Inlets, curb, type J-5, <10' (0425-1451) | EACH | 1 | $12,100 | $10,000 | $13,050 | $14,000 | $9,633.10 | $20,000 |
| 0300 | Inlets, curb, type J-5, >10' (0425-1452) | EACH | 1 | $18,000 | $15,200 | $20,950 | $25,000 | $13,176 | $28,100 |
| 0305 | Inlets, curb, type 7, <10' (0425-1471) | EACH | 6 | $16,700 | $9,500.00 | $12,100 | $10,000 | $6,466.37 | $13,000 |
| 0310 | Inlets, curb, type 7, J bot , <10' (0425-1473) | EACH | 4 | $18,500 | $11,200 | $13,300 | $20,000 | $9,001.05 | $19,700 |
| 0315 | Inlets, curb, type 7, J bot ,>10' (0425-1474) | EACH | 1 | $20,700 | $15,000 | $14,400 | $30,000 | $10,040 | $21,200 |
| 0320 | Inlets, DT bot, type C,<10' (0425-1521) | EACH | 12 | $6,200.00 | $4,900.00 | $5,700.00 | $9,000.00 | $6,626.04 | $10,300 |
| 0325 | Inlets, DT bot, type C,jbot, <10' (0425-1523) | EACH | 2 | $8,700.00 | $5,500.00 | $7,750.00 | $12,500 | $9,959.43 | $17,800 |
| 0330 | Inlets, DT bot, type C, modify (0425-1529) | EACH | 6 | $16,600 | $6,900.00 | $7,300.00 | $7,500.00 | $5,449.85 | $11,000 |
| 0335 | Inlets, DT bot, type D, <10' (0425-1541) | EACH | 1 | $8,000.00 | $5,800.00 | $9,800.00 | $7,500.00 | $7,573.40 | $11,100 |
| 0340 | Inlets, ditch bottom, type D, partial (0425-1545) | EACH | 1 | $6,600.00 | $4,400.00 | $5,700.00 | $5,000.00 | $6,105.35 | $7,050.00 |
| 0345 | Inlets, DT bot, type E, <10' (0425-1551) | EACH | 10 | $7,300.00 | $6,200.00 | $6,550.00 | $7,500.00 | $8,136.49 | $11,800 |
| 0350 | Inlets, DT bot, type E, J bot, <10' (0425-1553) | EACH | 2 | $12,000 | $9,400.00 | $15,700 | $20,000 | $11,537 | $18,700 |
| 0355 | Inlets, DT bot, type E, modify (0425-1559) | EACH | 2 | $25,700 | $24,000 | $8,300.00 | $11,000 | $21,951 | $18,500 |
| 0360 | Inlets, DT bot, type H, <10' (0425-1581) | EACH | 3 | $8,800.00 | $7,800.00 | $10,500 | $9,000.00 | $10,478 | $19,000 |
| 0365 | Inlets, DT bot, type H, J bottom <10' (0425-1583) | EACH | 1 | $22,600 | $13,700 | $17,200 | $15,000 | $16,272 | $20,000 |
| 0370 | Inlets, gutter, type V, J bot, <10' (0425-1713) | EACH | 1 | $10,800 | $7,200.00 | $10,055 | $11,000 | $6,826.51 | $15,800 |
| 0375 | Inlets, gutter, type V, partial (0425-1715) | EACH | 6 | $6,900.00 | $5,300.00 | $7,650.00 | $6,500.00 | $6,393.70 | $9,470.00 |
| 0380 | Manholes, P-8, <10' (0425-2-61) | EACH | 2 | $6,500.00 | $5,400.00 | $7,800.00 | $8,000.00 | $4,833.82 | $12,500 |
| 0385 | Manholes, J-7, <10' (0425-2-71) | EACH | 8 | $17,800 | $9,200.00 | $13,900 | $12,000 | $9,381.65 | $17,900 |
| 0390 | Manholes, J-7, >10' (0425-2-72) | EACH | 6 | $37,700 | $16,500 | $22,800 | $22,000 | $14,487 | $29,000 |
| 0395 | Manholes, J-7, partial (0425-2-73) | EACH | 6 | $5,000.00 | $4,100.00 | $4,900.00 | $10,000 | $4,816.43 | $10,800 |
| 0400 | Manholes, J-8, <10' (0425-2-91) | EACH | 1 | $9,300.00 | $7,600.00 | $9,300.00 | $13,000 | $6,577.55 | $19,700 |
| 0405 | Manholes, J-8, >10' (0425-2-92) | EACH | 7 | $20,800 | $13,000 | $14,000 | $15,000 | $12,232 | $20,000 |
| 0410 | Manholes, J-8, partial (0425-2-93) | EACH | 4 | $8,000.00 | $4,800.00 | $4,200.00 | $7,000.00 | $5,672.70 | $12,100 |
| 0415 | Junction box, drainage, P-7, <10' (0425-3-41) | EACH | 1 | $6,900.00 | $5,300.00 | $8,700.00 | $5,000.00 | $4,678.36 | $12,500 |
| 0420 | Back of sidewalk endwall, 18" pipe diameter (0425-17-18) | EACH | 1 | $3,900.00 | $2,900.00 | $4,900.00 | $5,000.00 | $11,883 | $6,350.00 |
| 0425 | Pipe culvert, optional material, round, 18"SD (0430-174118) | LF | 77 | $57.00 | $99.00 | $150.00 | $150.00 | $126.40 | $305.00 |
| 0430 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 6,634 | $78.00 | $129.00 | $111.50 | $100.00 | $111.26 | $110.70 |
| 0435 | Pipe culvert,optional material,round, 24"S/CD (0430-175124) | LF | 3,031 | $105.30 | $165.00 | $110.00 | $110.00 | $132.56 | $161.80 |
| 0440 | Pipe culvert, opt material, round, 30"S/CD (0430-175130) | LF | 1,549 | $135.00 | $210.00 | $187.00 | $140.00 | $168.96 | $624.00 |
| 0445 | Pipe culvert, opt material, round, 36"S/CD (0430-175136) | LF | 1,830 | $158.50 | $220.00 | $198.00 | $180.00 | $216.87 | $266.40 |
| 0450 | Pipe culvert, opt material, round, 42"S/CD (0430-175142) | LF | 1,238 | $234.65 | $290.00 | $244.00 | $200.00 | $286.42 | $443.00 |
| 0455 | Pipe culvert, opt material, round, 48"S/CD (0430-175148) | LF | 2,254 | $237.10 | $355.00 | $273.00 | $250.00 | $314.44 | $513.00 |
| 0460 | Pipe culvert, opt material, round, 54"S/CD (0430-175154) | LF | 259 | $350.00 | $455.00 | $473.00 | $350.00 | $434.56 | $738.00 |
| 0465 | Pipe culvert, opt material, round, 60"S/CD (0430-175160) | LF | 69 | $400.00 | $785.00 | $753.00 | $500.00 | $405.40 | $760.00 |
| 0470 | Pipe culvert, opt material, shape - elip/arch, 36"S/CD (0430-175236) | LF | 160 | $320.00 | $337.00 | $330.00 | $300.00 | $291.82 | $253.50 |
| 0475 | Pipe culvert, opt material, shape - elip/arch, 42"S/CD (0430-175242) | LF | 145 | $430.00 | $485.00 | $370.00 | $300.00 | $361.32 | $235.60 |
| 0480 | Pipe culvert, opt material, shape - elip/arch, 60"S/CD (0430-175260) | LF | 78 | $670.00 | $875.00 | $710.00 | $600.00 | $638.05 | $953.00 |
| 0485 | Pipe culvert, opt material, shape - elip/arch, 72"S/CD (0430-175272) | LF | 680 | $1,100.00 | $1,140.00 | $1,100.00 | $630.00 | $1,077.11 | $1,540.00 |
| 0490 | Straight concrete endwalls, single, 0 degrees, round (0430-518100) | EACH | 1 | $3,100.00 | $2,200.00 | $4,900.00 | $5,000.00 | $3,192.15 | $6,350.00 |
| 0495 | Straight concrete endwalls, single, 0 degrees, elliptical (0430-536102) | EACH | 1 | $6,500.00 | $4,100.00 | $6,200.00 | $10,000 | $5,309.12 | $13,800 |
| 0500 | Straight concrete endwalls, single, 0 degrees, round (0430-542100) | EACH | 1 | $6,500.00 | $7,650.00 | $13,400 | $10,000 | $19,363 | $20,500 |
| 0505 | Straight concrete endwalls, single, 0 degrees, elliptical (0430-542102) | EACH | 2 | $7,500.00 | $5,900.00 | $8,125.00 | $12,000 | $17,694 | $17,300 |
| 0510 | Straight concrete endwalls, single, 0 degrees, round (0430-548100) | EACH | 1 | $9,600.00 | $13,700 | $14,700 | $15,000 | $20,852 | $19,900 |
| 0515 | Straight concrete endwalls, single, 0 degrees, round (0430-554100) | EACH | 1 | $13,700 | $21,300 | $20,625 | $15,000 | $23,764 | $22,700 |
| 0520 | Straight concrete endwalls, single, 0 degrees, elliptical (0430-560102) | EACH | 1 | $34,800 | $26,000 | $20,625 | $20,000 | $26,548 | $17,000 |
| 0525 | Straight concrete endwalls, single, 0 degrees, elliptical (0430-572102) | EACH | 1 | $45,000 | $40,000 | $28,600 | $25,000 | $36,620 | $31,000 |
| 0530 | Mitered end section, optional round, 18" CD (0430-982125) | EACH | 1 | $2,600.00 | $1,900.00 | $3,175.00 | $3,500.00 | $2,338.94 | $4,200.00 |
| 0535 | Mitered end section, optional round, 42" CD (0430-982140) | EACH | 2 | $7,100.00 | $6,400.00 | $6,825.00 | $10,000 | $7,668.81 | $11,200 |
| 0540 | Mitered end section, optional round, 48" CD (0430-982141) | EACH | 1 | $8,100.00 | $7,600.00 | $8,200.00 | $12,000 | $8,469.64 | $15,500 |
| 0545 | Mitered end section, optional round, 18" SD (0430-984125) | EACH | 4 | $2,600.00 | $1,900.00 | $2,200.00 | $3,500.00 | $2,080.08 | $4,830.00 |
| 0550 | Underdrain, type II (0440-1-20) | LF | 872 | $45.00 | $65.00 | $55.00 | $60.00 | $51.24 | $84.40 |
| 0555 | Pedestrian / bicycle railing, NS, 42" type 1 (0515-2111) | LF | 129 | $92.00 | $95.00 | $85.00 | $172.00 | $105.02 | $106.10 |
| 0560 | Concrete curb & gutter, type E (0520-1-7) | LF | 6,610 | $39.00 | $29.50 | $23.25 | $30.00 | $25.94 | $32.95 |
| 0565 | Concrete curb & gutter, type F (0520-1-10) | LF | 20,042 | $32.40 | $25.50 | $19.75 | $30.00 | $21.63 | $32.50 |
| 0570 | Concrete curb, type D (0520-2-4) | LF | 1,412 | $43.00 | $29.00 | $21.00 | $30.00 | $23.64 | $30.60 |
| 0575 | Traffic separator concrete- type I, 4' wide (0520-5-11) | LF | 538 | $110.00 | $72.00 | $69.00 | $80.00 | $73.34 | $23.80 |
| 0580 | Traffic separator concrete- type I, 6' wide (0520-5-12) | LF | 85 | $150.00 | $107.00 | $103.50 | $110.00 | $112.88 | $39.70 |
| 0585 | Concrete traffic separator, special- variable width (0520-70) | SY | 2,265 | $170.00 | $161.00 | $155.25 | $100.00 | $161.45 | $65.80 |
| 0590 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 9,130 | $65.00 | $64.00 | $61.00 | $60.00 | $60.01 | $60.90 |
| 0595 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 3,358 | $96.50 | $83.00 | $78.50 | $80.00 | $79.22 | $71.10 |
| 0600 | Concrete ditch pavement, non reinforced, 4" (0524-1-2) | SY | 39 | $320.00 | $84.00 | $80.25 | $115.00 | $80.78 | $83.00 |
| 0605 | Concrete ditch pavement, non reinforced, 6" (0524-1-4) | SY | 298 | $223.70 | $98.00 | $93.25 | $125.00 | $99.17 | $76.40 |
| 0610 | Detectable warnings (0527-2) | SF | 1,283 | $40.00 | $68.00 | $65.00 | $40.00 | $66.40 | $34.00 |
| 0615 | Riprap, rubble, F&I, ditch lining (0530-3-4) | TN | 213.20 | $130.00 | $168.00 | $191.00 | $135.00 | $149.77 | $173.30 |
| 0620 | Bedding stone (0530-74) | TN | 149.40 | $130.00 | $191.00 | $163.00 | $125.00 | $207.66 | $192.80 |
| 0625 | Bumper guards, concrete (0542-70) | EACH | 66 | $160.00 | $320.00 | $250.00 | $285.00 | $95.00 | $226.90 |
| 0630 | Performance turf, sod (0570-1-2) | SY | 70,527 | $5.25 | $5.45 | $4.60 | $3.00 | $4.56 | $3.10 |
| 0635 | Performance turf, sod and shoulder treatment index (0570-1-3) | SY | 25,772 | $5.80 | $5.50 | $4.70 | $3.00 | $4.26 | $3.10 |
| 0640 | Conduit, furnish & install, open trench (0630-2-11) | LF | 24 | $26.00 | $22.50 | $22.00 | $22.00 | $18.57 | $24.00 |
| 0645 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 2 | $1,400.00 | $1,070.00 | $1,032.00 | $1,032.00 | $1,272.73 | $1,860.00 |
| 0650 | Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1) | EACH | 4 | $2,500.00 | $2,400.00 | $2,332.00 | $2,332.00 | $3,079.66 | $3,280.00 |
| 0655 | Traffic monitoring site speed/classification unit, furnish & install, volume speed and classification (0695-3-11) | AS | 2 | $12,100 | $9,800.00 | $9,533.00 | $9,533.00 | $13,477 | $11,000 |
| 0660 | Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12) | EACH | 4 | $2,600.00 | $1,950.00 | $1,895.00 | $1,895.00 | $2,869.03 | $3,050.00 |
| 0665 | Traffic monitoring site cabinet, furnish & install, type 3, pedestal mount (0695-7132) | EACH | 2 | $5,800.00 | $5,900.00 | $5,752.00 | $5,752.00 | $8,683.84 | $8,330.00 |
| 0670 | Raised pavement marker, type B (0706-1-3) | EACH | 5,005 | $5.50 | $5.10 | $5.00 | $5.00 | $5.00 | $5.65 |
| 0675 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 9.45 | $1,800.00 | $1,620.00 | $1,599.83 | $1,600.00 | $1,599.83 | $1,810.00 |
| 0680 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 883 | $0.85 | $0.77 | $0.75 | $0.75 | $0.75 | $0.85 |
| 0685 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 1,506 | $1.00 | $1.30 | $1.25 | $1.25 | $1.25 | $1.40 |
| 0690 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 3.35 | $880.00 | $810.00 | $799.76 | $800.00 | $799.76 | $907.00 |
| 0695 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 1.16 | $880.00 | $810.00 | $798.62 | $800.00 | $798.62 | $906.00 |
| 0700 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 6 | $94.00 | $86.00 | $85.00 | $85.00 | $85.00 | $96.40 |
| 0705 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 92 | $50.00 | $46.00 | $45.00 | $45.00 | $45.00 | $51.10 |
| 0710 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 8.18 | $1,800.00 | $1,620.00 | $1,599.41 | $1,600.00 | $1,599.41 | $1,810.00 |
| 0715 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 832 | $1.00 | $1.05 | $1.00 | $1.00 | $1.00 | $1.15 |
| 0720 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.46 | $880.00 | $805.00 | $794.82 | $800.00 | $794.82 | $901.00 |
| 0725 | Disputes review board, meeting- DO not bid (0999-20-1) | DA | 15 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 |
| 0730 | Disputes review board, hearing- DO not bid (0999-20-2) | EACH | 2 | $5,750.00 | $5,750.00 | $5,750.00 | $5,750.00 | $5,750.00 | $5,750.00 |
| 0735 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $150,000 | $150,000 | $150,000 | $150,000 | $150,000 | $150,000 |
| 0740 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 98 | $540.00 | $495.00 | $490.00 | $490.00 | $490.00 | $556.00 |
| 0745 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 36 | $2,200.00 | $2,050.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,270.00 |
| 0750 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 7 | $2,300.00 | $2,150.00 | $2,100.00 | $2,100.00 | $2,100.00 | $2,380.00 |
| 0755 | Single column ground sign assembly, relocate (0700-1500) | EACH | 18 | $440.00 | $405.00 | $400.00 | $400.00 | $400.00 | $454.00 |
| 0760 | Single column ground sign assembly, remove (0700-1600) | EACH | 81 | $11.00 | $10.20 | $10.00 | $10.00 | $10.00 | $11.35 |
| 0765 | Single column ground sign assembly, F&I cantilever mount, 12.0-20.0 SF (0700-1912) | EACH | 1 | $2,900.00 | $2,700.00 | $2,600.00 | $2,600.00 | $2,600.00 | $2,950.00 |
| 0770 | Multi-column ground sign assembly, F&I ground mount, 20.0 SF (0700-2112) | EACH | 5 | $6,600.00 | $6,100.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,800.00 |
| 0775 | Multi-column ground sign assembly, F&I ground mount, 30.0 SF (0700-2113) | EACH | 1 | $8,800.00 | $8,100.00 | $8,000.00 | $8,000.00 | $8,000.00 | $9,070.00 |
| 0780 | Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114) | EACH | 1 | $9,900.00 | $9,100.00 | $9,000.00 | $9,000.00 | $9,000.00 | $10,200 |
| 0785 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 6 | $2,200.00 | $2,050.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,270.00 |
| 0790 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 63 | $110.00 | $102.00 | $100.00 | $100.00 | $100.00 | $113.40 |
| 0795 | Tubular marker, 36" white post (0704-1-3) | EACH | 6 | $170.00 | $152.00 | $150.00 | $150.00 | $150.00 | $170.10 |
| 0800 | Tubular marker, 36" yellow (0704-1-4) | EACH | 11 | $170.00 | $152.00 | $150.00 | $150.00 | $150.00 | $170.10 |
| 0805 | Object marker, type 1 (0705-10-1) | EACH | 11 | $280.00 | $255.00 | $250.00 | $250.00 | $250.00 | $283.60 |
| 0810 | Raised pavement marker, type B (0706-1-3) | EACH | 2,172 | $6.00 | $5.10 | $5.00 | $5.00 | $5.00 | $5.65 |
| 0815 | Painted pavement markings, surface (0710-90) | LS | 1 | $41,300 | $35,000 | $37,500 | $37,500 | $37,500 | $42,500 |
| 0820 | Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102) | GM | 0.39 | $7,100.00 | $6,600.00 | $6,466.84 | $6,500.00 | $6,466.84 | $7,330.00 |
| 0825 | Thermoplastic, standard, solid, 12" for interchange markings (0711-11103) | GM | 0.28 | $10,800 | $10,000 | $9,818.18 | $10,000 | $10,182 | $11,100 |
| 0830 | Thermoplastic, standard, solid, 6" for parking spaces (0711-11121) | LF | 1,079 | $1.00 | $1.05 | $1.00 | $1.00 | $1.00 | $1.15 |
| 0835 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 4,548 | $4.00 | $4.05 | $4.00 | $4.00 | $4.00 | $4.55 |
| 0840 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 497 | $6.00 | $5.10 | $5.00 | $5.00 | $5.00 | $5.65 |
| 0845 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 893 | $7.00 | $6.10 | $6.00 | $6.00 | $6.00 | $6.80 |
| 0850 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.33 | $3,800.00 | $3,600.00 | $3,489.43 | $3,500.00 | $3,489.43 | $3,960.00 |
| 0855 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 21 | $280.00 | $255.00 | $250.00 | $250.00 | $250.00 | $283.60 |
| 0860 | Thermoplastic, standard, arrow (0711-11170) | EACH | 122 | $94.00 | $86.00 | $85.00 | $85.00 | $85.00 | $96.40 |
| 0865 | Thermoplastic, standard, yield line (0711-11180) | LF | 26 | $22.00 | $20.50 | $20.00 | $20.00 | $20.00 | $22.70 |
| 0870 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 795 | $6.00 | $5.10 | $5.00 | $5.00 | $5.00 | $5.65 |
| 0875 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.16 | $3,900.00 | $3,600.00 | $3,500.00 | $3,500.00 | $3,500.00 | $3,970.00 |
| 0880 | Thermoplastic, standard, blue, solid,6" (0711-11421) | LF | 180 | $11.00 | $10.20 | $10.00 | $10.00 | $10.00 | $11.35 |
| 0885 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 1,770 | $17.00 | $15.20 | $15.00 | $15.00 | $15.00 | $17.00 |
| 0890 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 20 | $220.00 | $203.00 | $200.00 | $200.00 | $200.00 | $226.90 |
| 0895 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 5.94 | $5,700.00 | $5,300.00 | $5,199.12 | $5,200.00 | $5,199.12 | $5,900.00 |
| 0900 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 2.86 | $3,300.00 | $3,050.00 | $2,992.65 | $3,000.00 | $3,003.15 | $3,390.00 |
| 0905 | Thermoplastic, standard-other surfaces white, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-16133) | GM | 0.13 | $6,800.00 | $6,250.00 | $6,141.73 | $6,500.00 | $6,653.54 | $6,970.00 |
| 0910 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 4.62 | $5,700.00 | $5,270.00 | $5,193.24 | $5,200.00 | $5,204.51 | $5,890.00 |
| 0915 | Itsfm subsurface documentation- project length (0611-1-1) | MI | 1.54 | $4,500.00 | $4,050.00 | $3,947.44 | $3,950.00 | $4,170.89 | $4,390.00 |
| 0920 | Itsfm location documentation- intersection (0611-2-1) | EACH | 3 | $3,000.00 | $1,650.00 | $1,580.00 | $1,580.00 | $2,832.94 | $2,980.00 |
| 0925 | Itsfm location documentation- ITS site (0611-2-2) | EACH | 1 | $2,500.00 | $2,450.00 | $2,370.00 | $2,370.00 | $2,286.99 | $2,410.00 |
| 0930 | Conduit, furnish & install, open trench (0630-2-11) | LF | 646 | $26.00 | $40.00 | $38.50 | $38.50 | $18.57 | $21.05 |
| 0935 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 7,819 | $35.00 | $27.50 | $26.60 | $26.60 | $27.91 | $29.55 |
| 0940 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 3 | $10,600 | $17,100 | $16,668 | $16,668 | $18,823 | $16,100 |
| 0945 | Fiber optic cable, F&I, underground, 97 - 144 fibers (0633-1124) | LF | 8,558 | $6.60 | $6.00 | $5.85 | $5.85 | $6.37 | $6.70 |
| 0950 | Fiber optic connection, install, splice (0633-2-31) | EACH | 96 | $58.00 | $52.00 | $50.50 | $50.50 | $54.59 | $57.40 |
| 0955 | Fiber optic connection, install, termination (0633-2-32) | EACH | 96 | $98.00 | $86.00 | $84.00 | $84.00 | $91.00 | $95.70 |
| 0960 | Fiber optic connection hardware, F&I, splice enclosure (0633-3-11) | EACH | 8 | $1,700.00 | $1,475.00 | $1,431.00 | $1,431.00 | $1,552.96 | $1,630.00 |
| 0965 | Fiber optic connection hardware, F&I, splice tray (0633-3-12) | EACH | 8 | $65.00 | $58.00 | $56.00 | $56.00 | $60.67 | $63.80 |
| 0970 | Fiber optic connection hardware, F&I, buffer tube fan out kit (0633-3-14) | EACH | 8 | $110.00 | $97.00 | $95.00 | $95.00 | $103.13 | $108.50 |
| 0975 | Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16) | EACH | 4 | $1,700.00 | $1,550.00 | $1,493.00 | $1,493.00 | $1,619.71 | $1,700.00 |
| 0980 | Fiber optic connection hardware, F&I, connector panel (0633-3-17) | EACH | 8 | $160.00 | $137.00 | $134.00 | $134.00 | $145.60 | $153.10 |
| 0985 | Fiber optic cable locator (0633-6) | DA | 690 | $155.75 | $140.00 | $137.00 | $10.00 | $145.60 | $153.10 |
| 0990 | Span wire assembly, F&I, two point, diagonal (0634-4152) | PI | 2 | $5,400.00 | $4,000.00 | $3,897.00 | $3,897.00 | $13,136 | $10,500 |
| 0995 | Span wire assembly, F&I, two point, box or drop box (0634-4153) | PI | 2 | $10,300 | $9,800.00 | $9,596.00 | $9,596.00 | $12,348 | $15,600 |
| 1000 | Fiberglass insulator, furnish & install (0634-5-1) | LF | 645 | $63.00 | $59.00 | $57.00 | $57.00 | $37.54 | $61.50 |
| 1005 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 75 | $1,435.00 | $1,060.00 | $1,032.00 | $1,032.00 | $1,389.87 | $1,860.00 |
| 1010 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 22 | $3,100.00 | $2,750.00 | $2,657.00 | $2,657.00 | $2,610.46 | $2,990.00 |
| 1015 | Pull & splice box, F&I, 30" X 60" rectangular or 36" round size (0635-2-13) | EACH | 4 | $6,600.00 | $5,150.00 | $4,999.00 | $4,999.00 | $4,662.36 | $5,120.00 |
| 1020 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 3 | $4,700.00 | $5,300.00 | $5,181.00 | $5,181.00 | $3,783.93 | $4,860.00 |
| 1025 | Electrical service wire, & install (0639-2-1) | LF | 320 | $7.00 | $7.35 | $7.15 | $7.15 | $13.24 | $5.80 |
| 1030 | Electrical service disconnect, F&I, pole mount (0639-3-11) | EACH | 3 | $1,400.00 | $2,350.00 | $2,272.00 | $2,272.00 | $1,493.27 | $2,710.00 |
| 1035 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 3 | $2,100.00 | $2,500.00 | $2,423.00 | $2,423.00 | $2,391.26 | $2,410.00 |
| 1040 | Aluminum signals pole, (0646-1-11) | EACH | 27 | $3,200.00 | $2,470.00 | $2,400.00 | $2,400.00 | $2,075.37 | $3,010.00 |
| 1045 | Aluminum signals pole, remove (0646-1-60) | EACH | 2 | $460.00 | $300.00 | $291.00 | $291.00 | $585.59 | $1,020.00 |
| 1050 | Steel strain pole, F&I, type PS- (0649-1-14) | EACH | 8 | $67,200 | $48,000 | $46,790 | $46,790 | $51,669 | $67,400 |
| 1055 | Steel strain pole, F&I, type PS- IX (0649-1-16) | EACH | 4 | $77,900 | $68,200 | $66,742 | $66,742 | $65,118 | $70,700 |
| 1060 | Vehicular traffic signal, furnish & install 3 section, 1 way (0650-1-34) | AS | 36 | $1,400.00 | $1,700.00 | $1,638.00 | $1,638.00 | $1,701.63 | $2,300.00 |
| 1065 | Vehicular traffic signal, furnish & install 4 section, 1 way (0650-1-36) | AS | 1 | $1,800.00 | $2,000.00 | $1,929.00 | $1,929.00 | $2,224.39 | $2,660.00 |
| 1070 | Vehicular traffic signal, furnish & install 5 section cluster, 1 way (0650-1-39) | AS | 1 | $2,300.00 | $2,300.00 | $2,240.00 | $2,244.00 | $2,747.24 | $3,650.00 |
| 1075 | Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109) | EACH | 16 | $710.00 | $490.00 | $478.00 | $478.00 | $440.89 | $526.00 |
| 1080 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 27 | $930.00 | $665.00 | $648.00 | $648.00 | $865.86 | $733.00 |
| 1085 | Vehicle detection system- furnish & install cabinet equipment (0660-4-11) | EACH | 3 | $34,700 | $29,100 | $28,511 | $28,511 | $24,226 | $30,800 |
| 1090 | Vehicle detection system- furnish & install above ground equipment (0660-4-12) | EACH | 18 | $8,500.00 | $7,600.00 | $7,412.00 | $7,412.00 | $3,610.08 | $7,310.00 |
| 1095 | Signal priority and preemption system, furnish and install, detector (0663-1122) | EACH | 3 | $8,900.00 | $9,200.00 | $8,987.00 | $8,987.00 | $10,409 | $10,800 |
| 1100 | Signal priority and preemption system, furnish and install, cabinet electronics (0663-1123) | EACH | 3 | $9,800.00 | $8,800.00 | $8,545.00 | $8,548.00 | $9,848.13 | $8,590.00 |
| 1105 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 27 | $440.00 | $245.00 | $240.00 | $240.00 | $367.36 | $393.00 |
| 1110 | Traffic controller assembly, F&I, NEMA W/standard lock, 2 preemption (0670-5162) | AS | 3 | $46,900 | $42,000 | $40,469 | $40,469 | $41,450 | $49,700 |
| 1115 | Traffic controller assembly, relocate controller with cabinet (0670-5500) | AS | 1 | $6,200.00 | $6,200.00 | $6,032.00 | $6,032.00 | $5,017.85 | $12,100 |
| 1120 | Managed field ethernet switch, furnish & install (0684-1-1) | EACH | 3 | $5,800.00 | $4,200.00 | $4,084.00 | $4,084.00 | $5,441.46 | $8,800.00 |
| 1125 | Uninterruptible power supply, furnish and install, online/double conversion with cabinet (0685-1-14) | EACH | 3 | $10,200 | $16,400 | $15,996 | $15,996 | $14,475 | $19,800 |
| 1130 | Remote power management rpmu, furnish and install (0685-2-1) | EACH | 3 | $1,000.00 | $2,120.00 | $2,061.00 | $2,061.00 | $1,242.35 | $936.00 |
| 1135 | Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201) | EACH | 2 | $830.00 | $905.00 | $885.00 | $885.00 | $986.13 | $1,130.00 |
| 1140 | Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22) | EACH | 14 | $4,000.00 | $6,150.00 | $6,000.00 | $6,000.00 | $4,312.61 | $8,780.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of June 10, 2026. Compiled by Mirage Metrics.