FDOT contract T6589 bid tabulation
SR 90 (US 41/SW 7TH ST) FROM E OF SW 27 AVE TO BRICKELL AVE. Let by Florida DOT on March 25, 2026, Miami-Dade, District 6. 6 bids received; low bid $11,399,399 by Aum Construction Inc..
- Owner
- Florida DOT
- Letting
- 25 MAR 2026
- Pay items
- 212
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Aum Construction Inc. | $11,399,399 | Low |
| 2 | Jva Engineering Contractor, Inc | $12,038,627 | +6.0% |
| 3 | Florida Engineering & Development Corp | $12,493,627 | +10% |
| 4 | Asphalt Group, Inc. | $13,794,856 | +21% |
| 5 | Sice Inc | $14,208,516 | +25% |
| 6 | Roadway Construction, LLC | $15,323,839 | +34% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Aum Construction Inc. | 2. Jva Engineering Contractor, Inc | 3. Florida Engineering & Development Corp | 4. Asphalt Group, Inc. | 5. Sice Inc | 6. Roadway Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Removal of existing structures/bridges 870479 (0110-3) | SF | 1 | $26,000 | $109,000 | $15,225 | $18,148 | $26,030 | $18,148 |
| 0010 | Concrete class II, approach slabs (0400-2-10) | CY | 2 | $6,500.00 | $10,900 | $6,090.00 | $8,091.00 | $11,606 | $8,091.20 |
| 0015 | Reinforcing steel- approach slabs (0415-1-9) | LB | 112 | $13.00 | $80.00 | $6.09 | $3.90 | $5.58 | $3.90 |
| 0020 | Mobilization (0101-1) | LS | 1 | $275,000 | $485,500 | $1,161,900 | $680,000 | $433,084 | $766,192 |
| 0025 | Mobilization (0101-1) | LS | 1 | $275,000 | $373,500 | $704,946 | $670,000 | $962,530 | $766,192 |
| 0030 | Maintenance of traffic (0102-1) | DA | 1 | $200,000 | $321,700 | $146,971 | $550,000 | $106,568 | $1,099,444 |
| 0035 | Maintenance of traffic (0102-1) | DA | 1 | $200,000 | $222,300 | $146,971 | $550,000 | $183,965 | $549,303 |
| 0040 | Commercial material for temporary driveway maintenance (0102-3) | CY | 24.10 | $100.00 | $42.00 | $199.79 | $100.00 | $565.23 | $329.50 |
| 0045 | Traffic control officer (0102-14) | HR | 2,236 | $65.00 | $81.75 | $76.13 | $90.00 | $106.51 | $85.00 |
| 0050 | Work zone sign (0102-60) | ED | 45,235 | $0.20 | $0.21 | $0.18 | $0.18 | $0.21 | $0.18 |
| 0055 | Business sign (0102-61) | EACH | 3 | $100.00 | $35.00 | $50.75 | $30.00 | $35.50 | $30.00 |
| 0060 | Barrier mounted work zone sign- index 700-012 (0102-62-12) | ED | 720 | $10.00 | $0.47 | $36.31 | $0.40 | $0.47 | $0.40 |
| 0065 | Temporary barrier, F&I, anchored (0102-71-15) | LF | 300 | $75.00 | $54.50 | $36.39 | $50.00 | $46.15 | $62.33 |
| 0070 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 46,800 | $0.15 | $1.05 | $0.10 | $0.09 | $0.11 | $0.09 |
| 0075 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 30,270 | $0.10 | $0.06 | $0.04 | $0.05 | $0.06 | $0.05 |
| 0080 | Arrow board / advance warning arrow panel (0102-76) | ED | 4,050 | $7.00 | $5.25 | $5.08 | $4.50 | $5.33 | $4.50 |
| 0085 | Temporary crash cushion, redirective option (0102-89-1) | LO | 1 | $1,500.00 | $1,166.30 | $918.57 | $5,000.00 | $1,183.43 | $1,000.00 |
| 0090 | Portable changeable message sign, temporary (0102-99) | ED | 1,735 | $10.00 | $10.50 | $8.63 | $9.00 | $10.65 | $9.00 |
| 0095 | Temporary signalization and maintenance, intersection (0102-104) | ED | 7,820 | $5.00 | $8.70 | $6.51 | $6.41 | $10.06 | $5.00 |
| 0100 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 7,820 | $5.00 | $8.70 | $6.51 | $6.41 | $10.06 | $5.00 |
| 0105 | Type III barricade (0102-115) | ED | 7,500 | $0.50 | $0.27 | $0.24 | $0.23 | $0.27 | $0.23 |
| 0110 | Removable tape, white, solid 6" (0102-913-21) | GM | 0.13 | $14,500 | $28,700 | $26,796 | $9,000.00 | $14,201 | $11,163 |
| 0115 | Inlet protection system (0104-18) | EACH | 145 | $150.00 | $148.70 | $93.64 | $100.00 | $102.86 | $314.19 |
| 0120 | Litter removal (0107-1) | ACRE | 100.76 | $10.00 | $257.90 | $7.20 | $50.00 | $47.34 | $0.04 |
| 0125 | Mowing (0107-2) | ACRE | 17.84 | $50.00 | $239.00 | $48.63 | $100.00 | $120.71 | $1,581.46 |
| 0130 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $30,000 | $6,540.00 | $6,546.75 | $5,000.00 | $28,136 | $39,625 |
| 0135 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $30,000 | $7,520.00 | $6,546.75 | $5,000.00 | $65,651 | $39,625 |
| 0140 | Monitor existing structures- vibration monitoring (0108-2) | LS | 1 | $30,000 | $10,900 | $2,791.25 | $5,000.00 | $7,242.60 | $10,200 |
| 0145 | Monitor existing structures- vibration monitoring (0108-2) | LS | 1 | $30,000 | $9,150.00 | $2,791.25 | $5,000.00 | $16,899 | $10,200 |
| 0150 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $5,000.00 | $8,175.00 | $12,190 | $200,000 | $15,429 | $29,977 |
| 0155 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $13,855 | $21,800 | $27,875 | $200,000 | $15,429 | $95,872 |
| 0160 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $5,000.00 | $5,450.00 | $2,263.45 | $200,000 | $15,429 | $35,000 |
| 0165 | Removal of existing concrete (0110-4-10) | SY | 4,840 | $26.00 | $17.75 | $18.30 | $30.00 | $34.29 | $79.53 |
| 0170 | Tree protection barrier (0110-21) | LF | 1,400 | $10.00 | $3.00 | $9.76 | $5.00 | $9.47 | $11.05 |
| 0175 | Tree root and branch pruning (0110-22) | EACH | 12 | $500.00 | $1,798.50 | $3,045.00 | $3,000.00 | $3,550.30 | $800.00 |
| 0180 | Tree removal (0110-23) | EACH | 12 | $1,200.00 | $2,071.00 | $793.56 | $2,500.00 | $2,130.18 | $1,475.00 |
| 0185 | Regular excavation (0120-1) | CY | 75.90 | $40.00 | $72.30 | $203.32 | $50.00 | $80.00 | $403.05 |
| 0190 | Embankment (0120-6) | CY | 232.60 | $40.00 | $40.40 | $119.00 | $50.00 | $62.86 | $252.90 |
| 0195 | Regular excavation (3-R projects only) (0120-71) | LS | 1 | $26,000 | $1,718.90 | $1,079.86 | $5,000.00 | $3,428.57 | $8,356.69 |
| 0200 | Type B stabilization (0160-4) | SY | 559 | $33.00 | $20.67 | $23.42 | $10.00 | $61.71 | $79.31 |
| 0205 | Reworking limerock base, 3" (0210-1-9) | SY | 204 | $26.00 | $44.80 | $19.99 | $1.00 | $26.40 | $81.93 |
| 0210 | Optional base, base group 01 (0285-701) | SY | 214 | $80.00 | $68.40 | $86.72 | $80.00 | $67.43 | $107.22 |
| 0215 | Optional base, base group 02 (0285-702) | SY | 111 | $80.00 | $112.50 | $41.29 | $80.00 | $123.43 | $161.17 |
| 0220 | Optional base, base group 06 (0285-706) | SY | 270 | $100.00 | $137.80 | $46.20 | $90.00 | $70.86 | $105.51 |
| 0225 | Optional base, base group 11 (0285-711) | SY | 25 | $140.00 | $218.00 | $104.14 | $150.00 | $653.71 | $197.08 |
| 0230 | Milling existing asphalt pavement, 2" avg depth (0327-70-5) | SY | 12,277 | $5.00 | $4.75 | $4.31 | $8.00 | $10.00 | $4.30 |
| 0235 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 60,679 | $4.25 | $4.00 | $4.01 | $8.00 | $5.00 | $4.30 |
| 0240 | Superpave asphaltic conc, traffic B (0334-1-12) | TN | 94.80 | $335.00 | $249.00 | $275.18 | $250.00 | $281.26 | $250.00 |
| 0245 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 96 | $220.00 | $247.00 | $302.93 | $250.00 | $438.86 | $250.00 |
| 0250 | Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81) | TN | 242 | $335.00 | $210.00 | $213.15 | $250.00 | $264.06 | $210.00 |
| 0255 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 6,166.20 | $220.00 | $206.00 | $200.97 | $250.00 | $240.00 | $198.00 |
| 0260 | Miscellaneous asphalt (0339-1) | TN | 6.40 | $650.00 | $1,090.00 | $889.91 | $1,000.00 | $882.29 | $892.00 |
| 0265 | Plain cement concrete 9" (0350-3-7) | SY | 214 | $390.00 | $183.28 | $249.99 | $150.00 | $367.41 | $503.93 |
| 0270 | Cleaning & sealing joints- concrete pavement (0350-5) | LF | 658 | $40.00 | $10.90 | $7.39 | $8.00 | $10.86 | $7.58 |
| 0275 | Grinding concrete pavement (0352-70) | SY | 214 | $78.00 | $32.00 | $20.30 | $35.00 | $109.71 | $10.00 |
| 0280 | Bridge approach expansion for concrete pavement (0370-1) | LF | 39 | $40.00 | $109.00 | $76.33 | $65.00 | $112.00 | $78.22 |
| 0285 | Conc class IV, retaining walls (0400-4-11) | CY | 36 | $2,500.00 | $1,300.00 | $2,009.70 | $1,800.00 | $3,074.29 | $2,240.21 |
| 0290 | Reinforcing steel- retaining wall (0415-1-3) | LB | 3,003 | $5.00 | $2.10 | $2.29 | $2.00 | $8.00 | $2.35 |
| 0295 | Inlets, curb, type 9, <10' (0425-1201) | EACH | 3 | $16,900 | $7,960.00 | $6,958.30 | $12,000 | $17,543 | $24,549 |
| 0300 | Inlets, curb, type 9, partial (0425-1205) | EACH | 1 | $8,450.00 | $6,480.00 | $4,311.20 | $8,000.00 | $5,847.53 | $11,787 |
| 0305 | Inlets, curb, type P-3, <10' (0425-1331) | EACH | 2 | $21,450 | $11,170 | $13,744 | $12,500 | $20,466 | $36,669 |
| 0310 | Inlets, curb, type P-4, <10' (0425-1341) | EACH | 1 | $22,100 | $11,460 | $12,573 | $12,500 | $20,466 | $34,511 |
| 0315 | Inlets, curb, type P-5, partial (0425-1355) | EACH | 1 | $9,100.00 | $7,010.00 | $4,398.80 | $7,500.00 | $14,619 | $14,195 |
| 0320 | Inlets, curb, type P-6, <10' (0425-1361) | EACH | 1 | $18,000 | $8,800.00 | $7,891.31 | $12,500 | $16,081 | $29,152 |
| 0325 | Inlets, curb, type J-5, <10' (0425-1451) | EACH | 1 | $19,500 | $9,900.00 | $11,781 | $15,000 | $197,354 | $35,260 |
| 0330 | Inlets, curb, type J-5, >10' (0425-1452) | EACH | 1 | $45,000 | $11,830 | $14,893 | $18,000 | $28,507 | $53,403 |
| 0335 | Manholes, P-7, <10' (0425-2-41) | EACH | 2 | $17,500 | $8,500.00 | $8,634.62 | $11,000 | $13,888 | $31,382 |
| 0340 | Manholes, P-7, >10' (0425-2-42) | EACH | 1 | $26,500 | $9,310.00 | $16,358 | $13,000 | $17,543 | $44,039 |
| 0345 | Manholes, P-7, partial (0425-2-43) | EACH | 4 | $7,800.00 | $5,920.00 | $4,284.64 | $2,500.00 | $10,233 | $10,498 |
| 0350 | Manhole, adjust (0425-5) | EACH | 91 | $1,200.00 | $1,090.00 | $939.62 | $500.00 | $1,800.00 | $550.00 |
| 0355 | Pipe culvert,optional material,round, 12"S/CD (0430-175112) | LF | 8 | $1,100.00 | $545.00 | $301.15 | $800.00 | $219.28 | $822.39 |
| 0360 | Pipe culvert,optional material,round, 15"S/CD (0430-175115) | LF | 5 | $1,850.00 | $545.00 | $338.04 | $500.00 | $438.57 | $1,699.70 |
| 0365 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 274 | $260.00 | $208.00 | $158.58 | $250.00 | $219.28 | $460.57 |
| 0370 | Trench drain, standard (0436-1-1) | LF | 55 | $495.00 | $573.00 | $476.50 | $350.00 | $511.66 | $2,729.88 |
| 0375 | French drain, 24" (0443-70-4) | LF | 96 | $390.00 | $383.00 | $231.20 | $350.00 | $475.11 | $1,106.96 |
| 0380 | Edgedrain draincrete, (0446-1-1) | LF | 142 | $195.00 | $111.00 | $146.14 | $50.00 | $80.40 | $144.59 |
| 0385 | Sheet piling steel, F&I (0455-133-3) | SF | 1,320 | $215.00 | $109.00 | $243.60 | $100.00 | $370.00 | $46.50 |
| 0390 | Pipe handrail - guiderail, aluminum (0515-1-2) | LF | 13 | $120.00 | $294.00 | $274.05 | $100.00 | $143.03 | $97.84 |
| 0395 | Concrete curb & gutter, type F (0520-1-10) | LF | 4,619 | $42.00 | $30.30 | $40.10 | $35.00 | $96.78 | $135.21 |
| 0400 | Concrete curb, type D (0520-2-4) | LF | 104 | $26.00 | $109.00 | $31.19 | $35.00 | $93.30 | $148.47 |
| 0405 | Concrete traffic separator, special- variable width (0520-70) | SY | 54 | $260.00 | $163.00 | $146.12 | $90.00 | $300.98 | $418.37 |
| 0410 | Shoulder concrete barrier, 38" wall shielding barrier (0521-72-60) | LF | 17 | $1,300.00 | $381.50 | $553.01 | $700.00 | $872.70 | $1,457.30 |
| 0415 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 1,005 | $91.00 | $55.10 | $59.94 | $60.00 | $173.66 | $201.97 |
| 0420 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 3,103 | $100.00 | $64.60 | $71.86 | $75.00 | $180.40 | $249.03 |
| 0425 | Pavers, architectural, remove existing and reinstall (0526-1101) | SY | 30 | $350.00 | $327.00 | $111.93 | $200.00 | $194.77 | $272.68 |
| 0430 | Detectable warnings (0527-2) | SF | 1,297 | $45.00 | $38.10 | $32.78 | $35.00 | $85.04 | $112.31 |
| 0435 | Guardrail -roadway, general (0536-1-1) | LF | 158 | $32.00 | $31.30 | $29.18 | $25.64 | $37.49 | $25.64 |
| 0440 | Special guardrail post- post for shallow mount (0536-7-3) | EACH | 1 | $195.00 | $223.40 | $208.07 | $160.00 | $234.62 | $160.49 |
| 0445 | Guardrail transition to rigid barrier, F&I- index 536- 001, approach TL-2 (0536-8111) | EACH | 1 | $2,900.00 | $4,905.00 | $4,567.50 | $2,387.00 | $3,489.86 | $2,387.23 |
| 0450 | Guardrail removal (0536-73) | LF | 35 | $10.00 | $49.05 | $5.07 | $2.41 | $731.00 | $2.41 |
| 0455 | Guardrail end treatment- trailing anchorage (0536-85-20) | EACH | 1 | $1,800.00 | $1,853.00 | $1,725.50 | $1,441.00 | $2,107.52 | $1,441.64 |
| 0460 | Performance turf (0570-1-1) | SY | 2 | $500.00 | $545.00 | $22.06 | $8.00 | $14.62 | $607.58 |
| 0465 | Performance turf, sod (0570-1-2) | SY | 631 | $20.00 | $11.00 | $13.91 | $8.00 | $7.31 | $33.58 |
| 0470 | Electrical power service- contribution in aid of construction (ciac), FPL (DO not bid) (0639-8130) | LS | 1 | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 |
| 0475 | Electrical power service- contribution in aid of construction (ciac), FPL (DO not bid) (0639-8130) | LS | 1 | $7,200.00 | $7,200.00 | $7,200.00 | $7,200.00 | $7,200.00 | $7,200.00 |
| 0480 | Electrical power service- contribution in aid of construction (ciac), FPL (DO not bid) (0639-8130) | LS | 1 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 |
| 0485 | Raised pavement marker, type B (0706-1-3) | EACH | 1,020 | $6.00 | $5.45 | $5.08 | $4.00 | $5.85 | $4.00 |
| 0490 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 3.69 | $2,000.00 | $2,877.00 | $2,679.60 | $1,700.00 | $1,606.33 | $1,698.16 |
| 0495 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 7,126 | $1.70 | $1.09 | $1.02 | $1.40 | $1.46 | $1.40 |
| 0500 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 179 | $3.60 | $1.74 | $1.62 | $1.50 | $2.19 | $1.50 |
| 0505 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 5,249 | $2.00 | $2.18 | $2.03 | $1.60 | $2.93 | $1.60 |
| 0510 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 3.96 | $600.00 | $436.00 | $406.00 | $500.00 | $1,096.14 | $499.87 |
| 0515 | Painted pavement marking, standard,white, 3'-9' skip drop line and approach to toll 12" wide, (0710-11133) | GM | 0.07 | $1,200.00 | $3,052.00 | $2,842.05 | $1,000.00 | $2,453.23 | $958.90 |
| 0520 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.08 | $1,200.00 | $719.40 | $669.87 | $650.00 | $971.58 | $575.95 |
| 0525 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 13 | $50.00 | $65.40 | $60.90 | $40.00 | $182.73 | $40.00 |
| 0530 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 43 | $50.00 | $43.60 | $40.60 | $40.00 | $138.88 | $40.00 |
| 0535 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 2.69 | $2,000.00 | $872.00 | $812.00 | $1,700.00 | $1,605.68 | $1,697.48 |
| 0540 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 125 | $3.60 | $1.64 | $1.52 | $1.50 | $2.19 | $1.50 |
| 0545 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.01 | $1,200.00 | $719.40 | $670.00 | $500.00 | $782.86 | $357.14 |
| 0550 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $29,585 | $29,585 | $29,585 | $29,585 | $29,585 | $29,585 |
| 0555 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $74,144 | $74,144 | $74,144 | $74,144 | $74,144 | $74,144 |
| 0560 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $15,548 | $15,548 | $15,548 | $15,548 | $15,548 | $15,548 |
| 0565 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 801 | $25.00 | $38.15 | $43.25 | $42.61 | $86.74 | $25.00 |
| 0570 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 17 | $1,500.00 | $1,907.50 | $1,432.67 | $1,411.00 | $1,538.46 | $1,349.00 |
| 0575 | Pull & splice box, install (0635-2-30) | EACH | 2 | $1,200.00 | $1,308.00 | $1,152.04 | $1,135.00 | $6,153.85 | $1,017.50 |
| 0580 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 2 | $7,000.00 | $4,469.00 | $5,341.21 | $5,262.00 | $5,069.23 | $6,290.00 |
| 0585 | Electrical service wire, & install (0639-2-1) | LF | 761 | $7.00 | $10.90 | $9.18 | $9.00 | $18.34 | $7.50 |
| 0590 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 2 | $2,500.00 | $2,289.00 | $2,885.67 | $2,843.00 | $2,927.53 | $3,102.00 |
| 0595 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 134 | $650.00 | $763.00 | $710.50 | $598.00 | $550.30 | $465.00 |
| 0600 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 18 | $2,000.00 | $2,561.00 | $2,385.25 | $1,850.00 | $2,011.83 | $1,700.00 |
| 0605 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 10 | $3,000.00 | $2,779.00 | $2,588.25 | $2,650.00 | $2,958.58 | $2,500.00 |
| 0610 | Single column ground sign assembly, F&I ground mount, SF sheeting area for back to back signs (0700-1114) | EACH | 9 | $3,600.00 | $2,888.00 | $2,689.75 | $3,950.00 | $3,550.30 | $3,000.00 |
| 0615 | Single column ground sign assembly, relocate (0700-1500) | EACH | 1 | $300.00 | $460.00 | $431.37 | $400.00 | $591.72 | $500.00 |
| 0620 | Single column ground sign assembly, remove (0700-1600) | EACH | 65 | $50.00 | $10.90 | $10.15 | $50.00 | $118.34 | $10.00 |
| 0625 | Single column ground sign assembly, F&I cantilever mount, less than 12 SF (0700-1911) | EACH | 25 | $900.00 | $817.00 | $761.25 | $3,300.00 | $887.57 | $750.00 |
| 0630 | Single column ground sign assembly, F&I cantilever mount, 12.0-20.0 SF (0700-1912) | EACH | 2 | $5,300.00 | $2,561.00 | $2,385.25 | $4,300.00 | $5,207.10 | $4,400.00 |
| 0635 | Single column ground sign assembly, F&I cantilever mount, 20.1-30.0 SF (0700-1913) | EACH | 1 | $3,600.00 | $2,779.00 | $2,588.25 | $4,600.00 | $3,550.30 | $3,000.00 |
| 0640 | Multi-column ground sign assembly, F&I ground mount, 20.0 SF (0700-2112) | EACH | 2 | $8,400.00 | $5,668.00 | $5,278.00 | $6,500.00 | $8,284.02 | $7,000.00 |
| 0645 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 101 | $100.00 | $130.00 | $121.80 | $150.00 | $143.14 | $85.00 |
| 0650 | Enhanced highway sign AC powered, F&I ground mount, W/eds, 12-20 SF of static sign panels (0700-141132) | EACH | 2 | $15,000 | $13,625 | $16,781 | $120.00 | $11,289 | $15,705 |
| 0655 | Enhanced highway sign solar powered, F&I ground mount, W/eds, 12-20 SF of static sign panels (0700-142132) | EACH | 4 | $16,000 | $19,075 | $18,072 | $25,000 | $16,158 | $17,588 |
| 0660 | Delineator, flexible tubular (0705-11-1) | EACH | 3 | $200.00 | $98.00 | $91.35 | $150.00 | $168.11 | $135.00 |
| 0665 | Raised pavement marker, type B (0706-1-3) | EACH | 1,264 | $6.00 | $5.45 | $5.08 | $4.00 | $5.85 | $4.00 |
| 0670 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 57 | $6.00 | $2.20 | $2.03 | $5.00 | $4.75 | $5.00 |
| 0675 | Painted pavement markings, surface (0710-90) | LS | 1 | $8,100.00 | $21,800 | $14,069 | $6,737.00 | $18,113 | $6,737.00 |
| 0680 | Painted pavement markings, surface (0710-90) | LS | 1 | $29,000 | $13,080 | $14,069 | $24,060 | $18,113 | $24,060 |
| 0685 | Painted pavement markings, surface (0710-90) | LS | 1 | $4,200.00 | $10,447 | $14,069 | $3,500.00 | $18,113 | $3,500.00 |
| 0690 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 8,711 | $4.80 | $2.62 | $2.44 | $3.22 | $3.29 | $3.22 |
| 0695 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 202 | $6.00 | $3.92 | $3.65 | $4.82 | $4.87 | $4.82 |
| 0700 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 1,936 | $7.20 | $5.23 | $4.87 | $6.44 | $5.99 | $6.44 |
| 0705 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.28 | $2,700.00 | $2,507.00 | $2,334.50 | $2,250.00 | $3,070.00 | $2,250.00 |
| 0710 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 26 | $90.00 | $130.80 | $121.80 | $75.00 | $292.38 | $75.00 |
| 0715 | Thermoplastic, standard, arrow (0711-11170) | EACH | 72 | $80.00 | $87.20 | $81.20 | $65.00 | $146.18 | $65.00 |
| 0720 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 176 | $5.35 | $3.92 | $3.65 | $4.45 | $4.87 | $4.45 |
| 0725 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.02 | $2,700.00 | $6,431.00 | $5,988.24 | $2,250.00 | $1,805.71 | $1,323.53 |
| 0730 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 4,942 | $18.00 | $20.71 | $19.29 | $15.07 | $26.31 | $15.07 |
| 0735 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 4 | $250.00 | $283.40 | $263.90 | $206.00 | $804.03 | $206.00 |
| 0740 | Thermoplastic, preformed, 12"X12" white elephant marking (0711-14163) | GM | 0.03 | $50,000 | $14.53 | $11.85 | $41,468 | $16,243 | $30,717 |
| 0745 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 3 | $366.00 | $163.50 | $152.25 | $305.00 | $804.03 | $305.00 |
| 0750 | Thermoplastic, preformed, white with black contrast on concrete pavement, message symbol (0711-14560) | EACH | 5 | $940.00 | $1,558.70 | $1,451.45 | $783.00 | $2,192.82 | $783.00 |
| 0755 | Thermoplastic, preformed, white with black contrast, arrow on concrete surface (0711-14570) | EACH | 9 | $850.00 | $1,286.20 | $1,197.70 | $705.00 | $1,315.69 | $705.00 |
| 0760 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 4.66 | $5,650.00 | $6,431.00 | $5,988.50 | $4,696.00 | $6,329.10 | $4,689.95 |
| 0765 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 4.48 | $1,400.00 | $2,507.00 | $2,334.50 | $1,174.00 | $1,534.97 | $1,174.00 |
| 0770 | Thermoplastic, standard-other surfaces white, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-16133) | GM | 0.07 | $2,800.00 | $5,014.00 | $4,668.99 | $2,348.00 | $2,669.65 | $2,041.74 |
| 0775 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 3.19 | $5,200.00 | $6,431.00 | $5,988.50 | $4,315.00 | $6,335.28 | $4,313.65 |
| 0780 | Green-colored pavement markings, bike lane (0714-10) | SF | 136 | $24.00 | $10.90 | $10.15 | $20.00 | $31.43 | $20.00 |
| 0785 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 13 | $2,000.00 | $1,907.50 | $1,432.67 | $1,411.00 | $2,958.58 | $1,349.00 |
| 0790 | Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211) | EACH | 1 | $2,000.00 | $3,270.00 | $1,818.55 | $1,791.00 | $1,258.88 | $1,749.00 |
| 0795 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 1 | $1,200.00 | $3,270.00 | $1,748.39 | $1,722.00 | $1,195.56 | $1,433.50 |
| 0800 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 6,776 | $20.00 | $43.60 | $45.68 | $45.00 | $50.00 | $40.00 |
| 0805 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 20 | $10,000 | $8,720.00 | $8,917.31 | $8,785.00 | $11,834 | $11,535 |
| 0810 | Signal cable, remove- intersection (0632-7-6) | PI | 16 | $500.00 | $926.00 | $1,201.87 | $1,184.00 | $2,044.97 | $1,728.00 |
| 0815 | Signal cable, remove- outside intersection (0632-7-7) | LF | 450 | $5.00 | $1.09 | $1.50 | $1.48 | $4.73 | $2.70 |
| 0820 | Fiber optic cable locator (0633-6) | DA | 390 | $100.00 | $381.50 | $229.49 | $226.00 | $127.81 | $0.01 |
| 0825 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 349 | $2,000.00 | $1,907.00 | $1,573.25 | $1,550.00 | $1,343.67 | $1,349.00 |
| 0830 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 17 | $2,500.00 | $3,270.00 | $2,334.56 | $2,300.00 | $3,550.30 | $2,898.00 |
| 0835 | Pull & splice box, install (0635-2-30) | EACH | 13 | $1,200.00 | $1,308.00 | $1,081.88 | $1,065.00 | $2,366.86 | $1,017.50 |
| 0840 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 13 | $7,000.00 | $4,469.00 | $5,341.20 | $5,262.00 | $4,979.29 | $6,545.00 |
| 0845 | Electrical power service, remove underground (0639-1620) | AS | 8 | $750.00 | $926.50 | $600.93 | $592.00 | $2,044.97 | $373.00 |
| 0850 | Electrical service wire, & install (0639-2-1) | LF | 1,585 | $7.00 | $10.90 | $9.95 | $9.80 | $18.25 | $10.00 |
| 0855 | Electrical service wire, (0639-2-6) | LF | 1,127 | $1.00 | $1.09 | $0.40 | $0.39 | $1.18 | $1.00 |
| 0860 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 13 | $2,500.00 | $2,398.00 | $2,885.67 | $2,843.00 | $2,927.53 | $3,292.50 |
| 0865 | Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60) | EACH | 4 | $750.00 | $490.00 | $801.25 | $789.00 | $1,022.49 | $968.00 |
| 0870 | Prestressed concrete pole, shallow pole removal- pole 30' and greater (0641-2-70) | EACH | 4 | $2,500.00 | $3,815.00 | $5,158.27 | $5,082.00 | $4,501.78 | $6,133.00 |
| 0875 | Aluminum signals pole, (0646-1-11) | EACH | 66 | $1,800.00 | $2,180.00 | $2,286.86 | $2,253.00 | $1,940.20 | $2,996.00 |
| 0880 | Aluminum signals pole, remove (0646-1-60) | EACH | 23 | $250.00 | $109.00 | $500.78 | $493.00 | $681.66 | $267.00 |
| 0885 | Steel mast arm assembly, and install, single arm 30' (0649-21-1) | EACH | 1 | $52,000 | $43,600 | $60,598 | $59,702 | $52,037 | $44,147 |
| 0890 | Steel mast arm assembly, and install, single arm 40' (0649-21-3) | EACH | 9 | $55,000 | $49,050 | $68,628 | $67,614 | $65,904 | $47,422 |
| 0895 | Steel mast arm assembly, and install, double arm 40'-40' (0649-21-5) | EACH | 1 | $74,000 | $79,570 | $82,126 | $80,912 | $76,303 | $64,309 |
| 0900 | Steel mast arm assembly, and install, single arm 50' (0649-21-6) | EACH | 3 | $59,500 | $58,315 | $70,194 | $69,156 | $64,378 | $95,777 |
| 0905 | Steel mast arm assembly, and install, double arm 50'-40' (0649-21-8) | EACH | 2 | $83,000 | $88,508 | $92,419 | $91,953 | $86,262 | $79,338 |
| 0910 | Steel mast arm assembly, and install, double arm 50'-50' (0649-21-9) | EACH | 1 | $85,000 | $92,650 | $93,752 | $92,366 | $87,366 | $83,712 |
| 0915 | Steel mast arm assembly, and install, single arm 60' (0649-21-10) | EACH | 2 | $69,000 | $65,400 | $100,852 | $99,362 | $104,907 | $102,277 |
| 0920 | Steel mast arm assembly, and install, double arm 60'-30' (0649-21-11) | EACH | 2 | $86,500 | $92,105 | $97,807 | $99,362 | $90,968 | $81,033 |
| 0925 | Steel mast arm assembly, and install, double arm 60'-50' (0649-21-13) | EACH | 1 | $90,000 | $98,100 | $140,887 | $138,804 | $154,730 | $139,071 |
| 0930 | Steel mast arm assembly, and install, single arm 70' (0649-21-15) | EACH | 1 | $75,000 | $76,300 | $88,200 | $86,896 | $83,517 | $76,389 |
| 0935 | Steel mast arm assembly, and install, double arm 70'-30' (0649-21-16) | EACH | 1 | $90,500 | $111,180 | $104,415 | $102,872 | $99,286 | $82,997 |
| 0940 | Steel mast arm assembly, remove, shallow foundation- bolt on attachment (0649-26-3) | EACH | 16 | $3,000.00 | $3,815.00 | $5,088.11 | $5,000.00 | $3,550.30 | $3,030.00 |
| 0945 | Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14) | AS | 79 | $1,500.00 | $1,635.00 | $1,488.08 | $1,466.00 | $1,465.88 | $1,859.00 |
| 0950 | Vehicular traffic signal, furnish & install aluminum, 4 section, 1 way (0650-1-16) | AS | 4 | $1,800.00 | $2,180.00 | $1,889.91 | $1,861.00 | $1,743.29 | $1,988.00 |
| 0955 | Vehicular traffic signal, furnish & install aluminum, 5 section straight, 1 way (0650-1-18) | AS | 5 | $2,200.00 | $2,289.00 | $2,214.58 | $2,181.00 | $1,957.24 | $2,347.50 |
| 0960 | Vehicular traffic signal, remove- poles to remain (0650-1-60) | AS | 9 | $250.00 | $54.50 | $200.31 | $197.00 | $255.62 | $198.00 |
| 0965 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 22 | $1,500.00 | $981.00 | $939.44 | $925.56 | $998.05 | $945.50 |
| 0970 | Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12) | AS | 46 | $2,000.00 | $1,853.00 | $1,782.41 | $1,756.00 | $1,577.46 | $1,649.50 |
| 0975 | Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60) | AS | 7 | $250.00 | $54.50 | $200.31 | $197.00 | $511.24 | $179.00 |
| 0980 | Vehicle detection system- microwave, furnish & install cabinet equipment (0660-3-11) | EACH | 8 | $13,000 | $58,315 | $10,302 | $10,150 | $8,235.73 | $9,916.00 |
| 0985 | Vehicle detection system- microwave, furnish & install, above ground equipment (0660-3-12) | EACH | 24 | $10,000 | $18,312 | $12,111 | $11,931 | $9,549.93 | $12,496 |
| 0990 | Vehicle detection system- furnish & install cabinet equipment (0660-4-11) | EACH | 17 | $5,500.00 | $5,668.00 | $15,772 | $15,538 | $13,671 | $11,552 |
| 0995 | Vehicle detection system- furnish & install above ground equipment (0660-4-12) | EACH | 24 | $7,500.00 | $4,469.00 | $8,490.55 | $11,981 | $6,551.48 | $5,536.00 |
| 1000 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 92 | $250.00 | $327.00 | $410.79 | $404.00 | $447.20 | $533.50 |
| 1005 | Pedestrian detector, furnish & install, accessible (0665-1-12) | EACH | 54 | $1,800.00 | $3,379.00 | $1,641.02 | $1,616.00 | $1,460.21 | $2,194.00 |
| 1010 | Pedestrian detector, remove- pole/pedestal to remain (0665-1-60) | EACH | 28 | $250.00 | $54.50 | $100.16 | $99.00 | $340.83 | $66.00 |
| 1015 | Traffic controller assembly, F&I, caltrans W/standard lock (0670-5180) | AS | 12 | $48,000 | $49,050 | $42,250 | $41,625 | $42,524 | $42,771 |
| 1020 | Traffic controller assembly, F&I, caltrans W/standard lock, preemption (0670-5181) | AS | 2 | $48,000 | $49,050 | $42,251 | $41,626 | $42,524 | $45,200 |
| 1025 | Traffic controller assembly, remove controller with (0670-5600) | AS | 9 | $1,200.00 | $926.50 | $1,602.49 | $1,578.00 | $2,044.97 | $1,518.00 |
| 1030 | Cellular modem, furnish and install (0684-8-1) | EACH | 14 | $2,500.00 | $2,289.00 | $2,559.08 | $2,521.00 | $2,107.94 | $3,888.00 |
| 1035 | Uninterruptible power supply, furnish and install, online/double conversion with cabinet (0685-1-14) | EACH | 1 | $18,000 | $22,890 | $17,231 | $16,976 | $11,153 | $15,290 |
| 1040 | Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201) | EACH | 43 | $1,500.00 | $1,199.00 | $1,062.05 | $1,046.00 | $1,005.92 | $985.50 |
| 1045 | Internally illuminated sign, furnish & install overhead mount, UP to 12 SF (0700-5-21) | EACH | 27 | $3,000.00 | $3,488.00 | $3,997.81 | $3,938.00 | $3,769.23 | $3,035.00 |
| 1050 | Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22) | EACH | 5 | $3,500.00 | $3,597.00 | $4,008.20 | $3,948.00 | $3,769.23 | $3,035.00 |
| 1055 | Enhanced highway sign AC powered, F&I overhead blank out sign <12 SF (0700-141360) | EACH | 4 | $9,000.00 | $13,080 | $7,165.32 | $7,059.00 | $9,291.72 | $13,837 |
| 1060 | Relocate trees and palms, palms, 10.0"-18.0" DBH, 14.0' or greater of clear trunk (0581-1282) | EACH | 5 | $8,000.00 | $8,175.00 | $7,105.00 | $7,000.00 | $8,284.02 | $7,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of March 25, 2026. Compiled by Mirage Metrics.