Hawkins Asphalt Paving, LLC: TDOT bid record

Hawkins Asphalt Paving, LLC submitted 25 bids on Tennessee DOT contracts in the data, from 15 MAY 2020 to 26 JUN 2026, and was the low bidder on 8 of them (32%). When it was not low, its total sat a median +10% above the low bid.

Owner
Tennessee DOT
Low bid volume
$12,561,883
Latest bid
26 JUN 2026
Data through
02 OCT 2026
25Bids
8Low bids
32Win rate, percent
+10%Median gap to the low bid when not low, 17 bids

By year

YearBidsLow bidsWin rate
2020100%
20246117%
20258225%
202610550%
Hawkins Asphalt Paving, LLC, TDOT: bids and low bids by year of letting

By county

CountyBidsLow bidsWin rate
Rutherford County13538%
Bedford County4250%
Cannon County300%
Williamson County2150%
Davidson County100%
Marshall And Williamson Counties100%
Bedford And Rutherford100%
Hawkins Asphalt Paving, LLC, TDOT: bids and low bids by county

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Signs (construction)712-06SF2523 (92%)$6.80$8.00
Removal of snowplowable reflective marker716-01.30EACH2114 (67%)$10.00$12.00
Flexible drums (channelizing)712-04.01EACH1712 (71%)$26.00$34.50
Enhanced flatline thermo PVMT MRKNG (6IN line)716-12.02LM2410 (42%)$7,000.00$7,425.00
Snowplowable raised pavement markers (BI-dir) (1 color)716-01.21EACH2110 (48%)$35.00$40.48
Plastic pavement marking (turn lane arrow)716-02.06EACH169 (56%)$200.00$200.68
Plastic pavement marking (stop line)716-02.05LF238 (35%)$20.00$17.30
Arrow board (type C)712-08.03EACH148 (57%)$962.50$1,170.00
Bituminous material for tack coat (TC)403-01TON227 (32%)$900.00$969.62
Brooming & degrassing shoulders208-01.05LM216 (29%)$1,325.00$1,500.00
Painted pavement marking (6" line)716-05.20LM166 (38%)$1,400.00$1,400.00
Plastic pavement marking(channelization striping)716-02.04SY136 (46%)$35.00$29.75
Hawkins Asphalt Paving, LLC, TDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

Hawkins Asphalt Paving, LLC, TDOT: the firms on the same contracts most often

Latest bids

LetContractCountyProjectRankIts bidAgainst the low bid
26 JUN 2026CN263048Bedford CountyThe resurfacing on s.r. 269 from s.r. 82 (l.m. 4.45) to s.r. 64 (l.m. 9.54)1 of 4$1,076,832Low, 3.0% under the second
26 JUN 2026CN263051Marshall And Williamson CountiesMicrosurfacing or thin mix overlay on u.s. 31a (s.r. 11) from near sw forest street in marshall county (l.m. 26.03) to the rutherford county2 of 4$1,558,446+5.0%
26 JUN 2026CN263046Rutherford CountyThe resurfacing on u.s. 231 (s.r. 10) from s.r. 268 (compton road) (l.m. 17.89) to the wilson county line (l.m. 24.97)1 of 3$1,627,881Low, 9.0% under the second
26 JUN 2026CN263053Rutherford CountyThe resurfacing on u.s. 31a (s.r. 11) from the williamson county line (l.m. 0.00) to the williamson county line (l.m. 2.57)1 of 4$670,110Low, 6.0% under the second
20 MAR 2026CN262021Cannon CountyThe resurfacing on s.r. 53 from near pleasant ridge road (l.m. 18.21) to the dekalb county line (l.m. 24.08)3 of 4$2,575,497+7.0%
20 MAR 2026CN263031Rutherford CountyThe resurfacing on s.r. 266 from u.s. 231 (s.r. 10) (l.m. 13.30) to near s.r. 96 (l.m. 18.66)1 of 4$1,128,555Low, 9.0% under the second
06 FEB 2026CN263011Bedford CountyThe resurfacing on s.r. 82 from west of couch lane (l.m. 16.70) to s.r. 64 (l.m. 22.16)1 of 3$1,265,644Low, 4.0% under the second
06 FEB 2026CN262016Cannon CountyThe resurfacing (microsurface or thin mix overlay) on s.r. 64 from the coffee county line to south of u.s. 70s (s.r. 1) and on s.r. 99 from 3 of 5$2,033,744+46%
06 FEB 2026CN263019Rutherford CountyThe resurfacing on s.r. 102 from near brackin court (l.m. 11.62) to s.r. 266 (l.m. 13.04)2 of 4$1,118,676+4.0%
06 FEB 2026CN263020Rutherford CountyThe resurfacing (microsurface or thin mix overlay) on s.r. 99 from west of mt. herman road (l.m. 24.50) to the cannon county line (l.m. 33.13 of 6$1,659,939+20%
03 OCT 2025CNZ263Williamson CountyThe resurfacing on s.r. 252 (wilson pike) from s.r. 96 (l.m. 0.00) to north of clovercroft road (l.m. 5.71)1 of 7$1,231,228Low, 1.0% under the second
27 JUN 2025CNZ204Rutherford CountyThe resurfacing on u.s. 41 (u.s. 70s, s.r. 1) from north of florence road (l.m. 9.80) to s.r. 268 (l.m. 14.10)1 of 3$2,960,096Low, 7.0% under the second
09 MAY 2025CNZ147Bedford CountyThe construction of turn lanes on u.s. 231 (s.r. 10) at the intersection of s.r. 82 (sawney webb memorial highway) (l.m. 17.52), including s2 of 6$2,060,007+10%
21 MAR 2025CNZ098Davidson CountyThe resurfacing on i-24 from haywood lane (l.m. 21.10) to the rutherford county line (l.m. 27.62), including bridge expansion joint repairs 2 of 4$7,510,748+6.0%
07 FEB 2025CNZ051Bedford CountyThe resurfacing on u.s. 231 (s.r. 10) from the intersection of lane parkway (l.m. 10.19) to the intersection of moreland avenue (l.m. 12.25)3 of 3$1,558,482+19%
07 FEB 2025CNZ066Cannon CountyThe resurfacing on s.r. 281 from s.r. 53 (l.m. 0.00) to west of todd road (l.m. 4.51)4 of 5$1,181,348+10%
07 FEB 2025CNZ004Rutherford CountyThe resurfacing on s.r. 102 from s.r. 96 (l.m. 0.00) to near mercedes drive (l.m. 6.00), including thin epoxy overlay on bridges3 of 6$1,673,575+7.0%
07 FEB 2025CNZ002Rutherford CountyThe resurfacing on u.s. 41 (s.r. 2) from kensington square court (l.m. 1.80) to south of cedar grove road (l.m. 6.78)3 of 5$1,950,103+11%
04 OCT 2024CNY236Rutherford CountyThe resurfacing on i-840 from the east fork stones river bridge (l.m. 15.50) to the wilson county line (l.m. 20.54)4 of 4$6,809,965+11%
21 JUN 2024CNY170Rutherford CountyThe miscellaneous safety improvements on u.s. 231 (s.r. 10) at the intersection of rock springs midland road (l.m. 3.44 to l.m. 3.82), inclu4 of 7$1,251,542+8.0%
09 FEB 2024CNY024Rutherford CountyThe resurfacing on i-24 from near the stones river (l.m. 15.52) to east of the csxt railroad (l.m. 19.07), including bridge expansion joint 3 of 4$8,764,275+17%
09 FEB 2024CNY061Rutherford CountyThe resurfacing on i-840 from near i-24 (l.m. 7.53) to near the west fork stones river (l.m. 10.46), including bridge deck and expansion joi2 of 4$6,087,439+3.0%
09 FEB 2024CNY020Rutherford CountyThe resurfacing on u.s. 41 (s.r. 2) from u.s. 70s (s.r. 1) to near kensington square court and on u.s. 70s (s.r. 1) from south of ash street1 of 2$2,601,536Low, 6.0% under the second
09 FEB 2024CNY017Williamson CountyThe resurfacing on u.s. 31a (u.s. 41a, s.r. 11) from s.r. 96 (l.m. 7.41) to the davidson county line (l.m. 17.14)4 of 7$3,323,874+17%
15 MAY 2020CNU207Bedford And Rutherford94,75015-8208-14,stp/hsip-82(6),02011-3224-94,02011-8224-14 the resurfacing on s.r. 269 from u.s. 231 (s.r. 10) in rutherford county to s.r.2 of 5$2,315,844+3.0%
Hawkins Asphalt Paving, LLC: latest TDOT bids in the data

How this record was read

TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

  • Every bid counted here matched its published total to within one dollar; TDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy