TDOT contract CNZ147 bid tabulation
The construction of turn lanes on u.s. 231 (s.r. 10) at the intersection of s.r. 82 (sawney webb memorial highway) (l.m. 17.52), including signals. Let by Tennessee DOT on May 9, 2025, Bedford County. 6 bids received; low bid $1,875,792 by Tinsley Asphalt, LLC.
- Owner
- Tennessee DOT
- Letting
- 09 MAY 2025
- Pay items
- 98
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Tinsley Asphalt, LLC | $1,875,792 | Low |
| 2 | Hawkins Asphalt Paving, LLC | $2,060,007 | +10% |
| 3 | Sessions Paving Company | $2,396,662 | +28% |
| 4 | Civil Constructors, LLC | $2,413,427 | +29% |
| 5 | Rogers Group, Inc. | $2,558,605 | +36% |
| 6 | Wiregrass Construction Company, Inc | $2,581,088 | +38% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Tinsley Asphalt, LLC | 2. Hawkins Asphalt Paving, LLC | 3. Sessions Paving Company | 4. Civil Constructors, LLC | 5. Rogers Group, Inc. | 6. Wiregrass Construction Company, Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $25,000 | $24,000 | $45,000 | $21,980 | $61,669 | $19,105 |
| 2 | Removal of structures and obstructions (202-01) | LS | 1 | $15,750 | $6,500.00 | $10,000 | $18,250 | $9,973.34 | $5,635.52 |
| 3 | Road & drainage excavation (unclassified) (203-01) | CY | 1,907 | $42.00 | $50.35 | $50.00 | $80.50 | $57.97 | $40.64 |
| 4 | Borrow excavation (unclassified) (203-03) | CY | 459 | $36.75 | $86.00 | $70.00 | $72.50 | $60.21 | $114.36 |
| 5 | Placing and spreading topsoil (203-04) | CY | 353 | $33.60 | $23.00 | $30.00 | $57.50 | $131.57 | $52.55 |
| 6 | Water (203-06) | MG | 22 | $105.00 | $11.00 | $25.00 | $15.00 | $127.85 | $17.70 |
| 7 | Sediment removal (209-05) | CY | 102 | $33.60 | $7.00 | $25.00 | $18.00 | $28.98 | $35.40 |
| 8 | Temporary silt fence (with backing) (209-08.02) | LF | 55 | $5.78 | $8.30 | $20.00 | $9.60 | $61.21 | $8.31 |
| 9 | Temporary silt fence (without backing) (209-08.03) | LF | 825 | $2.10 | $2.90 | $12.00 | $3.35 | $25.39 | $2.90 |
| 10 | Enhanced rock check dam (209-08.08) | EACH | 1 | $630.00 | $2,000.00 | $550.00 | $2,300.00 | $3,135.82 | $2,002.66 |
| 11 | Filter sock check dam (209-08.09) | EACH | 2 | $288.75 | $900.00 | $330.00 | $1,040.00 | $508.05 | $901.20 |
| 12 | Catch basin protection (type D) (209-40.33) | EACH | 2 | $210.00 | $800.00 | $550.00 | $921.00 | $426.97 | $801.06 |
| 13 | Mineral aggregate, type A base, grading D (303-01) | TON | 1,849 | $33.25 | $40.00 | $52.00 | $51.00 | $68.98 | $55.03 |
| 14 | Mineral aggregate (size 57) (303-10.01) | TON | 17 | $63.53 | $88.15 | $85.00 | $94.00 | $34.16 | $431.85 |
| 15 | Asp. conc. mix(PG70-22) (BPMB-HM) GR. A-S (307-01.21) | TON | 597 | $95.00 | $154.00 | $158.00 | $109.00 | $160.42 | $190.21 |
| 16 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01) | TON | 628 | $95.00 | $156.00 | $158.00 | $109.00 | $156.43 | $180.62 |
| 17 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08) | TON | 496 | $116.05 | $177.00 | $158.00 | $134.00 | $158.45 | $213.48 |
| 18 | Bituminous material for prime coat (PC) (402-01) | TON | 6 | $1,160.00 | $1,500.00 | $500.00 | $1,340.00 | $2,180.56 | $920.35 |
| 19 | Aggregate for cover material (PC) (402-02) | TON | 23 | $60.00 | $150.00 | $75.00 | $69.00 | $75.77 | $403.45 |
| 20 | Bituminous material for tack coat (TC) (403-01) | TON | 21 | $1,025.00 | $1,000.00 | $500.00 | $1,180.00 | $1,570.58 | $1,025.63 |
| 21 | Saw cutting asphalt pavement (407-20.05) | LF | 1,323 | $3.15 | $8.75 | $11.00 | $12.00 | $9.65 | $10.01 |
| 22 | Acs mix(PG70-22) grading D (411-02.10) | TON | 2,352 | $123.15 | $130.00 | $190.00 | $144.00 | $153.41 | $177.68 |
| 23 | Scoring shoulders (continuous) (16IN width) (411-12.01) | LM | 0.16 | $11,918 | $11,350 | $12,800 | $15,010 | $32,050 | $11,365 |
| 24 | Scoring shoulders (non-continuous) (16IN width) (411-12.02) | LM | 0.55 | $11,918 | $11,350 | $12,800 | $15,010 | $18,814 | $11,365 |
| 25 | Cold planing bituminous pavement (415-01.01) | TON | 1,801 | $16.00 | $19.00 | $59.00 | $20.20 | $57.67 | $41.11 |
| 26 | 18" concrete pipe culvert (class III) (607-03.02) | LF | 8 | $120.75 | $230.80 | $575.00 | $474.00 | $185.63 | $924.88 |
| 27 | 24" concrete pipe culvert (class III) (607-05.02) | LF | 330 | $204.75 | $187.00 | $220.00 | $160.00 | $226.55 | $191.25 |
| 28 | Manholes, > 4' - 8' depth (611-01.02) | EACH | 1 | $5,880.00 | $5,425.00 | $9,700.00 | $9,180.00 | $8,898.64 | $2,571.93 |
| 29 | 18IN endwall (side drain) (611-07.31) | EACH | 1 | $5,985.00 | $3,645.00 | $3,100.00 | $5,180.00 | $6,069.67 | $7,506.51 |
| 30 | 24IN endwall (side drain) (611-07.32) | EACH | 2 | $8,295.00 | $5,075.00 | $5,000.00 | $6,750.00 | $7,764.46 | $9,184.83 |
| 31 | Portable barrier rail delineator (705-04.50) | EACH | 85 | $9.45 | $9.00 | $10.00 | $11.50 | $56.06 | $18.52 |
| 32 | High-visibility construction fence (707-08.11) | LF | 1,800 | $2.10 | $2.95 | $11.00 | $3.40 | $4.18 | $2.95 |
| 33 | Machined rip-rap (class A-3) (709-05.05) | TON | 201 | $56.70 | $54.00 | $85.00 | $53.00 | $55.71 | $106.74 |
| 34 | Machined rip-rap (class A-1) (709-05.06) | TON | 91 | $77.70 | $57.00 | $85.00 | $72.00 | $69.03 | $99.93 |
| 35 | Aggregate underdrains (with pipe) (710-02) | LF | 1,015 | $13.39 | $20.00 | $15.00 | $14.70 | $14.10 | $43.10 |
| 36 | Lateral underdrain (710-05) | LF | 112 | $12.60 | $20.00 | $14.00 | $13.80 | $13.29 | $86.54 |
| 37 | Lateral underdrain endwall (6:1) (710-06.15) | EACH | 5 | $1,575.00 | $1,500.00 | $1,750.00 | $1,730.00 | $1,655.54 | $3,641.27 |
| 38 | Traffic control (712-01) | LS | 1 | $52,500 | $48,000 | $85,000 | $78,115 | $57,721 | $48,865 |
| 39 | Interconnected portable barrier rail (712-02.02) | LF | 2,920 | $35.00 | $48.00 | $55.00 | $88.00 | $56.06 | $61.71 |
| 40 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 7 | $7,024.00 | $10,490 | $9,500.00 | $7,490.00 | $896.81 | $11,095 |
| 41 | Flexible drums (channelizing) (712-04.01) | EACH | 173 | $31.50 | $35.50 | $50.00 | $37.00 | $37.76 | $35.55 |
| 42 | Warning lights (type A) (712-05.01) | EACH | 40 | $36.75 | $36.00 | $50.00 | $23.00 | $23.60 | $36.05 |
| 43 | Warning lights (type C) (712-05.03) | EACH | 43 | $5.25 | $38.00 | $52.00 | $23.00 | $23.60 | $38.05 |
| 44 | Signs (construction) (712-06) | SF | 903 | $7.14 | $6.80 | $9.00 | $8.80 | $8.97 | $6.81 |
| 45 | Temporary barricades (type III) (712-07.03) | LF | 20 | $12.60 | $17.00 | $20.00 | $32.50 | $33.04 | $17.02 |
| 46 | Arrow board (type C) (712-08.03) | EACH | 2 | $3,780.00 | $950.00 | $1,750.00 | $1,380.00 | $1,416.01 | $1,552.06 |
| 47 | "U" section steel posts (713-11.01) | LB | 23 | $7.35 | $7.00 | $8.00 | $3.40 | $6.41 | $7.01 |
| 48 | Perforated/knockout square tube post (713-11.02) | LB | 1,778 | $7.30 | $6.95 | $8.00 | $4.10 | $6.58 | $6.96 |
| 49 | P post slip base (713-11.21) | EACH | 44 | $315.00 | $300.00 | $330.00 | $513.00 | $748.75 | $300.40 |
| 50 | U post slip base (713-11.22) | EACH | 1 | $630.00 | $600.00 | $700.00 | $513.00 | $428.18 | $600.80 |
| 51 | Flat sheet aluminum signs (0.080" thick) (713-13.02) | SF | 294 | $17.33 | $16.50 | $18.00 | $15.10 | $19.68 | $16.52 |
| 52 | Flat sheet aluminum signs (0.100" thick) (713-13.03) | SF | 86 | $17.85 | $17.00 | $18.50 | $16.90 | $20.21 | $17.02 |
| 53 | Street name sign (rigid 0.100IN thick (713-14.21) | SF | 32 | $40.00 | $40.00 | $44.00 | $46.00 | $64.10 | $23.03 |
| 54 | Removal of signs, posts and footings (713-15) | LS | 1 | $420.00 | $400.00 | $500.00 | $1,440.00 | $2,139.64 | $400.53 |
| 55 | Removal & relocation of sign & support (713-15.02) | EACH | 2 | $105.00 | $100.00 | $150.00 | $339.00 | $1,676.04 | $100.14 |
| 56 | Suspended flat sheet aluminum sign (0.080" thick) (713-15.07) | EACH | 4 | $750.00 | $750.00 | $800.00 | $864.00 | $969.97 | $175.23 |
| 57 | Changeable message sign unit (713-16.01) | EACH | 4 | $9,135.00 | $7,800.00 | $8,500.00 | $6,850.00 | $7,021.05 | $7,810.36 |
| 58 | Solar flashing assembly (with 48” sign) (713-16.11) | EACH | 8 | $3,150.00 | $3,000.00 | $3,300.00 | $3,420.00 | $2,950.02 | $300.40 |
| 59 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 109 | $36.75 | $45.00 | $45.00 | $52.00 | $50.99 | $45.06 |
| 60 | Snowplowable raised pavement markers (BI-dir)(2 color) (716-01.23) | EACH | 150 | $37.80 | $45.00 | $45.00 | $52.00 | $45.61 | $45.06 |
| 61 | Plastic pavement marking(channelization striping) (716-02.04) | SY | 192 | $36.75 | $30.00 | $30.00 | $34.50 | $28.08 | $30.04 |
| 62 | Plastic pavement marking (stop line) (716-02.05) | LF | 172 | $21.00 | $20.00 | $20.00 | $23.00 | $17.11 | $20.03 |
| 63 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 11 | $183.75 | $200.00 | $200.00 | $230.00 | $255.24 | $200.27 |
| 64 | Plastic pavement marking (8" dotted line) (716-02.08) | LF | 1,003 | $2.63 | $3.00 | $3.00 | $3.45 | $3.48 | $3.00 |
| 65 | Plastic pavement marking (8IN line) (716-02.12) | LM | 0.10 | $10,500 | $20,000 | $20,000 | $23,030 | $12,049 | $20,027 |
| 66 | Plastic pavement marking (straight-turn arrow) (716-04.01) | EACH | 1 | $367.50 | $300.00 | $300.00 | $346.00 | $412.71 | $300.40 |
| 67 | Plastic pavement marking (transverse shoulder) (716-04.04) | LF | 1,347 | $12.60 | $10.00 | $10.00 | $11.50 | $9.48 | $10.01 |
| 68 | Painted pavement marking (8" barrier line) (716-05.02) | LF | 7,540 | $1.05 | $0.80 | $0.80 | $0.90 | $0.53 | $0.80 |
| 69 | Painted pavement marking (stop line) (716-05.05) | LF | 164 | $15.75 | $12.00 | $12.00 | $13.80 | $9.11 | $12.02 |
| 70 | Painted pavement marking (6" line) (716-05.20) | LM | 0.57 | $1,365.00 | $3,500.00 | $3,500.00 | $4,030.00 | $1,781.28 | $3,504.65 |
| 71 | Removal of pavement marking (line) (716-08.01) | LF | 4,288 | $1.00 | $1.50 | $1.50 | $1.75 | $1.42 | $1.50 |
| 72 | Removal of pavement marking (stop line) (716-08.05) | LF | 27 | $7.35 | $12.00 | $12.00 | $13.80 | $4.55 | $12.02 |
| 73 | Removal of pavement marking (turn lane arrow) (716-08.06) | EACH | 2 | $105.00 | $100.00 | $100.00 | $115.00 | $94.98 | $100.14 |
| 74 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 2.25 | $8,400.00 | $9,500.00 | $9,500.00 | $10,665 | $8,667.10 | $9,512.62 |
| 75 | Mobilization (717-01) | LS | 1 | $117,425 | $115,000 | $85,000 | $192,175 | $136,609 | $288,471 |
| 76 | Signal head assembly (130 with backplate) (730-02.09) | EACH | 6 | $1,522.50 | $1,450.00 | $1,450.00 | $1,670.00 | $1,556.17 | $1,451.93 |
| 77 | Signal head assembly (140 A1 with backplate) (730-02.14) | EACH | 2 | $1,706.25 | $1,625.00 | $1,625.00 | $1,870.00 | $1,742.86 | $1,627.16 |
| 78 | Signal head assembly (140 A3F with backplate) (730-02.57) | EACH | 2 | $1,706.25 | $1,625.00 | $1,625.00 | $1,960.00 | $2,113.59 | $1,627.16 |
| 79 | Signal head assembly (140 A4F with backplate) (730-02.59) | EACH | 2 | $1,706.25 | $1,625.00 | $1,625.00 | $1,960.00 | $2,113.59 | $1,627.16 |
| 80 | Install pull box (type B) (730-03.21) | EACH | 4 | $1,050.00 | $1,000.00 | $1,000.00 | $1,150.00 | $1,143.36 | $1,001.33 |
| 81 | Electrical service connection (730-05.01) | EACH | 1 | $8,400.00 | $8,000.00 | $8,000.00 | $9,210.00 | $3,856.75 | $8,010.62 |
| 82 | Signal cable - 7 conductor (730-08.03) | LF | 1,160 | $2.63 | $2.50 | $2.50 | $2.90 | $5.18 | $2.50 |
| 83 | Conduit 2" diameter (PVC schedule 40) (730-12.02) | LF | 200 | $29.40 | $28.00 | $28.00 | $32.50 | $24.74 | $28.04 |
| 84 | Conduit 2" diameter (directional bore) (730-12.23) | LF | 755 | $89.25 | $85.00 | $85.00 | $98.00 | $69.01 | $85.11 |
| 85 | Vehicle detector (radar - stop line) (730-13.12) | EACH | 4 | $12,600 | $12,000 | $12,000 | $13,820 | $12,993 | $12,016 |
| 86 | Vehicle detector (radar - advance) (730-13.13) | EACH | 3 | $12,600 | $12,000 | $12,000 | $13,820 | $14,798 | $12,016 |
| 87 | Cabinet (eight phase base mounted) (730-15.32) | EACH | 1 | $21,000 | $20,000 | $20,000 | $23,030 | $28,572 | $20,027 |
| 88 | Controller (atc) (730-16.04) | EACH | 1 | $6,300.00 | $6,000.00 | $6,000.00 | $6,910.00 | $8,121.66 | $6,007.97 |
| 89 | Cantilever signal support (1 arm @ 45') (730-23.88) | EACH | 1 | $28,875 | $27,500 | $27,500 | $31,670 | $35,642 | $27,537 |
| 90 | Cantilever signal support (1 arm @ 55') (730-25.07) | EACH | 1 | $33,863 | $32,250 | $32,250 | $37,140 | $38,064 | $32,293 |
| 91 | Cantilever signal support (1 arm @ 85') (730-25.17) | EACH | 2 | $58,538 | $55,750 | $55,750 | $64,210 | $80,736 | $55,824 |
| 92 | Temporary traffic signal system (730-40) | EACH | 1 | $31,500 | $30,000 | $30,000 | $34,550 | $90,186 | $30,040 |
| 93 | Geotextile (type III)(erosion control) (740-10.03) | SY | 559 | $4.20 | $3.10 | $9.00 | $3.45 | $5.89 | $5.41 |
| 94 | Temporary sediment tube 12IN (740-11.02) | LF | 225 | $3.68 | $7.90 | $15.00 | $9.10 | $4.53 | $7.91 |
| 95 | Seeding (with mulch) (801-01) | UNIT | 56 | $78.75 | $55.00 | $100.00 | $86.50 | $209.27 | $55.07 |
| 96 | Temporary seeding (with mulch) (801-01.07) | UNIT | 112 | $52.50 | $43.00 | $90.00 | $57.50 | $64.78 | $43.06 |
| 97 | Water (seeding & sodding) (801-03) | MG | 17 | $105.00 | $100.00 | $100.00 | $115.00 | $97.39 | $100.13 |
| 98 | Project mowing (806-02.03) | CYCL | 2 | $2,100.00 | $500.00 | $5,000.00 | $2,300.00 | $7,499.90 | $2,002.66 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of May 9, 2025. Compiled by Mirage Metrics.