TDOT contract CNZ147 bid tabulation

The construction of turn lanes on u.s. 231 (s.r. 10) at the intersection of s.r. 82 (sawney webb memorial highway) (l.m. 17.52), including signals. Let by Tennessee DOT on May 9, 2025, Bedford County. 6 bids received; low bid $1,875,792 by Tinsley Asphalt, LLC.

Owner
Tennessee DOT
Letting
09 MAY 2025
Pay items
98
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Tinsley Asphalt, LLC$1,875,792Low
2Hawkins Asphalt Paving, LLC$2,060,007+10%
3Sessions Paving Company$2,396,662+28%
4Civil Constructors, LLC$2,413,427+29%
5Rogers Group, Inc.$2,558,605+36%
6Wiregrass Construction Company, Inc$2,581,088+38%
TDOT contract CNZ147: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Tinsley Asphalt, LLC2. Hawkins Asphalt Paving, LLC3. Sessions Paving Company4. Civil Constructors, LLC5. Rogers Group, Inc.6. Wiregrass Construction Company, Inc
1Construction stakes, lines and grades (105-01)LS1$25,000$24,000$45,000$21,980$61,669$19,105
2Removal of structures and obstructions (202-01)LS1$15,750$6,500.00$10,000$18,250$9,973.34$5,635.52
3Road & drainage excavation (unclassified) (203-01)CY1,907$42.00$50.35$50.00$80.50$57.97$40.64
4Borrow excavation (unclassified) (203-03)CY459$36.75$86.00$70.00$72.50$60.21$114.36
5Placing and spreading topsoil (203-04)CY353$33.60$23.00$30.00$57.50$131.57$52.55
6Water (203-06)MG22$105.00$11.00$25.00$15.00$127.85$17.70
7Sediment removal (209-05)CY102$33.60$7.00$25.00$18.00$28.98$35.40
8Temporary silt fence (with backing) (209-08.02)LF55$5.78$8.30$20.00$9.60$61.21$8.31
9Temporary silt fence (without backing) (209-08.03)LF825$2.10$2.90$12.00$3.35$25.39$2.90
10Enhanced rock check dam (209-08.08)EACH1$630.00$2,000.00$550.00$2,300.00$3,135.82$2,002.66
11Filter sock check dam (209-08.09)EACH2$288.75$900.00$330.00$1,040.00$508.05$901.20
12Catch basin protection (type D) (209-40.33)EACH2$210.00$800.00$550.00$921.00$426.97$801.06
13Mineral aggregate, type A base, grading D (303-01)TON1,849$33.25$40.00$52.00$51.00$68.98$55.03
14Mineral aggregate (size 57) (303-10.01)TON17$63.53$88.15$85.00$94.00$34.16$431.85
15Asp. conc. mix(PG70-22) (BPMB-HM) GR. A-S (307-01.21)TON597$95.00$154.00$158.00$109.00$160.42$190.21
16Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01)TON628$95.00$156.00$158.00$109.00$156.43$180.62
17Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08)TON496$116.05$177.00$158.00$134.00$158.45$213.48
18Bituminous material for prime coat (PC) (402-01)TON6$1,160.00$1,500.00$500.00$1,340.00$2,180.56$920.35
19Aggregate for cover material (PC) (402-02)TON23$60.00$150.00$75.00$69.00$75.77$403.45
20Bituminous material for tack coat (TC) (403-01)TON21$1,025.00$1,000.00$500.00$1,180.00$1,570.58$1,025.63
21Saw cutting asphalt pavement (407-20.05)LF1,323$3.15$8.75$11.00$12.00$9.65$10.01
22Acs mix(PG70-22) grading D (411-02.10)TON2,352$123.15$130.00$190.00$144.00$153.41$177.68
23Scoring shoulders (continuous) (16IN width) (411-12.01)LM0.16$11,918$11,350$12,800$15,010$32,050$11,365
24Scoring shoulders (non-continuous) (16IN width) (411-12.02)LM0.55$11,918$11,350$12,800$15,010$18,814$11,365
25Cold planing bituminous pavement (415-01.01)TON1,801$16.00$19.00$59.00$20.20$57.67$41.11
2618" concrete pipe culvert (class III) (607-03.02)LF8$120.75$230.80$575.00$474.00$185.63$924.88
2724" concrete pipe culvert (class III) (607-05.02)LF330$204.75$187.00$220.00$160.00$226.55$191.25
28Manholes, > 4' - 8' depth (611-01.02)EACH1$5,880.00$5,425.00$9,700.00$9,180.00$8,898.64$2,571.93
2918IN endwall (side drain) (611-07.31)EACH1$5,985.00$3,645.00$3,100.00$5,180.00$6,069.67$7,506.51
3024IN endwall (side drain) (611-07.32)EACH2$8,295.00$5,075.00$5,000.00$6,750.00$7,764.46$9,184.83
31Portable barrier rail delineator (705-04.50)EACH85$9.45$9.00$10.00$11.50$56.06$18.52
32High-visibility construction fence (707-08.11)LF1,800$2.10$2.95$11.00$3.40$4.18$2.95
33Machined rip-rap (class A-3) (709-05.05)TON201$56.70$54.00$85.00$53.00$55.71$106.74
34Machined rip-rap (class A-1) (709-05.06)TON91$77.70$57.00$85.00$72.00$69.03$99.93
35Aggregate underdrains (with pipe) (710-02)LF1,015$13.39$20.00$15.00$14.70$14.10$43.10
36Lateral underdrain (710-05)LF112$12.60$20.00$14.00$13.80$13.29$86.54
37Lateral underdrain endwall (6:1) (710-06.15)EACH5$1,575.00$1,500.00$1,750.00$1,730.00$1,655.54$3,641.27
38Traffic control (712-01)LS1$52,500$48,000$85,000$78,115$57,721$48,865
39Interconnected portable barrier rail (712-02.02)LF2,920$35.00$48.00$55.00$88.00$56.06$61.71
40Temporary work zone crash cushion (MASH TL-3) (712-02.60)EACH7$7,024.00$10,490$9,500.00$7,490.00$896.81$11,095
41Flexible drums (channelizing) (712-04.01)EACH173$31.50$35.50$50.00$37.00$37.76$35.55
42Warning lights (type A) (712-05.01)EACH40$36.75$36.00$50.00$23.00$23.60$36.05
43Warning lights (type C) (712-05.03)EACH43$5.25$38.00$52.00$23.00$23.60$38.05
44Signs (construction) (712-06)SF903$7.14$6.80$9.00$8.80$8.97$6.81
45Temporary barricades (type III) (712-07.03)LF20$12.60$17.00$20.00$32.50$33.04$17.02
46Arrow board (type C) (712-08.03)EACH2$3,780.00$950.00$1,750.00$1,380.00$1,416.01$1,552.06
47"U" section steel posts (713-11.01)LB23$7.35$7.00$8.00$3.40$6.41$7.01
48Perforated/knockout square tube post (713-11.02)LB1,778$7.30$6.95$8.00$4.10$6.58$6.96
49P post slip base (713-11.21)EACH44$315.00$300.00$330.00$513.00$748.75$300.40
50U post slip base (713-11.22)EACH1$630.00$600.00$700.00$513.00$428.18$600.80
51Flat sheet aluminum signs (0.080" thick) (713-13.02)SF294$17.33$16.50$18.00$15.10$19.68$16.52
52Flat sheet aluminum signs (0.100" thick) (713-13.03)SF86$17.85$17.00$18.50$16.90$20.21$17.02
53Street name sign (rigid 0.100IN thick (713-14.21)SF32$40.00$40.00$44.00$46.00$64.10$23.03
54Removal of signs, posts and footings (713-15)LS1$420.00$400.00$500.00$1,440.00$2,139.64$400.53
55Removal & relocation of sign & support (713-15.02)EACH2$105.00$100.00$150.00$339.00$1,676.04$100.14
56Suspended flat sheet aluminum sign (0.080" thick) (713-15.07)EACH4$750.00$750.00$800.00$864.00$969.97$175.23
57Changeable message sign unit (713-16.01)EACH4$9,135.00$7,800.00$8,500.00$6,850.00$7,021.05$7,810.36
58Solar flashing assembly (with 48” sign) (713-16.11)EACH8$3,150.00$3,000.00$3,300.00$3,420.00$2,950.02$300.40
59Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21)EACH109$36.75$45.00$45.00$52.00$50.99$45.06
60Snowplowable raised pavement markers (BI-dir)(2 color) (716-01.23)EACH150$37.80$45.00$45.00$52.00$45.61$45.06
61Plastic pavement marking(channelization striping) (716-02.04)SY192$36.75$30.00$30.00$34.50$28.08$30.04
62Plastic pavement marking (stop line) (716-02.05)LF172$21.00$20.00$20.00$23.00$17.11$20.03
63Plastic pavement marking (turn lane arrow) (716-02.06)EACH11$183.75$200.00$200.00$230.00$255.24$200.27
64Plastic pavement marking (8" dotted line) (716-02.08)LF1,003$2.63$3.00$3.00$3.45$3.48$3.00
65Plastic pavement marking (8IN line) (716-02.12)LM0.10$10,500$20,000$20,000$23,030$12,049$20,027
66Plastic pavement marking (straight-turn arrow) (716-04.01)EACH1$367.50$300.00$300.00$346.00$412.71$300.40
67Plastic pavement marking (transverse shoulder) (716-04.04)LF1,347$12.60$10.00$10.00$11.50$9.48$10.01
68Painted pavement marking (8" barrier line) (716-05.02)LF7,540$1.05$0.80$0.80$0.90$0.53$0.80
69Painted pavement marking (stop line) (716-05.05)LF164$15.75$12.00$12.00$13.80$9.11$12.02
70Painted pavement marking (6" line) (716-05.20)LM0.57$1,365.00$3,500.00$3,500.00$4,030.00$1,781.28$3,504.65
71Removal of pavement marking (line) (716-08.01)LF4,288$1.00$1.50$1.50$1.75$1.42$1.50
72Removal of pavement marking (stop line) (716-08.05)LF27$7.35$12.00$12.00$13.80$4.55$12.02
73Removal of pavement marking (turn lane arrow) (716-08.06)EACH2$105.00$100.00$100.00$115.00$94.98$100.14
74Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM2.25$8,400.00$9,500.00$9,500.00$10,665$8,667.10$9,512.62
75Mobilization (717-01)LS1$117,425$115,000$85,000$192,175$136,609$288,471
76Signal head assembly (130 with backplate) (730-02.09)EACH6$1,522.50$1,450.00$1,450.00$1,670.00$1,556.17$1,451.93
77Signal head assembly (140 A1 with backplate) (730-02.14)EACH2$1,706.25$1,625.00$1,625.00$1,870.00$1,742.86$1,627.16
78Signal head assembly (140 A3F with backplate) (730-02.57)EACH2$1,706.25$1,625.00$1,625.00$1,960.00$2,113.59$1,627.16
79Signal head assembly (140 A4F with backplate) (730-02.59)EACH2$1,706.25$1,625.00$1,625.00$1,960.00$2,113.59$1,627.16
80Install pull box (type B) (730-03.21)EACH4$1,050.00$1,000.00$1,000.00$1,150.00$1,143.36$1,001.33
81Electrical service connection (730-05.01)EACH1$8,400.00$8,000.00$8,000.00$9,210.00$3,856.75$8,010.62
82Signal cable - 7 conductor (730-08.03)LF1,160$2.63$2.50$2.50$2.90$5.18$2.50
83Conduit 2" diameter (PVC schedule 40) (730-12.02)LF200$29.40$28.00$28.00$32.50$24.74$28.04
84Conduit 2" diameter (directional bore) (730-12.23)LF755$89.25$85.00$85.00$98.00$69.01$85.11
85Vehicle detector (radar - stop line) (730-13.12)EACH4$12,600$12,000$12,000$13,820$12,993$12,016
86Vehicle detector (radar - advance) (730-13.13)EACH3$12,600$12,000$12,000$13,820$14,798$12,016
87Cabinet (eight phase base mounted) (730-15.32)EACH1$21,000$20,000$20,000$23,030$28,572$20,027
88Controller (atc) (730-16.04)EACH1$6,300.00$6,000.00$6,000.00$6,910.00$8,121.66$6,007.97
89Cantilever signal support (1 arm @ 45') (730-23.88)EACH1$28,875$27,500$27,500$31,670$35,642$27,537
90Cantilever signal support (1 arm @ 55') (730-25.07)EACH1$33,863$32,250$32,250$37,140$38,064$32,293
91Cantilever signal support (1 arm @ 85') (730-25.17)EACH2$58,538$55,750$55,750$64,210$80,736$55,824
92Temporary traffic signal system (730-40)EACH1$31,500$30,000$30,000$34,550$90,186$30,040
93Geotextile (type III)(erosion control) (740-10.03)SY559$4.20$3.10$9.00$3.45$5.89$5.41
94Temporary sediment tube 12IN (740-11.02)LF225$3.68$7.90$15.00$9.10$4.53$7.91
95Seeding (with mulch) (801-01)UNIT56$78.75$55.00$100.00$86.50$209.27$55.07
96Temporary seeding (with mulch) (801-01.07)UNIT112$52.50$43.00$90.00$57.50$64.78$43.06
97Water (seeding & sodding) (801-03)MG17$105.00$100.00$100.00$115.00$97.39$100.13
98Project mowing (806-02.03)CYCL2$2,100.00$500.00$5,000.00$2,300.00$7,499.90$2,002.66
TDOT contract CNZ147: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of May 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy