TDOT contract CN261026 bid tabulation

The construction of a small drainage structure on s.r. 347 at l.m. 5.77. Let by Tennessee DOT on March 20, 2026, Sullivan County. 4 bids received; low bid $1,469,878 by Southern Constructors, Inc..

Owner
Tennessee DOT
Letting
20 MAR 2026
Pay items
64
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Southern Constructors, Inc.$1,469,878Low
2Summers-Taylor, Inc.$1,732,601+18%
3King General Contractors, Inc.$1,924,170+31%
4Jones Road & Bridge, Inc$1,989,460+35%
TDOT contract CN261026: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Southern Constructors, Inc.2. Summers-Taylor, Inc.3. King General Contractors, Inc.4. Jones Road & Bridge, Inc
1Construction stakes, lines and grades (105-01)LS1$30,000$17,300$58,706$40,000
2Clearing and grubbing (201-01)LS1$25,000$49,500$21,930$60,000
3Road & drainage excavation (unclassified) (203-01)CY3,682$50.00$72.00$33.06$80.00
4Placing and spreading topsoil (203-04)CY388$38.00$40.00$47.23$50.00
5Furnishing & spreading topsoil (203-07)CY159$100.00$85.00$117.41$120.00
6Channel substrate (203-20.01)CY116$200.00$301.00$1,248.35$98.00
7Natural streambed material(removal-storage-placement) (203-20.02)CY52$225.00$455.00$742.26$98.00
8Foundation fill material (204-08)CY51$175.00$162.00$458.85$90.00
9Sediment removal (209-05)CY20$50.00$56.00$33.74$40.00
10Temporary silt fence (with backing) (209-08.02)LF720$10.00$11.80$13.56$12.00
11Enhanced rock check dam (209-08.08)EACH7$2,000.00$1,250.00$809.74$1,000.00
12Sandbags (209-09.01)BAG300$20.00$15.00$44.54$12.00
13Sediment filter bag(15' X 10') (209-09.04)EACH2$1,000.00$1,600.00$1,855.66$3,000.00
14Polyethylene sheeting (6 mil. minimum) (209-20.03)SY300$12.00$13.60$12.08$15.00
15Temporary diversion channel (209-65.03)LF332$125.00$245.00$176.79$122.00
16Mineral aggregate, type A base, grading D (303-01)TON1,119$80.00$91.65$111.00$80.00
17Granular backfill (roadway) (303-01.01)TON807$80.00$78.00$121.12$90.00
18Mineral aggregate (size 57) (303-10.01)TON16$90.00$144.00$182.19$100.00
19Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON194$260.00$252.00$313.10$324.00
20Bituminous material for prime coat (PC) (402-01)TON4$2,000.00$2,130.00$2,699.14$2,280.00
21Aggregate for cover material (PC) (402-02)TON14$410.00$138.00$356.29$420.00
22Bituminous material for tack coat (TC) (403-01)TON1$1,000.00$1,350.00$2,699.14$1,560.00
23Acs mix(PG64-22) grading D (411-01.10)TON159$330.00$337.00$361.68$449.00
24Cold planing bituminous pavement (415-01.02)SY267$25.00$29.65$20.22$59.00
25Class A concrete (roadway) (604-01.01)CY134$1,650.00$2,575.00$1,207.86$2,600.00
26Steel bar reinforcement (roadway) (604-01.02)LB23,036$2.00$0.25$7.45$7.00
2718" pipe culvert (side drain) (607-39.02)LF250$150.00$169.00$109.32$175.00
28Class A concrete (pipe endwalls) (611-07.01)CY3$2,500.00$3,900.00$3,485.93$4,000.00
29Steel bar reinforcement (pipe endwalls) (611-07.02)LB135$2.00$1.30$9.78$12.00
3018IN endwall (side drain) (611-07.31)EACH6$4,500.00$7,500.00$6,220.16$6,000.00
3118IN endwall (cross drain) 3:1 (611-07.54)EACH5$2,200.00$3,250.00$3,326.69$2,300.00
32Concrete driveway (701-02)SF1,874$15.00$14.00$48.25$18.00
33Stock fence (707-03.01)LF140$45.00$54.00$31.71$30.00
34End, braced line, corner post assembly(stock fence) (707-03.02)EACH4$500.00$625.00$742.26$1,000.00
35Drive gate (stock fence) (description) (707-03.20)EACH1$2,500.00$2,780.00$3,306.44$1,200.00
36Machined rip-rap (class A-3) (709-05.05)TON200$90.00$107.00$134.96$102.00
37Machined rip-rap (class A-1) (709-05.06)TON999$100.00$91.00$134.96$102.00
38Machined rip-rap (class B) (709-05.08)TON260$100.00$104.00$148.45$100.00
39Machined rip-rap (class C) (709-05.09)TON32$110.00$110.00$178.82$100.00
40Traffic control (712-01)LS1$30,000$21,500$51,958$75,000
41Warning lights (type A) (712-05.01)EACH8$40.00$34.25$67.48$300.00
42Signs (construction) (712-06)SF483$12.00$9.60$9.45$35.00
43Temporary barricades (type III) (712-07.03)LF96$40.00$20.00$20.24$80.00
44Sign post delineation enhancement (713-02.21)LF30$5.00$5.20$9.45$40.00
45"U" section steel posts (713-11.01)LB89$7.50$6.50$12.15$10.00
46Perforated/knockout square tube post (713-11.02)LB64$10.00$6.20$9.45$8.00
47P post slip base (713-11.21)EACH1$750.00$720.00$16.19$550.00
48Flat sheet aluminum signs (0.080" thick) (713-13.02)SF12$15.00$16.50$26.99$40.00
49Flat sheet aluminum signs (0.100" thick) (713-13.03)SF9$17.00$18.50$29.69$40.00
50Removal of signs, posts and footings (713-15)LS1$500.00$135.00$607.31$5,000.00
51Changeable message sign unit (713-16.01)EACH4$7,500.00$7,600.00$9,784.37$4,000.00
52Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21)EACH7$60.00$70.80$101.22$300.00
53Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM0.41$13,000$12,850$13,496$60,000
54Mobilization (717-01)LS1$135,000$149,500$96,494$93,000
55Geotextile (type III)(erosion control) (740-10.03)SY1,993$12.00$9.50$11.47$5.00
56Temporary sediment tube 12IN (740-11.02)LF1,165$7.00$5.40$12.15$20.00
57Temporary sediment tube 20IN (740-11.04)LF234$10.00$6.10$16.19$25.00
58Seeding (with mulch) (801-01)UNIT28$50.00$58.00$87.72$200.00
59Temporary seeding (with mulch) (801-01.07)UNIT14$100.00$48.00$87.72$200.00
60Natve seed MX final stablizatn of slopes (801-01.38)UNIT7$150.00$148.00$236.17$300.00
61Seeding (without mulch) (801-02)UNIT31$50.00$34.00$67.48$180.00
62Fertilizer (801-02.15)TON1$2,600.00$1,270.00$4,048.70$2,200.00
63Water (seeding & sodding) (801-03)MG9$160.00$106.00$269.91$800.00
64Erosion control blanket (type II) (805-12.02)SY3,397$2.00$1.65$6.75$4.00
TDOT contract CN261026: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of March 20, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy