TDOT contract CN261026 bid tabulation
The construction of a small drainage structure on s.r. 347 at l.m. 5.77. Let by Tennessee DOT on March 20, 2026, Sullivan County. 4 bids received; low bid $1,469,878 by Southern Constructors, Inc..
- Owner
- Tennessee DOT
- Letting
- 20 MAR 2026
- Pay items
- 64
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Southern Constructors, Inc. | $1,469,878 | Low |
| 2 | Summers-Taylor, Inc. | $1,732,601 | +18% |
| 3 | King General Contractors, Inc. | $1,924,170 | +31% |
| 4 | Jones Road & Bridge, Inc | $1,989,460 | +35% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Southern Constructors, Inc. | 2. Summers-Taylor, Inc. | 3. King General Contractors, Inc. | 4. Jones Road & Bridge, Inc |
|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $30,000 | $17,300 | $58,706 | $40,000 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $25,000 | $49,500 | $21,930 | $60,000 |
| 3 | Road & drainage excavation (unclassified) (203-01) | CY | 3,682 | $50.00 | $72.00 | $33.06 | $80.00 |
| 4 | Placing and spreading topsoil (203-04) | CY | 388 | $38.00 | $40.00 | $47.23 | $50.00 |
| 5 | Furnishing & spreading topsoil (203-07) | CY | 159 | $100.00 | $85.00 | $117.41 | $120.00 |
| 6 | Channel substrate (203-20.01) | CY | 116 | $200.00 | $301.00 | $1,248.35 | $98.00 |
| 7 | Natural streambed material(removal-storage-placement) (203-20.02) | CY | 52 | $225.00 | $455.00 | $742.26 | $98.00 |
| 8 | Foundation fill material (204-08) | CY | 51 | $175.00 | $162.00 | $458.85 | $90.00 |
| 9 | Sediment removal (209-05) | CY | 20 | $50.00 | $56.00 | $33.74 | $40.00 |
| 10 | Temporary silt fence (with backing) (209-08.02) | LF | 720 | $10.00 | $11.80 | $13.56 | $12.00 |
| 11 | Enhanced rock check dam (209-08.08) | EACH | 7 | $2,000.00 | $1,250.00 | $809.74 | $1,000.00 |
| 12 | Sandbags (209-09.01) | BAG | 300 | $20.00 | $15.00 | $44.54 | $12.00 |
| 13 | Sediment filter bag(15' X 10') (209-09.04) | EACH | 2 | $1,000.00 | $1,600.00 | $1,855.66 | $3,000.00 |
| 14 | Polyethylene sheeting (6 mil. minimum) (209-20.03) | SY | 300 | $12.00 | $13.60 | $12.08 | $15.00 |
| 15 | Temporary diversion channel (209-65.03) | LF | 332 | $125.00 | $245.00 | $176.79 | $122.00 |
| 16 | Mineral aggregate, type A base, grading D (303-01) | TON | 1,119 | $80.00 | $91.65 | $111.00 | $80.00 |
| 17 | Granular backfill (roadway) (303-01.01) | TON | 807 | $80.00 | $78.00 | $121.12 | $90.00 |
| 18 | Mineral aggregate (size 57) (303-10.01) | TON | 16 | $90.00 | $144.00 | $182.19 | $100.00 |
| 19 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 194 | $260.00 | $252.00 | $313.10 | $324.00 |
| 20 | Bituminous material for prime coat (PC) (402-01) | TON | 4 | $2,000.00 | $2,130.00 | $2,699.14 | $2,280.00 |
| 21 | Aggregate for cover material (PC) (402-02) | TON | 14 | $410.00 | $138.00 | $356.29 | $420.00 |
| 22 | Bituminous material for tack coat (TC) (403-01) | TON | 1 | $1,000.00 | $1,350.00 | $2,699.14 | $1,560.00 |
| 23 | Acs mix(PG64-22) grading D (411-01.10) | TON | 159 | $330.00 | $337.00 | $361.68 | $449.00 |
| 24 | Cold planing bituminous pavement (415-01.02) | SY | 267 | $25.00 | $29.65 | $20.22 | $59.00 |
| 25 | Class A concrete (roadway) (604-01.01) | CY | 134 | $1,650.00 | $2,575.00 | $1,207.86 | $2,600.00 |
| 26 | Steel bar reinforcement (roadway) (604-01.02) | LB | 23,036 | $2.00 | $0.25 | $7.45 | $7.00 |
| 27 | 18" pipe culvert (side drain) (607-39.02) | LF | 250 | $150.00 | $169.00 | $109.32 | $175.00 |
| 28 | Class A concrete (pipe endwalls) (611-07.01) | CY | 3 | $2,500.00 | $3,900.00 | $3,485.93 | $4,000.00 |
| 29 | Steel bar reinforcement (pipe endwalls) (611-07.02) | LB | 135 | $2.00 | $1.30 | $9.78 | $12.00 |
| 30 | 18IN endwall (side drain) (611-07.31) | EACH | 6 | $4,500.00 | $7,500.00 | $6,220.16 | $6,000.00 |
| 31 | 18IN endwall (cross drain) 3:1 (611-07.54) | EACH | 5 | $2,200.00 | $3,250.00 | $3,326.69 | $2,300.00 |
| 32 | Concrete driveway (701-02) | SF | 1,874 | $15.00 | $14.00 | $48.25 | $18.00 |
| 33 | Stock fence (707-03.01) | LF | 140 | $45.00 | $54.00 | $31.71 | $30.00 |
| 34 | End, braced line, corner post assembly(stock fence) (707-03.02) | EACH | 4 | $500.00 | $625.00 | $742.26 | $1,000.00 |
| 35 | Drive gate (stock fence) (description) (707-03.20) | EACH | 1 | $2,500.00 | $2,780.00 | $3,306.44 | $1,200.00 |
| 36 | Machined rip-rap (class A-3) (709-05.05) | TON | 200 | $90.00 | $107.00 | $134.96 | $102.00 |
| 37 | Machined rip-rap (class A-1) (709-05.06) | TON | 999 | $100.00 | $91.00 | $134.96 | $102.00 |
| 38 | Machined rip-rap (class B) (709-05.08) | TON | 260 | $100.00 | $104.00 | $148.45 | $100.00 |
| 39 | Machined rip-rap (class C) (709-05.09) | TON | 32 | $110.00 | $110.00 | $178.82 | $100.00 |
| 40 | Traffic control (712-01) | LS | 1 | $30,000 | $21,500 | $51,958 | $75,000 |
| 41 | Warning lights (type A) (712-05.01) | EACH | 8 | $40.00 | $34.25 | $67.48 | $300.00 |
| 42 | Signs (construction) (712-06) | SF | 483 | $12.00 | $9.60 | $9.45 | $35.00 |
| 43 | Temporary barricades (type III) (712-07.03) | LF | 96 | $40.00 | $20.00 | $20.24 | $80.00 |
| 44 | Sign post delineation enhancement (713-02.21) | LF | 30 | $5.00 | $5.20 | $9.45 | $40.00 |
| 45 | "U" section steel posts (713-11.01) | LB | 89 | $7.50 | $6.50 | $12.15 | $10.00 |
| 46 | Perforated/knockout square tube post (713-11.02) | LB | 64 | $10.00 | $6.20 | $9.45 | $8.00 |
| 47 | P post slip base (713-11.21) | EACH | 1 | $750.00 | $720.00 | $16.19 | $550.00 |
| 48 | Flat sheet aluminum signs (0.080" thick) (713-13.02) | SF | 12 | $15.00 | $16.50 | $26.99 | $40.00 |
| 49 | Flat sheet aluminum signs (0.100" thick) (713-13.03) | SF | 9 | $17.00 | $18.50 | $29.69 | $40.00 |
| 50 | Removal of signs, posts and footings (713-15) | LS | 1 | $500.00 | $135.00 | $607.31 | $5,000.00 |
| 51 | Changeable message sign unit (713-16.01) | EACH | 4 | $7,500.00 | $7,600.00 | $9,784.37 | $4,000.00 |
| 52 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 7 | $60.00 | $70.80 | $101.22 | $300.00 |
| 53 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 0.41 | $13,000 | $12,850 | $13,496 | $60,000 |
| 54 | Mobilization (717-01) | LS | 1 | $135,000 | $149,500 | $96,494 | $93,000 |
| 55 | Geotextile (type III)(erosion control) (740-10.03) | SY | 1,993 | $12.00 | $9.50 | $11.47 | $5.00 |
| 56 | Temporary sediment tube 12IN (740-11.02) | LF | 1,165 | $7.00 | $5.40 | $12.15 | $20.00 |
| 57 | Temporary sediment tube 20IN (740-11.04) | LF | 234 | $10.00 | $6.10 | $16.19 | $25.00 |
| 58 | Seeding (with mulch) (801-01) | UNIT | 28 | $50.00 | $58.00 | $87.72 | $200.00 |
| 59 | Temporary seeding (with mulch) (801-01.07) | UNIT | 14 | $100.00 | $48.00 | $87.72 | $200.00 |
| 60 | Natve seed MX final stablizatn of slopes (801-01.38) | UNIT | 7 | $150.00 | $148.00 | $236.17 | $300.00 |
| 61 | Seeding (without mulch) (801-02) | UNIT | 31 | $50.00 | $34.00 | $67.48 | $180.00 |
| 62 | Fertilizer (801-02.15) | TON | 1 | $2,600.00 | $1,270.00 | $4,048.70 | $2,200.00 |
| 63 | Water (seeding & sodding) (801-03) | MG | 9 | $160.00 | $106.00 | $269.91 | $800.00 |
| 64 | Erosion control blanket (type II) (805-12.02) | SY | 3,397 | $2.00 | $1.65 | $6.75 | $4.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of March 20, 2026. Compiled by Mirage Metrics.