TDOT contract CN264031 bid tabulation
The construction of a concrete bulb-tee beam bridge on u.s. 51 (s.r. 3, thomas street) over overflow (l.m. 15.69), including grading, drainage, and paving. Let by Tennessee DOT on March 20, 2026, Shelby County. 3 bids received; low bid $7,342,446 by Dement Construction Group, LLC.
- Owner
- Tennessee DOT
- Letting
- 20 MAR 2026
- Pay items
- 122
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Dement Construction Group, LLC | $7,342,446 | Low |
| 2 | Chris-Hill Construction Co., LLC | $7,921,589 | +8.0% |
| 3 | Bell & Associates Construction, LLC | $8,094,869 | +10% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Dement Construction Group, LLC | 2. Chris-Hill Construction Co., LLC | 3. Bell & Associates Construction, LLC |
|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $100,000 | $75,000 | $177,725 |
| 2 | Trainee (109-10.01) | HR | 1,100 | $0.80 | $0.80 | $0.80 |
| 3 | Clearing and grubbing (201-01) | LS | 1 | $200,000 | $80,000 | $208,995 |
| 4 | Removal of asphalt pavement (202-03.01) | SY | 180 | $35.00 | $10.50 | $13.45 |
| 5 | Road & drainage excavation (unclassified) (203-01) | CY | 3,514 | $28.00 | $6.30 | $35.85 |
| 6 | Borrow excavation (unclassified) (203-03) | CY | 2,150 | $45.00 | $26.25 | $43.95 |
| 7 | Water (203-06) | MG | 25 | $40.00 | $21.00 | $44.25 |
| 8 | Furnishing & spreading topsoil (203-07) | CY | 755 | $25.00 | $26.25 | $56.90 |
| 9 | Sediment removal (209-05) | CY | 112 | $35.00 | $24.00 | $69.20 |
| 10 | Temporary silt fence (with backing) (209-08.02) | LF | 3,950 | $6.50 | $6.80 | $7.19 |
| 11 | Temporary silt fence (without backing) (209-08.03) | LF | 500 | $3.50 | $3.70 | $3.87 |
| 12 | Rock check dam (209-08.07) | EACH | 4 | $500.00 | $1,770.00 | $2,065.00 |
| 13 | Sandbags (209-09.01) | BAG | 25 | $15.00 | $20.00 | $31.00 |
| 14 | Polyethylene sheeting (10 mil.) (209-20.04) | SY | 200 | $5.00 | $4.90 | $9.33 |
| 15 | Mineral aggregate, type A base, grading D (303-01) | TON | 1,338 | $64.45 | $60.90 | $68.20 |
| 16 | Mineral aggregate (size 57) (303-10.01) | TON | 50 | $75.00 | $62.50 | $91.20 |
| 17 | Mineral aggregate (size 57) (303-10.04) | TON | 1,700 | $60.00 | $67.00 | $71.00 |
| 18 | Asp. conc. mix(PG70-22) (BPMB-HM) GR. A-S (307-01.21) | TON | 62 | $515.00 | $540.75 | $569.75 |
| 19 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01) | TON | 79 | $435.00 | $456.75 | $481.25 |
| 20 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08) | TON | 735 | $155.25 | $163.00 | $171.75 |
| 21 | Bituminous material for prime coat (PC) (402-01) | TON | 7 | $1,325.00 | $1,390.00 | $1,466.00 |
| 22 | Aggregate for cover material (PC) (402-02) | TON | 130 | $44.00 | $46.20 | $48.65 |
| 23 | Bituminous material for tack coat (TC) (403-01) | TON | 3 | $1,325.00 | $1,390.00 | $1,466.00 |
| 24 | Saw cutting asphalt pavement (407-20.05) | LF | 1,050 | $8.50 | $6.30 | $7.74 |
| 25 | Acs mix(PG70-22) grading D (411-02.10) | TON | 397 | $186.00 | $195.30 | $205.75 |
| 26 | Cold planing bituminous pavement (415-01.02) | SY | 1,657 | $11.00 | $11.55 | $12.15 |
| 27 | 18" temporary drainage pipe (621-03.02) | LF | 50 | $115.00 | $105.00 | $93.50 |
| 28 | Guardrail transition 27IN to 31IN (705-02.10) | EACH | 4 | $150.00 | $157.50 | $247.00 |
| 29 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 1,100 | $32.00 | $33.60 | $29.75 |
| 30 | Thrie beam bridge transition MASH TL-2 (705-06.26) | EACH | 4 | $2,550.00 | $2,675.00 | $2,808.00 |
| 31 | Guardrail removed (706-01) | LF | 1,270 | $4.00 | $4.20 | $3.82 |
| 32 | Chain link fence (6 foot) (707-01.11) | LF | 228 | $39.00 | $40.95 | $41.55 |
| 33 | Removal of fence (6 FT cahin link) (707-06.01) | LF | 228 | $15.00 | $15.75 | $20.20 |
| 34 | High-visibility construction fence (707-08.11) | LF | 2,724 | $3.00 | $3.15 | $3.32 |
| 35 | Machined rip-rap (class A-3) (709-05.05) | TON | 160 | $75.85 | $81.90 | $79.40 |
| 36 | Machined rip-rap (class A-1) (709-05.06) | TON | 5,259 | $60.00 | $81.90 | $63.90 |
| 37 | Aggregate underdrains (with pipe) (710-02) | LF | 1,050 | $18.00 | $31.50 | $24.35 |
| 38 | Lateral underdrain (710-05) | LF | 100 | $22.00 | $31.50 | $27.10 |
| 39 | Lateral underdrain endwall (3:1) (710-06.12) | EACH | 4 | $3,750.00 | $1,185.00 | $708.00 |
| 40 | Traffic control (712-01) | LS | 1 | $102,500 | $90,100 | $73,450 |
| 41 | Interconnected portable barrier rail (712-02.02) | LF | 600 | $65.00 | $70.00 | $112.75 |
| 42 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 2 | $10,000 | $8,925.00 | $9,402.00 |
| 43 | Flexible drums (channelizing) (712-04.01) | EACH | 100 | $50.00 | $39.90 | $42.05 |
| 44 | Barrier rail delineator (712-04.50) | EACH | 50 | $11.00 | $10.50 | $11.05 |
| 45 | Warning lights (type A) (712-05.01) | EACH | 50 | $25.00 | $6.30 | $6.64 |
| 46 | Warning lights (type C) (712-05.03) | EACH | 100 | $25.00 | $6.30 | $6.64 |
| 47 | Signs (construction) (712-06) | SF | 436 | $6.00 | $7.35 | $7.74 |
| 48 | Temporary barricades (type III) (712-07.03) | LF | 80 | $18.00 | $16.80 | $17.70 |
| 49 | Arrow board (type C) (712-08.03) | EACH | 2 | $1,500.00 | $1,575.00 | $1,659.00 |
| 50 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 7,360 | $7.00 | $7.35 | $7.74 |
| 51 | Perforated/knockout square tube post (713-11.02) | LB | 94 | $4.50 | $4.75 | $4.98 |
| 52 | Flat sheet aluminum signs (0.100" thick) (713-13.03) | SF | 24 | $16.00 | $16.80 | $17.70 |
| 53 | Remove sign, support & footing (713-15.36) | EACH | 3 | $50.00 | $52.50 | $55.30 |
| 54 | Changeable message sign unit (713-16.01) | EACH | 2 | $9,500.00 | $2,940.00 | $3,097.00 |
| 55 | Signs (D12-5) (713-16.20) | EACH | 2 | $1,200.00 | $1,260.00 | $1,327.00 |
| 56 | Jacked or bored conduit (714-03) | LF | 320 | $28.71 | $10.05 | $58.60 |
| 57 | Foundation (only) for light standard (714-08.20) | EACH | 6 | $3,361.45 | $3,150.00 | $3,446.00 |
| 58 | LED luminaires (110 watt LED roadway) (714-09.47) | EACH | 5 | $1,017.09 | $1,575.00 | $1,593.00 |
| 59 | LED luminaires (140 watt LED interstate) (714-09.48) | EACH | 3 | $1,017.09 | $1,575.00 | $1,593.00 |
| 60 | Electrical connection (psa) (714-25.01) | LS | 1 | $7,700.00 | $2,625.00 | $4,956.00 |
| 61 | Electrical connection (PSB) (714-25.02) | LS | 1 | $7,700.00 | $2,625.00 | $4,956.00 |
| 62 | #4 AWG 2-1/C rugg insulated & jacketed copper cable 600V (714-70.14) | LF | 4,274 | $4.90 | $4.50 | $4.98 |
| 63 | #6 AWG ground wire insulated solid copper (714-70.58) | LF | 1,700 | $2.55 | $2.95 | $3.98 |
| 64 | Steel lighting pole 30FT (714-71.21) | EACH | 2 | $6,147.41 | $10,500 | $6,720.00 |
| 65 | Steel lighting pole 38FT (714-71.22) | EACH | 6 | $6,476.80 | $12,600 | $7,561.00 |
| 66 | 2IN rigid PVC conduit (714-72.03) | LF | 1,186 | $18.12 | $1.00 | $14.40 |
| 67 | Pull box with cover medium (714-72.10) | EACH | 6 | $1,620.72 | $5,250.00 | $1,825.00 |
| 68 | Bracket arm 15FT for steel pole W/simplex (714-74.01) | EACH | 6 | $1,472.07 | $525.00 | $586.25 |
| 69 | Bracket arm 6FT W/simplex-high rise for steel pole (714-74.02) | EACH | 2 | $1,264.56 | $315.00 | $508.75 |
| 70 | Photo electric relay 240V (714-75.02) | EACH | 8 | $468.00 | $73.50 | $83.00 |
| 71 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 28 | $55.00 | $57.75 | $60.80 |
| 72 | Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22) | EACH | 28 | $55.00 | $57.75 | $60.80 |
| 73 | Painted pavement marking (6" line) (716-05.20) | LM | 2 | $3,800.00 | $3,990.00 | $4,203.00 |
| 74 | Removal of pavement marking (line) (716-08.01) | LF | 5,655 | $1.35 | $1.40 | $1.49 |
| 75 | Contrast pavement shadow marking 6" (716-09.97) | LF | 160 | $18.75 | $19.70 | $20.75 |
| 76 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 1 | $15,000 | $15,750 | $16,593 |
| 77 | Mobilization (717-01) | LS | 1 | $532,750 | $267,630 | $795,225 |
| 78 | Geogrid reinforcement type 2 (740-07.04) | SY | 2,950 | $5.50 | $5.80 | $6.04 |
| 79 | Geotextile (type III)(erosion control) (740-10.03) | SY | 6,132 | $4.05 | $3.15 | $6.86 |
| 80 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 6,667 | $6.05 | $3.85 | $4.55 |
| 81 | Temporary sediment tube 20IN (740-11.04) | LF | 500 | $7.50 | $7.85 | $8.30 |
| 82 | Temporary seeding (with mulch) (801-01.07) | UNIT | 1 | $250.00 | $265.00 | $276.50 |
| 83 | Special wetland seed mixture (801-01.36) | UNIT | 1 | $500.00 | $525.00 | $553.00 |
| 84 | Natve seed MX final stablizatn of slopes (801-01.38) | UNIT | 1 | $500.00 | $525.00 | $553.00 |
| 85 | Water (seeding & sodding) (801-03) | MG | 30 | $20.00 | $21.00 | $22.10 |
| 86 | Salix nigra (black willow seedlng B.R.) (802-12.40) | EACH | 14 | $25.00 | $26.25 | $27.65 |
| 87 | Ulmus americana (american elm seedlng B.R.) (802-12.44) | EACH | 14 | $25.00 | $26.25 | $27.65 |
| 88 | Alnus serrulata (hazel alder seedling B.R.) (802-12.61) | EACH | 11 | $25.00 | $26.25 | $27.65 |
| 89 | Cephalanthus occidentalis (buttonbush SDLNG bare root) (802-13.53) | EACH | 11 | $25.00 | $26.25 | $27.65 |
| 90 | Cornus amomum (silky dogwood SDLNG bare root) (802-13.54) | EACH | 11 | $25.00 | $26.25 | $27.65 |
| 91 | Sodding (new sod) (803-01) | SY | 547 | $9.00 | $9.45 | $19.90 |
| 92 | Erosion control blanket (type II) (805-12.02) | SY | 5,732 | $3.00 | $3.15 | $3.32 |
| 93 | Removal of structures (exist. BR. no. 79SR0030027) (202-04.01) | LS | 1 | $350,000 | $440,000 | $475,100 |
| 94 | Dry excavation (bridges) (204-02.01) | CY | 278 | $30.00 | $26.80 | $38.25 |
| 95 | Granular backfill (bridges) (303-01.02) | TON | 88 | $100.00 | $75.00 | $119.25 |
| 96 | Epoxy coated reinforcing steel (604-02.03) | LB | 166,298 | $1.96 | $2.40 | $1.82 |
| 97 | Class A concrete (bridges) (604-03.01) | CY | 357 | $1,000.00 | $1,465.00 | $1,255.00 |
| 98 | Steel bar reinforcement (bridges) (604-03.02) | LB | 40,121 | $1.90 | $2.45 | $1.37 |
| 99 | Pavement @ bridge ends (604-03.04) | SY | 390 | $400.00 | $430.00 | $441.25 |
| 100 | Class DS concrete (604-03.32) | CY | 694 | $1,100.00 | $1,310.00 | $872.25 |
| 101 | Applied texture finish (new structures) (604-04.01) | SY | 1,527 | $11.50 | $12.00 | $12.70 |
| 102 | Bridge deck grooving (mechanical) (604-05.31) | SY | 2,397 | $3.33 | $3.50 | $4.25 |
| 103 | Test piles (steel pipe piles, 14-inch) (606-18.01) | LF | 140 | $150.00 | $220.00 | $175.50 |
| 104 | Loading test (steel pipe piles, 14-inch) (606-18.02) | EACH | 1 | $6,000.00 | $17,400 | $12,169 |
| 105 | Steel pipe piles (14-inch) (606-18.03) | LF | 2,040 | $90.00 | $121.25 | $96.00 |
| 106 | Steel pipe piles (24 in) (606-22.13) | LF | 2,600 | $125.00 | $225.00 | $213.25 |
| 107 | Test piles (steel pipe piles 24 in) (606-22.15) | LF | 220 | $250.00 | $295.00 | $236.75 |
| 108 | Load testing (steel pipe piles 24 in) (606-22.16) | EACH | 1 | $10,000 | $22,000 | $12,169 |
| 109 | Deck drains (grate type 2) (610-10.45) | EACH | 8 | $2,500.00 | $3,325.00 | $3,233.00 |
| 110 | Prestressed concrete bulb tee beam (6" web)(BT-63) (615-01.11) | LF | 2,646 | $550.00 | $575.00 | $600.00 |
| 111 | Bridge deck crack sealing (617-02) | LF | 300 | $10.00 | $10.00 | $3.87 |
| 112 | Sealant (HMWM) (617-05) | GAL | 2 | $750.00 | $240.00 | $396.00 |
| 113 | Concrete parapet with structural tubing (620-05) | LF | 670 | $450.00 | $475.00 | $419.75 |
| 114 | 6" perforated pipe with vertical drain system (710-09.01) | LF | 206 | $90.00 | $50.00 | $143.75 |
| 115 | 6" pipe underdrain (710-09.02) | LF | 72 | $20.00 | $35.00 | $61.00 |
| 116 | Structural lighting (714-01) | LS | 1 | $26,000 | $39,575 | $27,654 |
| 117 | Marker post (793-11.19) | EACH | 5 | $150.00 | $157.50 | $140.50 |
| 118 | 2 duct formation @ 72IN depth (793-13.20) | LF | 50 | $125.00 | $131.25 | $70.80 |
| 119 | 4IN core drill into manhole (793-14.10) | EACH | 4 | $525.00 | $551.25 | $565.25 |
| 120 | 4IN SCH 80 orange flexpipe (793-14.19) | LF | 3,136 | $25.50 | $26.75 | $5.53 |
| 121 | MH(retire/remove/gravel backfill) (793-16.01) | EACH | 1 | $5,000.00 | $5,250.00 | $1,239.00 |
| 122 | Directional bore 4IN/flex sleeve X 2 (793-16.53) | LF | 1,518 | $100.00 | $105.00 | $37.60 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of March 20, 2026. Compiled by Mirage Metrics.