TDOT contract CNZ192 bid tabulation

The interchange modifications on i-40 at s.r. 13, including grading, drainage, lighting, and paving (l.m. 7.64 to l.m. 8.64). Let by Tennessee DOT on June 27, 2025, Humphreys County. 3 bids received; low bid $5,182,241 by Delta Contracting Company, LLC.

Owner
Tennessee DOT
Letting
27 JUN 2025
Pay items
92
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Delta Contracting Company, LLC$5,182,241Low
2Bell & Associates Construction, LLC$5,891,802+14%
3Jones Bros. Contractors, LLC$7,101,645+37%
TDOT contract CNZ192: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Delta Contracting Company, LLC2. Bell & Associates Construction, LLC3. Jones Bros. Contractors, LLC
1Construction stakes, lines and grades (105-01)LS1$44,180$35,000$40,000
2Trainee (109-10.01)HR1,160$0.80$0.80$0.80
3Clearing and grubbing (201-01)LS1$139,210$140,000$310,000
4Removal of structures and obstructions (202-01)LS1$5,400.00$33,000$87,000
5Removal of asphalt pavement (202-03.01)SY2,465$12.00$15.00$52.00
6Road & drainage excavation (unclassified) (203-01)CY16,457$22.00$42.00$59.00
7Borrow excavation (unclassified) (203-03)CY4,195$3.00$52.00$60.00
8Placing and spreading topsoil (203-04)CY2,335$17.00$18.00$25.00
9Water (203-06)MG280$32.00$60.00$10.00
10Backfill material (flowable fill) (204-08.01)CY35$400.00$430.00$500.00
11Brooming & degrassing shoulders (208-01.05)LM2$1,425.00$5,000.00$4,336.00
12Filter sock (12 inch) (209-03.21)LF5,572$3.00$4.20$3.90
13Sediment removal (209-05)CY101$28.00$80.00$38.00
14Temporary silt fence (with backing) (209-08.02)LF2,308$4.80$5.00$4.80
15Rock check dam (209-08.07)EACH4$750.00$1,100.00$1,000.00
16Enhanced rock check dam (209-08.08)EACH6$1,150.00$1,300.00$1,200.00
17Sandbags (209-09.01)BAG126$9.25$25.00$11.00
18Polyethylene sheeting (6 mil. minimum) (209-20.03)SY525$5.00$14.00$5.00
19Catch basin protection (type B) (209-40.31)EACH2$1,200.00$664.00$600.00
20Mineral aggregate, type A base, grading D (303-01)TON11,507$37.00$55.50$50.00
21Mineral aggregate (size 57) (303-10.01)TON26$50.00$130.00$50.00
22Asp. conc. mix(PG76-22) (BPMB-HM) GR. A-S (307-01.22)TON989$168.00$118.00$178.00
23Asphalt concrete mix (PG76-22) (BPMB-HM) grading A (307-03.01)TON1,349$172.00$120.00$181.00
24Asphalt concrete mix (PG76-22) (BPMB-HM) grading B-M2 (307-03.08)TON1,019$188.00$125.00$193.00
25Bituminous material for tack coat (TC) (403-01)TON126$300.00$1,000.00$1,018.00
26Saw cutting asphalt pavement (407-20.05)LF16,110$2.82$2.60$4.75
27Acs mix(PG76-22) grading D (411-03.10)TON3,494$195.00$138.00$174.00
28Cold planing bituminous pavement (415-01.01)TON2,809$57.00$55.00$53.00
2918" concrete pipe culvert (class III) (607-03.02)LF35$145.00$271.00$130.00
3030" concrete pipe culvert (class III) (607-06.02)LF23$205.00$350.00$160.00
31Class A concrete (pipe endwalls) (611-07.01)CY9.15$1,600.00$3,000.00$2,300.00
32Steel bar reinforcement (pipe endwalls) (611-07.02)LB305$3.50$7.00$5.00
33W beam GR (type 2) MASH TL-3 (705-06.01)LF3,855$32.50$26.00$32.50
34GR terminaltrailing end (type 13) MASH TL-3 (705-06.10)EACH2$1,425.00$1,600.00$1,425.00
35Tangent energy absorbing term MASH TL-3 (705-06.20)EACH1$3,850.00$3,800.00$3,850.00
36Portable impact attenuator NCHRP350 TL-3 (705-08.11)EACH1$12,000$9,500.00$9,200.00
37Guardrail removed (706-01)LF1,310$5.00$2.50$5.00
38Removal and reset fence (R.O.W.) (707-06.03)LF1,700$15.06$17.00$8.00
39High-visibility construction fence (707-08.11)LF835$3.90$4.00$3.90
40Machined rip-rap (class A-3) (709-05.05)TON100$50.00$100.00$75.00
41Machined rip-rap (class A-1) (709-05.06)TON193$50.00$100.00$75.00
42Aggregate underdrains (with pipe) (710-02)LF4,790$12.50$13.00$15.00
43Lateral underdrain (710-05)LF754$11.75$13.00$11.75
44Lateral underdrain endwall (2:1) (710-06.11)EACH6$1,200.00$1,250.00$1,200.00
45Lateral underdrain endwall (3:1) (710-06.12)EACH16$1,200.00$1,300.00$1,200.00
46Lateral underdrain endwall (6:1) (710-06.15)EACH6$1,200.00$1,350.00$1,200.00
47Traffic control (712-01)LS1$121,200$172,000$300,000
48Interconnected portable barrier rail (712-02.02)LF13,870$45.00$47.00$48.00
49Temporary work zone crash cushion (MASH TL-3) (712-02.60)EACH4$7,800.00$7,900.00$9,200.00
50Flexible drums (channelizing) (712-04.01)EACH140$45.00$36.00$43.00
51Barrier rail delineator (712-04.50)EACH694$10.00$10.50$12.20
52Warning lights (type A) (712-05.01)EACH22$25.00$15.00$32.50
53Signs (construction) (712-06)SF1,523$7.35$8.00$7.65
54Arrow board (type C) (712-08.03)EACH3$1,250.00$1,150.00$2,150.00
55Queue protection truck (712-08.12)DAY40$1,000.00$1,250.00$1,425.00
56Removable black-out tape (8IN) (712-09.31)LF1,000$5.00$5.00$5.00
57Class A concrete (foundation for sign supports) (713-01.01)CY2$750.00$760.00$750.00
58Steel bar reinforcement(foundation for sign supports) (713-01.02)LB150$3.50$3.50$3.50
59Perforated/knockout square tube post (713-11.02)LB250$5.25$7.50$7.20
60P post slip base (713-11.21)EACH6$500.00$550.00$510.00
61Flat sheet aluminum signs (0.080" thick) (713-13.02)SF72$25.00$17.00$16.80
62Removal & relocation of sign & support (713-15.02)EACH4$1,000.00$550.00$500.00
63Changeable message sign unit (713-16.01)EACH6$5,900.00$6,100.00$10,200
64Jacked or bored conduit (714-03)LF909$24.00$3.60$3.56
65Direct burial conduit (2" PVC, schedule 40) (714-03.01)LF7,657$10.00$10.00$9.53
66Pull boxes (type C) (714-05.04)EACH18$1,100.00$1,250.00$1,222.00
67Cable (1/C # 4 AWG) (714-06.06)LF25,698$3.00$2.40$2.17
68Light standards (40FT offset) (714-08.09)EACH19$5,300.00$2,400.00$2,360.00
69Light standards (100FT high mast) (714-08.10)EACH4$45,000$80,000$78,165
70Removal of light standard & foundation (714-08.32)EACH7$2,500.00$2,500.00$2,494.00
71Foundation for light standards - high mast (100FT) (714-08.40)EACH4$16,000$10,500$10,000
72LED luminaires (180W offset) (714-09.47)EACH19$1,355.00$750.00$700.00
73LED luminaires-high mast (295W) (714-09.64)EACH32$2,200.00$1,050.00$1,000.00
74Control center (no. 1) (714-12.01)LS1$22,000$12,500$12,000
75Control center (no. 2) (714-12.02)LS1$22,000$12,500$12,000
76Removal of existing control center (CC1 & CC2) (714-12.30)EACH2$2,000.00$2,500.00$2,441.00
77Electrical connection (CC1) (714-25.01)LS1$5,000.00$9,800.00$2,100.00
78Electrical connection (CC2) (714-25.02)LS1$5,000.00$9,800.00$9,000.00
79Snowplowable raised pavement markers (BI-dir)(2 color) (716-01.23)EACH191$75.00$80.00$75.00
80Removal of snowplowable reflective marker (716-01.30)EACH136$15.00$15.00$9.00
81Plastic pavement marking (24" barrier line) (716-02.07)LF405$12.00$12.00$12.00
82Painted pavement marking (8" barrier line) (716-05.02)LF49,800$0.75$0.80$0.75
83Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM2$9,500.00$10,500$9,500.00
84Enhanced flatline thermo PVMT MRKNG (8IN barrier line) (716-12.03)LF1,745$3.00$3.10$3.00
85Enhanced flatline thermo PVMT MRKNG (6IN dotted line) (716-12.05)LF3,470$2.00$2.10$2.00
86Mobilization (717-01)LS1$452,137$559,645$710,000
87Geotextile (type III)(erosion control) (740-10.03)SY557$1.50$10.00$5.00
88Temporary sediment tube 8IN (740-11.01)LF510$3.60$4.00$3.60
89Seeding (with mulch) (801-01)UNIT299$45.00$46.00$45.00
90Temporary seeding (with mulch) (801-01.07)UNIT967$32.00$33.00$32.00
91Fertilizer (801-02.15)TON3$1,360.00$1,500.00$1,360.00
92Water (seeding & sodding) (801-03)MG128$80.00$80.00$80.00
TDOT contract CNZ192: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of June 27, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.