TDOT contract CNZ215 bid tabulation
The construction of a concrete box culvert on fern avenue over cane creek (l.m. 1.26) in camden. Let by Tennessee DOT on August 15, 2025, Benton County. 2 bids received; low bid $994,621 by Thomson & Thomson, Inc..
- Owner
- Tennessee DOT
- Letting
- 15 AUG 2025
- Pay items
- 67
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Thomson & Thomson, Inc. | $994,621 | Low |
| 2 | Ford Construction Company | $1,067,419 | +7.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Thomson & Thomson, Inc. | 2. Ford Construction Company |
|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $17,500 | $30,000 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $10,500 | $30,000 |
| 3 | Removal of asphalt pavement (202-03.01) | SY | 263 | $25.00 | $20.00 |
| 4 | Road & drainage excavation (unclassified) (203-01) | CY | 1,267 | $45.00 | $20.00 |
| 5 | Undercutting (203-05) | CY | 371 | $45.00 | $23.00 |
| 6 | Water (203-06) | MG | 5 | $200.00 | $35.00 |
| 7 | Furnishing & spreading topsoil (203-07) | CY | 88 | $56.00 | $33.00 |
| 8 | Channel excavation (unclassified) (203-08) | CY | 700 | $48.00 | $20.00 |
| 9 | Channel substrate (203-20.01) | CY | 418 | $90.00 | $70.00 |
| 10 | Foundation fill material (204-08) | CY | 28 | $165.00 | $95.00 |
| 11 | Sediment removal (209-05) | CY | 47 | $75.00 | $16.00 |
| 12 | Temporary silt fence (with backing) (209-08.02) | LF | 400 | $11.50 | $10.00 |
| 13 | Enhanced rock check dam (209-08.08) | EACH | 9 | $2,200.00 | $900.00 |
| 14 | Sandbags (209-09.01) | BAG | 100 | $32.50 | $10.00 |
| 15 | Sediment filter bag (15' X 15') (209-09.03) | EACH | 2 | $775.00 | $600.00 |
| 16 | Polyethylene sheeting (10 mil.) (209-20.04) | SY | 826 | $5.00 | $5.00 |
| 17 | Temporary in stream diversion (209-65.04) | LF | 165 | $90.00 | $86.00 |
| 18 | Mineral aggregate, type A base, grading D (303-01) | TON | 183 | $86.00 | $30.00 |
| 19 | Granular backfill (roadway) (303-01.01) | TON | 424 | $72.50 | $51.00 |
| 20 | Mineral aggregate (size 57) (303-10.01) | TON | 51 | $110.00 | $43.00 |
| 21 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 27 | $455.00 | $495.00 |
| 22 | Bituminous material for prime coat (PC) (402-01) | TON | 1 | $2,500.00 | $1,300.00 |
| 23 | Aggregate for cover material (PC) (402-02) | TON | 2 | $100.00 | $250.00 |
| 24 | Bituminous material for tack coat (TC) (403-01) | TON | 1 | $2,500.00 | $1,300.00 |
| 25 | Saw cutting asphalt pavement (407-20.05) | LF | 34 | $7.50 | $11.00 |
| 26 | Acs mix(PG64-22) grading D (411-01.10) | TON | 23 | $480.00 | $595.00 |
| 27 | Class A concrete (roadway) (604-01.01) | CY | 16 | $1,150.00 | $800.00 |
| 28 | 18" temporary drainage pipe (621-03.02) | LF | 36 | $55.00 | $88.00 |
| 29 | Metal beam guard fence (705-01.04) | LF | 88 | $112.50 | $130.00 |
| 30 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 50 | $45.00 | $48.00 |
| 31 | GR terminaltrailing end (type 13) MASH TL-3 (705-06.10) | EACH | 4 | $2,175.00 | $1,375.00 |
| 32 | Guardrail removed (706-01) | LF | 50 | $2.50 | $7.00 |
| 33 | High-visibility construction fence (707-08.11) | LF | 220 | $7.00 | $7.50 |
| 34 | Machined rip-rap (class A-3) (709-05.05) | TON | 100 | $67.50 | $40.00 |
| 35 | Machined rip-rap (class C) (709-05.09) | TON | 858 | $67.50 | $40.00 |
| 36 | 6" perforated plastic pipe (710-10.02) | LF | 60 | $15.00 | $27.00 |
| 37 | Traffic control (712-01) | LS | 1 | $7,500.00 | $30,000 |
| 38 | Warning lights (type A) (712-05.01) | EACH | 74 | $15.00 | $15.00 |
| 39 | Signs (construction) (712-06) | SF | 359 | $10.00 | $7.00 |
| 40 | Temporary barricades (type III) (712-07.03) | LF | 60 | $22.00 | $28.00 |
| 41 | Sign post delineation enhancement (713-02.21) | LF | 7 | $12.00 | $7.18 |
| 42 | Remove sign, support & footing (713-15.36) | EACH | 7 | $150.00 | $225.00 |
| 43 | Changeable message sign unit (713-16.01) | EACH | 2 | $4,000.00 | $5,950.00 |
| 44 | Signs (I2-5) (713-16.20) | EACH | 2 | $400.00 | $925.00 |
| 45 | Signs (OM3-R) (713-16.21) | EACH | 3 | $400.00 | $229.50 |
| 46 | Signs (OM3-L) (713-16.22) | EACH | 2 | $400.00 | $229.50 |
| 47 | Signs (R1-1, W5-3A, OM3-L) (713-16.23) | EACH | 1 | $400.00 | $391.00 |
| 48 | Plastic pavement marking (stop line) (716-02.05) | LF | 12 | $100.00 | $100.00 |
| 49 | Painted pavement marking (4" line) (716-05.01) | LM | 0.10 | $25,000 | $25,000 |
| 50 | Mobilization (717-01) | LS | 1 | $115,000 | $220,000 |
| 51 | Geotextile (type III)(erosion control) (740-10.03) | SY | 432 | $7.65 | $7.00 |
| 52 | Temporary sediment tube 8IN (740-11.01) | LF | 50 | $40.00 | $20.00 |
| 53 | Temporary seeding (with mulch) (801-01.07) | UNIT | 5 | $400.00 | $150.00 |
| 54 | Natve seed MX final stablizatn of slopes (801-01.38) | UNIT | 1 | $500.00 | $200.00 |
| 55 | Water (seeding & sodding) (801-03) | MG | 6 | $200.00 | $100.00 |
| 56 | Sodding (new sod) (803-01) | SY | 584 | $12.75 | $13.50 |
| 57 | Removal of structures and obstructions (202-01) | LS | 1 | $22,000 | $50,000 |
| 58 | Class A concrete (box bridges) (604-02.01) | CY | 144 | $1,575.00 | $1,800.00 |
| 59 | Steel bar reinforcement (box bridges) (604-02.02) | LB | 34,693 | $2.10 | $2.00 |
| 60 | Mineral aggregate (size 57) (303-10.01) | TON | 50 | $90.00 | $90.00 |
| 61 | 6IN dip restrained joint water line (795-01.03) | LF | 200 | $150.00 | $150.00 |
| 62 | Connect to 6IN water line (795-06.04) | EACH | 2 | $6,500.00 | $6,500.00 |
| 63 | Cut and cap 6IN water line (795-06.33) | EACH | 2 | $2,500.00 | $2,500.00 |
| 64 | 6IN gate valve assembly (795-08.04) | EACH | 1 | $4,000.00 | $4,000.00 |
| 65 | Retire in place existing water main (795-11.12) | LF | 135 | $25.00 | $25.00 |
| 66 | DI fittings (795-13.01) | LB | 1,000 | $1.00 | $1.00 |
| 67 | Creek crossing (#1) (795-13.05) | LS | 1 | $20,000 | $20,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of August 15, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.