TDOT contract CNZ266 bid tabulation

The repair of the bridge on s.r. 141 over little goose creek (l.m. 4.82). Let by Tennessee DOT on October 3, 2025, Trousdale County. 4 bids received; low bid $1,344,692 by Bell & Associates Construction, LLC.

Owner
Tennessee DOT
Letting
03 OCT 2025
Pay items
68
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Bell & Associates Construction, LLC$1,344,692Low
2Jamison Construction, LLC$1,421,665+6.0%
3Mid-State Construction Company, Inc.$1,564,037+16%
4Jones Bros. Contractors, LLC$1,736,378+29%
TDOT contract CNZ266: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Bell & Associates Construction, LLC2. Jamison Construction, LLC3. Mid-State Construction Company, Inc.4. Jones Bros. Contractors, LLC
1Construction stakes, lines and grades (105-01)LS1$11,213$14,000$30,517$37,500
2Clearing and grubbing (201-01)LS1$29,178$10,000$35,168$80,000
3Removal of rigid pavement, sidewalk, etc. (202-03)SY50$162.00$110.00$30.70$20.00
4Removal of structures (bridge no. 85-SR141-04.82) (202-04.01)LS1$134,378$160,000$198,832$500,000
5Road & drainage excavation (unclassified) (203-01)CY7$400.00$120.00$460.42$95.00
6Borrow excavation (graded solid rock) (203-02.01)TON1,199$109.00$80.00$50.35$31.00
7Water (203-06)MG20$123.00$90.00$30.70$1.00
8Dry excavation (bridges) (204-02.01)CY379$76.00$70.00$71.65$50.00
9Sediment removal (209-05)CY8$186.00$50.00$153.48$75.00
10Temporary silt fence (with backing) (209-08.02)LF682$6.50$7.00$6.61$7.00
11Enhanced rock check dam (209-08.08)EACH2$769.00$1,200.00$776.25$1,100.00
12Sediment filter bag(15' X 10') (209-09.04)EACH1$838.00$1,500.00$1,607.61$700.00
13Catch basin filter assembly(type 1) (209-40.41)EACH2$655.00$950.00$661.25$700.00
14Temporary in stream diversion (209-65.04)LF150$648.00$135.00$140.44$100.00
15Mineral aggregate, type A base, grading D (303-01)TON31$269.00$193.00$287.50$100.00
16Granular backfill (bridges) (303-01.02)TON732$90.00$75.00$88.23$60.00
17Mineral aggregate (size 57) (303-10.01)TON9$447.00$110.00$87.84$75.00
18Mineral aggregate (size 57) (303-10.04)TON32$194.00$110.00$87.84$100.00
19Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01)TON10$854.00$825.00$575.00$320.00
20Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON7$1,138.00$1,100.00$575.00$330.00
21Bituminous material for prime coat (PC) (402-01)TON1$1,708.00$1,700.00$1,150.00$2,000.00
22Aggregate for cover material (PC) (402-02)TON1$228.00$220.00$1,150.00$100.00
23Bituminous material for tack coat (TC) (403-01)TON2$1,138.00$1,100.00$1,150.00$2,000.00
24Saw cutting asphalt pavement (407-20.05)LF203$3.40$15.00$10.74$10.00
25Acs mix(PG64-22) grading D (411-01.10)TON205$228.00$225.00$287.50$225.00
26Cold planing bituminous pavement (415-01.02)SY3,024$4.30$5.50$6.90$10.00
27Applied texture finish (existing structures) (604-04.02)SY94$25.00$25.00$25.30$22.00
28Concrete (604-10.05)SF10$891.00$500.00$1,870.80$500.00
29Reinforcing steel (repairs) (604-10.18)LB9,404$4.70$2.50$3.31$6.00
30Concrete repairs (604-10.42)CF1,319$104.00$250.00$212.88$175.00
31Concrete repairs (604-10.54)SF10$891.00$500.00$1,954.82$500.00
32Drill & grout steel bars (604-12.15)EACH42$663.00$80.00$97.59$250.00
33Adjustment of existing catchbasin (611-09.01)EACH1$7,271.00$4,500.00$5,175.00$3,100.00
34Prestressed concrete box beam (18" X 36") (615-02.22)LF47$1,480.00$1,050.00$959.17$1,000.00
35Partial depth precast deck panel (615-04.05)SY38$641.00$475.00$535.01$1,000.00
36Concrete parapet with structural tubing (620-05)LF47$494.00$478.00$853.06$500.00
37Concrete sidewalk (4 ") (701-01.01)SF347$9.60$9.50$17.04$10.00
38Concrete curb ramp (retrofit) (701-02.01)SF66$74.00$75.00$83.53$30.00
39Concrete curb ramp (701-02.03)SF66$28.00$28.00$44.83$70.00
40Concrete combined curb & gutter (702-03)CY20$601.00$675.00$690.00$625.00
41High-visibility construction fence (707-08.11)LF150$2.50$6.00$10.70$2.75
42Bike/pedestrian box tube safety rail (707-16.01)LF18$1,174.00$900.00$2,996.50$450.00
43Machined rip-rap (class A-3) (709-05.05)TON50$159.00$80.00$150.73$75.00
44Machined rip-rap (class B) (709-05.08)TON15$505.00$100.00$210.90$100.00
456" perforated pipe with vertical drain system (710-09.01)LF20$108.00$80.00$149.45$40.00
466" pipe underdrain (710-09.02)LF26$52.00$40.00$71.26$10.00
47Traffic control (712-01)LS1$12,078$105,000$97,928$120,000
48Interconnected portable barrier rail (712-02.02)LF300$120.00$60.00$90.50$50.00
49Temporary work zone crash cushion (MASH TL-3) (712-02.60)EACH2$5,805.00$9,000.00$5,865.00$7,500.00
50Flexible drums (channelizing) (712-04.01)EACH32$36.00$40.00$36.80$28.00
51Barrier rail delineator (712-04.50)EACH8$13.00$20.00$13.80$14.00
52Warning lights (type A) (712-05.01)EACH44$22.00$40.00$23.00$25.00
53Signs (construction) (712-06)SF419$8.50$12.00$8.63$8.00
54Temporary barricades (type III) (712-07.03)LF108$31.00$25.00$32.20$14.00
55Removable pavement marking (stop line) (712-09.04)LF48$46.00$25.00$46.00$40.00
56Removable pavement marking (6" line) (712-09.08)LF1,264$4.00$4.80$5.18$4.50
57Changeable message sign unit (713-16.01)EACH2$6,031.00$7,000.00$6,095.00$6,500.00
58Signs (OM3-L) (713-16.20)EACH1$228.00$240.00$230.00$200.00
59Signs (W3-1) (713-16.21)EACH1$228.00$600.00$230.00$500.00
60Barrier mounted sign support (mounted on bridge parapet) (713-30.09)EACH2$427.00$1,200.00$431.25$1,000.00
61Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21)EACH9$227.00$330.00$230.00$200.00
62Removal of snowplowable reflective marker (716-01.30)EACH9$57.00$150.00$57.50$50.00
63Plastic pavement marking (stop line) (716-02.05)LF24$34.00$33.00$34.50$30.00
64Plastic pavement marking (longitudinal cross-walk) (716-02.09)LF64$57.00$72.00$57.50$50.00
65Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM0.60$11,384$16,500$11,500$10,000
66Mobilization (717-01)LS1$131,107$140,000$156,303$170,000
67Temporary traffic signal system (730-40)EACH1$66,823$70,000$87,983$70,000
68Geotextile (type III)(erosion control) (740-10.03)SY1,060$6.60$6.00$8.05$4.00
TDOT contract CNZ266: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of October 3, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy