TxDOT contract A00121975 bid tabulation

Highway Improvement, US 290 (US 290/Greenhouse Rd, From Mound Rd to Skinner Rd at US 290). Let by Texas DOT on February 4, 2026, Harris, Houston District. 10 bids received; low bid $74,036,475 by Harper Brothers Construction LLC, -6.2% against the engineer's estimate of $78,925,854.

Owner
Texas DOT
Letting
04 FEB 2026
Pay items
258
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Harper Brothers Construction LLC$74,036,475Low-6.0%
2R Construction Civil, LLC$78,783,439+6.0%0.0%
3MC2 Civil, LLC$79,474,318+7.0%+1.0%
4Ser Construction Partners, LLC$79,533,035+7.0%+1.0%
5Ragle Construction, Inc.$80,436,126+9.0%+2.0%
6Webber, LLC$84,127,222+14%+7.0%
7Posillico Civil, Inc.$88,136,214+19%+12%
8Pulice Construction, Inc.$90,359,704+22%+14%
9Zachry Construction Corporation$95,000,760+28%+20%
10Granite Construction Company$97,871,055+32%+24%
TxDOT contract A00121975: bids by rank

Engineer's estimate: $78,925,854.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Harper Brothers Construction LLC2. R Construction Civil, LLC3. MC2 Civil, LLC4. Ser Construction Partners, LLC5. Ragle Construction, Inc.6. Webber, LLC
1Preparing row (100-7002)STA36.66$4,000.00$28,500$1,254.87$72,500$56,000$25,690$229,479
2Removing concrete (pavement) (104-7001)SY18,113$15.00$5.00$7.60$5.00$4.00$6.50$2.25
3Removing concrete (medians) (104-7008)SY704$15.00$2.71$5.41$5.00$2.80$15.00$2.60
4Removing concrete (driveways) (104-7011)SY199$20.00$2.75$5.67$5.00$4.80$17.00$2.60
5Removing concrete (sidewalk, ramp or shared use path) (104-7013)SY414$20.00$3.00$5.67$5.00$3.20$15.00$3.05
6Removing concrete (curb & gutter) (104-7017)LF8,225$4.00$1.50$4.68$0.10$1.70$6.50$1.55
7Remove (10"-14") TRT/untrt base & asphalt pavement (105-7010)SY17,675$10.00$1.75$2.85$5.00$4.50$9.00$1.65
8Excavation (roadway) (110-7001)CY142,458$15.00$14.00$18.00$15.00$15.90$20.00$12.80
9Embankment (final)(DC)(type C) (132-7006)CY3,746$30.00$13.25$31.54$7.00$2.20$15.00$12.60
10Embankment (final)(DC)(type C)(csbe) (132-7029)CY32,462$50.00$58.00$44.09$50.00$66.30$55.00$76.25
11Block sodding (162-7002)SY3,249$7.00$5.00$3.41$3.50$4.70$7.50$3.25
12Drill seed (temporary_warm_cool) (164-7015)SY14,777$2.00$0.20$0.23$0.25$0.20$0.19$0.20
13Drill seed (OPT1) (164-7016)SY14,777$1.00$0.75$0.34$0.35$0.20$0.29$0.30
14Straw/hay mulch (164-7065)SY14,777$1.00$0.27$0.19$0.20$0.30$0.42$0.20
15Fertilizer (166-7001)ACRE3.90$1,000.00$800.00$787.24$800.00$936.00$880.63$750.00
16Vegetative watering (168-7001)TGL468$25.00$55.00$35.16$30.00$36.40$35.00$35.00
17FL BS (compacted in place)(type D GR 1-2)(9") (247-7344)SY1,142$30.00$27.25$34.60$28.00$35.50$30.00$27.50
18Geogrid base reinforcement (type 1) (250-7001)SY1,142$3.00$2.00$14.73$5.00$4.30$4.50$6.10
19Lime (com or QK)(slurry) or QK(dry) (260-7001)TON902$350.00$360.00$341.14$350.00$364.50$333.00$334.00
20Lime TRT (subgrade)(12") (260-7026)SY33,258$2.00$5.00$5.39$7.00$6.60$3.45$10.30
21Cem TRT(PLNT MX)(CL N)(type E)(GR 4)(6") (276-7343)SY33,258$10.00$22.00$32.79$20.00$23.60$19.30$19.70
22Asphalt TRT base (GR 4)(PG 64) (292-7014)TON1,835$160.00$140.00$164.11$140.00$153.00$150.00$140.00
23Concrete pavement (CRCP) (10") (360-7004)SY14,094$80.00$90.00$78.90$50.00$84.70$80.00$94.75
24Concrete pavement (CRCP) (11") (360-7005)SY17,277$90.00$93.00$86.12$61.00$89.30$85.00$105.00
25Cem stabil BKFL (400-7010)CY11,691$80.00$70.00$60.97$50.00$62.40$50.00$57.25
26Trench excavation protection (402-7001)LF5,875$10.00$6.00$13.53$10.00$1.00$4.00$8.30
27Temporary special shoring (403-7001)SF11,651$110.00$32.00$45.00$75.00$89.00$100.00$38.75
28Foundation load test (D4945) (pile) (405-7002)EACH7$20,000$6,000.00$5,248.28$16,000$15,686$5,500.00$4,400.00
29Steel H-piling (HP 14 X 102) (407-7022)LF12,620$250.00$179.00$267.75$140.00$138.90$170.00$135.00
30Soil nail anchors (410-7001)LF12,110$34.36$130.00$138.67$100.00$54.30$80.00$69.50
31Drilled shaft (48 in) (416-7008)LF15,311$580.00$390.00$574.65$530.00$516.10$410.00$418.00
32Drilled shaft (high mast pole) (60 in) (416-7037)LF34$800.00$1,105.00$671.78$950.00$1,560.00$640.00$983.00
33Drilled shaft (traffic signal pole) (36 in) (416-7044)LF28$395.00$200.00$288.66$390.00$395.20$275.00$272.00
34Drilled shaft (traffic signal pole) (48 in) (416-7046)LF88$650.00$384.00$530.08$610.00$499.20$505.00$383.00
35Class B concrete (miscellaneous) (420-7011)CY30.40$735.00$925.00$1,172.32$1,250.00$857.50$600.00$363.00
36Class C concrete (abutment) (420-7012)CY5$1,600.00$1,250.00$1,181.35$2,300.00$4,424.40$3,700.00$13,290
37Class C concrete (cap) (420-7022)CY377$1,655.00$800.00$1,273.29$1,000.00$647.20$720.00$788.00
38Class C concrete (column) (420-7038)CY466.30$1,800.00$1,200.00$1,731.57$1,000.00$1,620.00$1,150.00$1,560.00
39Class C concrete (footing)(mass) (420-7046)CY1,115.10$1,250.00$125.00$1,183.77$1,000.00$504.00$700.00$626.00
40Class C concrete (miscellaneous) (420-7067)CY710.80$1,120.00$1,800.00$1,181.20$1,000.00$900.00$1,050.00$1,200.00
41CL F concrete (cap)(invt) (420-7079)CY459.90$1,300.00$1,500.00$1,200.31$1,550.00$1,713.80$1,250.00$1,440.00
42CL F concrete (footing)(mass) (420-7113)CY711.10$1,000.00$1,000.00$1,200.31$750.00$455.90$550.00$514.00
43CL F concrete (abutment) (420-7155)CY610.70$1,120.00$680.00$1,196.08$650.00$924.50$550.00$593.00
44CL F concrete (bent)(HPC) (420-7159)CY332.30$1,120.00$720.00$1,196.08$550.00$716.80$575.00$644.00
45Reinforced concrete slab (422-7001)SF57,728$25.00$22.00$27.40$23.00$23.40$25.00$23.50
46Approach slab (422-7013)CY351$900.00$700.00$917.81$700.00$578.30$555.00$561.00
47Retaining wall (MSE) (423-7001)SF33,227$90.00$56.75$46.05$70.00$52.10$35.00$50.00
48Ret wall (DS)(fascia)(vert schedule) (423-7032)SF8,498$79.00$73.00$62.10$42.00$92.90$50.00$54.50
49Prestressed concrete girder (TX46) (425-7004)LF4,309.98$205.00$230.00$210.31$215.00$218.40$240.00$234.00
50Prestressed concrete girder (TX54) (425-7005)LF2,451.54$245.00$235.00$217.58$215.00$218.40$240.00$248.00
51Riprap (concrete)(6 in) (432-7003)CY960$300.00$470.00$303.58$500.00$482.60$460.00$524.00
52Elastomeric bearing (sliding)(SPG) (434-7117)EACH40$5,000.00$6,800.00$1,574.49$6,000.00$3,721.90$5,500.00$5,400.00
53STR steel (rolled beam) (442-7004)LB36,400$4.00$3.25$3.20$3.60$3.70$2.60$2.55
54STR steel (railroad deck-girder) (442-7005)LB1,492,700$3.00$3.10$3.86$3.20$3.70$3.00$2.55
55STR steel (miscellaneous bridge) (442-7008)LB5,800$8.00$3.10$3.20$6.50$3.90$4.00$2.55
56STR steel (diaphragm & stiffener) (442-7009)LB146,500$3.00$3.10$3.36$3.70$3.70$2.90$2.55
57Rail (type SSTR) (450-7024)LF1,980$100.00$85.00$90.42$85.00$53.70$74.00$60.50
58Rail (type PR11) (450-7044)LF2,858$125.00$135.00$142.64$150.00$120.80$130.00$108.00
59Rail (handrail)(RR bridge) (450-7070)LF284.40$250.00$189.00$167.43$190.00$170.80$165.00$135.00
60Sealed expansion joint (4 in) (SEJ - M) (454-7004)LF349$265.00$210.00$166.21$190.00$190.00$195.00$221.00
61Waterproofing (type RR - 1) (458-7008)SY642$345.00$15.00$519.58$500.00$27.40$75.00$495.00
62Concrete box culvert (4 FT X 3 FT) (462-7004)LF458$380.00$350.00$400.78$350.00$311.90$425.00$256.00
63Concrete box culvert (6 FT X 4 FT) (462-7012)LF2,032$500.00$570.00$555.12$554.00$527.40$715.00$404.00
64Concrete box culvert (12 FT X 10 FT) (462-7053)LF2,951$2,300.00$1,900.00$1,579.00$1,900.00$1,625.80$1,850.00$1,360.00
65Concrete box culvert (12 FT X 10 FT)(C E-80) (462-7135)LF261$2,500.00$3,200.00$5,200.00$4,000.00$4,920.70$2,625.00$1,790.00
66RC pipe (CL III)(12 in) (464-7001)LF34$90.00$54.00$199.93$125.00$86.50$90.00$64.25
67RC pipe (CL III)(24 in) (464-7005)LF4,156$95.00$93.00$215.47$110.00$96.60$95.00$72.50
68RC pipe (CL III)(30 in) (464-7007)LF43$160.00$132.00$120.69$220.00$138.50$135.00$117.00
69RC pipe (CL III)(36 in) (464-7009)LF42$215.00$168.00$153.29$450.00$172.00$165.00$210.00
70RC pipe (CL III)(48 in) (464-7011)LF34$350.00$233.00$135.74$450.00$261.40$265.00$308.00
71RC pipe (CL III)(66 in) (464-7014)LF91$580.00$565.00$378.96$600.00$482.80$530.00$429.00
72Junction box(complete)(PJB)(5FTX5FT) (465-7009)EACH1$15,000$9,900.00$8,388.56$10,000$7,114.40$9,300.00$7,020.00
73Junction box(complete)(PJB)(6FTX6FT) (465-7011)EACH1$16,000$11,700$12,117$12,000$9,465.90$12,700$10,790
74Junction box(complete)(PJB)(8FTX8FT) (465-7012)EACH3$20,000$24,500$20,726$19,000$23,479$30,300$20,210
75Inlet (complete)(curb)(type C1)(left)(hou) (465-7310)EACH17$4,500.00$7,200.00$6,608.52$7,000.00$7,706.70$9,900.00$8,410.00
76Inlet (complete)(curb)(type C1)(both)(hou) (465-7312)EACH30$8,000.00$8,000.00$7,192.02$7,800.00$8,200.60$10,050$8,910.00
77Inlet (complete)(type AD)(hou) (465-7314)EACH6$12,000$4,500.00$4,290.82$4,500.00$5,206.50$7,100.00$5,350.00
78Inlet (complete)(type AZ2G)(hou) (465-7317)EACH1$7,500.00$7,800.00$10,061$7,500.00$7,727.50$10,150$12,020
79Manh (complete)(type A)(hou) (465-7320)EACH11$7,700.00$4,200.00$7,184.41$5,500.00$7,774.20$8,850.00$7,990.00
80JCT box (complete)(special) (465-7332)EACH4$2,400.00$85,000$89,351$140,000$158,570$75,000$66,600
81Manh(complete)(type A)(mod) (465-7401)EACH7$10,000$4,000.00$3,804.19$3,500.00$4,714.00$5,250.00$4,570.00
82Jack bor or tun pipe(24 in)(RC)(CL III) (476-7011)LF58$1,800.00$1,480.00$603.25$1,000.00$209.40$1,500.00$1,500.00
83Adjusting manholes (479-7001)EACH2$1,200.00$700.00$3,152.20$750.00$520.00$1,225.00$1,730.00
84Removing structure (inlet) (496-7002)EACH14$500.00$650.00$728.66$600.00$481.50$620.00$1,550.00
85Removing structure (manhole) (496-7003)EACH2$1,200.00$2,250.00$728.23$850.00$772.80$770.00$1,550.00
86Removing structure (set) (496-7004)EACH4$1,500.00$550.00$546.55$600.00$1,379.00$620.00$788.00
87Removing structure (headwall) (496-7006)EACH4$3,000.00$1,800.00$2,623.42$600.00$1,379.00$1,040.00$1,600.00
88Removing structure (pipe) (496-7007)LF220$40.00$30.00$1,093.09$25.00$35.30$25.00$29.10
89Removing structure (box culvert) (496-7008)LF1,695$30.00$64.00$91.67$75.00$161.20$95.00$49.00
90Removing structure (bridge 100 - 499 FT length) (496-7010)EACH1$226,900$140,000$375,518$240,000$160,493$1,000,000$134,108
91Mobilization (500-7001)LS1$5,018,926$5,140,000$2,000,000$7,500,000$7,500,000$8,000,000$8,412,722
92Barricades, signs and traffic handling (502-7001)MO29$10,000$6,000.00$7,100.00$11,000$5,742.40$75,000$45,963
93Portable changeable message sign (503-7002)EACH5$36,000$15,000$18,000$19,000$18,200$50,000$22,550
94TMA (stationary) (505-7001)DAY410$200.00$300.00$200.00$250.00$208.00$350.00$426.40
95TMA (mobile operation) (505-7002)HR100$90.00$150.00$262.00$75.00$104.00$100.00$81.90
96Temporary sediment control fence (install) (506-7039)LF3,553$4.00$3.84$3.15$3.00$1.90$3.84$3.00
97Temporary sediment control fence (remove) (506-7041)LF3,553$1.00$1.00$1.00$1.00$0.60$0.96$1.00
98Biodegradable erosion control logs (install) (8") (506-7043)LF750$10.00$7.29$5.75$6.00$5.20$6.50$5.50
99Biodegradable erosion control logs (install) (12") (506-7044)LF144$15.00$7.29$8.13$7.00$6.20$7.29$6.75
100Biodegradable erosion control logs (remove) (506-7046)LF894$3.00$1.25$2.60$3.00$2.10$1.24$2.50
101Constructing detours (508-7001)SY2,480$110.00$90.00$93.46$100.00$147.00$130.00$102.00
102Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001)LF24,360$60.00$54.00$55.34$60.00$46.70$50.00$76.00
103Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009)LF1,860$75.00$14.00$88.00$33.00$17.00$30.00$47.25
104Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010)LF62$95.00$13.75$88.13$33.00$17.00$85.00$79.75
105Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025)LF11,400$20.00$7.25$5.00$6.00$12.60$9.00$8.65
106Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033)LF820$20.00$10.00$12.69$8.00$18.20$8.00$21.60
107Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034)LF80$45.00$25.00$12.68$8.00$18.20$10.50$22.00
108Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049)LF14,310$50.00$10.00$5.69$9.00$11.80$11.50$8.75
109Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057)LF1,860$16.00$12.00$5.55$9.00$15.50$10.00$11.80
110Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058)LF62$30.00$16.00$6.54$9.00$15.50$15.00$12.60
111Permanent CTB (single slope) (type 3) (42 ) (514-7002)LF160$230.00$325.00$420.00$190.00$116.00$270.00$259.00
112Colored textured concrete (6") (527-7003)SY41$200.00$165.00$272.02$225.00$140.40$150.00$102.00
113Concrete curb (mono) (type II) (529-7007)LF14,797$10.00$4.00$4.20$4.00$4.00$6.30$3.85
114Driveways (concrete) (530-7006)SY301$110.00$132.00$78.57$100.00$92.10$98.00$95.75
115Concrete sidewalks (6") (531-7003)SY2,213$95.00$69.00$72.29$75.00$67.50$65.00$72.00
116Curb ramps (type 5) (531-7008)EACH1$3,500.00$2,750.00$2,220.00$3,000.00$1,580.10$2,045.00$2,540.00
117Curb ramps (type 7) (531-7010)EACH4$4,000.00$1,850.00$1,900.00$2,400.00$3,238.40$2,370.00$2,540.00
118Curb ramps (type 10) (531-7011)EACH1$4,300.00$2,050.00$2,220.00$2,800.00$3,132.00$2,840.00$2,650.00
119Curb ramps (type 21) (531-7013)EACH1$9,700.00$2,450.00$2,220.00$3,500.00$2,201.20$3,340.00$2,650.00
120Metal W-beam guard fence (timber post) (540-7001)LF75$30.00$28.50$47.23$45.00$32.50$31.25$28.50
121Metal beam guard fence trans (TL2) (540-7006)EACH2$1,400.00$1,635.00$1,427.00$1,400.00$1,742.00$1,675.00$1,640.00
122Driveway terminal anchor section (540-7014)EACH1$650.00$1,525.00$3,835.00$1,650.00$1,768.00$1,700.00$3,300.00
123Guardrail end treatment (install) (544-7001)EACH3$3,500.00$3,300.00$3,700.00$3,600.00$3,666.00$3,525.00$3,300.00
124Crash cushion attenuator (move & reset) (545-7002)EACH16$2,005.00$1,650.00$1,626.00$1,200.00$1,612.00$1,050.00$1,650.00
125Crash cushion attenuator (remove) (545-7004)EACH11$1,450.00$1,100.00$850.00$500.00$842.40$1,040.00$1,100.00
126Crash cushion attenuator (install)(S)(N)(TL2) (545-7013)EACH2$6,800.00$18,900$2,700.00$8,000.00$7,763.60$17,200$13,000
127Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH11$8,510.00$7,850.00$6,290.00$8,000.00$8,195.20$7,500.00$7,850.00
128Chain link fence (install) (8') (550-7005)LF154$75.00$75.00$53.00$75.00$52.00$50.00$75.00
129Chain link fence (remove) (550-7007)LF260$5.00$10.00$12.00$5.00$11.40$11.00$5.00
130Pipe underdrains (type 6) (6") (556-7006)LF2,862$50.00$13.00$52.39$48.00$4.40$35.00$28.80
131Pipe underdrains (type 8)(8") (556-7011)LF730$75.00$128.00$56.60$80.00$29.10$40.00$204.00
132In RD IL (U/P) (type 1) (150W EQ) LED (610-7014)EACH41$5,000.00$4,068.00$1,495.00$2,400.00$2,652.00$1,425.00$2,100.00
133In RD IL (U/P) (type 2) (150W EQ) LED (610-7016)EACH16$2,662.00$4,200.00$1,360.00$1,250.00$2,652.00$1,295.00$1,610.00
134LED HI MST IL asm (6 fixt) (type A) (614-7002)EACH1$40,000$8,115.00$8,230.00$53,000$59,280$7,795.00$8,390.00
135Conduit (PVC) (schedule 40) (3") (618-7036)LF4,247$10.00$14.65$15.90$25.00$22.90$15.15$17.30
136Conduit (PVC) (schedule 40) (4") (618-7040)LF361$20.00$20.00$35.00$23.00$27.00$33.25$25.40
137Conduit (PVC) (schedule 40) (6") (618-7044)LF347$25.00$20.00$48.00$47.00$39.50$45.00$33.75
138Conduit (PVC) (schedule 80) (2") (618-7054)LF4,263$16.00$13.82$11.70$14.00$19.80$11.50$10.30
139Conduit (PVC) (schedule 80) (3") (618-7060)LF2,066$23.00$16.30$15.80$20.00$23.90$15.05$15.00
140Conduit (PVC) (schedule 80) (4") (618-7064)LF2,330$20.00$19.35$32.30$23.00$31.20$30.75$18.80
141Conduit (PVC) (schedule 80) (4") (bore) (618-7065)LF82$150.00$27.85$215.18$29.50$56.20$205.00$19.10
142Conduit (RM) (3/4") (618-7070)LF860$25.00$16.66$34.38$33.00$29.10$32.75$19.30
143Conduit (RM) (2") (618-7078)LF64$35.00$32.22$52.75$45.00$35.40$50.25$29.10
144Conduit (RM) (6") (618-7088)LF882$100.00$75.00$288.66$100.00$57.20$275.00$125.00
145ITS multi-duct CND (PVC-40) (619-7001)LF2,357$30.00$44.52$30.00$20.00$45.80$28.25$31.75
146ITS multi-duct CND (PVC-80) (619-7005)LF4,918$40.00$45.16$57.73$30.00$49.90$55.00$33.25
147Electrical conductor (no.12) bare (620-7003)LF860$1.34$1.75$2.00$1.50$1.60$1.65$1.40
148Electrical conductor (no.12) insulated (620-7004)LF1,720$1.70$1.75$2.00$1.50$1.80$1.75$1.40
149Electrical conductor (no.8) bare (620-7007)LF1,800$2.50$2.25$2.30$2.00$2.10$2.15$1.80
150Electrical conductor (no.8) insulated (620-7008)LF80$2.00$2.70$6.00$2.25$2.30$5.00$2.10
151Electrical conductor (no.6) bare (620-7009)LF4,562$2.00$2.85$2.60$2.50$2.60$2.45$2.30
152Electrical conductor (no.6) insulated (620-7010)LF7,765$3.00$3.17$2.60$2.75$2.90$2.50$2.50
153Tray cable (3 conductor) (12 AWG) (621-7002)LF2,155$3.50$3.97$3.50$4.00$2.10$3.35$3.00
154ITS GND box(pcast) type 1 (243660)W/aprn (623-7006)EACH11$6,000.00$4,385.00$6,114.25$4,700.00$4,680.00$5,825.00$5,890.00
155Ground box type D (162922)W/apron (624-7008)EACH17$1,375.00$1,246.00$1,422.28$1,200.00$1,612.00$1,355.00$1,070.00
156Remove ground box (624-7013)EACH5$680.00$107.00$450.00$500.00$884.00$425.00$50.00
157Elc SRV type D 120/240 060(NS)SS(E)SP(O) (628-7148)EACH1$9,000.00$10,530$7,600.00$8,500.00$8,840.00$7,200.00$7,760.00
158Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH4$700.00$557.00$590.00$600.00$764.40$735.00$557.00
159Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH19$800.00$590.00$620.00$625.00$858.00$825.00$590.00
160Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025)EACH1$1,000.00$730.00$770.00$750.00$946.40$910.00$730.00
161Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH1$1,300.00$900.00$950.00$950.00$1,242.80$1,195.00$900.00
162Relocate SM RD SN sup&AM type 10BWG (644-7065)EACH6$1,000.00$3,700.00$450.00$450.00$769.60$740.00$425.00
163Relocate SM RD SN sup&AM type S80 (644-7067)EACH1$750.00$425.00$520.00$500.00$832.00$740.00$490.00
164Remove SM RD SN sup&AM (644-7073)EACH10$105.00$95.00$100.00$100.00$98.80$110.00$95.00
165Remove SM RD SN sup&AM (sign only) (644-7075)EACH2$100.00$35.00$37.00$40.00$124.80$75.00$35.00
166Work zone pavement marking non-removing (W)4"(broken) (662-7001)LF130$1.00$1.00$1.10$1.00$0.50$0.45$1.00
167Work zone pavement marking non-removing (W)4"(DOT) (662-7002)LF102$1.00$1.00$1.10$1.00$0.50$0.45$1.00
168Work zone pavement marking non-removing (W)4"(solid) (662-7004)LF1,371$0.50$1.00$1.10$1.00$0.50$0.45$1.00
169Work zone pavement marking non-removing (W)8"(solid) (662-7012)LF140$1.00$1.00$1.10$2.00$0.60$0.60$1.00
170Work zone pavement marking non-removing (W)24"(solid) (662-7017)LF56$8.00$6.00$6.50$6.00$3.30$3.20$6.00
171Work zone pavement marking non-removing (W)(arrow) (662-7018)EACH3$100.00$110.00$116.00$120.00$78.00$75.00$110.00
172Work zone pavement marking non-removing(W)(word) (662-7030)EACH3$120.00$110.00$116.00$120.00$78.00$75.00$110.00
173Work zone pavement marking non-removing (Y)4"(solid) (662-7035)LF123$1.00$1.00$1.10$1.00$0.50$0.45$1.00
174Work zone pavement marking removing (reflectorized) type II-C-R (662-7053)EACH36$7.00$4.00$4.20$4.00$3.10$3.00$4.00
175Work zone pavement marking removing (W)4"(broken) (662-7061)LF230$1.00$1.50$1.60$1.50$1.60$1.50$1.50
176Work zone pavement marking removing (W)4"(DOT) (662-7062)LF22$2.00$2.50$2.60$2.50$1.60$1.50$2.50
177Work zone pavement marking removing (W)4"(solid) (662-7064)LF4,886$1.50$0.80$1.00$0.80$1.60$1.50$0.80
178Work zone pavement marking removing (W)6"(broken) (662-7065)LF2,000$1.42$1.40$1.50$1.40$1.30$1.25$1.40
179Work zone pavement marking removing (W)6"(DOT) (662-7066)LF492$2.55$1.80$2.00$1.80$1.30$1.25$1.80
180Work zone pavement marking removing (W)6"(solid) (662-7068)LF61,109$1.54$0.80$1.00$0.80$1.30$1.25$0.80
181Work zone pavement marking removing (W)8"(solid) (662-7072)LF450$2.50$1.40$1.50$1.40$2.10$2.00$1.40
182Work zone pavement marking removing (W)24"(solid) (662-7077)LF108$17.00$8.00$9.00$8.00$5.20$5.00$8.00
183Work zone pavement marking removing (W)(arrow) (662-7082)EACH3$300.00$150.00$159.00$150.00$156.00$150.00$150.00
184Work zone pavement marking removing (W)(word) (662-7092)EACH3$300.00$150.00$159.00$150.00$156.00$150.00$150.00
185Work zone pavement marking removing (Y)4"(solid) (662-7097)LF14,161$1.55$0.80$1.00$0.80$1.60$1.50$0.80
186Work zone pavement marking removing (Y)24"(solid) (662-7105)LF4,645$1.50$8.00$9.00$8.00$5.20$5.00$8.00
187Reflectorized pavement marking type II (W) (entr gore) (666-7195)EACH2$150.00$450.00$475.00$450.00$468.00$450.00$450.00
188Reflectorized pavement marking type II (W) (exit gore) (666-7196)EACH2$150.00$450.00$475.00$450.00$468.00$450.00$450.00
189Reflectorized pavement marking type II (Y)(curb) (666-7221)LF1,332$5.00$1.10$1.20$1.10$2.30$2.25$1.10
190Reflectorized pavement marking type III (W)(6")(solid) (666-7236)LF20,345$1.30$0.95$1.00$1.00$0.80$0.80$0.95
191Reflectorized pavement marking type III (W)(6")(broken) (666-7237)LF10,513$1.40$0.95$1.00$1.00$0.80$0.80$0.95
192Reflectorized pavement marking type III (W)(6")(DOT) (666-7238)LF690$1.62$1.25$1.30$1.25$0.80$0.80$1.25
193Reflectorized pavement marking type III (W)(8")(solid) (666-7239)LF3,971$3.00$1.80$2.00$2.00$1.40$1.30$1.80
194Reflectorized pavement marking type III (W)(24")(solid) (666-7244)LF692$15.00$11.50$12.00$12.00$12.50$12.00$11.50
195Reflectorized pavement marking type III (Y)(6")(solid) (666-7248)LF15,029$1.30$0.95$1.00$1.00$0.80$0.80$0.95
196Reflectorized pavement marking type III (BLK)(6")(shadow) (666-7262)LF10,513$1.50$1.60$1.70$1.60$0.90$0.85$1.60
197Prefabricated PM type C (W)(arrow) (668-7091)EACH26$400.00$250.00$265.00$250.00$260.00$250.00$250.00
198Prefabricated PM type C (W)(double arrow) (668-7093)EACH3$450.00$460.20$490.00$500.00$364.00$350.00$460.00
199Prefabricated PM type C (W)(uturn arrow) (668-7096)EACH3$400.00$535.00$565.00$600.00$260.00$250.00$534.00
200Prefabricated PM type C (W)(word) (668-7103)EACH26$410.00$360.00$380.00$400.00$260.00$250.00$360.00
201Reflectorized pavement marker type I-C (672-7002)EACH137$8.00$5.00$5.30$5.00$6.80$6.50$5.00
202Reflectorized pavement marker type II-A-A (672-7004)EACH22$5.00$5.00$5.30$5.00$6.80$6.50$5.00
203Reflectorized pavement marker type II-C-R (672-7006)EACH577$5.90$5.00$5.30$5.00$6.80$6.50$5.00
204Eliminating existing PM & markers (6") (677-7002)LF29,218$1.46$0.40$0.50$0.40$0.70$0.69$0.40
205Eliminating existing PM & markers (arrow) (677-7009)EACH2$60.00$55.00$58.00$55.00$26.00$25.00$55.00
206Eliminating existing PM & markers (word) (677-7015)EACH2$65.00$55.00$58.00$55.00$26.00$25.00$55.00
207Pavement surface preparation for marking (6") (678-7002)LF8,474$1.00$0.10$0.15$0.10$0.01$0.01$0.10
208Pavement surface preparation for marking (8") (678-7004)LF3,971$0.40$0.20$0.20$0.20$0.02$0.02$0.20
209Pavement surface preparation for marking (24") (678-7008)LF692$2.00$0.40$0.40$0.40$0.10$0.06$0.40
210Pavement surface preparation for marking (arrow) (678-7009)EACH26$30.00$5.00$5.30$5.00$10.40$10.00$5.00
211Pavement surface preparation for marking (double arrow) (678-7010)EACH3$70.00$5.00$5.30$5.00$0.01$15.00$5.00
212Pavement surface preparation for marking (uturn arr) (678-7012)EACH3$25.00$15.00$16.00$15.00$15.60$15.00$15.00
213Pavement surface preparation for marking (word) (678-7016)EACH26$30.00$15.00$16.00$15.00$10.40$10.00$15.00
214Install highway traffic signal (system) (680-7003)EACH1$36,300$39,000$40,672$42,000$57,564$38,750$33,570
215Removing traffic signals (diamond) (680-7012)EACH1$15,000$3,361.00$4,000.00$11,000$5,720.00$3,575.00$3,500.00
216Temporary traffic signals (681-7001)EACH3$50,000$35,600$48,806$56,000$43,680$46,500$27,700
217Vehicle signal section (12")LED(green) (682-7001)EACH14$305.00$290.00$330.00$250.00$260.00$315.00$285.00
218Vehicle signal section (12")LED(green arrow) (682-7002)EACH4$305.00$290.00$330.00$250.00$260.00$315.00$285.00
219Vehicle signal section (12")LED(yel) (682-7003)EACH14$312.00$290.00$330.00$250.00$260.00$315.00$285.00
220Vehicle signal section (12")LED(yel arrow) (682-7004)EACH4$305.00$290.00$330.00$250.00$260.00$315.00$285.00
221Vehicle signal section (12")LED(red) (682-7005)EACH14$312.00$290.00$330.00$250.00$260.00$315.00$285.00
222Vehicle signal section (12")LED(red arrow) (682-7006)EACH8$305.00$290.00$330.00$250.00$260.00$315.00$285.00
223Pedestrian signal section (LED)(countdown) (682-7018)EACH8$700.00$640.00$771.50$700.00$884.00$735.00$700.00
224Backplate W/reflectorized border(4 sec) (682-7037)EACH4$200.00$247.00$240.00$250.00$208.00$225.00$200.00
225Backplate W/reflectorized border(3 sec) (682-7054)EACH14$180.00$185.00$210.00$210.00$156.00$200.00$150.00
226Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007)LF1,340$2.20$2.30$2.50$2.30$2.30$2.25$1.95
227Traffic signal CBL (type A)(12 AWG)(4 conductor) (684-7009)LF1,330$2.80$3.62$3.50$3.50$2.60$3.10$2.95
228Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012)LF3,130$3.20$5.75$4.50$5.40$3.10$4.35$4.95
229Ins traffic signal PL AM(S)1 arm(36')lum (686-7039)EACH1$15,300$14,750$16,650$15,700$18,876$15,750$14,370
230Ins traffic signal PL AM(S)1 arm(44')lum (686-7047)EACH1$18,600$16,500$18,300$17,500$20,644$17,250$16,870
231Ins traffic signal PL AM(S)1 arm(55')lum (686-7059)EACH2$31,700$40,000$33,327$34,000$40,196$31,750$28,490
232Ins traffic signal PL AM(S)1 arm(65')lum (686-7067)EACH2$33,000$40,000$34,927$35,000$41,548$33,275$29,810
233Pedestrian pole assembly (687-7001)EACH4$3,000.00$2,405.00$2,750.00$3,800.00$3,640.00$2,595.00$2,000.00
234Pedestrian detect push button (APS) (688-7001)EACH7$1,000.00$925.00$870.00$800.00$884.00$825.00$776.00
235Pedestrian detector controller unit (688-7003)EACH1$4,000.00$4,100.00$3,900.00$4,000.00$3,640.00$3,675.00$3,470.00
236Removal of conduit (690-7001)LF3,518$15.00$10.18$7.70$11.00$17.30$7.25$2.00
237Removal of signal pole assembly (690-7051)EACH2$3,000.00$268.00$1,150.00$850.00$1,560.00$1,075.00$1,500.00
238Remove pedestrian pole assembly (690-7089)EACH9$900.00$169.00$290.00$500.00$1,248.00$275.00$500.00
239Deck drains (4068-7001)LF280$30.00$10.00$94.00$40.00$61.50$375.00$64.25
240Stormwater pump station (5082-7001)EACH1$10,540,390$13,443,883$12,000,000$11,700,000$12,316,967$12,500,000$14,500,000
241Railroad track construction (5085-7001)LS1$3,806,300$3,800,000$6,000,000$4,800,000$4,591,509$5,570,000$4,310,600
242VIVDS temporary (6006-7006)EACH1$54,600$13,649$35,600$15,000$26,884$33,750$13,500
243VIVDS cabling (6006-7007)LF1,185$4.25$2.80$3.00$3.00$2.60$2.50$3.95
244Bbu system (external battery cabinet) (6007-7001)EACH2$9,100.00$8,800.00$9,500.00$9,500.00$8,840.00$8,975.00$8,010.00
245RVDS (presence detection only) (6008-7001)EACH6$8,150.00$8,460.00$6,166.73$9,000.00$7,800.00$5,875.00$7,900.00
246RVDS (advance detection only) (6008-7002)EACH4$8,720.00$8,500.00$6,822.77$9,000.00$8,840.00$6,500.00$8,020.00
247Radar presence detector comm cable (6008-7009)LF3,650$2.50$2.78$2.00$3.00$2.60$1.75$2.90
248ITS pole MNT cab (type 2) (conf 2) (6011-7011)EACH1$6,000.00$6,671.00$6,200.00$7,000.00$6,448.00$5,875.00$4,710.00
249ITS pole (55 FT)(110 MPH) (6011-7027)EACH1$19,000$20,800$24,272$22,000$29,640$23,125$19,920
250CCTV field equipment (digital) (6018-7002)EACH1$5,300.00$2,700.00$9,000.00$3,000.00$9,880.00$8,575.00$8,510.00
251Remove CCTV field equipment (6018-7008)EACH1$600.00$1,400.00$800.00$1,500.00$1,560.00$750.00$500.00
252CTMS relocation (hub BLDG) (6018-7012)EACH1$14,500$3,360.00$9,400.00$3,500.00$19,084$8,875.00$4,250.00
253Relocate high mast lighting assembly (6019-7002)EACH2$20,000$11,821$16,000$13,000$9,880.00$15,250$23,000
254Fiber optic CBL(single-mode)(144 fiber) (6027-7006)LF12,199$4.00$3.85$9.39$4.00$9.60$8.95$5.55
255Fiber optic CBL (single-mode)(6 fiber) (6027-7011)LF2,082$2.00$1.61$4.50$2.00$5.80$4.35$3.50
256Remove fiber optic cable (6027-7018)LF11,269$2.00$0.60$2.50$1.00$4.10$2.40$1.00
257Install GND MT comm cabinet foundation (6050-7003)EACH1$7,000.00$4,520.00$2,800.00$5,000.00$3,640.00$2,675.00$3,030.00
258Remove existing cables (power) (6072-7001)LF590$2.00$1.15$3.00$2.00$3.60$2.50$2.00
TxDOT contract A00121975: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of February 4, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy