TxDOT contract A00132533 bid tabulation

Bridge Replacement, SS 348 (LP 12 NB to IH 35E NB DIRECT CONNECTORS). Let by Texas DOT on March 4, 2026, Dallas, Dallas District. 9 bids received; low bid $16,606,597 by Highway 19 Construction LLC, +2.7% against the engineer's estimate of $16,165,949.

Owner
Texas DOT
Letting
04 MAR 2026
Pay items
184
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Highway 19 Construction LLC$16,606,597Low+3.0%
2R Construction Civil, LLC$16,856,015+2.0%+4.0%
3Indus Road & Bridge, Inc.$17,236,229+4.0%+7.0%
4Altus Construction LLC$17,327,418+4.0%+7.0%
5Harper Brothers Construction LLC$18,525,942+12%+15%
6Ragle Construction, Inc.$19,232,026+16%+19%
7Webber, LLC$19,951,728+20%+23%
8Ed Bell Construction Company$21,415,405+29%+32%
9Copasa Inc$24,831,323+50%+54%
TxDOT contract A00132533: bids by rank

Engineer's estimate: $16,165,949.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Highway 19 Construction LLC2. R Construction Civil, LLC3. Indus Road & Bridge, Inc.4. Altus Construction LLC5. Harper Brothers Construction LLC6. Ragle Construction, Inc.
1Preparing row (100-7002)STA30.10$16,000$10,000$3,000.00$13,500$56,991$7,800.00$9,700.00
2Removing concrete (pavement) (104-7001)SY2,799$21.00$25.00$45.00$18.00$9.65$15.00$11.00
3Removing concrete (riprap) (104-7006)SY1,247$11.00$25.00$11.00$20.00$10.45$5.00$9.00
4Removing concrete (curb) (104-7016)LF677$8.75$10.00$5.00$5.00$12.88$5.00$7.00
5Removing concrete (appr slab) (104-7030)SY932$38.50$50.00$15.00$19.00$14.48$5.00$15.00
6Removing concrete (traffic barrier) (104-7035)LF1,239$30.00$10.00$60.00$44.00$28.96$20.00$14.60
7Remove (18"-22") TRT/untrt base & asphalt pavement (105-7018)SY7,567$10.50$10.00$17.00$17.00$5.64$15.00$11.50
8Excavation (roadway) (110-7001)CY18,069$18.50$15.00$22.00$17.00$21.52$10.00$30.00
9Embankment (final)(DC)(type C1) (132-7008)CY16,591$18.00$20.00$22.00$17.00$28.94$15.00$20.00
10Embankment (final)(DC)(type C2) (132-7010)CY37,062$25.00$18.00$22.00$53.00$36.29$50.00$54.00
11Compost manuf topsoil (4") (161-7002)SY20,905$2.20$1.00$1.50$2.00$10.47$1.25$0.95
12Block sodding (162-7002)SY20,905$3.00$5.00$4.00$4.20$4.99$4.00$6.00
13Drill seed (temporary_warm_cool) (164-7015)SY18,568$0.33$0.13$0.25$0.27$0.14$0.25$0.31
14Vegetative watering (168-7001)TGL5,873$1.00$20.00$36.00$10.00$6.25$5.00$35.30
15FL BS (compacted in place)(type D GR 1-2) (8") (247-7079)SY12,535$18.70$25.00$33.00$15.00$13.80$20.95$17.80
16Lime (com or QK)(slurry) (260-7005)TON169$300.00$350.00$350.00$410.00$337.17$375.00$468.69
17Lime TRT (existing material & new base)(8") (260-7011)SY12,535$5.00$8.00$6.00$6.00$4.97$10.00$4.00
18Prime coat(MC-30 or AE-P) (310-7013)GAL3,762$4.25$4.50$5.50$6.00$5.29$5.20$6.00
19SP mixes SP-B PG76-22 (344-7007)TON6,896$100.00$134.00$150.00$147.00$142.11$131.00$110.00
20SP mixes SP-D PG64-22 (344-7041)TON1,379$126.00$143.00$180.00$137.00$170.30$121.00$130.00
21Tack coat (344-7077)GAL3,289$4.25$1.50$3.50$4.50$3.53$4.00$6.00
22Stone-MTRX-asphalt SMA-D sac-A PG76-22 (346-7009)TON1,694$175.00$200.00$210.00$177.00$199.66$158.00$172.00
23Planing asphalt concrete pavement(0" to 2") (354-7032)SY1,994$3.00$10.00$5.50$4.00$5.04$8.00$7.30
24Planing asphalt concrete pavement(0" to 6") (354-7035)SY573$18.00$15.00$11.00$4.50$5.04$14.00$17.40
25Cem stabil BKFL (400-7010)CY441$185.00$180.00$60.00$290.00$145.04$275.00$140.00
26Trench excavation protection (402-7001)LF702$17.00$10.00$2.00$4.50$7.07$5.00$16.20
27Temporary special shoring (403-7001)SF16,064$30.00$35.00$54.00$50.00$47.16$30.00$39.00
28Drilled shaft (18 in) (416-7002)LF90$280.00$350.00$165.00$100.00$88.18$100.00$143.00
29Drilled shaft (36 in) (416-7006)LF10$296.00$300.00$800.00$750.00$217.80$662.00$662.00
30Drilled shaft (42 in) (416-7007)LF1,706$285.00$650.00$420.00$300.00$283.65$600.00$334.00
31Drilled shaft (48 in) (416-7008)LF21$350.00$600.00$925.00$850.00$287.45$765.00$765.00
32Drilled shaft (traffic signal pole) (36 in) (416-7044)LF13$750.00$521.00$750.00$720.00$527.78$647.00$647.00
33Class B concrete (flume) (420-7010)CY9.81$675.00$1,000.00$2,000.00$770.00$685.48$1,500.00$740.00
34Class C concrete (abutment)(HPC) (420-7013)CY117.10$1,220.00$1,400.00$2,000.00$870.00$960.00$2,000.00$880.00
35Class C concrete (cap)(HPC) (420-7023)CY52.40$1,600.00$1,700.00$2,800.00$1,150.00$820.71$2,250.00$1,010.00
36Class C concrete (column)(HPC) (420-7039)CY34.20$1,500.00$1,800.00$1,800.00$1,250.00$1,619.67$2,500.00$1,350.00
37Class C concrete (rail foundation) (420-7052)CY274$665.00$1,000.00$460.00$475.00$337.94$675.00$636.00
38Reinforced concrete slab (HPC) (422-7002)SF16,221$27.50$27.00$26.00$24.00$23.38$35.00$29.10
39Approach slab (HPC) (422-7014)CY262$715.00$750.00$900.00$625.00$516.02$750.00$563.00
40Retaining wall (MSE) (423-7001)SF34,821$84.00$85.00$60.00$58.00$54.82$50.00$45.00
41Prestressed concrete girder (TX62) (425-7006)LF3,061.80$240.00$277.00$240.00$270.00$223.40$315.00$252.00
42Riprap (concrete)(4 in) (432-7001)CY28.25$375.00$700.00$685.00$640.00$448.72$650.00$764.00
43Riprap (concrete)(5 in) (432-7002)CY1$1,100.00$1,000.00$455.00$1,000.00$483.87$1,250.00$1,500.00
44Riprap (mow strip)(4 in) (432-7013)CY100.28$720.00$55.00$475.00$590.00$575.06$900.00$691.00
45Riprap (stone common)(grout)(12 in) (432-7038)CY77$285.00$180.00$195.00$190.00$92.28$275.00$223.00
46Rail (type T222)(HPC) (450-7007)LF127$135.00$220.00$360.00$290.00$106.37$225.00$155.30
47Rail (type SSTR) (450-7024)LF1,695$88.00$120.00$115.00$72.00$53.25$75.00$65.00
48Rail (type SSTR)(HPC) (450-7025)LF2,285.90$90.00$160.00$125.00$80.00$56.21$50.00$65.00
49Rail (type T80PP)(HPC) (450-7052)LF114$140.00$220.00$375.00$310.00$105.41$350.00$224.00
50Sealed expansion joint (4 in) (SEJ - M) (454-7004)LF186$105.00$190.00$200.00$225.00$185.97$275.00$209.00
51Concrete box culvert (4 FT X 2 FT) (462-7003)LF435$350.00$550.00$420.00$350.00$402.77$418.17$404.00
52RC pipe (CL IV)(24 in) (464-7021)LF340$160.00$110.00$250.00$150.00$148.61$375.00$133.00
53Junction box(complete)(PJB)(3FTX3FT) (465-7005)EACH1$7,200.00$6,500.00$6,400.00$6,000.00$5,343.41$7,425.00$4,700.00
54Junction box(complete)(PJB)(5FTX5FT) (465-7009)EACH1$6,100.00$9,000.00$10,500$8,200.00$6,849.21$12,075$7,075.00
55Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126)EACH2$9,300.00$6,500.00$8,200.00$8,600.00$5,653.78$20,500$11,775
56Inlet (complete)(PSL)(FG)(4FTX4FT-4FTX4FT) (465-7128)EACH3$12,200$7,500.00$6,600.00$8,700.00$7,089.82$17,175$8,400.00
57Headwall (CH - FW - 0) (diameter= 24 in) (466-7005)EACH1$7,900.00$4,500.00$8,300.00$11,500$6,035.89$3,090.00$6,200.00
58Wingwall (PW - 1) (HW=7 FT) (466-7177)EACH1$27,500$21,000$35,000$32,000$23,928$28,160$31,000
59Wingwall (SW - 0) (HW=3 FT) (466-7202)EACH1$8,300.00$9,000.00$8,100.00$21,000$5,185.38$7,762.00$11,200
60Removing structure (inlet) (496-7002)EACH3$750.00$1,000.00$775.00$1,400.00$1,955.12$2,500.00$912.00
61Removing structure (set) (496-7004)EACH2$425.00$500.00$585.00$1,300.00$749.63$750.00$610.00
62Removing structure (pipe) (496-7007)LF326$25.00$50.00$1,150.00$80.00$27.66$30.00$22.00
63Removing structure (bridge 100 - 499 FT length) (496-7010)EACH1$125,000$100,000$100,000$100,000$137,771$650,350$1,000,000
64Mobilization (500-7001)LS1$1,408,268$1,700,000$1,600,000$1,721,286$1,724,099$1,850,000$1,900,000
65Barricades, signs and traffic handling (502-7001)MO27$25,000$5,000.00$8,400.00$20,000$32,088$37,000$83,850
66Portable changeable message sign (503-7002)EACH4$14,000$15,000$2,250.00$20,000$4,558.58$35,000$25,000
67TMA (stationary) (505-7001)DAY662$150.00$250.00$230.00$200.00$173.28$75.00$290.00
68TMA (mobile operation) (505-7003)DAY24$300.00$1,000.00$940.00$550.00$153.63$700.00$630.00
69Rock filter dams (install) (type 2) (506-7002)LF512$38.00$50.00$80.00$48.00$49.64$42.00$35.50
70Rock filter dams (remove) (506-7011)LF512$10.00$5.00$13.00$10.00$10.74$12.00$12.00
71Construction exits (install) (type 1) (506-7020)SY224$27.00$35.00$40.00$40.00$47.61$40.00$35.00
72Construction exits (remove) (506-7024)SY224$6.00$10.00$12.00$12.00$14.89$12.00$11.00
73Temporary sediment control fence (install) (506-7039)LF4,824$3.60$4.00$4.50$4.00$4.05$4.50$3.50
74Temporary sediment control fence (remove) (506-7041)LF4,824$1.20$1.00$0.50$0.85$1.52$0.50$1.00
75Biodegradable erosion control logs (install) (12") (506-7044)LF365$4.00$4.00$6.00$6.00$9.72$6.00$5.75
76Biodegradable erosion control logs (remove) (506-7046)LF365$1.00$1.00$1.00$2.00$2.63$1.00$1.10
77Constructing detours (508-7001)SY3,094$85.00$85.00$100.00$115.00$148.91$120.00$110.00
78Portable concrete traffic barrier (furnish and install)(F-shape)(type 1) (512-7005)LF6,060$35.60$75.00$21.00$75.00$6.01$85.00$21.00
79Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029)LF4,920$7.00$10.00$5.50$10.00$11.14$15.00$7.10
80Portable concrete traffic barrier (remove)(F-shape)(type 1) (512-7053)LF6,060$15.60$25.00$19.00$11.00$11.14$20.00$10.50
81Permanent CTB (F-shape) (mod) (514-7017)LF336$87.50$180.00$400.00$400.00$72.18$250.00$186.00
82Concrete curb (type I) (529-7001)LF352$51.45$35.00$28.00$27.00$13.81$15.00$24.00
83Metal W-beam guard fence (timber post) (540-7001)LF1,375$24.00$25.00$27.00$23.00$27.66$22.45$22.50
84Metal beam guard fence trans (thrie-beam) (540-7005)EACH6$2,560.00$2,035.00$1,900.00$1,900.00$2,000.71$2,035.00$1,850.00
85Short radius (28") (540-7013)LF50$28.00$49.00$80.00$27.00$50.85$48.88$25.50
86Downstream anchor terminal section (540-7015)EACH1$1,200.00$1,650.00$2,700.00$1,210.00$1,134.58$1,645.00$1,200.00
87Remove metal beam guard fence (542-7001)LF2,733$2.75$3.00$3.50$3.00$3.04$2.55$2.50
88Remove terminal anchor section (542-7002)EACH2$265.00$260.00$625.00$155.00$222.86$255.00$150.00
89Remove downstream anchor terminal (542-7003)EACH2$210.00$255.00$710.00$155.00$232.99$255.00$150.00
90RM metal beam guard fence trans (thrie-beam) (542-7004)EACH1$375.00$255.00$275.00$205.00$263.38$255.00$200.00
91Guardrail end treatment (install) (544-7001)EACH1$4,200.00$3,110.00$3,400.00$3,000.00$3,317.63$3,110.00$2,950.00
92Guardrail end treatment (remove) (544-7003)EACH1$385.00$255.00$275.00$255.00$334.30$255.00$250.00
93Crash cushion attenuator (move & reset) (545-7002)EACH4$2,800.00$1,100.00$1,600.00$2,000.00$1,544.85$1,145.00$1,500.00
94Crash cushion attenuator (remove) (545-7004)EACH6$3,800.00$1,000.00$900.00$1,200.00$820.54$995.00$1,500.00
95Crash cushion attenuator (install)(L)(W)(TL3) (545-7008)EACH1$52,000$46,500$47,000$50,000$39,001$46,500$42,000
96Cca (install)(N)(TL3)(work zone) (545-7018)EACH5$9,750.00$7,500.00$8,700.00$14,000$13,862$7,575.00$15,000
97Pipe underdrains (type 8) (6") (556-7008)LF1,900$45.00$15.00$55.00$45.00$12.79$55.00$56.60
98Remove RD IL asm (trans-base) (610-7009)EACH2$400.00$1,300.00$1,150.00$1,100.00$1,296.66$941.00$941.00
99Conduit (PVC) (schedule 40) (2") (618-7030)LF2,466$19.50$10.00$16.00$15.00$9.82$13.35$13.35
100Conduit (PVC) (schedule 40) (2") (bore) (618-7031)LF1,108$30.00$28.00$42.00$42.00$23.77$37.75$37.75
101Conduit (PVC) (schedule 40) (3") (618-7036)LF6,752$25.50$11.00$12.00$12.00$10.69$10.25$10.25
102Conduit (PVC) (schedule 40) (3") (bore) (618-7037)LF924$50.00$34.00$40.00$40.00$34.13$35.50$35.50
103Conduit (prepare) (618-7090)LF227$2.00$5.00$5.50$5.50$4.87$4.80$4.80
104ITS multi-duct CND (PVC-40) (619-7001)LF4,222$27.50$29.00$35.00$35.00$28.77$31.00$31.00
105ITS multi-duct CND (PVC-40)(bore) (619-7002)LF767$45.00$40.00$79.00$79.00$30.28$71.30$71.30
106Electrical conductor (no.12) insulated (620-7004)LF1,226$2.85$1.09$2.00$1.80$1.10$1.60$1.60
107Electrical conductor (no.10) insulated (620-7006)LF780$2.00$1.31$2.00$2.00$1.33$1.80$1.80
108Electrical conductor (no.8) bare (620-7007)LF273$3.00$1.93$2.00$2.00$1.98$1.75$1.75
109Electrical conductor (no.8) insulated (620-7008)LF4,831$3.00$2.00$2.50$2.50$1.88$2.25$2.25
110Electrical conductor (no.6) bare (620-7009)LF3,815$4.00$2.00$2.50$2.50$2.03$2.20$2.20
111Electrical conductor (no.6) insulated (620-7010)LF4,384$7.20$2.00$3.25$3.20$2.03$2.80$2.80
112Electrical conductor (no.4) bare (620-7011)LF1,032$3.00$3.50$3.30$3.30$3.55$2.95$2.95
113Electrical conductor (no.4) insulated (620-7012)LF10,376$3.75$3.50$4.00$4.00$3.32$3.60$3.50
114ITS GND box(pcast) type 1 (243660)W/aprn (623-7006)EACH12$7,000.00$4,500.00$7,200.00$7,200.00$4,473.48$6,485.00$6,485.00
115ITS GND box(pcast) type 2 (366060)W/aprn (623-7012)EACH1$13,500$6,300.00$10,800$10,900$6,366.81$9,680.00$9,680.00
116Remove ITS ground box (623-7041)EACH5$835.00$1,000.00$400.00$400.00$1,570.18$355.00$355.00
117Ground box type C (162911)W/apron (624-7006)EACH7$2,915.00$1,400.00$2,400.00$2,400.00$1,365.55$2,090.00$2,090.00
118Aluminum signs (type A) (636-7001)SF28$45.00$35.00$50.00$43.00$24.31$42.69$50.00
119Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH1$620.00$690.00$600.00$36.00$545.24$665.00$1,000.00
120Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH4$975.00$717.00$600.00$920.00$1,023.15$775.00$1,200.00
121Install small roadside sign support and assembly (rail mount) (644-7063)EACH1$4,865.00$6,000.00$600.00$5,000.00$4,178.70$6,960.00$7,500.00
122Relocate SM RD SN sup&AM type S80 (644-7067)EACH1$535.00$500.00$500.00$660.00$815.48$875.00$700.00
123Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012)EACH26$18.00$65.00$55.00$21.00$24.31$15.00$20.00
124Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018)EACH55$20.00$65.00$55.00$56.00$30.39$25.00$25.00
125Work zone pavement marking removing (W)6"(broken) (662-7065)LF1,790$1.55$1.75$2.50$2.20$1.01$1.75$1.50
126Work zone pavement marking removing (W)6"(DOT) (662-7066)LF76$4.70$2.00$5.00$2.50$5.07$2.00$1.50
127Work zone pavement marking removing (W)6"(solid) (662-7068)LF6,706$1.75$1.50$2.00$1.90$1.01$1.50$1.25
128Work zone pavement marking removing (W)8"(DOT) (662-7070)LF234$3.75$3.00$5.00$3.80$5.07$3.00$2.00
129Work zone pavement marking removing (W)8"(solid) (662-7072)LF666$2.50$2.25$4.50$2.80$2.03$2.25$2.00
130Work zone pavement marking removing (W)12"(solid) (662-7075)LF50$12.45$6.00$9.00$7.50$10.13$6.00$3.50
131Work zone pavement marking removing (W)(arrow) (662-7082)EACH2$385.00$200.00$600.00$250.00$253.25$200.00$250.00
132Work zone pavement marking removing (W)(word) (662-7092)EACH2$425.00$245.00$650.00$305.00$253.25$245.00$250.00
133Work zone pavement marking removing (Y)6"(solid) (662-7100)LF7,394$1.12$1.75$2.00$2.20$0.51$1.75$1.25
134Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009)LF268$1.87$1.65$4.25$2.10$2.03$1.65$1.50
135Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF225$2.25$1.75$2.50$2.20$5.07$1.75$2.00
136Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030)LF131$2.20$4.00$10.00$5.00$5.07$4.00$4.00
137Reflectorized pavement marking type I(W)(lane drop arrow)(100MIL) (666-7060)EACH2$680.00$425.00$650.00$530.00$607.81$425.00$350.00
138Reflectorized pavement marking type I(W)(entr gore)(100MIL) (666-7069)EACH1$1,700.00$1,400.00$2,300.00$1,800.00$709.11$1,400.00$1,500.00
139Reflectorized pavement marking type I(W)(exit gore)(100MIL) (666-7072)EACH1$1,600.00$1,950.00$2,400.00$2,500.00$709.11$1,950.00$2,000.00
140Pavement sler 6" (666-7347)LF2,305$0.28$0.30$0.40$0.40$0.30$0.30$0.25
141Pavement sler 8" (666-7348)LF225$1.31$0.60$0.65$0.80$1.01$0.60$0.25
142Pavement sler 12" (666-7350)LF131$1.45$1.75$2.00$2.20$1.01$1.75$0.50
143Pavement sler (arrow) (666-7353)EACH1$50.00$50.00$60.00$63.00$101.30$50.00$20.00
144Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF1,610$2.50$1.70$1.50$2.20$1.01$1.70$0.90
145Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF3,053$1.09$1.35$1.50$1.70$1.01$1.35$0.65
146Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF3,772$1.50$1.35$1.50$1.70$1.01$1.35$0.65
147Reflectorized pavement marker type II-C-R (672-7006)EACH217$7.00$7.25$7.00$9.10$10.13$7.25$4.25
148Eliminating existing PM & markers (6") (677-7002)LF4,868$0.65$0.85$1.00$1.10$1.01$0.85$0.55
149Eliminating existing PM & markers (8") (677-7004)LF705$2.50$125.00$2.00$1.60$3.04$1.25$0.65
150Pavement surface preparation for marking (6") (678-7002)LF15,350$0.70$0.25$0.25$0.32$0.27$0.25$0.07
151Pavement surface preparation for marking (8") (678-7004)LF1,029$1.00$0.30$0.25$0.40$0.30$0.30$0.07
152Pavement surface preparation for marking (12") (678-7006)LF293$1.30$1.00$1.00$1.25$0.30$1.00$0.14
153Pavement surface preparation for marking (arrow) (678-7009)EACH2$20.00$45.00$30.00$56.00$70.91$45.00$10.00
154Ins traffic signal PL AM(S)1 arm(48') (686-7049)EACH1$17,500$15,000$19,000$18,500$15,195$16,260$16,260
155Remove traffic signal PL (686-7313)EACH1$4,300.00$2,600.00$3,400.00$3,400.00$2,583.19$3,000.00$3,000.00
156Install circuit breaker (690-7234)EACH4$198.00$270.00$260.00$260.00$405.01$228.00$228.00
157Stone columns (30 in) (4052-7001)LF21,270$50.00$10.00$41.00$37.00$38.75$45.00$51.00
158Barrier gate (5034-7001)EACH1$25,000$5,000.00$11,000$21,000$3,798.82$29,991$21,500
159ITS RVSD (data collect & wwa) sys (6010-7001)EACH1$26,500$10,000$15,000$15,000$10,130$12,715$12,715
160ITS RVSD (DC & wwa)(relocate) (6010-7004)EACH6$3,100.00$3,300.00$1,300.00$1,350.00$3,337.89$1,175.00$1,175.00
161ITS pole MNT cab (type 2)(conf 2) (6011-7002)EACH2$7,420.00$6,740.00$8,600.00$8,600.00$12,641$7,750.00$7,750.00
162ITS pole (60 FT)(90 MPH) (6011-7003)EACH1$29,500$24,000$36,000$36,000$46,300$32,270$32,270
163ITS pole (40 FT)(relocate) (6011-7013)EACH1$5,200.00$8,450.00$4,500.00$4,500.00$12,534$4,020.00$4,020.00
164ITS pole MNT cab (type 3)(conf 1)(rel) (6011-7026)EACH1$8,300.00$1,870.00$1,800.00$1,800.00$1,894.34$1,595.00$1,595.00
165Ground box (prepare) (6013-7006)EACH14$235.00$290.00$400.00$400.00$739.44$357.00$357.00
166CCTV field equip (digital) (install only) (6018-7001)EACH1$5,500.00$1,000.00$1,100.00$1,100.00$989.72$941.00$941.00
167Relocate CCTV field equipment (6018-7007)EACH1$2,800.00$1,900.00$1,300.00$1,400.00$5,478.53$1,175.00$1,175.00
168CCTV mount (pedestal) (6018-7010)EACH1$2,500.00$390.00$1,400.00$1,450.00$395.08$1,265.00$1,265.00
169Fiber optic CBL (single-mode)(12 fiber) (6027-7001)LF250$6.00$2.90$8.00$8.00$2.89$7.10$7.10
170Fiber optic CBL (single-mode)(36 fiber) (6027-7002)LF660$5.00$2.40$10.00$10.00$2.42$8.80$8.80
171Fiber optic fusion splice (6027-7004)EACH300$90.00$325.00$89.00$89.00$329.23$80.00$80.00
172Fiber optic patch panel (12 position) (6027-7005)EACH2$1,500.00$1,350.00$1,500.00$1,500.00$13,200$1,295.00$1,295.00
173Fiber optic patch panel (36 positions) (6027-7007)EACH1$1,800.00$2,200.00$2,100.00$2,100.00$2,218.51$1,838.00$1,838.30
174FO splice enclosure (type 1) (6027-7009)EACH7$2,800.00$3.00$1,700.00$1,700.00$2,932.69$1,475.00$1,475.00
175Fiber optic CBL (single-mode)(6 fiber) (6027-7011)LF1,940$4.00$3.00$7.00$7.00$2.34$5.75$5.75
176Fiber optic patch panel (6 position) (6027-7012)EACH4$1,730.00$2,900.00$1,150.00$1,290.00$2,850.63$1,012.00$1,012.00
177Fiber optic CBL (SNGL-mode)(48 fiber) (6027-7013)LF5,891$5.00$5.00$11.00$11.00$4.93$9.85$9.85
178Fiber optic CBL (sing-mode)(24 fiber) (6027-7019)LF1,675$4.00$4.00$8.00$8.00$7.79$7.15$7.15
179Fiber optic patch panel (48 position) (6027-7038)EACH3$2,000.00$8,000.00$2,200.00$2,200.00$12,366$1,985.00$1,985.00
180Fiber optic patch panel (24 position) (6027-7043)EACH1$2,000.00$4,000.00$1,700.00$1,700.00$3,976.09$1,500.00$1,500.00
181Ethernet switch (install only) (6036-7001)EACH4$2,750.00$10,000$1,500.00$1,400.00$1,519.53$1,245.00$1,245.00
182Installation of terminal server (6046-7001)EACH1$1,950.00$1,000.00$175.00$175.00$1,013.02$155.00$155.00
183Remove hub building (6048-7001)EACH1$4,000.00$23,610$9,000.00$9,000.00$23,917$8,110.00$7,500.00
184ITS GRND MNT cab (type 4) (conf 2) (6050-7004)EACH1$19,000$8,690.00$17,000$16,500$8,803.12$14,891$20,000
TxDOT contract A00132533: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of March 4, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy