FDOT contract T4764 bid tabulation
SR 512 FROM E OF I-95 TO W OF 106TH AVE. Let by Florida DOT on August 26, 2026, Indian River, District 4. 9 bids received; low bid $2,295,224 by Ohla USA Inc.
- Owner
- Florida DOT
- Letting
- 26 AUG 2026
- Pay items
- 160
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ohla USA Inc | $2,295,224 | Low |
| 2 | Timothy Rose Contracting, Inc. | $2,456,988 | +7.0% |
| 3 | Ranger Construction Industries, Inc. | $2,467,235 | +7.0% |
| 4 | C.W. Roberts Contracting, Inc. | $2,721,084 | +19% |
| 5 | Carr Construction, LLC | $2,815,661 | +23% |
| 6 | Halley Engineering Contractors, Inc. | $2,833,352 | +23% |
| 7 | Watson Civil Construction, Inc. | $3,013,053 | +31% |
| 8 | Florida Engineering & Development Corp | $3,228,959 | +41% |
| 9 | Traffic Management Solutions, LLC | $3,347,802 | +46% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ohla USA Inc | 2. Timothy Rose Contracting, Inc. | 3. Ranger Construction Industries, Inc. | 4. C.W. Roberts Contracting, Inc. | 5. Carr Construction, LLC | 6. Halley Engineering Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $229,500 | $251,500 | $246,000 | $350,000 | $304,246 | $282,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $145,000 | $105,000 | $249,700 | $130,000 | $72,000 | $650,000 |
| 0015 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $0.01 | $3,378.00 | $14,200 | $8,500.00 | $34,046 | $15,000 |
| 0020 | Pedestrian escort/flagger (0102-5) | HR | 40 | $100.00 | $51.35 | $34.25 | $33.00 | $110.00 | $75.00 |
| 0025 | Traffic control officer (0102-14) | HR | 128 | $80.00 | $81.76 | $90.90 | $87.00 | $116.00 | $100.00 |
| 0030 | Work zone sign (0102-60) | ED | 17,989 | $0.19 | $0.01 | $0.20 | $0.20 | $0.20 | $0.23 |
| 0035 | Business sign (0102-61) | EACH | 1 | $60.00 | $0.01 | $68.20 | $61.50 | $70.00 | $37.00 |
| 0040 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 1,596 | $0.01 | $43.01 | $39.75 | $40.42 | $40.75 | $0.01 |
| 0045 | Temporary barrier, relocate, low profile concrete (0102-71-23) | LF | 168 | $0.01 | $22.12 | $20.45 | $20.80 | $21.00 | $0.01 |
| 0050 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 16,247 | $0.13 | $0.01 | $0.15 | $0.13 | $0.20 | $0.25 |
| 0055 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 183,890 | $0.04 | $0.01 | $0.05 | $0.04 | $0.10 | $0.08 |
| 0060 | Arrow board / advance warning arrow panel (0102-76) | ED | 233 | $5.20 | $0.01 | $5.90 | $5.33 | $6.10 | $7.00 |
| 0065 | Temporary raised/retroreflective pavement marker, type B (0102-78-2) | EACH | 835 | $6.00 | $6.54 | $6.80 | $4.60 | $7.00 | $4.00 |
| 0070 | Portable changeable message sign, temporary (0102-99) | ED | 1,527 | $8.75 | $9.54 | $9.95 | $8.90 | $10.25 | $12.00 |
| 0075 | Temporary signalization and maintenance, intersection (0102-104) | ED | 592 | $0.01 | $18.10 | $18.75 | $18.60 | $8.00 | $20.00 |
| 0080 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 592 | $0.01 | $18.10 | $18.75 | $18.60 | $8.00 | $20.00 |
| 0085 | Existing ITS maintenance (0102-112) | DA | 296 | $0.01 | $126.14 | $130.70 | $130.00 | $31.00 | $122.00 |
| 0090 | Type III barricade (0102-115) | ED | 1,546 | $0.29 | $0.01 | $0.35 | $0.30 | $0.30 | $0.30 |
| 0095 | Removable tape, white, solid 6" (0102-913-21) | GM | 0.01 | $13,500 | $17,267 | $20,000 | $123,000 | $17,451 | $15,840 |
| 0100 | Removable tape, white, 10'-30', 6'-10', or 2'-4' skip, 6" wide (0102-913-22) | GM | 0.05 | $6,000.00 | $4,316.79 | $4,500.00 | $6,600.00 | $6,980.00 | $3,960.00 |
| 0105 | Removable tape, white, symbol or arrow (0102-913-29) | EACH | 4 | $500.00 | $21.80 | $568.00 | $550.00 | $582.00 | $20.00 |
| 0110 | Sediment barrier (0104-10-3) | LF | 1,908 | $3.72 | $2.96 | $4.65 | $8.50 | $4.00 | $2.00 |
| 0115 | Inlet protection system (0104-18) | EACH | 4 | $250.00 | $54.97 | $484.60 | $150.00 | $546.00 | $150.00 |
| 0120 | Litter removal (0107-1) | ACRE | 26.27 | $300.00 | $91.52 | $150.60 | $48.00 | $438.00 | $100.00 |
| 0125 | Mowing (0107-2) | ACRE | 17.82 | $400.00 | $181.33 | $490.00 | $67.00 | $584.00 | $400.00 |
| 0130 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $10,000 | $7,521.67 | $7,840.00 | $16,050 | $3,490.00 | $3,000.00 |
| 0135 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $194,000 | $200,000 | $67,500 | $52,500 | $43,608 | $50,000 |
| 0140 | Removal of existing concrete (0110-4-10) | SY | 266 | $59.00 | $41.87 | $36.40 | $60.00 | $42.25 | $30.00 |
| 0145 | Regular excavation (0120-1) | CY | 886.70 | $34.14 | $21.87 | $20.15 | $30.00 | $23.50 | $30.00 |
| 0150 | Embankment (0120-6) | CY | 750.40 | $50.00 | $33.29 | $11.75 | $21.25 | $13.75 | $30.00 |
| 0155 | Type B stabilization (0160-4) | SY | 3,940 | $7.11 | $11.31 | $5.45 | $19.25 | $6.30 | $15.00 |
| 0160 | Optional base, base group 01 (0285-701) | SY | 859 | $9.85 | $19.92 | $16.95 | $21.50 | $19.75 | $18.50 |
| 0165 | Optional base, base group 04 (0285-704) | SY | 2,240 | $45.01 | $17.73 | $13.65 | $25.00 | $16.00 | $18.50 |
| 0170 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 11,232 | $4.50 | $2.82 | $3.45 | $3.10 | $4.00 | $3.70 |
| 0175 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 298.70 | $215.00 | $154.22 | $183.95 | $290.00 | $214.00 | $166.00 |
| 0180 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 1,176.30 | $164.00 | $185.34 | $179.35 | $265.00 | $209.00 | $202.00 |
| 0185 | Miscellaneous asphalt (0339-1) | TN | 11.60 | $999.00 | $436.18 | $478.75 | $590.00 | $557.00 | $230.00 |
| 0190 | Inlets, DT bot, type C,<10' (0425-1521) | EACH | 5 | $6,650.74 | $4,602.13 | $8,850.00 | $6,150.00 | $6,527.00 | $4,800.00 |
| 0195 | Inlets, ditch bottom, type G, <10' (0425-1571) | EACH | 3 | $9,787.82 | $11,585 | $13,800 | $11,300 | $11,983 | $8,800.00 |
| 0200 | Manholes, P-7, <10' (0425-2-41) | EACH | 2 | $6,000.00 | $5,463.41 | $10,600 | $7,700.00 | $8,144.00 | $5,800.00 |
| 0205 | Manholes, J-7, <10' (0425-2-71) | EACH | 1 | $12,000 | $9,009.54 | $13,000 | $9,775.00 | $10,354 | $6,950.00 |
| 0210 | Manholes, J-8, <10' (0425-2-91) | EACH | 1 | $12,500 | $8,456.84 | $14,900 | $8,450.00 | $8,958.00 | $6,600.00 |
| 0215 | Manhole, adjust, utilities (0425-5-1) | EACH | 1 | $1,540.00 | $1,204.86 | $2,410.00 | $1,150.00 | $1,222.00 | $750.00 |
| 0220 | Valve boxes, adjust (0425-6) | EACH | 12 | $1,100.00 | $1,164.72 | $963.00 | $875.00 | $931.00 | $500.00 |
| 0225 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 750 | $120.00 | $169.74 | $129.75 | $200.00 | $209.00 | $150.00 |
| 0230 | Pipe culvert,optional material,round, 24"S/CD (0430-175124) | LF | 16 | $350.00 | $1,117.77 | $902.00 | $890.00 | $942.00 | $650.00 |
| 0235 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 44 | $91.84 | $79.71 | $122.95 | $145.00 | $123.00 | $80.00 |
| 0240 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 237 | $91.84 | $114.47 | $138.05 | $170.00 | $161.00 | $80.00 |
| 0245 | Detectable warnings (0527-2) | SF | 138 | $40.82 | $42.99 | $46.60 | $42.00 | $40.75 | $70.00 |
| 0250 | Guardrail -roadway, general (0536-1-1) | LF | 364 | $22.95 | $27.24 | $26.10 | $23.50 | $39.50 | $34.00 |
| 0255 | Special guardrail post- deep post for slope break timber or steel (0536-7-1) | EACH | 61 | $67.86 | $73.97 | $77.10 | $70.00 | $58.00 | $51.00 |
| 0260 | Special guardrail post- post for shallow mount (0536-7-3) | EACH | 8 | $61.64 | $67.19 | $70.05 | $63.00 | $155.00 | $134.00 |
| 0265 | Guardrail end treatment- trailing anchorage (0536-85-20) | EACH | 2 | $1,333.58 | $1,494.18 | $1,520.00 | $1,350.00 | $1,654.00 | $1,422.00 |
| 0270 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 2 | $3,108.62 | $3,388.70 | $3,530.00 | $3,175.00 | $3,569.00 | $3,068.00 |
| 0275 | Performance turf, sod (0570-1-2) | SY | 4,618 | $2.25 | $5.22 | $4.30 | $8.00 | $41.25 | $5.00 |
| 0280 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 2.29 | $1,798.43 | $1,495.61 | $1,560.00 | $1,750.00 | $2,101.00 | $1,372.00 |
| 0285 | Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102) | GM | 0.12 | $1,913.04 | $1,498.88 | $1,490.00 | $2,300.00 | $2,428.00 | $1,372.00 |
| 0290 | Painted pavement markings, standard, white, solid for interchange markings, 12" (0710-11103) | GM | 0.03 | $2,322.58 | $3,453.43 | $3,480.00 | $3,725.00 | $3,603.00 | $3,168.00 |
| 0295 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 1,883 | $2.00 | $0.65 | $0.70 | $1.65 | $2.30 | $0.60 |
| 0300 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 270 | $3.00 | $1.09 | $1.15 | $2.55 | $3.50 | $1.00 |
| 0305 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 1,901 | $4.00 | $1.36 | $1.40 | $2.45 | $4.70 | $1.25 |
| 0310 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 1.22 | $1,000.00 | $386.98 | $403.40 | $935.40 | $1,163.00 | $355.00 |
| 0315 | Painted pavement marking, standard,white, 3'-9' skip drop line and approach to toll 12" wide, (0710-11133) | GM | 0.13 | $1,889.76 | $654.06 | $644.00 | $1,600.00 | $2,382.00 | $600.00 |
| 0320 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.30 | $979.73 | $545.05 | $557.00 | $862.50 | $1,179.00 | $500.00 |
| 0325 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 4 | $100.00 | $43.60 | $45.45 | $60.50 | $116.00 | $40.00 |
| 0330 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 61 | $50.00 | $43.60 | $45.45 | $46.20 | $58.00 | $40.00 |
| 0335 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 0.77 | $1,785.90 | $1,495.61 | $1,550.00 | $1,750.00 | $2,187.00 | $1,372.00 |
| 0340 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 359 | $3.00 | $1.09 | $1.15 | $2.55 | $3.50 | $1.00 |
| 0345 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.07 | $869.57 | $2,398.21 | $2,170.00 | $765.50 | $1,180.00 | $2,200.00 |
| 0350 | Partnering, DO not bid (0999-16) | LS | 1 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 |
| 0355 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0360 | Local agency initial amount (DO not bid) (0999-26) | LS | 1 | $612.00 | $612.00 | $612.00 | $612.00 | $612.00 | $612.00 |
| 0365 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 9 | $615.00 | $539.60 | $787.00 | $717.00 | $814.00 | $495.00 |
| 0370 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 3 | $1,850.00 | $1,962.18 | $1,890.00 | $2,560.00 | $2,909.00 | $1,800.00 |
| 0375 | Single column ground sign assembly, remove (0700-1600) | EACH | 7 | $50.00 | $27.25 | $98.85 | $35.75 | $40.75 | $25.00 |
| 0380 | Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114) | EACH | 3 | $7,500.00 | $8,611.77 | $3,100.00 | $7,685.00 | $8,726.00 | $7,900.00 |
| 0385 | Multi-column ground sign assembly, F&I ground mount, 100.0 SF (0700-2115) | EACH | 1 | $10,300 | $15,261 | $8,490.00 | $11,750 | $13,379 | $14,000 |
| 0390 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 1 | $1,200.00 | $2,289.20 | $1,860.00 | $2,560.00 | $2,909.00 | $2,100.00 |
| 0395 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 1 | $50.00 | $27.25 | $121.35 | $35.75 | $55.00 | $25.00 |
| 0400 | Retroreflective sign strip- furnish and install, 2' (0700-13-12) | EACH | 2 | $110.00 | $13.08 | $150.25 | $92.25 | $105.00 | $12.00 |
| 0405 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 4 | $140.00 | $16.35 | $129.85 | $123.00 | $140.00 | $15.00 |
| 0410 | Tubular marker, 36" yellow (0704-1-4) | EACH | 18 | $250.00 | $130.81 | $178.35 | $116.75 | $233.00 | $120.00 |
| 0415 | Object marker, type 2 (0705-10-2) | EACH | 16 | $375.00 | $272.52 | $197.90 | $128.00 | $145.00 | $250.00 |
| 0420 | Raised pavement marker, type B (0706-1-3) | EACH | 254 | $6.00 | $4.36 | $4.55 | $4.40 | $7.00 | $4.00 |
| 0425 | Painted pavement markings, surface (0710-90) | LS | 1 | $10,000 | $6,019.52 | $6,280.00 | $5,725.00 | $11,634 | $5,522.00 |
| 0430 | Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102) | GM | 0.03 | $7,258.06 | $8,066.72 | $8,140.00 | $8,525.00 | $1,351.00 | $7,400.00 |
| 0435 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 753 | $5.00 | $2.18 | $2.25 | $6.60 | $5.80 | $2.00 |
| 0440 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 177 | $7.00 | $4.36 | $4.55 | $9.90 | $8.10 | $4.00 |
| 0445 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 167 | $9.00 | $6.54 | $6.80 | $13.20 | $10.50 | $6.00 |
| 0450 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.13 | $4,320.00 | $2,507.22 | $2,510.00 | $3,170.00 | $5,445.00 | $2,300.00 |
| 0455 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 2 | $300.00 | $119.91 | $125.00 | $220.10 | $349.00 | $110.00 |
| 0460 | Thermoplastic, standard, arrow (0711-11170) | EACH | 24 | $90.00 | $92.66 | $96.60 | $143.00 | $105.00 | $85.00 |
| 0465 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 195 | $7.00 | $4.36 | $4.55 | $9.90 | $8.10 | $4.00 |
| 0470 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.07 | $3,970.59 | $2,616.23 | $2,410.00 | $2,915.00 | $5,389.00 | $2,400.00 |
| 0475 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 569 | $20.00 | $17.44 | $18.20 | $18.15 | $23.25 | $16.00 |
| 0480 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 0.90 | $5,973.45 | $7,412.66 | $7,690.00 | $6,750.00 | $7,027.00 | $6,800.00 |
| 0485 | Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102) | GM | 0.04 | $6,190.48 | $7,412.66 | $7,360.00 | $8,400.00 | $7,202.00 | $6,800.00 |
| 0490 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 0.46 | $4,421.40 | $2,616.23 | $2,680.00 | $4,325.00 | $5,258.00 | $2,400.00 |
| 0495 | Thermoplastic, standard-other surfaces white, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-16133) | GM | 0.06 | $7,619.05 | $4,360.39 | $4,330.00 | $7,350.00 | $10,341 | $4,000.00 |
| 0500 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.40 | $5,894.21 | $7,412.66 | $7,590.00 | $6,475.00 | $7,033.00 | $6,800.00 |
| 0505 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 1,625 | $22.64 | $24.13 | $25.00 | $24.90 | $27.00 | $21.90 |
| 0510 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 10 | $843.99 | $1,434.26 | $1,130.00 | $927.50 | $1,456.00 | $1,160.00 |
| 0515 | Electrical service disconnect, F&I, pole mount (0639-3-11) | EACH | 1 | $535.21 | $570.38 | $591.00 | $588.00 | $4,583.00 | $810.00 |
| 0520 | Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60) | EACH | 1 | $174.97 | $186.47 | $193.20 | $192.25 | $219.00 | $540.00 |
| 0525 | Electrical power service- transformer, F&I, 5-10 kva, phase, copper windings (0639-6121) | EACH | 1 | $3,803.08 | $4,052.97 | $4,200.00 | $4,180.00 | $3,400.00 | $3,335.00 |
| 0530 | Electrical power service- transformer, replace, <25 kva, copper windings (0639-6201) | EACH | 1 | $5,403.57 | $5,758.62 | $5,970.00 | $5,935.00 | $4,200.00 | $6,365.00 |
| 0535 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 5,658 | $2.73 | $2.91 | $3.00 | $3.00 | $2.70 | $3.60 |
| 0540 | Lighting conductors, remove & dispose, contractor owns (0715-1-60) | LF | 491 | $0.77 | $0.82 | $0.85 | $0.85 | $0.30 | $1.70 |
| 0545 | Luminaire & bracket arm, luminaire and arm; pole remains (0715-5-51) | EACH | 2 | $174.98 | $186.47 | $193.20 | $192.25 | $219.00 | $270.00 |
| 0550 | Light pole complete, F&I, standard pole standard foundation, 30' mounting height, 8' arm length (0715-61111) | EACH | 2 | $6,484.29 | $6,910.34 | $7,670.00 | $7,125.00 | $10,860 | $7,976.00 |
| 0555 | Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 8' arm length (0715-61311) | EACH | 2 | $6,767.33 | $7,211.99 | $7,980.00 | $7,435.00 | $11,711 | $8,506.00 |
| 0560 | Light pole complete, F&I, utility conflict pole standard foundation, 35' mounting height, 16' arm length (0715-65266) | EACH | 1 | $7,616.46 | $8,116.91 | $8,920.00 | $8,350.00 | $13,260 | $9,613.00 |
| 0565 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 5 | $885.16 | $943.32 | $977.00 | $972.00 | $1,289.00 | $617.00 |
| 0570 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 801 | $25.73 | $27.42 | $28.40 | $28.25 | $39.00 | $39.00 |
| 0575 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 1 | $15,670 | $16,700 | $17,300 | $17,220 | $21,053 | $15,006 |
| 0580 | Signal cable, remove- intersection (0632-7-6) | PI | 1 | $2,778.98 | $2,961.58 | $3,070.00 | $3,050.00 | $1,314.00 | $135.00 |
| 0585 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 25 | $843.99 | $1,434.26 | $932.00 | $927.00 | $1,778.00 | $1,450.00 |
| 0590 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 1 | $1,492.41 | $1,590.48 | $1,650.00 | $1,640.00 | $5,139.00 | $4,900.00 |
| 0595 | Electrical power service, remove underground (0639-1620) | AS | 1 | $524.92 | $559.41 | $580.00 | $576.75 | $548.00 | $270.00 |
| 0600 | Electrical service wire, & install (0639-2-1) | LF | 189 | $10.55 | $11.24 | $11.65 | $11.60 | $10.75 | $12.90 |
| 0605 | Electrical service wire, (0639-2-6) | LF | 192 | $2.16 | $2.30 | $2.40 | $2.40 | $1.80 | $1.40 |
| 0610 | Electrical service disconnect, F&I, pole mount (0639-3-11) | EACH | 1 | $566.09 | $603.28 | $625.00 | $622.00 | $1,333.00 | $2,142.00 |
| 0615 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 1 | $1,312.30 | $1,398.52 | $1,450.00 | $1,440.00 | $2,511.00 | $3,240.00 |
| 0620 | Strain pole, wood, remove (0643-600) | EACH | 1 | $823.40 | $877.50 | $909.00 | $900.00 | $437.00 | $405.00 |
| 0625 | Aluminum signals pole, (0646-1-11) | EACH | 7 | $2,197.45 | $2,341.84 | $2,430.00 | $2,400.00 | $4,253.00 | $1,580.00 |
| 0630 | Steel mast arm assembly, and install, single arm 50' (0649-21-6) | EACH | 1 | $67,576 | $72,016 | $74,600 | $74,250 | $96,386 | $71,353 |
| 0635 | Steel mast arm assembly, and install, single arm 78' (0649-21-21) | EACH | 1 | $99,770 | $106,326 | $110,200 | $109,500 | $146,900 | $108,218 |
| 0640 | Steel mast arm assembly, remove, shallow foundation- bolt on attachment (0649-26-3) | EACH | 2 | $14,487 | $15,439 | $16,000 | $16,000 | $4,789.00 | $3,240.00 |
| 0645 | Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14) | AS | 3 | $1,374.05 | $1,464.33 | $1,520.00 | $1,500.00 | $2,433.00 | $1,596.00 |
| 0650 | Vehicular traffic signal, furnish & install aluminum, 4 section, 1 way (0650-1-16) | AS | 1 | $1,734.29 | $1,848.24 | $1,910.00 | $1,900.00 | $2,913.00 | $1,919.00 |
| 0655 | Vehicular traffic signal, furnish & install aluminum, 5 section straight, 1 way (0650-1-18) | AS | 2 | $2,032.77 | $2,166.34 | $2,240.00 | $2,250.00 | $3,295.00 | $2,174.00 |
| 0660 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 6 | $972.64 | $1,036.55 | $1,070.00 | $1,100.00 | $1,231.00 | $885.00 |
| 0665 | Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12) | AS | 1 | $1,785.75 | $1,903.09 | $1,970.00 | $1,960.00 | $2,541.00 | $1,774.00 |
| 0670 | Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60) | AS | 4 | $200.71 | $213.89 | $221.60 | $220.55 | $55.00 | $135.00 |
| 0675 | Vehicle detection system- furnish & install cabinet equipment (0660-4-11) | EACH | 1 | $29,740 | $31,694 | $32,800 | $32,675 | $48,437 | $29,558 |
| 0680 | Vehicle detection system- furnish & install above ground equipment (0660-4-12) | EACH | 2 | $6,535.75 | $6,965.19 | $7,220.00 | $7,200.00 | $17,254 | $10,155 |
| 0685 | Vehicle detection system- remove above ground (0660-4-62) | EACH | 2 | $303.63 | $323.58 | $335.25 | $330.00 | $219.00 | $135.00 |
| 0690 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 8 | $313.92 | $334.55 | $346.60 | $345.00 | $393.00 | $312.00 |
| 0695 | Pedestrian detector, remove- pole/pedestal to remain (0665-1-60) | EACH | 4 | $82.34 | $87.75 | $90.90 | $90.50 | $27.50 | $68.00 |
| 0700 | Traffic controller assembly, F&I, NEMA W/standard lock (0670-5160) | AS | 1 | $48,370 | $51,548 | $53,400 | $53,150 | $77,897 | $74,810 |
| 0705 | Traffic controller assembly, remove controller with (0670-5600) | AS | 1 | $977.79 | $1,042.04 | $1,080.00 | $1,075.00 | $657.00 | $1,080.00 |
| 0710 | ITS CCTV camera, pressurized, high definition (0682-1163) | EACH | 1 | $6,916.57 | $7,371.03 | $7,640.00 | $7,600.00 | $6,428.00 | $6,600.00 |
| 0715 | Managed field ethernet switch, furnish & install (0684-1-1) | EACH | 1 | $6,252.70 | $6,663.55 | $6,900.00 | $6,875.00 | $5,811.00 | $5,988.00 |
| 0720 | Uninterruptible power supply, furnish and install, line interactive with cabinet (0685-1-13) | EACH | 1 | $33,060 | $35,232 | $36,500 | $36,300 | $15,712 | $10,973 |
| 0725 | Internally illuminated sign, furnish & install overhead mount, UP to 12 SF (0700-5-21) | EACH | 2 | $3,211.27 | $3,422.27 | $3,550.00 | $3,500.00 | $4,856.00 | $3,750.00 |
| 0730 | Itsfm subsurface documentation- project length (0611-1-1) | MI | 0.38 | $3,664.78 | $3,915.86 | $4,050.00 | $4,000.00 | $4,049.00 | $4,080.00 |
| 0735 | Itsfm location documentation- intersection (0611-2-1) | EACH | 1 | $2,429.03 | $2,588.64 | $2,680.00 | $2,650.00 | $2,618.00 | $3,360.00 |
| 0740 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 1,344 | $30.47 | $32.47 | $33.65 | $33.50 | $33.00 | $33.00 |
| 0745 | Fiber optic cable, F&I, underground,2-12 fibers (0633-1121) | LF | 62 | $4.07 | $4.33 | $4.50 | $4.45 | $4.40 | $4.10 |
| 0750 | Fiber optic cable, F&I, underground,49-96 fibers (0633-1123) | LF | 1,882 | $4.27 | $4.55 | $4.70 | $4.70 | $4.60 | $4.10 |
| 0755 | Fiber optic cable, remove, underground (0633-1620) | LF | 1,306 | $1.08 | $1.15 | $1.20 | $1.20 | $1.20 | $1.20 |
| 0760 | Fiber optic connection, install, splice (0633-2-31) | EACH | 204 | $48.37 | $51.55 | $53.40 | $53.15 | $52.00 | $93.00 |
| 0765 | Fiber optic connection, install, termination (0633-2-32) | EACH | 12 | $91.60 | $97.62 | $101.15 | $100.00 | $99.00 | $65.00 |
| 0770 | Fiber optic connection hardware, F&I, splice enclosure (0633-3-11) | EACH | 3 | $1,399.78 | $1,491.76 | $1,550.00 | $1,525.00 | $1,507.00 | $1,350.00 |
| 0775 | Fiber optic connection hardware, F&I, splice tray (0633-3-12) | EACH | 1 | $53.52 | $57.04 | $59.10 | $58.50 | $58.00 | $60.00 |
| 0780 | Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16) | EACH | 1 | $1,862.95 | $1,985.35 | $2,060.00 | $2,050.00 | $2,007.00 | $1,850.00 |
| 0785 | Fiber optic cable locator (0633-6) | DA | 296 | $0.01 | $142.59 | $147.75 | $150.00 | $125.00 | $150.00 |
| 0790 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 4 | $1,543.88 | $2,180.14 | $2,000.00 | $1,600.00 | $2,984.00 | $2,204.00 |
| 0795 | Pull & splice box, F&I, 30" X 60" rectangular or 36" round size (0635-2-13) | EACH | 2 | $4,276.54 | $5,092.35 | $5,120.00 | $4,600.00 | $5,217.00 | $3,686.00 |
| 0800 | Fiber optic splice vault, & install, 54"W X 54"L X 48"D (0635-4-11) | EACH | 1 | $6,237.26 | $7,181.91 | $7,280.00 | $6,850.00 | $14,699 | $5,071.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of August 26, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.