FDOT contract T6595 bid tabulation

SR 985 (SW 107 AVE) FROM SR 94 (SW 88 ST) TO N OF SW 56 ST. Let by Florida DOT on July 29, 2026, Miami-Dade, District 6. 12 bids received; low bid $4,378,413 by Bacallao Construction & Engineering Development, LLC D/B/A BC&E.

Owner
Florida DOT
Letting
29 JUL 2026
Pay items
152
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Bacallao Construction & Engineering Development, LLC D/B/A BC&E$4,378,413Low
2General Asphalt Company, LLC$4,413,442+1.0%
3Horizon Contractors, Inc.$4,503,471+3.0%
4Weekley Asphalt Paving, Inc.$4,512,561+3.0%
5H & R Paving, Inc.$4,577,100+5.0%
6Ohla USA Inc$4,640,446+6.0%
7The Stout Group LLC$4,678,875+7.0%
8Florida Engineering & Development Corp$4,844,048+11%
9Jva Engineering Contractor, Inc$4,946,946+13%
10Asphalt Group, Inc.$5,069,430+16%
11Aum Construction Inc.$5,159,159+18%
12Ranger Construction Industries, Inc.$5,479,889+25%
FDOT contract T6595: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Bacallao Construction & Engineering Development, LLC D/B/A BC&E2. General Asphalt Company, LLC3. Horizon Contractors, Inc.4. Weekley Asphalt Paving, Inc.5. H & R Paving, Inc.6. Ohla USA Inc
0005Removal of existing structures/bridges 870692 (0110-3)SF1$11,000$6,760.00$30,000$26,778$23,000$25,000
0010Concrete traffic railing- 36" single-slope (0521-5-13)LF45$480.00$253.76$500.00$458.00$795.00$300.00
0015Mobilization (0101-1)LS1$440,000$300,000$420,000$113,100$946,466$464,000
0020Maintenance of traffic (0102-1)DA1$73,061$480,000$150,000$281,481$138,498$218,754
0025Pedestrian or bicycle special detour (0102-4-1)SY1$2,500.00$1,040.00$1,000.00$29,000$5,000.00$1.00
0030Traffic control officer (0102-14)HR316$80.00$88.40$80.00$93.00$1.00$80.00
0035Work zone sign (0102-60)ED13,802$0.20$0.20$0.22$0.19$0.19$0.19
0040Temporary barrier, F&I, low profile, concrete (0102-71-13)LF276$0.01$39.52$50.00$47.00$38.00$0.15
0045Temporary barrier, relocate, low profile concrete (0102-71-23)LF455$0.01$16.64$0.01$39.00$16.00$0.02
0050Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED63,960$0.10$0.11$0.20$0.10$0.01$0.10
0055Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD4,800$0.07$0.11$0.12$0.10$0.10$0.10
0060Arrow board / advance warning arrow panel (0102-76)ED540$5.00$5.20$6.00$5.00$5.00$5.08
0065Portable changeable message sign, temporary (0102-99)ED1,456$10.00$9.52$10.00$9.15$0.01$9.29
0070Temporary signalization and maintenance, intersection (0102-104)ED2,040$8.00$8.58$22.00$7.16$8.50$8.38
0075Temporary traffic detection and maintenance, intersection (0102-107-1)ED2,040$8.00$8.58$22.00$7.16$8.50$8.38
0080Type III barricade (0102-115)ED1,496$0.25$0.42$0.50$0.40$0.40$0.41
0085Removable tape, black, solid 6" (0102-913-11)GM0.09$44,000$45,760$16,000$12,000$15,000$10,909
0090Removable tape, black, 10'-30', 6'-10', or 2'-4' skip (0102-913-12)GM0.03$68,000$70,720$17,000$3,000.00$15,000$2,068.97
0095Removable tape, white, solid 6" (0102-913-21)GM0.09$22,000$22,880$16,000$12,000$15,000$10,909
0100Removable tape, white, 10'-30', 6'-10', or 2'-4' skip, 6" wide (0102-913-22)GM0.03$68,000$70,720$20,000$3,000.00$15,000$2,068.97
0105Removable tape, white, 24" stop bar (0102-913-23)LF7$95.00$98.80$30.00$20.00$20.00$20.00
0110Removable tape, white, symbol or arrow (0102-913-29)EACH1$850.00$884.00$400.00$375.00$300.00$375.00
0115Removable tape, yellow, solid, (0102-913-31)GM0.05$40,000$41,600$20,000$12,000$15,000$10,000
0120Inlet protection system (0104-18)EACH110$50.00$156.00$80.00$140.00$110.00$216.09
0125Litter removal (0107-1)ACRE68.53$0.01$1.04$0.01$40.00$1.00$179.43
0130Mowing (0107-2)ACRE26.18$0.01$1.04$0.01$40.00$1.00$470.85
0135Monitor existing structures- inspection and settlement monitoring (0108-1)LS1$1.00$104.00$5,000.00$16,600$64,500$25,000
0140Clearing & grubbing (0110-1-1)ACRE1$45,000$37,440$30,000$103,259$19,880$110,000
0145Removal of existing concrete (0110-4-10)SY3,478$30.00$40.56$21.00$39.50$38.00$45.00
0150Tree protection barrier (0110-21)LF298$0.01$10.40$0.01$6.11$14.00$3.00
0155Tree root and branch pruning (0110-22)EACH7$500.00$5,200.00$0.01$1,667.00$600.00$5,000.00
0160Borrow excavation, truck measure (0120-2-2)CY571.50$0.01$41.60$30.00$58.78$30.00$23.00
0165Regular excavation (3-R projects only) (0120-71)LS1$5,000.00$15,600$4,000.00$33,562$4,721.20$6,000.00
0170Type B stabilization (0160-4)SY162$5.00$10.40$10.00$49.00$30.00$0.01
0175Reworking limerock base, 3" (0210-1-9)SY3,979$0.01$8.32$0.01$4.09$5.00$10.00
0180Optional base, base group 11 (0285-711)SY162$65.00$69.68$100.00$116.12$125.00$37.00
0185Milling existing asphalt pavement, 1 1/4" avg depth (0327-70-12)SY73,049$3.25$2.31$2.90$3.00$8.20$4.00
0190Superpave asphaltic conc, traffic C (0334-1-13)TN82.70$500.00$239.19$320.00$300.00$300.00$185.00
0195Asphalt concrete friction course,traffic C, FC-9.5, PG 76-22 (0337-7-82)TN5,029.40$190.00$177.32$215.00$195.00$80.00$158.00
0200Miscellaneous asphalt (0339-1)TN3.50$500.00$1,338.99$400.00$550.00$500.00$1,100.00
0205Inlets, curb, type 9, modify (0425-1209)EACH1$6,000.00$4,534.40$4,800.00$8,200.00$5,000.00$3,290.00
0210Inlets, curb, type P-3, <10' (0425-1331)EACH1$9,125.00$9,568.00$7,800.00$24,980$11,000$9,868.00
0215Inlets, curb. type P-3, >10' (0425-1332)EACH1$11,160$11,638$8,800.00$27,000$11,000$9,868.00
0220Inlets, curb, type P-5, <10' (0425-1351)EACH2$9,500.00$8,174.40$6,800.00$9,300.00$11,000$9,868.00
0225Inlets, curb, type P-5, >10' (0425-1352)EACH3$10,625$13,707$7,800.00$12,000$6,042.00$10,022
0230Manhole, adjust (0425-5)EACH18$550.00$1,040.00$900.00$900.00$750.00$1,600.00
0235Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF320$190.00$193.44$300.00$201.00$215.00$180.50
0240Pipe culvert,optional material,other-elip/arch, (0430-175215)LF54$190.00$193.44$300.00$230.00$280.00$181.00
0245Pipe filling and plugging- place out of service (0430-830)CY31.30$10.00$290.16$250.00$302.00$1.00$247.00
0250Concrete curb & gutter, type E (0520-1-7)LF70$50.00$28.18$40.00$65.00$26.80$45.69
0255Concrete curb & gutter, type F (0520-1-10)LF2,614$50.00$26.31$38.00$55.87$24.90$69.55
0260Concrete curb, type D (0520-2-4)LF39$50.00$20.59$40.00$69.00$19.50$83.42
0265Valley gutter- concrete (0520-3)LF52$50.00$23.09$40.00$83.00$22.00$75.26
0270Traffic separator concrete- type IV, 4' wide (0520-5-41)LF21$180.00$57.41$100.00$200.00$55.00$253.81
0275Shoulder concrete barrier, curb and gutter barrier (0521-72-43)LF38$420.00$385.84$600.00$737.13$635.00$287.33
0280Concrete sidewalk and driveways, 4" thick (0522-1)SY257$80.00$56.16$55.00$104.02$53.10$129.20
0285Concrete sidewalk and driveways, 6" thick (0522-2)SY2,277$100.00$65.52$75.00$102.10$62.10$118.45
0290Detectable warnings (0527-2)SF1,213$30.00$37.44$36.00$41.00$35.00$40.61
0295Guardrail -roadway, general/low speed TL-2 (0536-1-0)LF120$30.00$31.20$35.00$24.00$30.00$26.47
0300Guardrail transition to rigid barrier, F&I- index 536- 001, approach TL-2 (0536-8111)EACH2$3,000.00$2,392.00$3,000.00$2,990.00$2,300.00$2,535.62
0305Guardrail removal (0536-73)LF235$2.25$3.12$4.00$4.00$3.00$1.92
0310Guardrail end treatment- trailing anchorage (0536-85-20)EACH1$2,400.00$1,768.00$2,500.00$1,900.00$1,700.00$1,978.21
0315Guardrail end treatment- parallel approach terminal (0536-85-24)EACH1$4,225.00$3,432.00$4,000.00$3,700.00$3,300.00$3,541.19
0320Performance turf, sod (0570-1-2)SY339$4.00$10.40$10.00$8.50$10.00$11.50
0325Conduit, furnish & install, directional bore (0630-2-12)LF201$30.00$24.91$42.00$35.41$25.00$24.31
0330Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH8$1,100.00$807.07$1,100.00$1,327.62$1,087.00$787.85
0335Electrical power service- contribution in aid of construction (ciac), FPL (DO not bid) (0639-8130)LS1$8,000.00$8,000.00$8,000.00$8,000.00$8,000.00$8,000.00
0340Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1)EACH8$3,500.00$2,652.51$2,300.00$1,816.76$3,000.00$2,553.80
0345Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12)EACH8$3,000.00$2,071.87$2,300.00$1,814.61$2,800.00$2,022.52
0350Raised pavement marker, type B (0706-1-3)EACH614$5.50$5.20$5.00$4.00$4.50$4.00
0355Painted pavement markings, standard, white, solid, 6" (0710-11101)GM0.62$1,000.00$1,038.96$3,000.00$2,000.00$2,800.00$2,000.00
0360Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF195$1.00$1.04$2.00$1.70$1.00$1.70
0365Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF160$2.25$2.08$3.00$2.00$2.00$2.00
0370Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM0.07$900.00$780.00$1,700.00$575.00$1,500.00$500.00
0375Painted pavement markings, standard, white, arrows (0710-11170)EACH8$85.00$78.00$55.00$40.00$50.00$40.00
0380Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM0.43$1,100.00$1,038.96$3,000.00$2,000.00$2,800.00$1,971.83
0385Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224)LF104$1.50$1.56$2.00$1.95$1.00$1.85
0390Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241)GM0.02$950.00$780.00$1,700.00$700.00$1,500.00$388.89
0395Initial contingency amount, DO not bid (0999-25)LS1$51,850$51,850$51,850$51,850$51,850$51,850
0400Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH40$650.00$650.00$650.00$595.00$450.00$595.00
0405Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH1$1,600.00$1,794.00$1,850.00$1,890.00$1,500.00$1,890.00
0410Single column ground sign assembly, relocate (0700-1500)EACH7$450.00$213.20$220.00$380.00$300.00$380.00
0415Single column ground sign assembly, remove (0700-1600)EACH17$20.00$52.00$54.00$50.00$60.00$50.00
0420Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH1$125.00$119.60$120.00$120.00$200.00$120.00
0425Tubular marker, 36" yellow (0704-1-4)EACH6$275.00$135.20$170.00$200.00$180.00$200.00
0430Object marker, type 3 (0705-10-3)EACH1$500.00$343.20$350.00$350.00$300.00$350.00
0435Raised pavement marker, type B (0706-1-3)EACH2,168$5.50$5.20$4.90$4.00$4.50$4.00
0440Painted pavement markings, surface (0710-90)LS1$50,000$48,755$24,000$29,020$20,000$29,020
0445Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102)GM0.14$6,700.00$6,780.00$6,500.00$6,424.00$6,000.00$6,140.59
0450Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF6,768$2.25$2.08$2.20$3.29$2.00$3.29
0455Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF402$3.50$3.12$3.25$4.94$3.00$4.94
0460Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF1,138$4.50$4.16$4.30$6.58$4.00$6.58
0465Thermoplastic, standard, message or symbol (0711-11160)EACH9$225.00$208.00$220.00$89.00$200.00$89.00
0470Thermoplastic, standard, arrow (0711-11170)EACH83$115.00$104.00$86.00$56.00$80.00$56.00
0475Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF1,387$3.50$3.12$3.25$4.94$3.00$4.94
0480Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.21$1,500.00$1,284.40$2,200.00$2,275.00$2,000.00$2,232.48
0485Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF2,621$19.00$18.72$19.00$14.53$18.00$14.53
0490Thermoplastic, preformed, white with black contrast, arrow on concrete surface (0711-14570)EACH1$1,050.00$936.00$1,300.00$1,055.00$1,200.00$1,055.00
0495Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM4.47$5,250.00$5,214.56$5,700.00$4,819.00$5,280.00$4,816.84
0500Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM3.43$1,450.00$1,284.40$2,200.00$1,205.00$2,000.00$1,202.54
0505Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM4.37$5,500.00$5,214.56$5,700.00$4,275.00$5,280.00$4,267.17
0510Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231)GM0.38$1,450.00$1,284.40$2,200.00$1,069.00$2,000.00$1,054.75
0515Permanent tape, white, solid, 6" for concrete bridges (0713-103101)GM0.08$2,300.00$18,720$38,000$60,000$35,000$58,537
0520Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181)GM0.02$50,000$43,680$22,000$12,500$20,000$7,352.94
0525Permanent tape, yellow, solid, for concrete bridges (0713-103201)GM0.05$15,000$15,600$38,000$60,000$35,000$50,000
0530Permanent tape, black, 10-30 6" wide, for concrete surfaces (0713-103381)GM0.02$40,000$41,080$22,000$12,500$20,000$6,944.44
0535Preformed/permanent tape, remove (0713-107)SF234$4.50$3.95$5.00$3.00$4.00$3.00
0540Conduit, furnish & install, directional bore (0630-2-12)LF2,803$30.00$24.91$21.00$30.08$25.00$24.31
0545Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH31$1,200.00$807.07$1,050.00$1,327.62$1,086.50$787.85
0550Pull & splice box, install (0635-2-30)EACH2$725.00$893.69$1,100.00$987.94$600.00$872.41
0555Electrical power service, F&I, underground, meter by contractor (0639-1122)AS2$7,000.00$3,944.99$7,500.00$5,082.54$6,691.00$3,735.52
0560Electrical power service, remove underground (0639-1620)AS2$1,100.00$482.35$900.00$537.14$1,056.00$470.87
0565Electrical service wire, (0639-2-6)LF20$1.50$0.86$1.00$0.36$1.40$0.84
0570Prestressed concrete pole, type P-II service pole (0641-2-12)EACH2$3,000.00$2,231.49$3,200.00$2,457.78$2,800.00$2,178.34
0575Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF9,838$3.50$2.62$4.00$2.76$3.00$2.56
0580Lighting conductors, remove & dispose, contractor owns (0715-1-60)LF4,917$0.50$0.89$0.25$0.36$0.50$0.87
0585Load center, F&I, secondary voltage (0715-7-11)EACH2$16,000$23,963$23,000$13,938$16,695$23,392
0590Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211)EACH19$1,750.00$3,340.48$1,450.00$1,343.17$1,613.00$3,260.93
0595Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 8' arm length (0715-61311)EACH1$8,500.00$8,603.03$8,500.00$9,772.25$7,429.00$8,398.11
0600Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 10' arm length (0715-61321)EACH12$8,000.00$8,221.28$8,500.00$9,935.30$7,850.00$8,025.46
0605Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH37$2,700.00$919.81$900.00$2,081.27$2,520.00$897.90
0610Conduit, furnish & install, directional bore (0630-2-12)LF3,798$30.00$26.18$42.00$32.55$28.00$25.55
0615Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI6$10,500$10,973$12,500$8,336.51$10,010$10,712
0620Signal cable, remove- intersection (0632-7-6)PI6$1,750.00$1,337.79$900.00$1,074.29$1,728.00$1,305.93
0625Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH157$1,100.00$807.07$1,100.00$1,294.30$1,086.50$787.85
0630Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH1$2,700.00$2,205.51$2,600.00$2,315.11$2,410.00$2,152.97
0635Pull & splice box, install (0635-2-30)EACH6$725.00$893.69$1,000.00$987.94$600.00$837.51
0640Electrical power service, F&I, underground, meter by contractor (0639-1122)AS6$6,500.00$3,944.99$11,000$5,193.65$6,290.00$3,851.03
0645Electrical power service, F&I, underground, meter not required (0639-1123)AS1$4,000.00$4,536.66$11,000$4,378.41$3,645.00$4,428.60
0650Electrical service wire, & install (0639-2-1)LF786$11.00$13.97$11.00$8.29$10.00$13.63
0655Electrical service wire, (0639-2-6)LF786$1.00$0.89$0.25$0.36$1.00$0.87
0660Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60)EACH5$800.00$602.93$660.00$358.10$742.50$588.57
0665Prestressed concrete pole, type P-II service pole (0641-2-12)EACH6$3,250.00$2,232.52$3,100.00$2,389.84$2,878.50$2,178.33
0670Aluminum signals pole, (0646-1-11)EACH25$3,100.00$2,796.59$2,500.00$2,317.83$2,998.50$2,729.98
0675Aluminum signals pole, remove (0646-1-60)EACH4$300.00$482.60$660.00$358.10$267.00$471.11
0680Vehicular traffic signal, relocate- includes removal reinstallation (0650-1-70)AS2$750.00$361.76$900.00$1,021.90$660.00$353.15
0685Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS18$1,000.00$1,063.03$800.00$893.39$921.50$1,037.71
0690Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12)AS12$1,750.00$2,021.58$1,700.00$1,708.84$1,534.00$1,973.47
0695Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60)AS37$220.00$232.36$110.00$179.05$179.00$226.82
0700Loop detector inductive, F&I, type 1 (0660-1101)EACH12$650.00$2,196.13$520.00$565.08$541.00$2,143.82
0705Loop assembly, F&I, type F (0660-2106)AS54$1,900.00$1,816.17$2,000.00$1,379.97$1,800.00$1,772.91
0710Vehicle detection system- microwave, furnish & install cabinet equipment (0660-3-11)EACH4$5,300.00$18,390$14,500$13,762$4,434.50$17,952
0715Vehicle detection system- microwave, furnish & install, above ground equipment (0660-3-12)EACH4$13,250$12,525$10,000$11,337$10,835$12,227
0720Pedestrian detector, furnish & install, standard (0665-1-11)EACH44$650.00$699.90$360.00$382.86$556.00$683.23
0725Pedestrian detector, remove- pole/pedestal to remain (0665-1-60)EACH20$75.00$130.12$110.00$89.52$66.00$127.03
0730Traffic controller assembly, F&I, caltrans W/standard lock (0670-5180)AS1$55,000$55,207$50,000$42,055$47,286$53,892
0735Traffic controller assembly, remove controller with (0670-5600)AS1$1,600.00$1,828.90$1,000.00$1,253.33$1,518.00$1,785.34
0740Traffic controller assembly, modify only - no components added (0670-5710)AS5$5,000.00$2,424.61$4,000.00$1,234.92$5,735.80$2,366.86
0745Cellular modem, furnish and install (0684-8-1)EACH1$4,700.00$3,079.90$2,500.00$2,280.39$3,918.00$3,006.54
0750Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH2$1,000.00$1,114.93$1,000.00$1,059.05$902.50$1,088.38
0755Sign panel, remove, UP to 12 SF (0700-3601)EACH7$150.00$120.59$220.00$179.05$139.50$117.72
0760Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF219$3.50$2.62$5.00$2.76$3.00$2.56
FDOT contract T6595: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of July 29, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy