TDOT contract CNZ242 bid tabulation

The resurfacing on i-240 from i-40 (l.m. 0.00) to i-55 (l.m. 6.00), including repair work on bridge. Let by Tennessee DOT on July 25, 2025, Shelby County. 3 bids received; low bid $9,453,041 by Lehman-Roberts Company.

Owner
Tennessee DOT
Letting
25 JUL 2025
Pay items
60
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Lehman-Roberts Company$9,453,041Low
2APAC-Tennessee, Inc.$9,823,322+4.0%
3Standard Construction Company, Inc.$13,404,956+42%
TDOT contract CNZ242: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Lehman-Roberts Company2. APAC-Tennessee, Inc.3. Standard Construction Company, Inc.
1Removal of asphalt pavement (202-03.01)SY20,433$15.42$20.00$35.00
2Water (203-06)MG7$440.21$5.00$25.00
3Brooming & degrassing shoulders (208-01.05)LM3.90$9,748.90$600.00$3,500.00
4Mineral aggregate, type B base, grading (C or D) (303-02)TON929$88.83$59.00$95.00
5Asphalt concrete mix (PG76-22) (BPMB-HM) grading A (307-03.01)TON1,258$151.60$188.00$335.00
6Asphalt concrete mix (PG76-22) (BPMB-HM) grading B-M2 (307-03.08)TON2,000$158.83$210.00$355.00
7Trackless tack coat (403-02.01)TON216$1,288.22$1,000.00$1,250.00
8Acs mix (PG64-22) grading E shoulder (411-01.07)TON8,851$132.82$144.00$171.75
9Longitudinal joint sealant (411-01.21)LM44.90$3,320.88$1,100.00$3,250.00
10Acs mix(PG76-22) grading D (411-03.10)TON23,167$141.45$164.00$188.10
11Scoring shoulders (continuous) (16IN width) (411-12.01)LM23$1,442.51$1,390.00$726.00
12Cold planing bituminous pavement (415-01.01)TON30,967$47.67$23.00$73.25
13Gray iron castings (catchbasin) (611-03.04)LB3,500$10.38$9.13$7.95
14Guardrail transition 27IN to 31IN (705-02.10)EACH17$186.80$182.70$189.00
15Guardrail terminal (type 12) (705-04.02)EACH3$4,358.65$4,263.00$4,410.00
16Earth pad for type 38 GR end treatment (705-04.09)EACH1$1,452.88$1,421.00$1,470.00
17GR terminaltrailing end (type 13) MASH TL-3 (705-06.10)EACH12$1,141.55$1,116.50$1,155.00
18Tangent energy absorbing term MASH TL-3 (705-06.20)EACH1$4,151.09$4,060.00$4,200.00
19Guardrail removed (706-01)LF330$8.30$8.12$8.40
20Traffic control (712-01)LS1$235,000$700,000$657,500
21Flexible drums (channelizing) (712-04.01)EACH1,033$37.05$30.45$42.00
22Warning lights (type A) (712-05.01)EACH170$15.88$3.05$1.05
23Warning lights (type C) (712-05.03)EACH864$15.88$3.05$1.05
24Signs (construction) (712-06)SF5,810$6.35$5.08$6.45
25Signs (construction)(reduced speed warning) (712-06.16)EACH16$529.26$456.75$525.00
26Arrow board (type C) (712-08.03)EACH8$1,746.57$1,522.50$1,207.50
27Speed feedback sign assembly (712-08.08)EACH2$3,175.59$2,537.50$3,570.00
28Digital speed limit sign assembly (712-08.09)EACH16$5,821.91$5,176.50$3,806.25
29Queue protection truck (712-08.12)DAY105$132.32$938.90$1,102.50
30Changeable message sign unit (713-16.01)EACH2$5,287.35$3,552.50$4,620.00
31Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22)EACH1,176$52.93$50.50$52.50
32Snowplowable raised pavement markers (BI-dir)(2 color) (716-01.23)EACH2,386$52.93$50.50$52.50
33Removal of snowplowable reflective marker (716-01.30)EACH2,386$16.35$10.00$40.00
34Plastic pavement marking (stop line) (716-02.05)LF97$31.76$30.30$31.50
35Plastic pavement marking (turn lane arrow) (716-02.06)EACH8$317.56$303.00$315.00
36Plastic pavement marking (24" barrier line) (716-02.07)LF3,050$31.76$30.30$31.50
37Plastic pavement marking (longitudinal cross-walk) (716-02.09)LF430$53.98$51.51$53.55
38Plastic word pavement marking (only) (716-03.01)EACH2$317.56$303.00$315.00
39Plastic pavement marking (straight-turn arrow) (716-04.01)EACH1$317.56$303.00$315.00
40Plastic pavement marking (transverse shoulder) (716-04.04)LF1,606$17.99$17.17$17.85
41Plastic pavement marking (wrong way arrow) (716-04.06)EACH6$476.34$454.50$472.50
42Plastic pavement marking (exit only arrow) (716-04.07)EACH5$476.34$454.50$472.50
43Plastic pavement marking (yield line) (716-04.12)SF51$40.22$38.38$39.90
44Painted pavement marking (8" barrier line) (716-05.02)LF10,504$1.32$1.27$1.35
45Painted pavement marking (6" line) (716-05.20)LM40$3,281.44$3,131.00$3,255.00
46Removal of pavement marking (cross-walk) (716-08.03)LF152$19.05$18.18$18.90
47Removal of pavement marking (stop line) (716-08.05)LF48$23.29$22.22$23.10
48Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM40$9,420.91$8,989.00$9,345.00
49Enhanced flatline thermo PVMT MRKNG (8IN barrier line) (716-12.03)LF10,504$3.70$3.54$3.70
50Enhanced flatline thermo PVMT MRKNG (6IN dotted line) (716-12.05)LF1,722$3.70$3.54$3.70
51Enhanced flat line thermo (12IN line) (716-12.09)LF4,319$11.64$11.11$11.55
52Enhanced flat line thermo (12IN dotted) (716-12.10)LF909$11.64$11.11$11.55
53Mobilization (717-01)LS1$375,000$460,000$615,000
54Install pull box (type A) (730-03.20)EACH3$2,594.43$669.50$2,625.00
55Install pull box (type B) (730-03.21)EACH2$3,113.32$875.50$3,150.00
56Conduit 2" diameter (PVC schedule 40) (730-12.02)LF245$33.21$18.80$33.60
57Saw slot (730-14.02)LF1,925$9.34$6.18$9.45
58Loop wire (730-14.03)LF5,600$2.08$1.03$2.10
59Expansion joint repairs (604-10.44)LF233$446.24$355.25$451.50
60Concrete repairs (604-10.53)SY13$1,219.38$3,045.00$1,233.75
TDOT contract CNZ242: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of July 25, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy