TDOT contract CNZ252 bid tabulation

The construction of a concrete box bridge on u.s. 25 (s.r. 9) over branch (l.m. 21.43), including grading, drainage, and paving. Let by Tennessee DOT on October 3, 2025, Cocke County. 3 bids received; low bid $2,115,010 by Adams Contracting, LLC.

Owner
Tennessee DOT
Letting
03 OCT 2025
Pay items
101
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Adams Contracting, LLC$2,115,010Low
2Charles Blalock & Sons, Inc.$2,684,674+27%
3Southern Constructors, Inc.$3,479,237+65%
TDOT contract CNZ252: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Adams Contracting, LLC2. Charles Blalock & Sons, Inc.3. Southern Constructors, Inc.
1Construction stakes, lines and grades (105-01)LS1$20,000$21,000$50,000
2Trainee (109-10.01)HR520$0.80$0.80$0.80
3Clearing and grubbing (201-01)LS1$25,000$50,000$50,000
4Road & drainage excavation (unclassified) (203-01)CY4,502$35.00$52.99$75.00
5Water (203-06)MG4$100.00$100.00$150.00
6Furnishing & spreading topsoil (203-07)CY392$90.00$10.00$85.00
7Channel excavation (unclassified) (203-08)CY347$45.00$52.99$85.00
8Channel substrate (203-20.01)CY121$75.00$98.95$100.00
9Brooming & degrassing shoulders (208-01.05)LM0.40$2,800.00$2,700.08$3,000.00
10Sediment removal (209-05)CY60$10.00$37.05$105.00
1112" dia coir log (stream bank lining) (209-06.02)LF380$19.00$22.50$30.00
12Temporary silt fence (with backing) (209-08.02)LF1,910$5.20$5.63$10.00
13Rock check dam (209-08.07)EACH12$800.00$2,200.00$1,750.00
14Enhanced rock check dam (209-08.08)EACH4$800.00$2,500.00$2,500.00
15Sediment filter bag (15' X 15') (209-09.03)EACH2$1,500.00$1,000.00$2,000.00
16Temporary in stream diversion (209-65.04)LF190$65.00$100.73$400.00
17Mineral aggregate, type A base, grading D (303-01)TON1,801$60.00$69.00$85.00
18Mineral aggregate (size 57) (303-10.01)TON762$75.00$69.00$100.00
19Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01)TON394$200.00$245.00$225.00
20Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON258$245.00$255.00$270.00
21Bituminous material for prime coat (PC) (402-01)TON6$1,200.00$2,500.00$1,250.00
22Aggregate for cover material (PC) (402-02)TON6$150.00$75.00$160.00
23Bituminous material for tack coat (TC) (403-01)TON2$1,200.00$2,500.00$1,250.00
24Acs mix(PG64-22) grading D (411-01.10)TON192$300.00$295.00$335.00
25Scoring for rumble stripe (non-continuous) (4IN width) (411-12.04)LM0.40$22,500$1,350.00$2,000.00
26Cold planing bituminous pavement (415-01.01)TON41$350.00$150.00$450.00
2718" concrete pipe culvert (class III) (607-03.02)LF126$175.00$200.00$325.00
28Class A concrete (pipe endwalls) (611-07.01)CY4$2,900.00$2,830.54$2,500.00
29Steel bar reinforcement (pipe endwalls) (611-07.02)LB180$8.00$12.15$3.00
30Temporary shoring (621-05.02)LS1$30,000$225,000$55,000
31Metal beam guard fence (705-01.04)LF88$97.00$100.76$110.00
32W beam GR (type 2) MASH TL-3 (long post) (705-06.02)LF932$31.50$36.48$40.00
33GR terminal (in-inline) MASH TL-3 (705-06.11)EACH1$1,300.00$1,505.64$2,000.00
34Tangent energy absorbing term MASH TL-3 (705-06.20)EACH3$3,270.00$3,787.26$4,500.00
35Radius rail (706-06.03)LF26$42.00$48.64$50.00
36Rounded end element (706-10.26)EACH1$137.00$158.67$200.00
37Markers (concrete R.O.W. posts) (708-02.01)EACH9$550.00$510.40$500.00
38Machined rip-rap (class A-3) (709-05.05)TON50$85.00$92.61$90.00
39Machined rip-rap (class A-1) (709-05.06)TON46$90.00$92.61$90.00
40Machined rip-rap (class B) (709-05.08)TON2,469$80.00$82.95$90.00
41Machined rip-rap (class C) (709-05.09)TON229$90.00$82.95$90.00
42Traffic control (712-01)LS1$125,000$62,807$200,000
43Portable barrier rail (MASH TL-3) (712-02.10)LF1,560$30.00$55.00$100.00
44Temporary work zone crash cushion (MASH TL-3) (712-02.60)EACH4$6,750.00$10,000$3,500.00
45Flexible drums (channelizing) (712-04.01)EACH46$28.00$50.00$60.00
46Barrier rail delineator (712-04.50)EACH40$18.50$24.75$30.00
47Signs (construction) (712-06)SF944$7.55$10.00$15.00
48Removable pavement marking (stop line) (712-09.04)LF52$20.00$33.75$35.00
49Class A concrete (foundation for sign supports) (713-01.01)CY1$250.00$284.10$2,000.00
50Steel bar reinforcement(foundation for sign supports) (713-01.02)LB100$1.00$1.14$7.00
51Perforated/knockout square tube post (713-11.02)LB190$4.50$5.11$11.00
52P post slip base (713-11.21)EACH4$525.00$596.59$750.00
53Flat sheet aluminum signs (0.080" thick) (713-13.02)SF5$16.85$19.15$27.00
54Flat sheet aluminum signs (0.100" thick) (713-13.03)SF36$17.46$19.84$55.00
55Removal of signs, posts and footings (713-15)LS1$200.00$227.27$1,500.00
56Signs (R1-1, stop sign, 36" X 36") (713-16.20)EACH1$375.00$426.14$550.00
57Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21)EACH13$100.00$225.00$220.00
58Removal of snowplowable reflective marker (716-01.30)EACH10$25.00$56.25$55.00
59Plastic pavement marking(channelization striping) (716-02.04)SY4.30$30.00$56.25$110.00
60Plastic pavement marking (stop line) (716-02.05)LF12$12.00$33.75$55.00
61Painted pavement marking (6" line) (716-05.20)LM3.80$1,150.00$2,250.00$2,200.00
62Removal of pavement marking (line) (716-08.01)LF6,864$0.70$1.13$1.50
63Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM1.30$8,500.00$10,688$10,000
64Mobilization (717-01)LS1$210,000$200,000$350,000
65Temporary traffic signal system (730-40)EACH2$35,000$60,000$25,000
66Geotextile (type III)(erosion control) (740-10.03)SY759$3.00$7.82$10.00
67Geotextile (type IV)(stabilization) (740-10.04)SY617$3.00$10.11$10.00
68Temporary seeding (with mulch) (801-01.07)UNIT14$130.00$66.47$125.00
69Natve seed MX final stablizatn of slopes (801-01.38)UNIT9$245.00$120.85$160.00
70Seeding (without mulch) (801-02)UNIT28$70.00$96.68$110.00
71Water (seeding & sodding) (801-03)MG2$100.00$151.06$250.00
72Erosion control blanket (type II) (805-12.02)SY3,142$1.00$1.51$12.00
73Removal of structures (34' three span concrete, sta. 22+88.73, 20.85' LT.) (202-04.01)LS1$80,000$26,604$175,000
74Foundation fill material (204-08)CY197$125.00$135.00$250.00
75Granular backfill (roadway) (303-01.01)TON641$70.00$69.00$85.00
76Class A concrete (box bridges) (604-02.01)CY194$1,000.00$2,300.00$2,500.00
77Steel bar reinforcement (box bridges) (604-02.02)LB47,806$1.25$1.90$3.00
78Pole 45FT class 4 wood (790-04.04)EACH1$8,860.00$5,214.38$7,000.00
79Pole 45FT class 3 metal (790-04.21)EACH1$23,595$11,751$17,000
801PH DBL primary support 15KV (790-21.05)EACH2$1,915.00$663.75$1,500.00
811PH primary LG angle 15KV (790-21.07)EACH1$2,085.00$736.88$1,500.00
821PH vertical dde 15KV (790-21.10)EACH2$2,440.00$1,012.50$1,750.00
83Down guy - insulated (790-32.06)EACH1$1,900.00$658.13$1,500.00
84OH guy - through bolt type (790-32.07)EACH2$2,210.00$911.25$1,550.00
85Screw type anchor 15,000LB (790-33.25)EACH1$2,645.00$1,344.38$1,750.00
86Transfer conductor (790-36.14)EACH2$2,510.00$517.50$2,250.00
87OH cond 1/0 6/1 acsr raven (790-40.03)LF1,208$11.76$8.84$4.50
88Fiber tangent assembly (790-74.31)EACH2$1,060.00$376.88$800.00
89Remove wire (790-98.01)LF1,202$7.32$3.96$4.25
90Remove poles (790-98.02)EACH2$1,643.00$793.13$1,000.00
91Remove framing/associated apparatus (790-98.03)EACH11$1,288.00$393.75$1,000.00
92Anchor 1IN (793-01.41)EACH4$1,450.00$656.14$2,000.00
93Guy wire 10M or 3/8IN (793-02.08)EACH4$1,315.00$281.25$1,500.00
94Install guy guard (793-02.99)EACH4$479.00$84.38$750.00
9510M strand (793-03.03)LF597$6.00$1.58$8.00
96Dig splice pit (see plans) (793-12.21)EACH1$2,940.00$1,631.25$3,500.00
971 duct formation @ 36IN depth (793-13.12)LF20$137.00$73.61$200.00
981 1/4IN innerduct (793-14.12)LF20$19.50$2.28$25.00
99Underground to overhead riser (793-14.26)EACH1$546.00$253.13$1,000.00
100Retire buried facilities in place (793-98.05)LF623$2.50$1.13$3.00
101Transfer fiberoptic cable (798-08.06)EACH2$1,140.00$1,282.50$2,000.00
TDOT contract CNZ252: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of October 3, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy