TDOT contract CNZ252 bid tabulation
The construction of a concrete box bridge on u.s. 25 (s.r. 9) over branch (l.m. 21.43), including grading, drainage, and paving. Let by Tennessee DOT on October 3, 2025, Cocke County. 3 bids received; low bid $2,115,010 by Adams Contracting, LLC.
- Owner
- Tennessee DOT
- Letting
- 03 OCT 2025
- Pay items
- 101
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Adams Contracting, LLC | $2,115,010 | Low |
| 2 | Charles Blalock & Sons, Inc. | $2,684,674 | +27% |
| 3 | Southern Constructors, Inc. | $3,479,237 | +65% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Adams Contracting, LLC | 2. Charles Blalock & Sons, Inc. | 3. Southern Constructors, Inc. |
|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $20,000 | $21,000 | $50,000 |
| 2 | Trainee (109-10.01) | HR | 520 | $0.80 | $0.80 | $0.80 |
| 3 | Clearing and grubbing (201-01) | LS | 1 | $25,000 | $50,000 | $50,000 |
| 4 | Road & drainage excavation (unclassified) (203-01) | CY | 4,502 | $35.00 | $52.99 | $75.00 |
| 5 | Water (203-06) | MG | 4 | $100.00 | $100.00 | $150.00 |
| 6 | Furnishing & spreading topsoil (203-07) | CY | 392 | $90.00 | $10.00 | $85.00 |
| 7 | Channel excavation (unclassified) (203-08) | CY | 347 | $45.00 | $52.99 | $85.00 |
| 8 | Channel substrate (203-20.01) | CY | 121 | $75.00 | $98.95 | $100.00 |
| 9 | Brooming & degrassing shoulders (208-01.05) | LM | 0.40 | $2,800.00 | $2,700.08 | $3,000.00 |
| 10 | Sediment removal (209-05) | CY | 60 | $10.00 | $37.05 | $105.00 |
| 11 | 12" dia coir log (stream bank lining) (209-06.02) | LF | 380 | $19.00 | $22.50 | $30.00 |
| 12 | Temporary silt fence (with backing) (209-08.02) | LF | 1,910 | $5.20 | $5.63 | $10.00 |
| 13 | Rock check dam (209-08.07) | EACH | 12 | $800.00 | $2,200.00 | $1,750.00 |
| 14 | Enhanced rock check dam (209-08.08) | EACH | 4 | $800.00 | $2,500.00 | $2,500.00 |
| 15 | Sediment filter bag (15' X 15') (209-09.03) | EACH | 2 | $1,500.00 | $1,000.00 | $2,000.00 |
| 16 | Temporary in stream diversion (209-65.04) | LF | 190 | $65.00 | $100.73 | $400.00 |
| 17 | Mineral aggregate, type A base, grading D (303-01) | TON | 1,801 | $60.00 | $69.00 | $85.00 |
| 18 | Mineral aggregate (size 57) (303-10.01) | TON | 762 | $75.00 | $69.00 | $100.00 |
| 19 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01) | TON | 394 | $200.00 | $245.00 | $225.00 |
| 20 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 258 | $245.00 | $255.00 | $270.00 |
| 21 | Bituminous material for prime coat (PC) (402-01) | TON | 6 | $1,200.00 | $2,500.00 | $1,250.00 |
| 22 | Aggregate for cover material (PC) (402-02) | TON | 6 | $150.00 | $75.00 | $160.00 |
| 23 | Bituminous material for tack coat (TC) (403-01) | TON | 2 | $1,200.00 | $2,500.00 | $1,250.00 |
| 24 | Acs mix(PG64-22) grading D (411-01.10) | TON | 192 | $300.00 | $295.00 | $335.00 |
| 25 | Scoring for rumble stripe (non-continuous) (4IN width) (411-12.04) | LM | 0.40 | $22,500 | $1,350.00 | $2,000.00 |
| 26 | Cold planing bituminous pavement (415-01.01) | TON | 41 | $350.00 | $150.00 | $450.00 |
| 27 | 18" concrete pipe culvert (class III) (607-03.02) | LF | 126 | $175.00 | $200.00 | $325.00 |
| 28 | Class A concrete (pipe endwalls) (611-07.01) | CY | 4 | $2,900.00 | $2,830.54 | $2,500.00 |
| 29 | Steel bar reinforcement (pipe endwalls) (611-07.02) | LB | 180 | $8.00 | $12.15 | $3.00 |
| 30 | Temporary shoring (621-05.02) | LS | 1 | $30,000 | $225,000 | $55,000 |
| 31 | Metal beam guard fence (705-01.04) | LF | 88 | $97.00 | $100.76 | $110.00 |
| 32 | W beam GR (type 2) MASH TL-3 (long post) (705-06.02) | LF | 932 | $31.50 | $36.48 | $40.00 |
| 33 | GR terminal (in-inline) MASH TL-3 (705-06.11) | EACH | 1 | $1,300.00 | $1,505.64 | $2,000.00 |
| 34 | Tangent energy absorbing term MASH TL-3 (705-06.20) | EACH | 3 | $3,270.00 | $3,787.26 | $4,500.00 |
| 35 | Radius rail (706-06.03) | LF | 26 | $42.00 | $48.64 | $50.00 |
| 36 | Rounded end element (706-10.26) | EACH | 1 | $137.00 | $158.67 | $200.00 |
| 37 | Markers (concrete R.O.W. posts) (708-02.01) | EACH | 9 | $550.00 | $510.40 | $500.00 |
| 38 | Machined rip-rap (class A-3) (709-05.05) | TON | 50 | $85.00 | $92.61 | $90.00 |
| 39 | Machined rip-rap (class A-1) (709-05.06) | TON | 46 | $90.00 | $92.61 | $90.00 |
| 40 | Machined rip-rap (class B) (709-05.08) | TON | 2,469 | $80.00 | $82.95 | $90.00 |
| 41 | Machined rip-rap (class C) (709-05.09) | TON | 229 | $90.00 | $82.95 | $90.00 |
| 42 | Traffic control (712-01) | LS | 1 | $125,000 | $62,807 | $200,000 |
| 43 | Portable barrier rail (MASH TL-3) (712-02.10) | LF | 1,560 | $30.00 | $55.00 | $100.00 |
| 44 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 4 | $6,750.00 | $10,000 | $3,500.00 |
| 45 | Flexible drums (channelizing) (712-04.01) | EACH | 46 | $28.00 | $50.00 | $60.00 |
| 46 | Barrier rail delineator (712-04.50) | EACH | 40 | $18.50 | $24.75 | $30.00 |
| 47 | Signs (construction) (712-06) | SF | 944 | $7.55 | $10.00 | $15.00 |
| 48 | Removable pavement marking (stop line) (712-09.04) | LF | 52 | $20.00 | $33.75 | $35.00 |
| 49 | Class A concrete (foundation for sign supports) (713-01.01) | CY | 1 | $250.00 | $284.10 | $2,000.00 |
| 50 | Steel bar reinforcement(foundation for sign supports) (713-01.02) | LB | 100 | $1.00 | $1.14 | $7.00 |
| 51 | Perforated/knockout square tube post (713-11.02) | LB | 190 | $4.50 | $5.11 | $11.00 |
| 52 | P post slip base (713-11.21) | EACH | 4 | $525.00 | $596.59 | $750.00 |
| 53 | Flat sheet aluminum signs (0.080" thick) (713-13.02) | SF | 5 | $16.85 | $19.15 | $27.00 |
| 54 | Flat sheet aluminum signs (0.100" thick) (713-13.03) | SF | 36 | $17.46 | $19.84 | $55.00 |
| 55 | Removal of signs, posts and footings (713-15) | LS | 1 | $200.00 | $227.27 | $1,500.00 |
| 56 | Signs (R1-1, stop sign, 36" X 36") (713-16.20) | EACH | 1 | $375.00 | $426.14 | $550.00 |
| 57 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 13 | $100.00 | $225.00 | $220.00 |
| 58 | Removal of snowplowable reflective marker (716-01.30) | EACH | 10 | $25.00 | $56.25 | $55.00 |
| 59 | Plastic pavement marking(channelization striping) (716-02.04) | SY | 4.30 | $30.00 | $56.25 | $110.00 |
| 60 | Plastic pavement marking (stop line) (716-02.05) | LF | 12 | $12.00 | $33.75 | $55.00 |
| 61 | Painted pavement marking (6" line) (716-05.20) | LM | 3.80 | $1,150.00 | $2,250.00 | $2,200.00 |
| 62 | Removal of pavement marking (line) (716-08.01) | LF | 6,864 | $0.70 | $1.13 | $1.50 |
| 63 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 1.30 | $8,500.00 | $10,688 | $10,000 |
| 64 | Mobilization (717-01) | LS | 1 | $210,000 | $200,000 | $350,000 |
| 65 | Temporary traffic signal system (730-40) | EACH | 2 | $35,000 | $60,000 | $25,000 |
| 66 | Geotextile (type III)(erosion control) (740-10.03) | SY | 759 | $3.00 | $7.82 | $10.00 |
| 67 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 617 | $3.00 | $10.11 | $10.00 |
| 68 | Temporary seeding (with mulch) (801-01.07) | UNIT | 14 | $130.00 | $66.47 | $125.00 |
| 69 | Natve seed MX final stablizatn of slopes (801-01.38) | UNIT | 9 | $245.00 | $120.85 | $160.00 |
| 70 | Seeding (without mulch) (801-02) | UNIT | 28 | $70.00 | $96.68 | $110.00 |
| 71 | Water (seeding & sodding) (801-03) | MG | 2 | $100.00 | $151.06 | $250.00 |
| 72 | Erosion control blanket (type II) (805-12.02) | SY | 3,142 | $1.00 | $1.51 | $12.00 |
| 73 | Removal of structures (34' three span concrete, sta. 22+88.73, 20.85' LT.) (202-04.01) | LS | 1 | $80,000 | $26,604 | $175,000 |
| 74 | Foundation fill material (204-08) | CY | 197 | $125.00 | $135.00 | $250.00 |
| 75 | Granular backfill (roadway) (303-01.01) | TON | 641 | $70.00 | $69.00 | $85.00 |
| 76 | Class A concrete (box bridges) (604-02.01) | CY | 194 | $1,000.00 | $2,300.00 | $2,500.00 |
| 77 | Steel bar reinforcement (box bridges) (604-02.02) | LB | 47,806 | $1.25 | $1.90 | $3.00 |
| 78 | Pole 45FT class 4 wood (790-04.04) | EACH | 1 | $8,860.00 | $5,214.38 | $7,000.00 |
| 79 | Pole 45FT class 3 metal (790-04.21) | EACH | 1 | $23,595 | $11,751 | $17,000 |
| 80 | 1PH DBL primary support 15KV (790-21.05) | EACH | 2 | $1,915.00 | $663.75 | $1,500.00 |
| 81 | 1PH primary LG angle 15KV (790-21.07) | EACH | 1 | $2,085.00 | $736.88 | $1,500.00 |
| 82 | 1PH vertical dde 15KV (790-21.10) | EACH | 2 | $2,440.00 | $1,012.50 | $1,750.00 |
| 83 | Down guy - insulated (790-32.06) | EACH | 1 | $1,900.00 | $658.13 | $1,500.00 |
| 84 | OH guy - through bolt type (790-32.07) | EACH | 2 | $2,210.00 | $911.25 | $1,550.00 |
| 85 | Screw type anchor 15,000LB (790-33.25) | EACH | 1 | $2,645.00 | $1,344.38 | $1,750.00 |
| 86 | Transfer conductor (790-36.14) | EACH | 2 | $2,510.00 | $517.50 | $2,250.00 |
| 87 | OH cond 1/0 6/1 acsr raven (790-40.03) | LF | 1,208 | $11.76 | $8.84 | $4.50 |
| 88 | Fiber tangent assembly (790-74.31) | EACH | 2 | $1,060.00 | $376.88 | $800.00 |
| 89 | Remove wire (790-98.01) | LF | 1,202 | $7.32 | $3.96 | $4.25 |
| 90 | Remove poles (790-98.02) | EACH | 2 | $1,643.00 | $793.13 | $1,000.00 |
| 91 | Remove framing/associated apparatus (790-98.03) | EACH | 11 | $1,288.00 | $393.75 | $1,000.00 |
| 92 | Anchor 1IN (793-01.41) | EACH | 4 | $1,450.00 | $656.14 | $2,000.00 |
| 93 | Guy wire 10M or 3/8IN (793-02.08) | EACH | 4 | $1,315.00 | $281.25 | $1,500.00 |
| 94 | Install guy guard (793-02.99) | EACH | 4 | $479.00 | $84.38 | $750.00 |
| 95 | 10M strand (793-03.03) | LF | 597 | $6.00 | $1.58 | $8.00 |
| 96 | Dig splice pit (see plans) (793-12.21) | EACH | 1 | $2,940.00 | $1,631.25 | $3,500.00 |
| 97 | 1 duct formation @ 36IN depth (793-13.12) | LF | 20 | $137.00 | $73.61 | $200.00 |
| 98 | 1 1/4IN innerduct (793-14.12) | LF | 20 | $19.50 | $2.28 | $25.00 |
| 99 | Underground to overhead riser (793-14.26) | EACH | 1 | $546.00 | $253.13 | $1,000.00 |
| 100 | Retire buried facilities in place (793-98.05) | LF | 623 | $2.50 | $1.13 | $3.00 |
| 101 | Transfer fiberoptic cable (798-08.06) | EACH | 2 | $1,140.00 | $1,282.50 | $2,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of October 3, 2025. Compiled by Mirage Metrics.