TDOT contract CNZ278 bid tabulation
The construction of a concrete box bridge on gap creek road over gap creek (l.m. 2.73), including grading, drainage, and paving. Let by Tennessee DOT on October 3, 2025, Carter County. 2 bids received; low bid $1,780,046 by Southern Constructors, Inc..
- Owner
- Tennessee DOT
- Letting
- 03 OCT 2025
- Pay items
- 79
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Southern Constructors, Inc. | $1,780,046 | Low |
| 2 | Summers-Taylor, Inc. | $2,149,011 | +21% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Southern Constructors, Inc. | 2. Summers-Taylor, Inc. |
|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $40,000 | $16,600 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $30,000 | $35,000 |
| 3 | Removal of pipe (15" CMP, PVT. drive sta. 103+65.01 RT.) (202-02.01) | LF | 41 | $70.00 | $97.00 |
| 4 | Road & drainage excavation (unclassified) (203-01) | CY | 1,029 | $70.00 | $132.00 |
| 5 | Placing and spreading topsoil (203-04) | CY | 167 | $65.00 | $66.50 |
| 6 | Water (203-06) | MG | 10 | $300.00 | $128.00 |
| 7 | Sediment removal (209-05) | CY | 18 | $50.00 | $66.00 |
| 8 | 12" dia coir log (low flow channel) (209-06.02) | LF | 117 | $35.00 | $28.00 |
| 9 | Temporary silt fence (with backing) (209-08.02) | LF | 1,593 | $8.00 | $8.00 |
| 10 | Enhanced rock check dam (209-08.08) | EACH | 1 | $3,400.00 | $1,670.00 |
| 11 | Sediment filter bag (15' X 15') (209-09.03) | EACH | 4 | $1,100.00 | $1,310.00 |
| 12 | Curb inlet protection (type 4) (209-09.43) | EACH | 2 | $700.00 | $468.00 |
| 13 | Catch basin protection (type D) (209-40.33) | EACH | 5 | $500.00 | $360.00 |
| 14 | Temporary in stream diversion (209-65.04) | LF | 191 | $400.00 | $189.00 |
| 15 | Mineral aggregate, type A base, grading D (303-01) | TON | 1,301 | $90.00 | $85.00 |
| 16 | Granular backfill (roadway) (303-01.01) | TON | 227 | $85.00 | $123.00 |
| 17 | Mineral aggregate (size 57) (303-10.01) | TON | 30 | $70.00 | $107.00 |
| 18 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 118 | $470.00 | $380.00 |
| 19 | Bituminous material for prime coat (PC) (402-01) | TON | 4 | $2,600.00 | $2,300.00 |
| 20 | Aggregate for cover material (PC) (402-02) | TON | 8 | $250.00 | $225.00 |
| 21 | Bituminous material for tack coat (TC) (403-01) | TON | 3 | $1,600.00 | $1,450.00 |
| 22 | Saw cutting asphalt pavement (407-20.05) | LF | 41 | $13.00 | $35.00 |
| 23 | Acs mix(PG64-22) grading D (411-01.10) | TON | 198 | $450.00 | $385.00 |
| 24 | Cold planing bituminous pavement (415-01.01) | TON | 98 | $180.00 | $140.00 |
| 25 | 18" concrete pipe culvert (class III) (607-03.02) | LF | 96 | $220.00 | $266.00 |
| 26 | Class A concrete (pipe endwalls) (611-07.01) | CY | 1 | $5,000.00 | $5,510.00 |
| 27 | Steel bar reinforcement (pipe endwalls) (611-07.02) | LB | 45 | $7.00 | $2.65 |
| 28 | Catch basins, type 12, 0' - 4' depth (611-12.01) | EACH | 1 | $13,000 | $6,900.00 |
| 29 | Catch basins, type 12, > 4' - 8' depth (611-12.02) | EACH | 1 | $14,000 | $7,230.00 |
| 30 | Catch basins, type 38, > 4' - 8' depth (611-38.02) | EACH | 2 | $8,000.00 | $8,520.00 |
| 31 | Temporary shoring (621-05.01) | SF | 660 | $60.00 | $91.50 |
| 32 | Concrete driveway (701-02) | SF | 842 | $18.00 | $18.50 |
| 33 | Concrete combined curb & gutter (702-03) | CY | 22 | $1,300.00 | $913.00 |
| 34 | Metal beam guard fence (705-01.04) | LF | 125 | $110.00 | $87.00 |
| 35 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 300 | $35.00 | $28.00 |
| 36 | GR terminal (in-inline) MASH TL-3 (705-06.11) | EACH | 2 | $1,400.00 | $1,250.00 |
| 37 | GR terminal (energy absorbing) MASH TL-2 (705-06.30) | EACH | 2 | $3,200.00 | $2,950.00 |
| 38 | Radius rail (706-06.03) | LF | 75 | $40.00 | $34.50 |
| 39 | Rounded end element (706-10.26) | EACH | 2 | $120.00 | $120.00 |
| 40 | High-visibility construction fence (707-08.11) | LF | 1,347 | $3.50 | $7.20 |
| 41 | Machined rip-rap (class A-3) (709-05.05) | TON | 100 | $80.00 | $124.00 |
| 42 | Machined rip-rap (class A-1) (709-05.06) | TON | 73 | $82.00 | $122.00 |
| 43 | Machined rip-rap (class B) (709-05.08) | TON | 146 | $95.00 | $144.00 |
| 44 | Traffic control (712-01) | LS | 1 | $45,000 | $44,500 |
| 45 | Interconnected portable barrier rail (712-02.02) | LF | 50 | $150.00 | $165.00 |
| 46 | Flexible drums (channelizing) (712-04.01) | EACH | 42 | $50.00 | $46.50 |
| 47 | Warning lights (type A) (712-05.01) | EACH | 14 | $45.00 | $38.50 |
| 48 | Signs (construction) (712-06) | SF | 507 | $15.00 | $12.50 |
| 49 | Temporary barricades (type III) (712-07.03) | LF | 144 | $20.00 | $15.50 |
| 50 | Sign post delineation enhancement (713-02.21) | LF | 12 | $8.00 | $17.00 |
| 51 | "U" section steel posts (713-11.01) | LB | 87 | $7.00 | $15.50 |
| 52 | Flat sheet aluminum signs (0.080" thick) (713-13.02) | SF | 9 | $22.00 | $47.33 |
| 53 | Removal of signs, posts and footings (713-15) | LS | 1 | $1,000.00 | $559.00 |
| 54 | Changeable message sign unit (713-16.01) | EACH | 2 | $10,000 | $7,500.00 |
| 55 | Spray thermo PVMT MRKNG (60 mil) (6IN line) (716-13.02) | LM | 1 | $5,500.00 | $5,400.00 |
| 56 | Mobilization (717-01) | LS | 1 | $150,000 | $201,500 |
| 57 | Geotextile (type III)(erosion control) (740-10.03) | SY | 438 | $12.00 | $8.80 |
| 58 | Temporary sediment tube 20IN (740-11.04) | LF | 1,277 | $8.00 | $5.38 |
| 59 | Seeding (with mulch) (801-01) | UNIT | 27 | $65.00 | $54.00 |
| 60 | Temporary seeding (with mulch) (801-01.07) | UNIT | 27 | $55.00 | $42.00 |
| 61 | Cover crop seed mix (ripzn/FLPL) W/mulch (801-01.30) | UNIT | 1 | $1,500.00 | $120.00 |
| 62 | Grass seed mix (ripzn/FLPL) W/mulch (801-01.35) | UNIT | 1 | $1,500.00 | $120.00 |
| 63 | Natve seed MX final stablizatn of slopes (801-01.38) | UNIT | 4 | $1,100.00 | $120.00 |
| 64 | Seeding (without mulch) (801-02) | UNIT | 10 | $50.00 | $29.90 |
| 65 | Water (seeding & sodding) (801-03) | MG | 18 | $250.00 | $90.00 |
| 66 | Seed (supplemental application) (801-07) | LB | 47 | $16.00 | $11.96 |
| 67 | Fertilizer (supplemental application) (801-08) | TON | 1 | $2,500.00 | $1,020.00 |
| 68 | Sodding (new sod) (803-01) | SY | 815 | $11.00 | $11.00 |
| 69 | Erosion control blanket (type II) (805-12.02) | SY | 615 | $2.00 | $2.09 |
| 70 | Erosion control blanket (type III) (805-12.03) | SY | 437 | $2.50 | $2.39 |
| 71 | Project mowing (806-02.03) | CYCL | 1 | $8,000.00 | $2,160.00 |
| 72 | Removal of structures (2@12'X6' RCBB, sta. 104+30.46) (202-04.50) | LS | 1 | $70,000 | $98,500 |
| 73 | Foundation fill material (204-08) | CY | 49 | $200.00 | $207.00 |
| 74 | Polyethylene sheeting (10 mil.) (209-20.04) | SY | 74 | $15.00 | $20.50 |
| 75 | Mineral aggregate (size 68) (303-10.03) | TON | 57 | $75.00 | $205.00 |
| 76 | Class A concrete (box bridges) (604-02.01) | CY | 269 | $1,650.00 | $3,100.00 |
| 77 | Steel bar reinforcement (box bridges) (604-02.02) | LB | 53,471 | $2.50 | $1.00 |
| 78 | 6" perforated plastic pipe (710-10.02) | LF | 75 | $20.00 | $48.00 |
| 79 | Asbestos removal (795-12.11) | LF | 40 | $350.00 | $400.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of October 3, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.