FDOT contract T4765 bid tabulation

SR 816 (OAKLAND PARK BLVD) FROM ROCK ISLAND RD TO E OF NW 31 AVE. Let by Florida DOT on October 28, 2026, Broward, District 4. 6 bids received; low bid $7,579,227 by General Asphalt Company, LLC.

Owner
Florida DOT
Letting
28 OCT 2026
Pay items
193
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1General Asphalt Company, LLC$7,579,227Low
2Ohla USA Inc$7,801,449+3.0%
3Weekley Asphalt Paving, Inc.$8,158,412+8.0%
4The Stout Group LLC$8,432,226+11%
5Asphalt Group, Inc.$8,567,164+13%
6Ranger Construction Industries, Inc.$9,546,901+26%
FDOT contract T4765: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. General Asphalt Company, LLC2. Ohla USA Inc3. Weekley Asphalt Paving, Inc.4. The Stout Group LLC5. Asphalt Group, Inc.6. Ranger Construction Industries, Inc.
0005Removal of existing structures/bridges 860245 (0110-3)SF1$26,400$50,000$52,225$26,400$2,333.13$159,091
0010Removal of existing structures/bridges 860246 (0110-3)SF1$26,400$51,000$52,225$26,400$2,333.13$142,045
0015Bridge deck expansion joint, rehabilitation, poured joint backer rod (0458-1-21)LF480$77.00$83.74$89.00$200.00$58.33$73.85
0020Polymer nosing for bridge expansion joint (0458-2)CF132$869.00$1,046.78$1,112.00$800.00$1,049.91$1,080.00
0025Galvanized steel sidewalk plate (0458-3-1)LF60$352.00$450.12$478.00$150.00$373.30$454.55
0030Mobilization (0101-1)LS1$5,000.00$153,000$21,450$420,000$75,000$825,709
0035Mobilization (0101-1)LS1$369,000$627,000$192,900$420,000$680,000$118,656
0040Maintenance of traffic (0102-1)DA1$5,000.00$5,000.00$68,663$115,000$58,328$350,000
0045Maintenance of traffic (0102-1)DA1$382,000$173,500$389,085$115,000$349,970$121,894
0050Pedestrian or bicycle special detour (0102-4-1)SY1$6,050.00$4,250.29$88,362$15,000$13,999$12,800
0055Traffic control officer (0102-14)HR752$85.60$70.00$91.00$80.00$83.99$85.25
0060Work zone sign (0102-60)ED36,662$0.20$0.22$0.19$0.19$0.22$0.20
0065Business sign (0102-61)EACH4$48.15$51.16$37.00$45.00$43.16$51.15
0070Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED73,600$0.10$0.10$0.09$0.09$0.10$0.10
0075Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD12,075$0.05$0.06$0.05$0.05$0.06$0.05
0080Arrow board / advance warning arrow panel (0102-76)ED886$5.35$5.68$5.00$5.00$5.83$5.70
0085Temporary raised/retroreflective pavement marker, type B (0102-78-2)EACH2,278$4.28$4.08$4.00$4.00$4.67$4.55
0090Portable changeable message sign, temporary (0102-99)ED1,136$9.95$10.57$10.00$9.30$11.67$10.55
0095Temporary signalization and maintenance, intersection (0102-104)ED3,960$2.14$2.04$2.00$5.00$17.50$5.35
0100Temporary traffic detection and maintenance, intersection (0102-107-1)ED3,960$2.14$2.04$2.00$5.00$17.50$5.35
0105Existing ITS maintenance (0102-112)DA360$160.50$0.01$100.00$90.00$174.98$225.00
0110Type III barricade (0102-115)ED106$0.80$0.85$0.25$0.75$0.29$0.85
0115Inlet protection system (0104-18)EACH79$155.15$170.00$22.50$100.00$128.32$187.50
0120Litter removal (0107-1)ACRE244.27$11.00$80.00$25.00$0.01$0.01$46.25
0125Mowing (0107-2)ACRE251.02$1.10$80.00$25.00$0.01$0.01$48.55
0130Clearing & grubbing (0110-1-1)ACRE1$8,800.00$14,580$35,000$13,500$11,082$54,231
0135Clearing & grubbing (0110-1-1)ACRE1$17,325$140,000$87,000$42,000$11,082$60,000
0140Clearing & grubbing (0110-1-1)ACRE1$8,800.00$14,250$8,143.00$1,000.00$11,082$55,000
0145Removal of existing concrete (0110-4-10)SY3,034$31.46$22.20$39.00$25.00$28.58$23.85
0150Tree protection barrier (0110-21)LF1,181$3.21$10.00$16.70$8.00$6.66$0.45
0155Tree root and branch pruning (0110-22)EACH10$1,650.00$1,530.61$1,667.00$550.00$1,294.89$1,700.00
0160Tree removal (0110-23)EACH4$3,300.00$3,061.23$1,900.00$650.00$1,405.71$1,700.00
0165Regular excavation (3-R projects only) (0120-71)LS1$14,740$1.00$6,000.00$21,000$5,832.83$11,400
0170Regular excavation (3-R projects only) (0120-71)LS1$26,158$1.00$14,000$80,000$3,383.04$11,400
0175Regular excavation (3-R projects only) (0120-71)LS1$29,854$1.00$8,706.00$14,000$3,383.04$11,400
0180Type B stabilization (0160-4)SY1,149$10.78$7.00$28.00$22.00$10.50$15.05
0185Optional base, base group 09 (0285-709)SY773$54.70$140.00$57.61$28.00$67.72$81.80
0190Optional base, base group 11 (0285-711)SY284$72.38$55.00$69.26$24.00$70.51$88.00
0195Milling existing asphalt pavement, 2 1/2" avg depth (0327-70-8)SY118,889$4.07$3.80$4.00$3.75$4.74$4.35
0200Milling existing asphalt pavement, 1 1/4" avg depth (0327-70-12)SY2,480$4.26$4.00$3.00$2.65$6.08$2.55
0205Milling existing asphalt pavement, 2 3/4" avg depth (0327-70-15)SY770$11.66$9.00$5.00$4.15$5.25$7.50
0210Superpave asphaltic conc, traffic C (0334-1-13)TN8,372.70$154.08$155.00$190.00$172.00$149.66$154.50
0215Asphalt concrete friction course,traffic C, FC-9.5, PG 76-22 (0337-7-82)TN8,457.70$169.57$160.00$210.00$209.00$156.31$190.35
0220Miscellaneous asphalt (0339-1)TN6.40$1,877.59$548.20$300.00$300.00$291.64$586.05
0225Inlets, curb, type 9, <10' (0425-1201)EACH1$14,190$11,224$15,000$10,375$9,157.54$12,500
0230Inlets, curb, type P-4, partial (0425-1345)EACH2$5,500.00$10,816$9,500.00$6,620.97$8,165.96$6,020.00
0235Inlets, curb, type P-5, partial (0425-1355)EACH2$6,050.00$9,438.78$9,500.00$6,067.24$9,682.50$5,260.00
0240Inlets, curb, type P-6, <10' (0425-1361)EACH1$15,510$10,673$14,500$11,068$10,732$11,900
0245Manholes, P-7, <10' (0425-2-41)EACH2$13,035$10,306$14,000$10,431$10,149$11,500
0250Manhole, adjust (0425-5)EACH50$909.50$994.90$500.00$750.00$863.26$1,110.00
0255Valve boxes, adjust (0425-6)EACH1$909.50$918.37$300.00$650.00$874.92$1,020.00
0260Pipe culvert, optional material, round, 15"SD (0430-174115)LF8$398.75$128.57$470.00$1,000.00$163.32$143.20
0265Pipe culvert, optional material, round, 18"SD (0430-174118)LF92$452.98$140.82$450.00$215.96$128.32$156.80
0270Concrete curb & gutter, type F (0520-1-10)LF3,674$23.32$45.45$37.07$30.00$38.50$48.85
0275Concrete curb, type D (0520-2-4)LF360$20.57$33.82$35.00$25.00$46.51$36.35
0280Traffic separator concrete- type IV, 4' wide (0520-5-41)LF190$31.90$78.22$84.65$75.00$80.46$84.10
0285Concrete traffic separator, special- variable width (0520-70)SY25$66.55$141.64$96.80$85.00$192.48$152.25
0290Concrete sidewalk and driveways, 4" thick (0522-1)SY734$49.01$63.42$62.10$65.00$72.33$68.20
0295Concrete sidewalk and driveways, 6" thick (0522-2)SY1,614$59.20$97.25$74.98$75.00$90.99$104.55
0300Bus shelter pad- concrete (0522-4)SY17$129.80$211.40$499.35$300.00$279.98$227.25
0305Detectable warnings (0527-2)SF1,059$33.00$41.22$40.00$35.00$39.77$44.30
0310Guardrail -roadway, general (0536-1-1)LF78$36.02$31.87$38.00$48.00$35.00$38.25
0315Guardrail removal (0536-73)LF72$5.84$2.43$7.00$1.72$4.67$6.20
0320Guardrail end treatment- parallel approach terminal (0536-85-24)EACH1$3,819.29$4,457.76$4,000.00$3,160.75$3,149.73$4,060.00
0325Performance turf, sod (0570-1-2)SY952$6.42$6.12$8.00$10.00$4.67$14.30
0330Irrigation system- modify existing system (0590-70-5)LS1$23,968$3,061.22$28,300$34,920$29,164$40,800
0335Irrigation system- modify existing system (0590-70-5)LS1$3,210.00$22,857$4,000.00$3,500.00$2,916.42$4,690.00
0340Conduit, furnish & install, directional bore (0630-2-12)LF50$53.50$51.02$50.00$35.00$46.66$40.25
0345Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH6$1,070.00$1,020.41$1,000.00$1,350.00$1,749.85$1,560.00
0350Electrical power service- contribution in aid of construction (ciac), FPL (DO not bid) (0639-8130)LS1$6,000.00$6,000.00$6,000.00$6,000.00$6,000.00$6,000.00
0355Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1)EACH18$2,996.00$2,857.14$2,600.00$1,800.00$3,266.39$2,100.00
0360Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12)EACH18$3,210.00$3,061.22$2,800.00$1,800.00$2,099.82$2,090.00
0365Traffic monitoring site cabinet, F&I, type 3, 2 pane back, pedestal mount (0695-7162)EACH1$4,494.00$4,285.71$4,000.00$7,600.00$9,332.53$8,800.00
0370Raised pavement marker, type B (0706-1-3)EACH100$4.28$4.08$4.00$5.00$4.67$4.55
0375Painted pavement markings, standard, white, solid, 6" (0710-11101)GM7.28$1,498.00$1,427.79$1,400.00$1,690.00$1,983.16$1,930.00
0380Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102)GM0.40$1,605.00$1,522.99$1,500.00$2,100.00$2,644.61$2,560.00
0385Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF6,345$1.07$1.02$1.00$0.80$1.17$1.15
0390Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF1,489$1.61$1.53$1.50$1.50$1.52$1.50
0395Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM7.04$749.00$714.08$700.00$650.00$524.95$511.20
0400Painted pavement marking, standard,white, 3'-9' skip drop line and approach to toll 12" wide, (0710-11133)GM0.02$1,391.00$1,263.33$1,300.00$1,000.00$1,049.91$974.30
0405Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM0.69$7,749.00$707.00$700.00$650.00$758.27$731.10
0410Painted pavement markings, standard, white, message or symbol (0710-11160)EACH12$74.90$71.43$70.00$50.00$40.83$39.75
0415Painted pavement markings, standard, white, arrows (0710-11170)EACH163$37.45$35.71$35.00$35.00$40.83$39.75
0420Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM4.55$1,498.00$1,426.06$1,400.00$1,690.00$1,983.16$1,930.00
0425Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224)LF425$1.34$1.28$1.25$1.50$1.40$1.35
0430Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241)GM0.11$749.00$673.87$700.00$650.00$758.27$696.90
0435Partnering, DO not bid (0999-16)LS1$6,000.00$6,000.00$6,000.00$6,000.00$6,000.00$6,000.00
0440Initial contingency amount, DO not bid (0999-25)LS1$3,671.58$3,671.58$3,671.58$3,671.58$3,671.58$3,671.58
0445Initial contingency amount, DO not bid (0999-25)LS1$76,496$76,496$76,496$76,496$76,496$76,496
0450Initial contingency amount, DO not bid (0999-25)LS1$6,647.67$6,647.67$6,647.67$6,647.67$6,647.67$6,647.67
0455Prestressed concrete pole, complete pole removal- pole 30' and greater (0641-2-80)EACH2$10,165$7,653.06$1,400.00$9,400.00$3,966.32$10,900
0460Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH59$492.20$469.39$460.00$460.00$670.78$522.75
0465Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH20$2,140.00$2,040.82$2,000.00$2,000.00$2,041.49$2,270.00
0470Single column ground sign assembly, install (0700-1400)EACH2$454.75$433.68$425.00$425.00$524.95$482.95
0475Single column ground sign assembly, remove (0700-1600)EACH66$10.70$10.20$10.00$10.00$58.33$11.35
0480Multi-column ground sign assembly, F&I ground mount, 30.0 SF (0700-2113)EACH2$7,490.00$7,142.86$7,000.00$7,000.00$7,932.65$7,950.00
0485Multi-column ground sign assembly, relocate (0700-2500)EACH1$2,889.00$2,755.10$2,700.00$2,700.00$4,316.29$3,070.00
0490Multi-column ground sign assembly, remove (0700-2600)EACH1$2,140.00$2,040.82$2,000.00$2,000.00$1,364.88$2,270.00
0495Sign panel, relocate, UP to 12 SF (0700-3501)EACH1$107.00$102.04$100.00$100.00$81.66$113.65
0500Sign panel, relocate, 31-50 SF (0700-3504)EACH1$428.00$408.16$400.00$400.00$291.64$454.55
0505Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH38$107.00$102.04$100.00$100.00$130.66$113.65
0510Tubular marker, 36" yellow (0704-1-4)EACH32$187.25$178.57$175.00$175.00$139.99$136.35
0515Object marker, type 1 (0705-10-1)EACH3$321.00$306.12$300.00$300.00$355.80$340.90
0520Raised pavement marker, type B (0706-1-3)EACH2,356$4.28$4.08$4.00$4.00$4.67$4.55
0525Painted pavement markings, surface (0710-90)LS1$2,675.00$2,551.02$2,500.00$20,000$5,832.83$5,680.00
0530Painted pavement markings, surface (0710-90)LS1$51,895$49,490$48,500$20,250$50,502$49,200
0535Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF6,345$4.28$4.08$4.00$3.00$3.50$3.40
0540Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF1,489$6.42$6.12$6.00$5.00$7.00$6.80
0545Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.65$3,210.00$3,065.95$3,000.00$1,350.00$2,449.79$2,350.00
0550Thermoplastic, standard, message or symbol (0711-11160)EACH12$214.00$204.08$200.00$120.00$82.83$80.70
0555Thermoplastic, standard, arrow (0711-11170)EACH155$90.95$86.73$85.00$85.00$60.66$59.10
0560Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF399$5.35$5.10$5.00$3.00$5.25$5.10
0565Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.11$3,210.00$2,887.92$3,000.00$1,350.00$2,449.79$2,250.00
0570Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF3,902$14.98$14.29$14.00$15.00$18.36$17.90
0575Thermoplastic, preformed, white, arrow (0711-14170)EACH42$160.50$153.06$150.00$150.00$313.81$305.70
0580Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM7.22$5,350.00$5,099.22$5,000.00$5,500.00$5,435.03$5,290.00
0585Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.32$5,885.00$5,471.07$5,500.00$6,350.00$7,246.71$6,880.00
0590Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM7.18$2,675.00$2,548.18$2,500.00$1,550.00$1,359.05$1,320.00
0595Thermoplastic, standard-other surfaces white, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-16133)GM0.02$5,350.00$4,859.05$5,000.00$2,200.00$2,718.10$2,520.00
0600Thermoplastic, standard other surfaces, white, 6", 6-10 dotted managed lane marking (0711-16171)GM0.92$3,210.00$3,057.90$3,000.00$1,550.00$2,449.79$2,380.00
0605Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM4.38$5,350.00$5,098.55$5,000.00$5,500.00$4,820.25$4,690.00
0610Permanent tape, white, solid, 6" for concrete bridges (0713-103101)GM0.13$34,240$31,347$32,000$32,000$45,685$42,700
0615Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181)GM0.25$10,700$10,204$10,000$12,000$11,421$11,100
0620Permanent tape, yellow, solid, for concrete bridges (0713-103201)GM0.13$34,240$31,347$32,000$32,000$45,673$42,700
0625Permanent tape, black, 10-30 6" wide, for concrete surfaces (0713-103381)GM0.25$10,700$10,204$10,000$12,000$11,421$11,100
0630Conduit, furnish & install, open trench (0630-2-11)LF56$26.75$25.51$25.00$32.50$29.16$15.30
0635Conduit, furnish & install, directional bore (0630-2-12)LF3,969$32.10$30.61$26.00$32.50$32.66$37.40
0640Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH35$1,284.00$1,224.49$1,000.00$1,350.00$1,749.85$1,560.00
0645Electrical power service, F&I, underground, meter by contractor (0639-1122)AS1$5,350.00$5,102.04$4,500.00$5,100.00$8,165.96$5,880.00
0650Electrical service disconnect, F&I, pole mount (0639-3-11)EACH1$3,424.00$3,265.31$3,200.00$2,800.00$2,916.42$3,250.00
0655Prestressed concrete pole, type P-II service pole (0641-2-12)EACH1$3,210.00$3,061.22$2,800.00$2,300.00$2,333.13$2,650.00
0660Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF13,356$4.28$4.08$4.00$2.85$3.50$3.30
0665Lighting conductors, F&I, insulated, no 4 to no 2 (0715-1-13)LF155$6.42$6.12$6.00$5.00$11.67$4.95
0670Lighting conductors, remove & dispose, contractor owns (0715-1-60)LF828$1.07$1.02$1.00$0.60$1.17$0.45
0675Load center, F&I, secondary voltage (0715-7-11)EACH1$14,445$13,776$13,500$18,000$19,248$20,800
0680Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211)EACH9$1,605.00$1,530.61$1,500.00$1,350.00$1,283.22$1,560.00
0685Light pole complete, F&I, standard pole standard foundation, 45' mounting height, 15' arm length (0715-61452)EACH2$9,630.00$9,183.68$9,000.00$10,750$10,791$12,400
0690Light pole complete, F&I, standard pole standard foundation, 50' mounting height, 15' arm length (0715-61552)EACH19$11,235$10,714$10,000$13,400$12,541$15,500
0695Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH22$695.50$663.27$650.00$800.00$874.92$916.80
0700Conduit, furnish & install, directional bore (0630-2-12)LF4,344$29.96$28.57$28.00$33.25$35.00$38.50
0705Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI12$9,630.00$9,183.67$7,000.00$8,800.00$11,666$10,100
0710Signal cable, remove- intersection (0632-7-6)PI12$535.00$510.20$500.00$1,125.00$583.28$1,290.00
0715Fiber optic cable, F&I, underground,2-12 fibers (0633-1121)LF155$4.28$4.08$4.00$5.00$8.17$5.45
0720Fiber optic connection, install, splice (0633-2-31)EACH4$69.55$66.33$65.00$70.00$93.33$80.10
0725Fiber optic connection hardware, F&I, splice enclosure (0633-3-11)EACH1$1,605.00$1,530.61$1,500.00$1,600.00$2,117.32$1,890.00
0730Fiber optic connection hardware, F&I, splice tray (0633-3-12)EACH1$74.90$71.43$70.00$70.00$93.33$80.10
0735Fiber optic connection hardware, F&I, preterminated connector assembly (0633-3-13)EACH4$107.00$102.04$100.00$110.00$139.99$123.80
0740Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16)EACH1$1,872.50$1,785.71$1,750.00$2,100.00$2,683.10$2,400.00
0745Fiber optic connection hardware, F&I, connector panel (0633-3-17)EACH1$128.40$122.45$120.00$130.00$174.98$145.65
0750Fiber optic cable locator (0633-6)DA360$90.95$0.01$85.00$30.00$116.66$182.15
0755Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH188$1,177.00$1,122.45$900.00$1,350.00$1,749.85$1,560.00
0760Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH10$2,354.00$2,244.90$2,200.00$2,150.00$2,916.42$2,480.00
0765Pull & splice box, install (0635-2-30)EACH11$1,070.00$1,020.41$1,000.00$1,100.00$1,399.88$1,250.00
0770Electrical power service, F&I, underground, meter by contractor (0639-1122)AS11$4,494.00$4,285.71$4,200.00$5,250.00$8,165.96$6,100.00
0775Electrical power service, remove underground (0639-1620)AS11$321.00$306.12$300.00$560.00$874.92$642.85
0780Electrical service wire, & install (0639-2-1)LF707$10.70$10.20$10.00$9.50$9.33$10.95
0785Electrical service wire, (0639-2-6)LF1,450$1.07$1.02$1.00$0.50$0.58$0.45
0790Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60)EACH8$321.00$306.12$300.00$475.00$2,916.42$535.70
0795Prestressed concrete pole, type P-II service pole (0641-2-12)EACH11$2,354.00$2,244.90$2,200.00$2,300.00$2,333.13$2,650.00
0800Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60)EACH3$535.00$510.20$500.00$600.00$874.92$642.85
0805Aluminum signals pole, (0646-1-11)EACH46$1,605.00$1,530.61$1,500.00$2,125.00$2,099.82$2,450.00
0810Aluminum signals pole, remove (0646-1-60)EACH12$267.50$255.10$250.00$380.00$583.28$428.60
0815Vehicular traffic signal, furnish & install aluminum, 1 section, 1 way (0650-1-11)AS1$1,284.00$1,224.49$1,200.00$1,000.00$874.92$1,130.00
0820Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14)AS35$1,284.00$1,224.49$1,000.00$1,575.00$2,099.82$1,820.00
0825Vehicular traffic signal, furnish & install aluminum, 4 section, 1 way (0650-1-16)AS2$1,819.00$1,734.70$1,700.00$1,900.00$2,333.13$2,140.00
0830Vehicular traffic signal, furnish & install aluminum, 5 section cluster, 1 way (0650-1-19)AS2$1,926.00$1,836.74$1,800.00$2,500.00$2,916.42$2,880.00
0835Vehicular traffic signal, remove- poles to remain (0650-1-60)AS19$214.00$204.08$200.00$280.00$291.64$321.45
0840Vehicular traffic signal, relocate- includes removal reinstallation (0650-1-70)AS28$642.00$612.25$600.00$975.00$874.92$1,140.00
0845Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- black with reflect border (0650-2102)EACH49$535.00$510.20$500.00$660.00$758.27$763.70
0850Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS44$1,070.00$1,020.41$900.00$940.00$1,749.85$1,080.00
0855Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12)AS3$1,605.00$1,530.61$1,500.00$1,900.00$2,916.42$2,100.00
0860Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60)AS31$160.50$153.06$150.00$95.00$291.64$107.15
0865Vehicle detection system- furnish & install cabinet equipment (0660-4-11)EACH4$1,070.00$1,020.41$1,000.00$4,000.00$2,333.13$4,650.00
0870Vehicle detection system- furnish & install above ground equipment (0660-4-12)EACH4$7,490.00$7,142.86$7,000.00$11,500$13,416$13,200
0875Vehicle detection system- relocate above ground equipment (0660-4-42)EACH16$1,070.00$1,020.41$1,000.00$2,350.00$2,916.42$2,700.00
0880Vehicle detection system- remove (0660-4-60)EACH4$535.00$510.21$500.00$600.00$583.28$642.85
0885Signal priority and preemption system, furnish and install, detector (0663-1122)EACH1$4,280.00$4,081.63$4,000.00$7,000.00$12,249$7,950.00
0890Signal priority and preemption system, furnish and install, cabinet electronics (0663-1123)EACH1$6,955.00$6,632.65$6,500.00$8,500.00$13,999$9,860.00
0895Signal priority & preemption system, remove (0663-1600)EACH1$428.00$408.16$400.00$465.00$583.28$535.70
0900Pedestrian detector, furnish & install, standard (0665-1-11)EACH56$642.00$612.24$600.00$390.00$408.30$448.10
0905Pedestrian detector, remove- pole/pedestal to remain (0665-1-60)EACH36$107.00$102.04$100.00$70.00$58.33$80.35
0910Traffic controller assembly, F&I, NEMA W/electronic lock, 1 preemption (0670-5171)AS1$48,150$45,918$41,562$43,000$58,328$50,000
0915Traffic controller assembly, remove controller with (0670-5600)AS1$535.00$510.20$500.00$1,200.00$874.92$1,290.00
0920Traffic signal controller cabinet, adjust/modify (0676-1500)EACH10$1,926.00$1,836.74$1,800.00$2,500.00$6,999.40$2,960.00
0925Managed field ethernet switch, furnish & install (0684-1-1)EACH1$7,490.00$7,142.86$7,000.00$8,400.00$11,082$9,660.00
0930Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH4$642.00$612.25$600.00$970.00$1,749.85$1,110.00
0935Internally illuminated sign, relocate (0700-5-50)EACH7$1,070.00$1,020.41$1,000.00$2,000.00$1,749.85$2,340.00
0940Relocate trees and palms, palms, 18.1" or greater DBH, 14.0' or greater of clear trunk (0581-1292)EACH1$8,025.00$7,653.06$8,400.00$6,500.00$3,091.40$28,400
0945Manhole, adjust, utilities (0425-5-1)EACH12$1,070.00$994.90$500.00$750.00$1,079.07$1,110.00
0950Valve boxes, adjust (0425-6)EACH50$909.50$918.37$300.00$650.00$874.92$909.10
0955Local agency initial amount (DO not bid) (0999-26)LS1$3,260.00$3,260.00$3,260.00$3,260.00$3,260.00$3,260.00
0960Utility structure, above adjust & modify (1060-25)EACH2$1,070.00$994.90$2,300.00$750.00$2,333.13$1,110.00
0965Fire hydrant, adjust & modify (1644-700)EACH1$19,260$2,142.86$2,270.00$3,500.00$3,499.70$2,390.00
FDOT contract T4765: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of October 28, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way