TDOT contract CN261063 bid tabulation
The grading, drainage, signals and paving on u.s. 25w (s.r. 9) at the intersection of hunters branch road in lafollette (l.m. 26.05 - l.m. 26.13). Let by Tennessee DOT on August 14, 2026, Campbell County. 5 bids received; low bid $1,493,000 by Rogers Group, Inc..
- Owner
- Tennessee DOT
- Letting
- 14 AUG 2026
- Pay items
- 90
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rogers Group, Inc. | $1,493,000 | Low |
| 2 | DelMae LLC | $1,734,059 | +16% |
| 3 | Charles Blalock & Sons, Inc. | $1,876,970 | +26% |
| 4 | Kenneth Rich Construction Company, Inc. | $1,904,597 | +28% |
| 5 | Advanced Grading Worx LLC | $2,264,712 | +52% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rogers Group, Inc. | 2. DelMae LLC | 3. Charles Blalock & Sons, Inc. | 4. Kenneth Rich Construction Company, Inc. | 5. Advanced Grading Worx LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $21,000 | $50,000 | $27,500 | $20,000 | $20,000 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $25,000 | $97,000 | $200,060 | $120,000 | $120,000 |
| 3 | Removal of pipe (15" RCP, sta. 600+48.76) (202-01.13) | LF | 45 | $25.00 | $40.00 | $29.07 | $50.00 | $50.00 |
| 4 | Removal of pipe (15" HDPE, sta. 602+28.06) (202-01.14) | LF | 40 | $27.75 | $35.00 | $29.01 | $50.00 | $50.00 |
| 5 | Removal of structures and obstructions (202-01.50) | EACH | 1 | $555.00 | $1,500.00 | $2,964.41 | $1,000.00 | $2,000.00 |
| 6 | Removal of structures and obstructions (202-01.51) | EACH | 1 | $1,665.00 | $2,500.00 | $2,437.42 | $5,000.00 | $2,000.00 |
| 7 | Removal of structures and obstructions (202-01.52) | EACH | 1 | $555.00 | $1,000.00 | $2,437.42 | $1,200.00 | $500.00 |
| 8 | Removal of structures and obstructions (202-01.53) | EACH | 1 | $555.00 | $350.00 | $2,437.42 | $1,000.00 | $500.00 |
| 9 | Road & drainage excavation (unclassified) (203-01) | CY | 23,410 | $24.00 | $26.25 | $23.53 | $25.76 | $40.00 |
| 10 | Borrow excavation (graded solid rock) (203-02.01) | TON | 125 | $50.00 | $40.00 | $86.51 | $45.00 | $80.00 |
| 11 | Water (203-06) | MG | 12 | $195.00 | $20.00 | $5.00 | $105.00 | $1.00 |
| 12 | Furnishing & spreading topsoil (203-07) | CY | 1,182 | $26.50 | $75.00 | $43.00 | $40.00 | $30.00 |
| 13 | Brooming & degrassing shoulders (208-01.05) | LM | 0.20 | $2,280.00 | $25,000 | $19,486 | $2,700.00 | $20,000 |
| 14 | Filter sock (12 inch) (209-03.21) | LF | 2,391 | $4.60 | $4.35 | $4.81 | $5.46 | $4.00 |
| 15 | Sediment removal (209-05) | CY | 50 | $66.00 | $20.00 | $5.00 | $35.00 | $1.00 |
| 16 | Rock check dam (209-08.07) | EACH | 18 | $375.00 | $600.00 | $628.35 | $500.00 | $900.00 |
| 17 | Enhanced rock check dam (209-08.08) | EACH | 1 | $875.00 | $800.00 | $874.22 | $800.00 | $1,500.00 |
| 18 | Mineral aggregate, type A base, grading D (303-01) | TON | 1,383 | $44.00 | $37.50 | $55.00 | $41.00 | $44.00 |
| 19 | Mineral aggregate (size 57) (303-10.01) | TON | 15 | $100.00 | $75.00 | $209.02 | $37.00 | $100.00 |
| 20 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 312 | $163.00 | $163.00 | $172.78 | $171.15 | $168.00 |
| 21 | Bituminous material for tack coat (TC) (403-01) | TON | 4 | $1,120.00 | $1,120.00 | $1,187.20 | $1,176.00 | $1,200.00 |
| 22 | Acs mix(PG64-22) grading D (411-01.10) | TON | 219 | $198.00 | $198.00 | $209.88 | $207.90 | $205.00 |
| 23 | Acs mix(PG70-22) grading D (411-02.10) | TON | 253 | $214.00 | $214.00 | $226.84 | $224.70 | $221.00 |
| 24 | Scoring for rumble stripe (non-continuous) (8IN width) (411-12.03) | LM | 0.20 | $2,115.00 | $46,105 | $12,114 | $48,410 | $15,000 |
| 25 | Cold planing bituminous pavement (415-01.01) | TON | 290 | $64.00 | $64.00 | $67.84 | $67.20 | $70.00 |
| 26 | Structural steel (602-01) | LB | 130 | $10.90 | $10.00 | $5.00 | $10.50 | $6.00 |
| 27 | Class A concrete (roadway) (604-01.01) | CY | 2 | $870.00 | $806.00 | $1,000.00 | $846.30 | $1,500.00 |
| 28 | 18" corrugated metal pipe culvert (607-37.02) | LF | 36 | $106.85 | $100.00 | $310.83 | $45.00 | $125.00 |
| 29 | 18" pipe culvert (side drain) (607-39.02) | LF | 33 | $125.00 | $85.00 | $309.26 | $45.00 | $100.00 |
| 30 | Class A concrete (pipe endwalls) (611-07.01) | CY | 2 | $1,360.00 | $5,000.00 | $8,879.59 | $650.00 | $3,500.00 |
| 31 | Steel bar reinforcement (pipe endwalls) (611-07.02) | LB | 90 | $10.50 | $5.00 | $49.28 | $8.00 | $1.00 |
| 32 | Guardrail transition 27IN to 31IN (705-02.10) | EACH | 1 | $56.00 | $53.00 | $265.00 | $197.40 | $200.00 |
| 33 | W beam GR (type 2) MASH TL-3 (long post) (705-06.02) | LF | 675 | $33.25 | $31.50 | $39.75 | $69.83 | $37.00 |
| 34 | GR terminaltrailing end (type 13) MASH TL-3 (705-06.10) | EACH | 1 | $1,850.00 | $1,750.00 | $1,510.50 | $3,360.00 | $1,650.00 |
| 35 | GR terminal (in-inline) MASH TL-3 (705-06.11) | EACH | 2 | $1,150.00 | $1,090.00 | $1,669.50 | $2,509.50 | $1,500.00 |
| 36 | Tangent energy absorbing term MASH TL-3 (705-06.20) | EACH | 1 | $3,580.00 | $3,390.00 | $3,577.50 | $7,129.50 | $3,750.00 |
| 37 | Guardrail removed (706-01) | LF | 210 | $4.75 | $4.50 | $2.12 | $5.78 | $5.00 |
| 38 | Radius rail (706-06.03) | LF | 119 | $38.50 | $36.50 | $50.62 | $85.58 | $50.00 |
| 39 | Rounded end element (706-10.26) | EACH | 1 | $126.75 | $120.00 | $106.00 | $362.25 | $300.00 |
| 40 | High-visibility construction fence (707-08.11) | LF | 960 | $2.85 | $2.59 | $2.84 | $4.20 | $1.75 |
| 41 | Markers (concrete R.O.W. posts) (708-02.01) | EACH | 1 | $800.00 | $600.00 | $1,079.03 | $500.00 | $1,500.00 |
| 42 | Machined rip-rap (class A-3) (709-05.05) | TON | 100 | $55.65 | $65.00 | $90.00 | $42.00 | $50.00 |
| 43 | Machined rip-rap (class A-1) (709-05.06) | TON | 46 | $64.00 | $65.00 | $90.00 | $44.00 | $100.00 |
| 44 | Machined rip-rap (class B) (709-05.08) | TON | 3 | $380.00 | $115.00 | $90.00 | $70.00 | $250.00 |
| 45 | Machined rip-rap (class C) (709-05.09) | TON | 845 | $51.50 | $35.00 | $60.00 | $44.00 | $50.00 |
| 46 | Traffic control (712-01) | LS | 1 | $20,000 | $75,000 | $25,064 | $127,245 | $162,500 |
| 47 | Portable barrier rail (MASH TL-3) (712-02.10) | LF | 820 | $80.00 | $64.50 | $72.49 | $63.00 | $60.00 |
| 48 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 4 | $9,435.00 | $8,000.00 | $5,565.00 | $6,825.00 | $7,500.00 |
| 49 | Flexible drums (channelizing) (712-04.01) | EACH | 79 | $39.30 | $40.00 | $42.40 | $42.00 | $50.00 |
| 50 | Barrier rail delineator (712-04.50) | EACH | 45 | $19.15 | $17.00 | $18.02 | $17.85 | $20.00 |
| 51 | Signs (construction) (712-06) | SF | 906.13 | $7.50 | $8.15 | $9.00 | $8.56 | $9.00 |
| 52 | Temporary barricades (type III) (712-07.03) | LF | 144 | $12.45 | $17.50 | $18.55 | $18.38 | $20.00 |
| 53 | Street name sign (rigid 0.100IN thick (713-14.21) | SF | 56 | $23.80 | $50.00 | $53.00 | $86.10 | $75.00 |
| 54 | Removal of signs, posts and footings (713-15) | LS | 1 | $103.50 | $100.00 | $106.00 | $105.00 | $200.00 |
| 55 | Removal & relocation of sign & support (713-15.02) | EACH | 1 | $103.50 | $100.00 | $159.00 | $157.50 | $250.00 |
| 56 | Suspended flat sheet aluminum sign (0.080" thick) (713-15.07) | EACH | 1 | $124.00 | $650.00 | $689.00 | $892.00 | $750.00 |
| 57 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 28 | $77.60 | $45.00 | $79.50 | $105.00 | $50.00 |
| 58 | Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22) | EACH | 15 | $77.60 | $45.00 | $79.50 | $105.00 | $55.00 |
| 59 | Removal of snowplowable reflective marker (716-01.30) | EACH | 30 | $20.70 | $25.00 | $21.20 | $26.25 | $50.00 |
| 60 | Plastic pavement marking(channelization striping) (716-02.04) | SY | 88 | $25.85 | $28.00 | $26.50 | $30.19 | $35.00 |
| 61 | Plastic pavement marking (stop line) (716-02.05) | LF | 75 | $15.50 | $15.00 | $15.90 | $13.13 | $20.00 |
| 62 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 1 | $258.00 | $250.00 | $265.00 | $210.00 | $500.00 |
| 63 | Plastic pavement marking (8" dotted line) (716-02.08) | LF | 75 | $2.05 | $2.25 | $2.12 | $3.94 | $5.00 |
| 64 | Plastic pavement marking (8IN line) (716-02.12) | LM | 0.10 | $11,380 | $12,500 | $11,660 | $9,975.00 | $15,000 |
| 65 | Painted pavement marking (6" line) (716-05.20) | LM | 1 | $2,585.00 | $1,750.00 | $2,650.00 | $2,625.00 | $2,000.00 |
| 66 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 1 | $9,315.00 | $7,500.00 | $9,540.00 | $8,137.50 | $8,000.00 |
| 67 | Mobilization (717-01) | LS | 1 | $71,504 | $72,500 | $185,000 | $190,000 | $180,043 |
| 68 | Signal head assembly (130 pole mounted) (730-02.08) | EACH | 1 | $1,370.00 | $1,485.00 | $1,457.50 | $1,443.75 | $1,500.00 |
| 69 | Signal head assembly (130 with backplate) (730-02.09) | EACH | 5 | $1,715.00 | $1,560.00 | $1,602.72 | $1,587.60 | $1,450.00 |
| 70 | Signal head assembly (150 A2H with backplate) (730-02.17) | EACH | 1 | $2,940.00 | $2,345.00 | $2,550.36 | $2,526.30 | $2,400.00 |
| 71 | Install pull box (type B) (730-03.21) | EACH | 2 | $1,230.00 | $950.00 | $1,272.00 | $1,260.00 | $3,500.00 |
| 72 | Electrical service connection (730-05.01) | EACH | 1 | $2,840.00 | $3,944.00 | $8,904.00 | $8,820.00 | $5,000.00 |
| 73 | Signal cable - 5 conductor (730-08.02) | LF | 196 | $2.60 | $3.50 | $2.92 | $2.89 | $10.00 |
| 74 | Signal cable - 7 conductor (730-08.03) | LF | 373 | $3.20 | $3.55 | $3.18 | $3.15 | $11.00 |
| 75 | Conduit 2" diameter (PVC schedule 40) (730-12.02) | LF | 100 | $36.00 | $20.85 | $29.68 | $29.40 | $20.00 |
| 76 | Conduit 2" diameter (directional bore) (730-12.23) | LF | 99 | $155.00 | $30.00 | $84.80 | $84.00 | $25.00 |
| 77 | Vehicle detector (radar - stop line) (730-13.12) | EACH | 3 | $12,540 | $13,090 | $10,876 | $10,773 | $9,000.00 |
| 78 | Vehicle detector (radar - advance) (730-13.13) | EACH | 2 | $11,550 | $12,282 | $10,876 | $10,773 | $9,000.00 |
| 79 | Cabinet (atc) (730-15.07) | EACH | 1 | $22,210 | $32,256 | $29,504 | $29,226 | $32,500 |
| 80 | Controller (atc) (730-16.04) | EACH | 1 | $7,125.00 | $7,021.00 | $8,145.04 | $8,068.20 | $10,000 |
| 81 | Cantilever signal support (2 @ 45' & 55') (730-24.91) | EACH | 1 | $49,856 | $49,665 | $50,439 | $49,963 | $52,500 |
| 82 | Cantilever signal support (1 arm @ 55') (730-25.07) | EACH | 1 | $34,650 | $37,153 | $37,337 | $36,985 | $62,500 |
| 83 | Geotextile (type III)(erosion control) (740-10.03) | SY | 1,342 | $7.75 | $5.50 | $2.73 | $5.00 | $3.00 |
| 84 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 150 | $2.00 | $14.00 | $4.81 | $5.00 | $20.00 |
| 85 | Temporary sediment tube 18IN (740-11.03) | LF | 1,429 | $4.40 | $4.25 | $4.92 | $4.73 | $4.25 |
| 86 | Seeding (with mulch) (801-01) | UNIT | 1 | $56.90 | $55.00 | $60.10 | $131.25 | $250.00 |
| 87 | Temporary seeding (with mulch) (801-01.07) | UNIT | 80 | $35.45 | $34.25 | $38.25 | $42.00 | $100.00 |
| 88 | Seeding (without mulch) (801-02) | UNIT | 80 | $28.95 | $27.98 | $32.78 | $39.90 | $75.00 |
| 89 | Water (seeding & sodding) (801-03) | MG | 16 | $76.00 | $73.50 | $81.96 | $105.00 | $200.00 |
| 90 | Erosion control blanket (type II) (805-12.02) | SY | 8,553 | $1.05 | $1.04 | $1.15 | $2.00 | $1.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of August 14, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.