TDOT contract CN261063 bid tabulation

The grading, drainage, signals and paving on u.s. 25w (s.r. 9) at the intersection of hunters branch road in lafollette (l.m. 26.05 - l.m. 26.13). Let by Tennessee DOT on August 14, 2026, Campbell County. 5 bids received; low bid $1,493,000 by Rogers Group, Inc..

Owner
Tennessee DOT
Letting
14 AUG 2026
Pay items
90
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Rogers Group, Inc.$1,493,000Low
2DelMae LLC$1,734,059+16%
3Charles Blalock & Sons, Inc.$1,876,970+26%
4Kenneth Rich Construction Company, Inc.$1,904,597+28%
5Advanced Grading Worx LLC$2,264,712+52%
TDOT contract CN261063: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Rogers Group, Inc.2. DelMae LLC3. Charles Blalock & Sons, Inc.4. Kenneth Rich Construction Company, Inc.5. Advanced Grading Worx LLC
1Construction stakes, lines and grades (105-01)LS1$21,000$50,000$27,500$20,000$20,000
2Clearing and grubbing (201-01)LS1$25,000$97,000$200,060$120,000$120,000
3Removal of pipe (15" RCP, sta. 600+48.76) (202-01.13)LF45$25.00$40.00$29.07$50.00$50.00
4Removal of pipe (15" HDPE, sta. 602+28.06) (202-01.14)LF40$27.75$35.00$29.01$50.00$50.00
5Removal of structures and obstructions (202-01.50)EACH1$555.00$1,500.00$2,964.41$1,000.00$2,000.00
6Removal of structures and obstructions (202-01.51)EACH1$1,665.00$2,500.00$2,437.42$5,000.00$2,000.00
7Removal of structures and obstructions (202-01.52)EACH1$555.00$1,000.00$2,437.42$1,200.00$500.00
8Removal of structures and obstructions (202-01.53)EACH1$555.00$350.00$2,437.42$1,000.00$500.00
9Road & drainage excavation (unclassified) (203-01)CY23,410$24.00$26.25$23.53$25.76$40.00
10Borrow excavation (graded solid rock) (203-02.01)TON125$50.00$40.00$86.51$45.00$80.00
11Water (203-06)MG12$195.00$20.00$5.00$105.00$1.00
12Furnishing & spreading topsoil (203-07)CY1,182$26.50$75.00$43.00$40.00$30.00
13Brooming & degrassing shoulders (208-01.05)LM0.20$2,280.00$25,000$19,486$2,700.00$20,000
14Filter sock (12 inch) (209-03.21)LF2,391$4.60$4.35$4.81$5.46$4.00
15Sediment removal (209-05)CY50$66.00$20.00$5.00$35.00$1.00
16Rock check dam (209-08.07)EACH18$375.00$600.00$628.35$500.00$900.00
17Enhanced rock check dam (209-08.08)EACH1$875.00$800.00$874.22$800.00$1,500.00
18Mineral aggregate, type A base, grading D (303-01)TON1,383$44.00$37.50$55.00$41.00$44.00
19Mineral aggregate (size 57) (303-10.01)TON15$100.00$75.00$209.02$37.00$100.00
20Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON312$163.00$163.00$172.78$171.15$168.00
21Bituminous material for tack coat (TC) (403-01)TON4$1,120.00$1,120.00$1,187.20$1,176.00$1,200.00
22Acs mix(PG64-22) grading D (411-01.10)TON219$198.00$198.00$209.88$207.90$205.00
23Acs mix(PG70-22) grading D (411-02.10)TON253$214.00$214.00$226.84$224.70$221.00
24Scoring for rumble stripe (non-continuous) (8IN width) (411-12.03)LM0.20$2,115.00$46,105$12,114$48,410$15,000
25Cold planing bituminous pavement (415-01.01)TON290$64.00$64.00$67.84$67.20$70.00
26Structural steel (602-01)LB130$10.90$10.00$5.00$10.50$6.00
27Class A concrete (roadway) (604-01.01)CY2$870.00$806.00$1,000.00$846.30$1,500.00
2818" corrugated metal pipe culvert (607-37.02)LF36$106.85$100.00$310.83$45.00$125.00
2918" pipe culvert (side drain) (607-39.02)LF33$125.00$85.00$309.26$45.00$100.00
30Class A concrete (pipe endwalls) (611-07.01)CY2$1,360.00$5,000.00$8,879.59$650.00$3,500.00
31Steel bar reinforcement (pipe endwalls) (611-07.02)LB90$10.50$5.00$49.28$8.00$1.00
32Guardrail transition 27IN to 31IN (705-02.10)EACH1$56.00$53.00$265.00$197.40$200.00
33W beam GR (type 2) MASH TL-3 (long post) (705-06.02)LF675$33.25$31.50$39.75$69.83$37.00
34GR terminaltrailing end (type 13) MASH TL-3 (705-06.10)EACH1$1,850.00$1,750.00$1,510.50$3,360.00$1,650.00
35GR terminal (in-inline) MASH TL-3 (705-06.11)EACH2$1,150.00$1,090.00$1,669.50$2,509.50$1,500.00
36Tangent energy absorbing term MASH TL-3 (705-06.20)EACH1$3,580.00$3,390.00$3,577.50$7,129.50$3,750.00
37Guardrail removed (706-01)LF210$4.75$4.50$2.12$5.78$5.00
38Radius rail (706-06.03)LF119$38.50$36.50$50.62$85.58$50.00
39Rounded end element (706-10.26)EACH1$126.75$120.00$106.00$362.25$300.00
40High-visibility construction fence (707-08.11)LF960$2.85$2.59$2.84$4.20$1.75
41Markers (concrete R.O.W. posts) (708-02.01)EACH1$800.00$600.00$1,079.03$500.00$1,500.00
42Machined rip-rap (class A-3) (709-05.05)TON100$55.65$65.00$90.00$42.00$50.00
43Machined rip-rap (class A-1) (709-05.06)TON46$64.00$65.00$90.00$44.00$100.00
44Machined rip-rap (class B) (709-05.08)TON3$380.00$115.00$90.00$70.00$250.00
45Machined rip-rap (class C) (709-05.09)TON845$51.50$35.00$60.00$44.00$50.00
46Traffic control (712-01)LS1$20,000$75,000$25,064$127,245$162,500
47Portable barrier rail (MASH TL-3) (712-02.10)LF820$80.00$64.50$72.49$63.00$60.00
48Temporary work zone crash cushion (MASH TL-3) (712-02.60)EACH4$9,435.00$8,000.00$5,565.00$6,825.00$7,500.00
49Flexible drums (channelizing) (712-04.01)EACH79$39.30$40.00$42.40$42.00$50.00
50Barrier rail delineator (712-04.50)EACH45$19.15$17.00$18.02$17.85$20.00
51Signs (construction) (712-06)SF906.13$7.50$8.15$9.00$8.56$9.00
52Temporary barricades (type III) (712-07.03)LF144$12.45$17.50$18.55$18.38$20.00
53Street name sign (rigid 0.100IN thick (713-14.21)SF56$23.80$50.00$53.00$86.10$75.00
54Removal of signs, posts and footings (713-15)LS1$103.50$100.00$106.00$105.00$200.00
55Removal & relocation of sign & support (713-15.02)EACH1$103.50$100.00$159.00$157.50$250.00
56Suspended flat sheet aluminum sign (0.080" thick) (713-15.07)EACH1$124.00$650.00$689.00$892.00$750.00
57Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21)EACH28$77.60$45.00$79.50$105.00$50.00
58Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22)EACH15$77.60$45.00$79.50$105.00$55.00
59Removal of snowplowable reflective marker (716-01.30)EACH30$20.70$25.00$21.20$26.25$50.00
60Plastic pavement marking(channelization striping) (716-02.04)SY88$25.85$28.00$26.50$30.19$35.00
61Plastic pavement marking (stop line) (716-02.05)LF75$15.50$15.00$15.90$13.13$20.00
62Plastic pavement marking (turn lane arrow) (716-02.06)EACH1$258.00$250.00$265.00$210.00$500.00
63Plastic pavement marking (8" dotted line) (716-02.08)LF75$2.05$2.25$2.12$3.94$5.00
64Plastic pavement marking (8IN line) (716-02.12)LM0.10$11,380$12,500$11,660$9,975.00$15,000
65Painted pavement marking (6" line) (716-05.20)LM1$2,585.00$1,750.00$2,650.00$2,625.00$2,000.00
66Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM1$9,315.00$7,500.00$9,540.00$8,137.50$8,000.00
67Mobilization (717-01)LS1$71,504$72,500$185,000$190,000$180,043
68Signal head assembly (130 pole mounted) (730-02.08)EACH1$1,370.00$1,485.00$1,457.50$1,443.75$1,500.00
69Signal head assembly (130 with backplate) (730-02.09)EACH5$1,715.00$1,560.00$1,602.72$1,587.60$1,450.00
70Signal head assembly (150 A2H with backplate) (730-02.17)EACH1$2,940.00$2,345.00$2,550.36$2,526.30$2,400.00
71Install pull box (type B) (730-03.21)EACH2$1,230.00$950.00$1,272.00$1,260.00$3,500.00
72Electrical service connection (730-05.01)EACH1$2,840.00$3,944.00$8,904.00$8,820.00$5,000.00
73Signal cable - 5 conductor (730-08.02)LF196$2.60$3.50$2.92$2.89$10.00
74Signal cable - 7 conductor (730-08.03)LF373$3.20$3.55$3.18$3.15$11.00
75Conduit 2" diameter (PVC schedule 40) (730-12.02)LF100$36.00$20.85$29.68$29.40$20.00
76Conduit 2" diameter (directional bore) (730-12.23)LF99$155.00$30.00$84.80$84.00$25.00
77Vehicle detector (radar - stop line) (730-13.12)EACH3$12,540$13,090$10,876$10,773$9,000.00
78Vehicle detector (radar - advance) (730-13.13)EACH2$11,550$12,282$10,876$10,773$9,000.00
79Cabinet (atc) (730-15.07)EACH1$22,210$32,256$29,504$29,226$32,500
80Controller (atc) (730-16.04)EACH1$7,125.00$7,021.00$8,145.04$8,068.20$10,000
81Cantilever signal support (2 @ 45' & 55') (730-24.91)EACH1$49,856$49,665$50,439$49,963$52,500
82Cantilever signal support (1 arm @ 55') (730-25.07)EACH1$34,650$37,153$37,337$36,985$62,500
83Geotextile (type III)(erosion control) (740-10.03)SY1,342$7.75$5.50$2.73$5.00$3.00
84Geotextile (type IV)(stabilization) (740-10.04)SY150$2.00$14.00$4.81$5.00$20.00
85Temporary sediment tube 18IN (740-11.03)LF1,429$4.40$4.25$4.92$4.73$4.25
86Seeding (with mulch) (801-01)UNIT1$56.90$55.00$60.10$131.25$250.00
87Temporary seeding (with mulch) (801-01.07)UNIT80$35.45$34.25$38.25$42.00$100.00
88Seeding (without mulch) (801-02)UNIT80$28.95$27.98$32.78$39.90$75.00
89Water (seeding & sodding) (801-03)MG16$76.00$73.50$81.96$105.00$200.00
90Erosion control blanket (type II) (805-12.02)SY8,553$1.05$1.04$1.15$2.00$1.50
TDOT contract CN261063: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of August 14, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy