FDOT contract T4715 bid tabulation
SR 817 (UNIVERSITY DR) FROM NOVA DR TO SR 84. Let by Florida DOT on August 27, 2025, Broward, District 4. 9 bids received; low bid $6,850,813 by Bacallao Construction & Engineering Development, LLC D/B/A BC&E.
- Owner
- Florida DOT
- Letting
- 27 AUG 2025
- Pay items
- 192
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Bacallao Construction & Engineering Development, LLC D/B/A BC&E | $6,850,813 | Low |
| 2 | General Asphalt Company, LLC | $7,472,654 | +9.0% |
| 3 | The Stout Group LLC | $7,481,823 | +9.0% |
| 4 | Horizon Contractors, Inc. | $7,631,640 | +11% |
| 5 | Weekley Asphalt Paving, Inc. | $7,635,667 | +11% |
| 6 | Roadway Construction, LLC | $7,670,948 | +12% |
| 7 | Florida Engineering & Development Corp | $7,902,895 | +15% |
| 8 | Ohla USA Inc | $8,985,014 | +31% |
| 9 | Ranger Construction Industries, Inc. | $9,118,924 | +33% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Bacallao Construction & Engineering Development, LLC D/B/A BC&E | 2. General Asphalt Company, LLC | 3. The Stout Group LLC | 4. Horizon Contractors, Inc. | 5. Weekley Asphalt Paving, Inc. | 6. Roadway Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $690,000 | $500,000 | $740,000 | $750,000 | $372,150 | $767,095 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $169,361 | $675,000 | $348,000 | $1,000,000 | $696,957 | $350,000 |
| 0015 | Special detour- temporary pavement (0102-2200) | SY | 1 | $10,000 | $16,500 | $35,000 | $16,000 | $142,945 | $33,208 |
| 0020 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $1,000.00 | $12,275 | $12,000 | $5,500.00 | $10,000 | $9,555.22 |
| 0025 | Traffic control officer (0102-14) | HR | 252 | $90.00 | $88.00 | $90.00 | $85.00 | $92.00 | $75.00 |
| 0030 | Work zone sign (0102-60) | ED | 12,783 | $0.20 | $0.29 | $0.19 | $0.20 | $0.19 | $0.20 |
| 0035 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 3,892 | $43.00 | $47.30 | $43.00 | $44.00 | $35.00 | $38.00 |
| 0040 | Temporary barrier, relocate, low profile concrete (0102-71-23) | LF | 1,374 | $16.00 | $17.60 | $16.00 | $15.00 | $28.00 | $18.00 |
| 0045 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 35,168 | $0.10 | $0.11 | $0.10 | $0.12 | $0.10 | $0.08 |
| 0050 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 213,188 | $0.05 | $0.05 | $0.04 | $0.05 | $0.04 | $0.04 |
| 0055 | Arrow board / advance warning arrow panel (0102-76) | ED | 188 | $5.00 | $10.08 | $5.00 | $6.00 | $10.00 | $4.50 |
| 0060 | Temporary raised/retroreflective pavement marker, type D (0102-78-1) | EACH | 359 | $5.00 | $10.08 | $7.00 | $10.00 | $4.50 | $4.00 |
| 0065 | Temporary crash cushion, redirective option (0102-89-1) | LO | 2 | $1,000.00 | $968.00 | $880.00 | $1.00 | $2,500.00 | $1,050.00 |
| 0070 | Portable changeable message sign, temporary (0102-99) | ED | 495 | $9.00 | $9.90 | $9.00 | $10.00 | $9.00 | $9.00 |
| 0075 | Temporary signalization and maintenance, intersection (0102-104) | ED | 1,218 | $18.00 | $5.50 | $18.00 | $20.00 | $4.00 | $10.00 |
| 0080 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 1,218 | $18.00 | $5.50 | $18.00 | $20.00 | $4.00 | $10.00 |
| 0085 | Type III barricade (0102-115) | ED | 3 | $0.75 | $0.83 | $0.75 | $100.00 | $5.00 | $0.25 |
| 0090 | Sediment barrier (0104-10-3) | LF | 3,206 | $2.00 | $1.10 | $6.00 | $3.00 | $2.95 | $3.27 |
| 0095 | Inlet protection system (0104-18) | EACH | 3 | $50.00 | $220.00 | $150.00 | $100.00 | $165.00 | $190.48 |
| 0100 | Litter removal (0107-1) | ACRE | 126.65 | $0.01 | $1.10 | $0.01 | $0.01 | $40.00 | $0.01 |
| 0105 | Mowing (0107-2) | ACRE | 100.06 | $0.01 | $1.10 | $0.01 | $0.01 | $40.00 | $0.01 |
| 0110 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $5,000.00 | $1.10 | $30,000 | $5,000.00 | $15,560 | $0.01 |
| 0115 | Monitor existing structures- vibration monitoring (0108-2) | LS | 1 | $5,000.00 | $1.10 | $30,000 | $5,000.00 | $12,840 | $0.01 |
| 0120 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $300,000 | $52,514 | $150,000 | $400,000 | $240,200 | $343,026 |
| 0125 | Removal of existing concrete (0110-4-10) | SY | 1,751 | $30.00 | $11.00 | $25.00 | $22.00 | $44.78 | $17.43 |
| 0130 | Regular excavation (0120-1) | CY | 3,165.70 | $36.00 | $22.00 | $30.00 | $11.00 | $38.00 | $16.96 |
| 0135 | Embankment (0120-6) | CY | 2,397 | $50.00 | $22.00 | $30.00 | $35.00 | $24.12 | $12.79 |
| 0140 | Type B stabilization (0160-4) | SY | 5,604 | $0.01 | $33.00 | $25.00 | $12.00 | $21.77 | $26.61 |
| 0145 | Optional base, base group 01 (0285-701) | SY | 1,593 | $20.00 | $23.65 | $32.00 | $20.00 | $24.33 | $19.31 |
| 0150 | Optional base, base group 09 (0285-709) | SY | 2,007 | $39.00 | $48.40 | $43.00 | $36.00 | $39.00 | $51.10 |
| 0155 | Optional base, base group 10 (0285-710) | SY | 1,686 | $98.00 | $74.29 | $120.00 | $45.00 | $41.00 | $95.92 |
| 0160 | Optional base, base group 11 (0285-711) | SY | 317 | $63.00 | $77.00 | $81.00 | $48.00 | $57.27 | $71.43 |
| 0165 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 25,733 | $4.00 | $3.90 | $3.75 | $5.00 | $3.00 | $4.50 |
| 0170 | Superpave asphaltic conc, traffic B (0334-1-12) | TN | 93.70 | $210.00 | $310.59 | $190.00 | $220.00 | $190.00 | $303.62 |
| 0175 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 304.70 | $210.00 | $239.21 | $190.00 | $220.00 | $190.00 | $299.27 |
| 0180 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 2,457.80 | $190.00 | $217.71 | $220.00 | $220.00 | $205.00 | $196.00 |
| 0185 | Miscellaneous asphalt (0339-1) | TN | 3.10 | $550.00 | $2,075.00 | $350.00 | $2,000.00 | $800.00 | $777.64 |
| 0190 | Concrete class NS, gravity index 400-011 (0400-0-11) | CY | 74.70 | $1,100.00 | $550.00 | $850.00 | $1,200.00 | $1,628.00 | $1,984.79 |
| 0195 | Inlets, curb, type P-1, <10' (0425-1311) | EACH | 1 | $11,700 | $12,100 | $19,000 | $9,600.00 | $18,100 | $20,658 |
| 0200 | Inlets, curb, type P-2, <10' (0425-1321) | EACH | 1 | $12,500 | $13,200 | $19,000 | $9,800.00 | $19,045 | $22,091 |
| 0205 | Inlets, curb, type P-5, <10' (0425-1351) | EACH | 3 | $10,500 | $8,800.00 | $16,000 | $7,300.00 | $11,930 | $15,115 |
| 0210 | Inlets, curb, type P-6, <10' (0425-1361) | EACH | 4 | $11,200 | $8,800.00 | $16,000 | $8,400.00 | $13,150 | $15,382 |
| 0215 | Inlets, curb, type J-2, <10' (0425-1421) | EACH | 1 | $17,400 | $19,800 | $22,000 | $14,000 | $24,650 | $31,866 |
| 0220 | Inlets, curb, type J-5, <10' (0425-1451) | EACH | 1 | $13,000 | $13,200 | $19,000 | $10,000 | $16,080 | $22,392 |
| 0225 | Inlets, curb, type J-6, <10' (0425-1461) | EACH | 1 | $13,500 | $13,200 | $19,000 | $12,000 | $16,000 | $22,962 |
| 0230 | Inlets, DT bot, type C,<10' (0425-1521) | EACH | 8 | $7,400.00 | $6,600.00 | $14,000 | $5,500.00 | $9,360.00 | $13,523 |
| 0235 | Inlets, ditch bottom, type C, partial (0425-1525) | EACH | 1 | $6,000.00 | $4,400.00 | $13,000 | $1,200.00 | $9,321.00 | $10,677 |
| 0240 | Inlets, gutter, type V, <10' (0425-1711) | EACH | 1 | $8,000.00 | $6,600.00 | $15,000 | $6,200.00 | $10,082 | $11,524 |
| 0245 | Inlets, barrier wall, rigid, curb & gutter, <=10' (0425-1881) | EACH | 2 | $12,500 | $6,600.00 | $15,000 | $8,000.00 | $13,395 | $14,967 |
| 0250 | Inlets, closed flume (0425-1910) | EACH | 5 | $12,500 | $8,800.00 | $24,000 | $9,800.00 | $11,789 | $14,883 |
| 0255 | Manholes, P-7, <10' (0425-2-41) | EACH | 4 | $7,500.00 | $8,800.00 | $13,000 | $5,600.00 | $9,965.00 | $12,613 |
| 0260 | Manholes, J-7, <10' (0425-2-71) | EACH | 1 | $13,250 | $9,900.00 | $18,000 | $11,000 | $15,533 | $23,608 |
| 0265 | Manhole, adjust (0425-5) | EACH | 4 | $900.00 | $440.00 | $950.00 | $1,000.00 | $1,200.00 | $600.00 |
| 0270 | Desilting pipe, 0 - 24" (0430-94-1) | LF | 52 | $200.00 | $110.00 | $25.00 | $10.00 | $106.00 | $40.00 |
| 0275 | Pipe culvert, optional material, round, 24"SD (0430-174124) | LF | 232 | $115.00 | $220.00 | $210.00 | $170.00 | $237.00 | $212.91 |
| 0280 | Pipe culvert, optional material, other shape - ellip/arch, 18"SD (0430-174218) | LF | 12 | $340.00 | $220.00 | $750.00 | $300.00 | $390.00 | $567.34 |
| 0285 | Pipe culvert,optional material,round, 12"S/CD (0430-175112) | LF | 16 | $300.00 | $220.00 | $500.00 | $300.00 | $395.00 | $454.85 |
| 0290 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 651 | $125.00 | $220.00 | $190.00 | $145.00 | $180.00 | $172.73 |
| 0295 | Pipe filling and plugging- place out of service (0430-830) | CY | 339 | $10.00 | $330.00 | $250.00 | $220.00 | $252.95 | $397.43 |
| 0300 | Mitered end section, optional round, 18" SD (0430-984125) | EACH | 2 | $4,350.00 | $2,200.00 | $4,000.00 | $2,400.00 | $3,900.00 | $6,725.42 |
| 0305 | Trench drain, standard (0436-1-1) | LF | 81 | $390.00 | $275.00 | $950.00 | $1,000.00 | $943.00 | $1,063.66 |
| 0310 | French drain, 24" (0443-70-4) | LF | 1,657 | $300.00 | $297.00 | $315.00 | $230.00 | $308.00 | $347.44 |
| 0315 | Pipe handrail - guiderail, aluminum (0515-1-2) | LF | 383 | $79.00 | $99.00 | $64.48 | $70.00 | $109.00 | $64.48 |
| 0320 | Pedestrian / bicycle railing, steel, 42" type 1 (0515-2211) | LF | 8 | $225.00 | $742.50 | $190.64 | $210.00 | $725.00 | $190.64 |
| 0325 | Concrete curb & gutter, type F (0520-1-10) | LF | 2,916 | $55.00 | $49.50 | $33.00 | $28.00 | $43.50 | $73.71 |
| 0330 | Concrete curb, type D (0520-2-4) | LF | 85 | $50.00 | $44.00 | $35.00 | $28.00 | $69.00 | $56.42 |
| 0335 | Shoulder gutter- concrete (0520-6) | LF | 143 | $35.00 | $88.00 | $35.00 | $60.00 | $44.75 | $81.62 |
| 0340 | Concrete traffic separator, special- variable width (0520-70) | SY | 6 | $355.00 | $330.00 | $250.00 | $120.00 | $218.00 | $496.72 |
| 0345 | Median concrete barrier, grade-separated (0521-1-12) | LF | 32 | $650.00 | $165.00 | $450.00 | $480.00 | $409.00 | $524.88 |
| 0350 | Median concrete barrier, tall grade-separated (0521-1-13) | LF | 153 | $775.00 | $220.00 | $600.00 | $480.00 | $558.00 | $833.76 |
| 0355 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 472 | $90.00 | $93.50 | $85.00 | $54.00 | $64.20 | $72.86 |
| 0360 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 2,634 | $105.00 | $99.00 | $90.00 | $95.00 | $70.83 | $99.93 |
| 0365 | Bus shelter pad- concrete (0522-4) | SY | 5 | $110.00 | $330.00 | $250.00 | $140.00 | $488.00 | $363.33 |
| 0370 | Detectable warnings (0527-2) | SF | 225 | $38.00 | $49.50 | $40.00 | $32.00 | $36.00 | $54.59 |
| 0375 | Guardrail -roadway, general (0536-1-1) | LF | 46 | $39.00 | $33.00 | $31.91 | $35.00 | $28.00 | $31.91 |
| 0380 | Guardrail removal (0536-73) | LF | 39 | $1.00 | $5.50 | $2.99 | $4.00 | $5.00 | $2.99 |
| 0385 | Crash cushion, TL-3, wide (0544-3-2) | EACH | 1 | $35,000 | $51,700 | $30,000 | $50,000 | $59,900 | $54,286 |
| 0390 | Fencing, type B, 5.1-6.0', standard (0550-10220) | LF | 1,014 | $20.00 | $30.25 | $19.08 | $21.00 | $18.00 | $19.08 |
| 0395 | Performance turf (0570-1-1) | SY | 4,047 | $8.50 | $4.84 | $12.00 | $4.00 | $7.50 | $10.90 |
| 0400 | Performance turf, sod (0570-1-2) | SY | 2,635 | $8.50 | $4.84 | $12.00 | $4.00 | $7.50 | $10.90 |
| 0405 | Performance turf, sod and shoulder treatment index (0570-1-3) | SY | 206 | $10.00 | $10.34 | $25.00 | $4.00 | $22.00 | $32.77 |
| 0410 | Conduit, furnish & install, open trench (0630-2-11) | LF | 196 | $38.00 | $23.10 | $38.30 | $41.00 | $22.00 | $20.00 |
| 0415 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 5 | $1,300.00 | $2,200.00 | $1,271.30 | $1,400.00 | $1,800.00 | $1,540.00 |
| 0420 | Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1) | EACH | 15 | $2,200.00 | $3,520.00 | $2,174.60 | $2,400.00 | $3,600.00 | $2,893.50 |
| 0425 | Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12) | EACH | 15 | $2,200.00 | $2,750.00 | $2,124.90 | $2,400.00 | $3,400.00 | $2,947.50 |
| 0430 | Traffic monitoring site cabinet, furnish & install, type 4, base mount (0695-7141) | EACH | 1 | $10,500 | $7,480.00 | $10,453 | $12,000 | $8,000.00 | $7,914.50 |
| 0435 | Traffic monitoring site cabinet, remove existing cabinet (0695-7600) | EACH | 1 | $750.00 | $2,750.00 | $716.90 | $1,000.00 | $1,000.00 | $990.00 |
| 0440 | Raised pavement marker, type B (0706-1-3) | EACH | 586 | $5.00 | $5.50 | $7.00 | $6.00 | $5.00 | $4.00 |
| 0445 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 3.59 | $1,600.00 | $2,750.00 | $1,800.00 | $1,500.00 | $1,350.00 | $1,698.58 |
| 0450 | Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102) | GM | 0.36 | $1,800.00 | $3,300.00 | $2,000.00 | $1,700.00 | $1,500.00 | $2,111.54 |
| 0455 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 5,890 | $1.00 | $1.10 | $2.00 | $1.10 | $1.00 | $1.50 |
| 0460 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 286 | $2.25 | $1.65 | $6.00 | $3.00 | $2.00 | $1.60 |
| 0465 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 1,675 | $3.25 | $2.20 | $4.00 | $3.50 | $3.00 | $1.70 |
| 0470 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 2.86 | $725.00 | $1,650.00 | $1,000.00 | $800.00 | $700.00 | $490.51 |
| 0475 | Painted pavement marking, standard,white, 3'-9' skip drop line and approach to toll 12" wide, (0710-11133) | GM | 0.05 | $1,700.00 | $2,200.00 | $2,000.00 | $2,000.00 | $1,320.00 | $1,042.55 |
| 0480 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.42 | $750.00 | $1,650.00 | $1,000.00 | $2,000.00 | $700.00 | $651.55 |
| 0485 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 18 | $70.00 | $110.00 | $100.00 | $70.00 | $60.00 | $35.00 |
| 0490 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 45 | $40.00 | $55.00 | $50.00 | $40.00 | $35.00 | $35.00 |
| 0495 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 0.97 | $1,500.00 | $2,750.00 | $1,800.00 | $1,500.00 | $1,350.00 | $1,694.76 |
| 0500 | Architectural, bus shelter, F&I, 101-150 SF (0751-35-13) | EACH | 1 | $110,000 | $131,230 | $150,000 | $130,000 | $108,000 | $86,000 |
| 0505 | Architectural, bus shelter, F&I, greater than 200 SF (0751-35-15) | EACH | 1 | $170,000 | $152,625 | $180,000 | $150,000 | $138,000 | $109,000 |
| 0510 | Bicycle rack, furnish & install, 2 bicycles (0751-36-11) | EACH | 2 | $3,500.00 | $1,155.00 | $6,500.00 | $2,000.00 | $850.00 | $2,000.00 |
| 0515 | Trash receptacle (0751-37) | EACH | 2 | $3,000.00 | $2,750.00 | $3,500.00 | $3,000.00 | $2,780.00 | $1,988.55 |
| 0520 | Bench, F&I, steel (0751-38-14) | EACH | 2 | $7,000.00 | $5,500.00 | $9,500.00 | $6,000.00 | $3,115.00 | $2,950.00 |
| 0525 | Bench, relocate (0751-38-50) | EACH | 1 | $1,000.00 | $1,650.00 | $6,500.00 | $2,000.00 | $900.00 | $1,285.21 |
| 0530 | Partnering, DO not bid (0999-16) | LS | 1 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 |
| 0535 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $77,464 | $77,464 | $77,464 | $77,464 | $77,464 | $77,464 |
| 0540 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $3,068.27 | $3,068.27 | $3,068.27 | $3,068.27 | $3,068.27 | $3,068.27 |
| 0545 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 14 | $550.00 | $550.00 | $585.54 | $650.00 | $595.00 | $450.00 |
| 0550 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 2 | $1,500.00 | $1,980.00 | $1,850.46 | $3,200.00 | $2,850.00 | $1,300.00 |
| 0555 | Single column ground sign assembly, relocate (0700-1500) | EACH | 3 | $350.00 | $660.00 | $415.00 | $600.00 | $550.00 | $285.00 |
| 0560 | Single column ground sign assembly, remove (0700-1600) | EACH | 10 | $24.00 | $165.00 | $50.00 | $11.00 | $10.00 | $20.00 |
| 0565 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 1 | $350.00 | $275.00 | $373.54 | $300.00 | $185.00 | $300.00 |
| 0570 | Sign panel, furnish & install overhead mount, 51-100 SF (0700-3205) | EACH | 1 | $4,250.00 | $4,620.00 | $3,517.00 | $4,000.00 | $5,000.00 | $5,000.00 |
| 0575 | Sign panel, furnish & install overhead mount, 101-200 SF (0700-3206) | EACH | 1 | $8,000.00 | $7,150.00 | $6,365.00 | $7,000.00 | $12,000 | $12,000 |
| 0580 | Sign panel, furnish & install overhead mount, 201-300 SF (0700-3207) | EACH | 2 | $10,000 | $8,250.00 | $7,918.00 | $9,000.00 | $15,000 | $15,000 |
| 0585 | Sign panel, remove, 101-200 SF (0700-3606) | EACH | 1 | $650.00 | $2,750.00 | $537.00 | $900.00 | $800.00 | $1,875.00 |
| 0590 | Sign panel, remove, 201-300 SF (0700-3607) | EACH | 2 | $900.00 | $3,850.00 | $716.00 | $1,100.00 | $1,000.00 | $2,830.00 |
| 0595 | Overhead static sign furnish & install, cantilever, 30 FT (0700-4112) | EACH | 1 | $100,000 | $122,494 | $96,925 | $110,000 | $100,000 | $108,500 |
| 0600 | Overhead static sign furnish & install, span, 151-200 (0700-4127) | EACH | 1 | $325,000 | $358,808 | $310,219 | $340,000 | $313,027 | $329,527 |
| 0605 | Overhead static sign deep foundation removal, cantilever (0700-4612) | EACH | 1 | $4,000.00 | $13,750 | $3,225.00 | $3,500.00 | $15,000 | $15,000 |
| 0610 | Overhead static sign deep foundation removal, span (0700-4622) | EACH | 1 | $4,500.00 | $24,200 | $3,584.00 | $3,700.00 | $28,000 | $28,000 |
| 0615 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 4 | $300.00 | $121.00 | $251.43 | $132.00 | $120.00 | $120.00 |
| 0620 | Tubular marker, 36" yellow (0704-1-4) | EACH | 4 | $100.00 | $220.00 | $200.00 | $105.00 | $95.00 | $90.00 |
| 0625 | Raised pavement marker, type B (0706-1-3) | EACH | 572 | $5.00 | $5.50 | $7.00 | $5.50 | $5.00 | $4.00 |
| 0630 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 18 | $4.50 | $11.00 | $20.00 | $5.00 | $4.00 | $4.00 |
| 0635 | Painted pavement markings, surface (0710-90) | LS | 1 | $15,000 | $19,800 | $22,000 | $16,000 | $13,285 | $11,836 |
| 0640 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 2,945 | $3.50 | $2.20 | $4.00 | $3.30 | $3.00 | $3.04 |
| 0645 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 286 | $4.50 | $3.85 | $6.00 | $4.40 | $4.00 | $4.56 |
| 0650 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 313 | $6.00 | $4.40 | $8.00 | $5.50 | $5.00 | $6.08 |
| 0655 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.21 | $2,500.00 | $2,750.00 | $4,500.00 | $2,600.00 | $2,300.00 | $2,260.77 |
| 0660 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 6 | $145.00 | $176.00 | $250.00 | $130.00 | $120.00 | $79.00 |
| 0665 | Thermoplastic, standard, arrow (0711-11170) | EACH | 33 | $95.00 | $88.00 | $120.00 | $90.00 | $80.00 | $50.00 |
| 0670 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 34 | $4.50 | $3.85 | $7.00 | $5.00 | $4.00 | $4.15 |
| 0675 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 1,380 | $22.00 | $22.00 | $18.00 | $22.00 | $20.00 | $15.54 |
| 0680 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 11 | $275.00 | $495.00 | $250.00 | $285.00 | $260.00 | $200.00 |
| 0685 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 17 | $175.00 | $165.00 | $125.00 | $165.00 | $150.00 | $85.00 |
| 0690 | Thermoplastic, preformed, color route shield (0711-14660) | EACH | 4 | $3,500.00 | $3,850.00 | $3,500.00 | $3,400.00 | $3,020.00 | $1,887.00 |
| 0695 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 1.67 | $7,500.00 | $5,720.00 | $6,500.00 | $7,000.00 | $6,336.00 | $4,881.85 |
| 0700 | Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102) | GM | 0.20 | $10,500 | $8,800.00 | $7,000.00 | $7,000.00 | $6,600.00 | $6,469.65 |
| 0705 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 1.70 | $2,800.00 | $2,750.00 | $4,500.00 | $3,000.00 | $2,300.00 | $1,217.57 |
| 0710 | Thermoplastic, standard-other surfaces white, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-16133) | GM | 0.07 | $4,500.00 | $3,300.00 | $8,000.00 | $4,000.00 | $3,168.00 | $2,509.71 |
| 0715 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.73 | $7,500.00 | $5,720.00 | $6,500.00 | $7,000.00 | $6,336.00 | $4,495.32 |
| 0720 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 0.24 | $2,750.00 | $2,750.00 | $4,500.00 | $3,000.00 | $2,300.00 | $1,140.00 |
| 0725 | Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1) | SF | 355 | $9.50 | $5.50 | $10.00 | $9.00 | $10.00 | $3.88 |
| 0730 | Conduit, furnish & install, open trench (0630-2-11) | LF | 2,844 | $42.00 | $23.10 | $35.60 | $32.00 | $15.00 | $10.00 |
| 0735 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 1,331 | $42.00 | $39.60 | $35.60 | $32.00 | $42.00 | $30.00 |
| 0740 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 31 | $1,600.00 | $2,200.00 | $1,271.30 | $1,400.00 | $1,800.00 | $1,540.00 |
| 0745 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 1 | $10,000 | $5,940.00 | $8,274.10 | $9,000.00 | $7,000.00 | $5,781.50 |
| 0750 | Electrical service wire, & install (0639-2-1) | LF | 198 | $13.50 | $11.00 | $10.70 | $12.00 | $15.00 | $10.00 |
| 0755 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 1 | $3,250.00 | $3,184.50 | $2,625.90 | $3,000.00 | $3,500.00 | $3,036.00 |
| 0760 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 15,315 | $4.00 | $4.95 | $3.60 | $4.00 | $5.00 | $2.90 |
| 0765 | Lighting conductors, remove & dispose, contractor owns (0715-1-60) | LF | 6,833 | $0.12 | $2.20 | $0.10 | $0.20 | $1.00 | $0.30 |
| 0770 | Load center, rework, voltage (0715-7-21) | EACH | 1 | $3,500.00 | $23,100 | $3,431.10 | $3,700.00 | $15,000 | $5,878.00 |
| 0775 | Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211) | EACH | 6 | $2,000.00 | $1,980.00 | $1,636.30 | $1,900.00 | $1,500.00 | $1,929.50 |
| 0780 | Light pole complete, F&I, standard pole standard foundation, 30' mounting height, 0' arm length (0715-61100) | EACH | 9 | $7,000.00 | $11,683 | $6,035.60 | $6,600.00 | $12,000 | $6,648.00 |
| 0785 | Light pole complete, F&I, standard pole standard foundation, 50' mounting height, 15' arm length (0715-61552) | EACH | 10 | $9,000.00 | $14,135 | $8,212.80 | $8,500.00 | $12,500 | $9,892.50 |
| 0790 | Light pole complete, remove pole and foundation (0715-69000) | EACH | 9 | $550.00 | $2,750.00 | $537.70 | $600.00 | $1,000.00 | $632.50 |
| 0795 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 25 | $750.00 | $1,210.00 | $688.90 | $710.00 | $750.00 | $912.00 |
| 0800 | Conduit, furnish & install, open trench (0630-2-11) | LF | 283 | $55.00 | $23.10 | $49.00 | $54.00 | $20.00 | $10.00 |
| 0805 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 1,576 | $55.00 | $39.60 | $49.00 | $54.00 | $42.00 | $45.50 |
| 0810 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 3 | $11,000 | $11,550 | $10,959 | $12,000 | $15,000 | $2,535.00 |
| 0815 | Signal cable, remove- intersection (0632-7-6) | PI | 3 | $850.00 | $2,200.00 | $716.90 | $1,000.00 | $700.00 | $1,728.00 |
| 0820 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 58 | $1,350.00 | $1,760.00 | $1,284.60 | $1,400.00 | $1,800.00 | $1,540.00 |
| 0825 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 3 | $7,000.00 | $5,940.00 | $6,809.30 | $7,000.00 | $6,800.00 | $5,592.50 |
| 0830 | Electrical power service, F&I, underground, meter not required (0639-1123) | AS | 1 | $7,000.00 | $5,280.00 | $5,761.50 | $6,000.00 | $6,500.00 | $5,401.50 |
| 0835 | Electrical service wire, & install (0639-2-1) | LF | 1,074 | $9.00 | $11.00 | $8.10 | $9.00 | $10.00 | $10.00 |
| 0840 | Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60) | EACH | 1 | $600.00 | $1,980.00 | $537.70 | $600.00 | $1,000.00 | $742.50 |
| 0845 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 4 | $3,000.00 | $3,135.00 | $2,625.90 | $3,000.00 | $3,500.00 | $3,000.00 |
| 0850 | Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60) | EACH | 2 | $800.00 | $2,750.00 | $716.90 | $800.00 | $500.00 | $1,089.00 |
| 0855 | Aluminum signals pole, (0646-1-11) | EACH | 6 | $2,100.00 | $2,750.00 | $2,068.70 | $2,200.00 | $2,000.00 | $2,985.00 |
| 0860 | Aluminum signals pole, remove (0646-1-60) | EACH | 4 | $600.00 | $1,650.00 | $537.70 | $600.00 | $250.00 | $268.00 |
| 0865 | Steel mast arm assembly, and install, single arm 78' (0649-21-21) | EACH | 2 | $90,000 | $112,750 | $83,573 | $90,000 | $100,000 | $98,104 |
| 0870 | Steel mast arm assembly, remove, shallow foundation- bolt on attachment (0649-26-3) | EACH | 2 | $3,500.00 | $7,150.00 | $3,225.80 | $3,500.00 | $5,500.00 | $5,302.50 |
| 0875 | Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14) | AS | 10 | $1,500.00 | $2,200.00 | $1,323.50 | $1,500.00 | $2,200.00 | $1,781.50 |
| 0880 | Vehicular traffic signal, furnish & install aluminum, 5 section straight, 1 way (0650-1-18) | AS | 1 | $2,250.00 | $3,080.00 | $2,000.70 | $2,200.00 | $2,500.00 | $2,347.50 |
| 0885 | Vehicular traffic signal, furnish & install aluminum, 5 section cluster, 1 way (0650-1-19) | AS | 1 | $2,500.00 | $3,080.00 | $2,280.40 | $2,400.00 | $2,500.00 | $2,751.50 |
| 0890 | Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109) | EACH | 29 | $500.00 | $1,045.00 | $406.20 | $450.00 | $800.00 | $558.00 |
| 0895 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 6 | $800.00 | $2,090.00 | $745.20 | $800.00 | $1,800.00 | $1,026.50 |
| 0900 | Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12) | AS | 1 | $1,600.00 | $3,080.00 | $1,554.30 | $1,700.00 | $2,000.00 | $1,649.50 |
| 0905 | Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60) | AS | 1 | $100.00 | $1,100.00 | $89.60 | $100.00 | $500.00 | $179.00 |
| 0910 | Vehicle detection system- furnish & install cabinet equipment (0660-4-11) | EACH | 5 | $3,500.00 | $11,000 | $3,127.90 | $3,300.00 | $5,000.00 | $11,552 |
| 0915 | Vehicle detection system- furnish & install above ground equipment (0660-4-12) | EACH | 5 | $10,000 | $9,020.00 | $9,251.80 | $10,000 | $7,500.00 | $5,536.00 |
| 0920 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 8 | $350.00 | $594.00 | $320.40 | $350.00 | $800.00 | $533.50 |
| 0925 | Pedestrian detector, remove- pole/pedestal to remain (0665-1-60) | EACH | 1 | $100.00 | $275.00 | $89.60 | $100.00 | $200.00 | $66.00 |
| 0930 | Traffic controller, modify (0671-2-40) | EACH | 3 | $7,000.00 | $5,060.00 | $6,554.80 | $7,000.00 | $40,000 | $4,770.50 |
| 0935 | Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201) | EACH | 3 | $800.00 | $550.00 | $725.50 | $800.00 | $800.00 | $902.50 |
| 0940 | Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22) | EACH | 2 | $3,500.00 | $5,280.00 | $3,098.90 | $3,300.00 | $4,200.00 | $3,602.50 |
| 0945 | Manhole, adjust, utilities (0425-5-1) | EACH | 7 | $950.00 | $1,045.00 | $1,150.00 | $1,000.00 | $1,200.00 | $600.00 |
| 0950 | Valve boxes, adjust (0425-6) | EACH | 13 | $900.00 | $935.00 | $950.00 | $700.00 | $750.00 | $450.00 |
| 0955 | Local agency initial amount (DO not bid) (0999-26) | LS | 1 | $7,963.25 | $7,963.25 | $7,963.25 | $7,963.25 | $7,963.25 | $7,963.25 |
| 0960 | Utility pipe,plug & place out of service, 20-49.9" (1050-18005) | LF | 2,151 | $5.00 | $44.00 | $15.00 | $55.00 | $63.52 | $3.30 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of August 27, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.