ODOT contract 250411 bid tabulation

HAM-CR 270-02.96 Miami Ave (MINOR RECONSTRUCTION). Let by Ohio DOT on September 11, 2025, HAM. 5 bids received; low bid $5,460,521 by Ford Development Corp, +34% against the engineer's estimate of $4,076,000.

Owner
Ohio DOT
Letting
11 SEP 2025
Pay items
150
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Ford Development Corp$5,460,521Low+34%
2Prus Construction Company$5,644,975+3.0%+38%
3Sunesis Construction Co$5,774,919+6.0%+42%
4Barrett Paving Materials Inc$6,371,806+17%+56%
5John R Jurgensen Company$6,429,484+18%+58%
ODOT contract 250411: bids by rank

Engineer's estimate: $4,076,000.

Bid tabulation

LinePay itemUnitQuantity1. Ford Development Corp2. Prus Construction Company3. Sunesis Construction Co4. Barrett Paving Materials Inc5. John R Jurgensen Company
1Clearing and grubbing (201E11000)LS1$30,000$3,000.00$18,603$25,000$17,975
2Structure removed (202E11004)EACH1$20,000$2,500.00$1,847.91$1,500.00$1,629.03
3Pavement removed (202E23000)SY7,331$50.00$21.00$38.18$36.00$22.61
4Walk removed (202E30000)SF37,354$5.00$3.50$7.66$2.50$4.45
5Curb removed (202E32000)FT4,214$10.00$16.00$9.95$12.00$8.78
6Pipe removed, 24" and under (202E35100)FT145$1.00$40.00$29.37$65.00$127.52
7Pipe removed, over 24" diameter (202E35200)FT65$1.00$68.00$31.65$75.00$169.26
8Guard post removed (202E38800)EACH2$100.00$135.00$76.92$100.00$476.35
9Manhole removed (202E58000)EACH2$250.00$2,400.00$1,660.40$1,200.00$1,413.64
10Catch basin removed (202E58100)EACH16$250.00$675.00$641.89$800.00$1,413.64
11Fence removed (202E75000)FT34$10.00$38.00$12.48$6.00$23.95
12Excavation (203E10000)CY78$50.00$45.00$71.09$115.00$95.16
13Embankment (203E20000)CY36$70.00$75.00$34.24$150.00$85.13
14Granular material, type C (204E30020)CY2,320$70.00$72.00$109.29$115.00$123.53
15Roadway, misc.:sewer cleanout adjusted to grade (203E98600)EACH2$250.00$625.00$485.74$1,500.00$2,313.28
16Subgrade compaction (204E10000)SY5,283$3.00$2.50$3.86$5.00$4.40
17Excavation of subgrade (204E13000)CY2,320$15.00$37.50$84.04$80.00$76.92
18Proof rolling (204E45000)HR8$125.00$150.00$332.95$2,000.00$300.71
19Curb ramp (608E52000)SF2,770$30.00$18.00$22.36$25.00$23.73
20Curb ramp, as per plan (608E52001)SF678$30.00$15.00$29.63$25.00$23.80
21Detectable warning, as per plan (608E53021)SF520$65.00$70.00$65.00$70.00$65.00
22Walkway, misc.:brick pavers, driveway (608E98000)SF7,594$41.00$50.00$47.66$50.00$54.16
23Walkway, misc.:brick pavers, walk (608E98000)SF43,086$34.50$38.00$34.23$40.00$41.35
24Pull box removed (625E31510)EACH44$412.00$335.00$375.00$350.00$300.00
25Light pole removed (625E75400)EACH29$742.00$725.00$675.00$1,000.00$650.00
26Special - consultant for concrete quaility contro (690E98400)LS1$70,000$75,000$28,600$40,000$25,691
27Topsoil (659E00300)CY27$100.00$70.00$184.34$100.00$115.61
28Seeding and mulching (659E10000)SY249$5.00$2.50$16.54$6.50$6.50
29Repair seeding and mulching (659E14000)SY12$1.00$10.00$5.00$6.50$6.50
30Inter-seeding (659E15000)SY12$1.00$10.00$5.00$4.00$4.00
31Commercial fertilizer (659E20000)TON0.03$100.00$2,500.00$5,000.00$2,000.00$2,000.00
32Lime (659E31000)ACRE0.05$100.00$6,000.00$2,500.00$600.00$600.00
33Water (659E35000)MGAL1.40$100.00$125.00$1.39$10.00$10.00
34Mowing (659E40000)MSF0.60$3.00$500.00$1,000.00$580.00$580.00
35Storm water pollution prevention plan (832E15000)LS1$3,500.00$2,950.00$2,635.00$18,500$2,635.00
36Storm water pollution prevention inspections (832E15002)LS1$10,000$21,000$14,981$25,000$17,460
37Storm water pollution prevention inspection software (832E15010)LS1$5,000.00$22,000$19,526$20,000$19,526
38Erosion control (832E30000)EACH35,065$1.00$1.00$1.00$1.00$1.00
396" base pipe underdrains (605E14000)FT2,920$10.00$42.00$26.72$32.00$39.84
406" conduit, type F for underdrain outlets (611E00510)FT240$15.00$46.25$65.47$50.00$60.81
418" conduit, type B (611E01800)FT12$145.00$225.00$177.18$145.00$178.04
4212" conduit, type B (611E04400)FT882$160.00$185.00$197.43$225.00$123.09
4318" conduit, type B (611E07400)FT29$170.00$270.00$201.84$360.00$220.52
4424" conduit, type B (611E10400)FT44$180.00$380.00$355.64$380.00$435.76
4530" conduit, type B (611E13400)FT16$200.00$675.00$464.17$525.00$672.38
46Catch basin, no. 3 (611E98150)EACH5$7,000.00$5,800.00$4,999.59$7,500.00$3,987.87
47Catch basin, no. 3A (611E98180)EACH11$6,000.00$5,225.00$3,675.82$6,000.00$3,925.35
48Catch basin, no. 3A, as per plan (611E98181)EACH4$7,500.00$11,000$7,262.87$11,000$5,540.62
49Catch basin, no. 6 (611E98370)EACH4$6,000.00$4,500.00$3,207.22$6,000.00$3,152.79
50Catch basin, no. 2-2C (611E98504)EACH1$3,000.00$4,700.00$2,954.31$4,500.00$4,529.34
51Catch basin adjusted to grade (611E98630)EACH3$1,000.00$1,050.00$694.65$1,250.00$1,488.92
52Manhole, no. 3 (611E99574)EACH1$6,000.00$8,100.00$5,043.07$6,250.00$4,705.83
53Manhole adjusted to grade (611E99654)EACH36$1,000.00$800.00$687.27$1,500.00$1,636.59
55Pavement planing, asphalt concrete, 3" (254E01000)SY6,531$13.75$14.00$8.06$12.00$12.50
56Asphalt concrete base, PG64-22, (449) (301E56000)CY931$341.00$347.00$310.00$350.00$310.00
57Aggregate base (304E20000)CY1,000$100.00$128.00$166.65$150.00$155.87
58Non-tracking tack coat (407E20000)GAL1,698$5.50$6.00$5.00$3.50$5.00
59Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY424$325.00$330.00$424.00$340.00$295.00
60Asphalt concrete intermediate course, type 2, (449) (441E70300)CY591$380.00$386.00$345.00$380.00$345.00
617" non-reinforced concrete pavement, class QC 1P (452E11010)SY67$150.00$185.00$101.11$92.00$104.55
62Curb, type 6 (609E26000)FT3,696$37.50$35.00$31.57$30.00$32.95
63Fire hydrant extended and adjusted to grade (638E10300)EACH8$9,000.00$875.00$1,692.03$2,500.00$2,540.41
64Valve box adjusted to grade (638E10800)EACH52$100.00$250.00$153.82$750.00$1,112.97
65Special - cut and plug existing 16" water line, PE (638E20886)EACH14$1,500.00$2,000.00$2,952.64$5,000.00$4,920.60
66Ground mounted support, no. 3 post (630E03100)FT408$16.00$16.25$17.91$18.00$17.91
67Sign post reflector (630E08600)EACH2$60.00$61.50$72.90$73.00$72.90
68Sign, flat sheet (630E80100)SF182$18.00$18.00$20.73$21.00$20.73
69Sign, double faced, street name (630E80500)EACH6$135.00$140.00$177.45$177.50$177.45
70Removal of ground mounted sign and disposal (630E84900)EACH39$11.00$11.50$17.02$18.00$17.02
71Removal of ground mounted post support and disposal (630E86002)EACH25$16.00$17.00$22.70$22.70$22.70
72Signing, misc.: solar powered rectangular rapid FL (630E97700)EACH2$7,828.00$8,800.00$7,117.50$7,800.00$7,800.00
73Removal of pavement marking (642E30000)FT775$6.60$6.75$1.70$1.70$1.70
74Removal of pavement marking (642E30020)EACH9$70.00$72.00$145.00$145.00$145.00
75Edge line, 4" (644E00100)MI0.11$4,229.00$4,300.00$5,335.00$5,500.00$5,335.00
76Lane line, 4" (644E00200)MI0.06$1,793.00$1,825.00$1,415.00$1,450.00$1,415.00
77Center line (644E00300)MI0.74$6,512.00$6,650.00$8,445.00$8,500.00$8,445.00
78Channelizing line, 8" (644E00400)FT908$2.40$2.50$1.50$4.25$1.50
79Stop line (644E00500)FT385$8.10$8.25$4.50$4.50$4.50
80Crosswalk line, 24" (644E00630)FT1,238$6.50$6.75$4.25$4.25$4.25
81Transverse/diagonal line (644E00700)FT150$8.10$8.25$4.25$4.25$4.25
82Island marking (644E00900)SF51$5.00$5.00$4.00$4.00$4.00
83Railroad symbol marking (644E01000)EACH2$566.00$575.00$450.00$450.00$450.00
84School symbol marking, 120" (644E01120)EACH1$407.00$425.00$500.00$500.00$500.00
85Parking lot stall marking (644E01200)FT64$3.25$3.50$3.50$3.50$3.50
86Lane arrow (644E01300)EACH27$132.00$135.00$100.00$100.00$100.00
87Dotted line, 4" (644E01500)FT107$3.25$3.50$1.25$1.25$1.25
88Yield line (644E20800)FT20$41.00$45.00$5.50$5.50$5.50
89Pavement marking, misc.:DO not block intersection (644E50200)SF1,732$3.25$3.50$4.00$4.00$4.00
90Conduit, 2", 725.051 (625E25408)FT118$1.40$17.00$1.25$15.00$15.00
91Conduit, 3", 725.051 (625E25504)FT42$2.60$22.50$2.39$20.00$20.00
92Conduit, 4", 725.051 (625E25604)FT8$3.65$28.00$3.30$25.00$25.00
93Conduit, jacked or drilled, 725.052, 4" (625E25908)FT145$71.50$65.00$65.00$58.00$58.00
94Conduit, misc.: bore and jack under railroad (625E25920)FT55$71.50$168.00$209.50$150.00$150.00
95Trench in paved area (625E29400)FT118$30.00$45.00$27.00$40.00$40.00
96Pull box, 725.06, size 4 (625E30510)EACH2$817.00$1,050.00$742.50$925.00$925.00
97Pull box, 725.06, size 7 (625E30520)EACH3$893.00$1,275.00$811.50$1,150.00$1,150.00
98Pull box, 725.06, size 18 (625E30530)EACH1$1,558.00$2,350.00$1,416.00$2,100.00$2,100.00
99Ground rod (625E32000)EACH7$137.50$308.00$125.00$305.00$275.00
100Underground warning marking tape (625E36010)FT118$2.20$3.50$2.00$3.00$3.00
101Sign hanger assembly, mast arm (630E79100)EACH2$242.00$560.00$220.00$750.00$696.61
102Sign, flat sheet (630E80100)SF15$250.00$252.00$29.42$30.00$29.42
103Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate, as per plan (632E05007)EACH4$1,320.00$2,184.00$1,200.00$1,950.00$1,950.00
104Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731)EACH2$550.00$980.00$500.00$875.00$875.00
105Accessible pedestrian pushbutton, as per plan (632E20751)EACH2$742.50$1,008.00$675.00$900.00$900.00
106Signal cable, 2 conductor, no. 14 AWG (632E40200)FT155$0.65$2.25$0.59$2.00$2.00
107Signal cable, 5 conductor, no. 14 AWG (632E40500)FT543$1.40$3.50$1.25$3.00$3.00
108Signal support foundation (632E64010)EACH2$4,400.00$8,400.00$4,000.00$7,500.00$7,500.00
109Pedestal foundation (632E64020)EACH3$1,485.00$1,568.00$1,350.00$1,400.00$1,400.00
110Power cable, 2 conductor, no. 6 AWG (632E68200)FT30$2.40$11.25$2.20$10.00$10.00
111Service cable, 2 conductor, no. 4 AWG (632E69600)FT100$4.00$11.25$3.61$10.00$10.00
112Power service, as per plan (632E70001)EACH1$4,180.00$2,800.00$3,800.00$2,500.00$2,500.00
113Signal support, type TC-81.22, design 4, as per plan (632E72111)EACH2$21,120$20,000$19,200$17,900$17,900
114Signal support, misc.: signal pole decorative clam (632E80700)EACH2$3,439.00$3,250.00$3,126.00$2,900.00$2,900.00
115Pedestal, 8', transformer base, as per plan (632E89901)EACH1$1,375.00$1,100.00$1,250.00$975.00$975.00
116Removal of traffic signal installation (632E90100)EACH1$8,800.00$560.00$8,000.00$500.00$500.00
117Cabinet, type TS-2, as per plan (633E65511)EACH1$18,150$18,000$16,500$15,850$15,850
118Cabinet foundation (633E67100)EACH1$3,025.00$3,250.00$2,750.00$2,911.50$2,911.50
119Uninterruptible power supply (UPS), 1000 watt, as per plan (633E75001)EACH1$8,250.00$8,500.00$7,500.00$7,661.50$7,661.50
120Atc controller, as per plan (809E69123)EACH1$6,000.00$6,725.00$5,500.00$6,000.00$6,000.00
121Railroad preemption interface, miami avenue crossi (819E10000)EACH1$13,750$16,000$12,500$14,000$13,944
122Planting, misc.: trees (661E99900)EACH44$5,800.00$6,275.00$6,705.03$7,000.00$6,327.34
123Law enforcement officer with patrol car for assistance (614E11110)HR16$100.00$135.00$95.00$85.00$167.80
124Detour signing (614E12420)LS1$4,000.00$3,150.00$8,644.99$7,500.00$2,815.00
125Work zone lane line, class III, 4", 642 paint (614E20550)MI0.06$607.00$618.00$675.00$675.00$675.00
126Work zone center line, class I (614E21000)MI0.45$1,366.00$1,400.00$2,200.00$220.00$2,200.00
127Work zone center line, class III, 642 paint (614E21550)MI0.74$1,366.00$1,400.00$1,900.00$1,900.00$1,900.00
128Work zone edge line, class I, 4" (614E22000)MI0.67$910.00$928.00$1,530.00$1,600.00$1,530.00
129Work zone edge line, class III, 4", 642 paint (614E22350)MI0.12$910.00$928.00$1,230.00$1,250.00$1,230.00
130Work zone channelizing line, class I, 8" (614E23000)FT145$0.93$1.00$0.75$0.75$0.75
131Work zone channelizing line, class III, 8", 642 paint (614E23680)FT919$0.93$1.00$0.70$0.70$0.70
132Work zone dotted line, class I (614E24000)FT220$0.77$1.00$0.65$0.65$0.65
133Work zone dotted line, class III, 4", 642 paint (614E24610)FT107$0.77$1.00$0.60$0.60$0.60
134Work zone transverse/diagonal line, class III, 642 paint (614E25620)FT150$1.50$1.50$3.20$3.20$3.20
135Work zone stop line, class I (614E26000)FT150$3.80$4.00$3.50$3.50$3.50
136Work zone stop line, class III, 642 paint (614E26610)FT367$3.80$4.00$3.45$3.50$3.45
137Work zone crosswalk line, class I, 12" (614E27010)FT373$1.87$2.00$3.00$3.00$3.00
138Work zone crosswalk line, class III, 24", 642 paint (614E27260)FT1,371$3.80$4.00$2.95$3.00$2.95
139Work zone arrow, class I (614E30000)EACH4$45.00$46.50$75.00$75.00$75.00
140Work zone arrow, class III, 642 paint (614E30650)EACH27$45.00$46.50$70.00$70.00$70.00
141Work zone railroad symbol marking, class I (614E32000)EACH3$148.00$155.00$300.00$300.00$300.00
142Work zone island marking, class III, 642 paint (614E32800)SF51$3.00$3.10$2.95$3.00$2.95
143Business entrance sign (614E40050)EACH17$250.00$325.00$214.42$250.00$214.42
144Water (616E10000)MGAL6$1.00$200.00$65.32$50.00$100.39
145Premium on railroads' protective public liability and property damage liability insurance (100E00300)LS1$10,000$5,000.00$8,731.96$5,000.00$5,000.00
146Premium for contract performance bond and for payment bond (103E05000)LS1$54,000$82,000$27,469$20,000$53,486
147Maintaining traffic (614E11000)LS1$115,000$125,000$179,000$300,000$422,098
148Construction layout stakes and surveying (623E10000)LS1$32,000$28,000$29,850$75,000$30,961
149Mobilization (624E10000)LS1$200,000$150,000$200,431$200,000$320,000
200Geotextile fabric (204E50000)SY5,283$1.00$6.25$1.45$3.00$4.47
201Inspection and compaction testing of unbound materials (878E25000)LS1$41,000$58,000$29,494$50,000$64,808
ODOT contract 250411: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of September 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy