TDOT contract CN264004 bid tabulation

The construction of a concrete bulb-tee beam bridge on s.r. 180 over lost creek (l.m. 4.75) and a concrete box beam bridge over overflow (l.m. 4.57), including grading, drainage, and paving. Let by Tennessee DOT on February 6, 2026, Haywood County. 3 bids received; low bid $2,284,348 by Ford Construction Company.

Owner
Tennessee DOT
Letting
06 FEB 2026
Pay items
76
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Ford Construction Company$2,284,348Low
2Dement Construction Group, LLC$2,752,259+20%
3Bell & Associates Construction, LLC$3,564,548+56%
TDOT contract CN264004: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Ford Construction Company2. Dement Construction Group, LLC3. Bell & Associates Construction, LLC
1Construction stakes, lines and grades (105-01)LS1$21,000$65,000$14,370
2Clearing and grubbing (201-01)LS1$15,000$60,000$93,093
3Road & drainage excavation (unclassified) (203-01)CY2,219$12.00$18.00$40.00
4Borrow excavation (unclassified) (203-03)CY5,504$12.00$23.00$50.00
5Placing and spreading topsoil (203-04)CY708$3.50$19.00$32.00
6Water (203-06)MG7$35.00$10.00$55.00
7Sediment removal (209-05)CY126$25.00$10.00$30.00
8Temporary silt fence (with backing) (209-08.02)LF8,498$3.40$3.40$6.00
9Rock check dam (209-08.07)EACH4$900.00$900.00$1,200.00
10Enhanced rock check dam (209-08.08)EACH2$1,030.00$1,200.00$1,400.00
11Temporary diversion channel (209-65.03)LF192$15.00$40.00$450.00
12Mineral aggregate, type A base, grading D (303-01)TON1,450$53.00$50.00$70.00
13Mineral aggregate (size 57) (303-10.01)TON1,058$61.50$55.00$75.00
14Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01)TON742$160.00$160.00$178.00
15Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON542$170.00$170.00$189.00
16Bituminous material for prime coat (PC) (402-01)TON8$200.00$200.00$222.00
17Aggregate for cover material (PC) (402-02)TON26$5.00$5.00$5.00
18Bituminous material for tack coat (TC) (403-01)TON4$1,000.00$1,000.00$1,110.00
19Saw cutting asphalt pavement (407-20.05)LF524$12.00$12.00$10.00
20Acs mix(PG64-22) grading D (411-01.10)TON344$180.00$180.00$200.00
21Scoring for rumble stripe (non-continuous) (8IN width) (411-12.03)LM0.60$14,955$14,955$20,807
22Cold planing bituminous pavement (415-01.02)SY409$45.00$35.00$27.00
23W beam GR (type 2) MASH TL-3 (705-06.01)LF350$31.00$29.25$34.50
24Tangent energy absorbing term MASH TL-3 (705-06.20)EACH8$3,250.00$3,100.00$3,607.00
25Thrie beam agt (long span) MASH TL-3 (705-06.28)EACH8$6,150.00$5,000.00$6,825.00
26Guardrail removed (706-01)LF537$3.00$1.00$1.00
27High-visibility construction fence (707-08.11)LF1,730$2.25$2.25$3.50
28Markers (concrete R.O.W. posts) (708-02.01)EACH20$350.00$500.00$300.00
29Machined rip-rap (class A-3) (709-05.05)TON200$60.00$45.00$50.00
30Machined rip-rap (class A-1) (709-05.06)TON503$60.00$55.00$90.00
31Machined rip-rap (class B) (709-05.08)TON975$60.00$55.00$80.00
32Traffic control (712-01)LS1$27,000$25,000$15,163
33Warning lights (type A) (712-05.01)EACH6$25.00$19.00$28.00
34Signs (construction) (712-06)SF709$7.50$9.00$8.50
35Temporary barricades (type III) (712-07.03)LF80$12.00$14.00$13.00
36Class A concrete (foundation for sign supports) (713-01.01)CY1$750.00$600.00$832.00
37Steel bar reinforcement(foundation for sign supports) (713-01.02)LB194$3.25$3.00$3.50
38Steel I-beams & WF-beams(breakaway) sign support (713-06)LB408$9.20$10.00$17.00
39Perforated/knockout square tube post (713-11.02)LB261$4.65$4.50$5.00
40P post slip base (713-11.21)EACH5$520.00$500.00$577.00
41Flat sheet aluminum signs (0.080" thick) (713-13.02)SF3$16.00$15.00$18.00
42Flat sheet aluminum signs (0.100" thick) (713-13.03)SF116$16.85$15.00$18.00
43Removal of signs, posts and footings (713-15)LS1$250.00$500.00$277.00
44Changeable message sign unit (713-16.01)EACH3$2,000.00$5,000.00$5,771.00
45Raised PVMT markers (BI-directional) (1 color lens) (716-01.11)EACH29$30.00$30.00$33.00
46Removal of snowplowable reflective marker (716-01.30)EACH7$35.00$100.00$10.00
47Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM1.60$12,500$12,500$13,872
48Mobilization (717-01)LS1$80,000$246,742$356,454
49Geogrid reinforcement type 2 (740-07.04)SY489$30.00$6.00$7.00
50Geotextile (type III)(erosion control) (740-10.03)SY514$5.00$3.00$4.00
51Geotextile (type IV)(stabilization) (740-10.04)SY540$4.00$6.00$6.00
52Seeding (with mulch) (801-01)UNIT84$50.00$50.00$83.00
53Temporary seeding (with mulch) (801-01.07)UNIT84$40.00$40.00$67.00
54Fertilizer (801-02.15)TON2$1,500.00$1,500.00$833.00
55Water (seeding & sodding) (801-03)MG59$50.00$50.00$22.00
56Sodding (new sod) (803-01)SY4,166$3.25$3.25$8.50
57Erosion control blanket (type I) (805-12.01)SY200$2.50$2.50$8.00
58Removal of asbestos (202-01.02)LS1$10,000$25,000$15,000
59Removal of structures (exist. bridge no. 38-SR180-0457) (202-04.02)LS1$5,000.00$70,000$23,500
60Removal of structures (superstructure) (202-04.01)LS1$8,000.00$70,000$35,000
61Dry excavation (bridges) (204-02.01)CY273$18.00$28.00$50.00
62Granular backfill (bridges) (303-01.02)TON82$77.00$77.00$55.00
63Epoxy coated reinforcing steel (604-02.03)LB53,256$1.74$2.00$1.75
64Class A concrete (bridges) (604-03.01)CY148$926.00$1,300.00$1,200.00
65Steel bar reinforcement (bridges) (604-03.02)LB22,726$1.64$1.75$1.50
66Pavement @ bridge ends (604-03.04)SY302$372.00$400.00$500.00
67Class D concrete (bridge deck) (604-03.09)CY184$1,200.00$1,300.00$1,400.00
68Applied texture finish (new structures) (604-04.01)SY961$15.99$16.00$18.00
69Bridge deck grooving (mechanical) (604-05.31)SY802$7.70$8.00$8.50
70Test piles (steel pipe piles, 14-inch) (606-18.01)LF379$133.00$127.00$150.00
71Loading test (steel pipe piles, 14-inch) (606-18.02)EACH3$7,000.00$6,500.00$17,100
72Steel pipe piles (14-inch) (606-18.03)LF3,273$118.00$93.00$157.00
73Erection of bridge beams (615-01.20)LS1$53,000$50,000$110,000
74Conc parapet single slope (STD-1-1SS) (620-05.01)LF508$170.00$175.00$160.00
756" perforated pipe with vertical drain system (710-09.01)LF248$26.00$44.00$80.00
766" pipe underdrain (710-09.02)LF68$15.00$17.00$37.00
TDOT contract CN264004: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of February 6, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy