TDOT contract CN264042 bid tabulation
The grading, drainage, and paving on u.s. 51 (s.r. 3) from north of myron creek (l.m. 7.00) to south of old hwy 51 south (l.m. 8.00). Let by Tennessee DOT on June 26, 2026, Tipton County. 3 bids received; low bid $2,022,557 by Ford Construction Company.
- Owner
- Tennessee DOT
- Letting
- 26 JUN 2026
- Pay items
- 75
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ford Construction Company | $2,022,557 | Low |
| 2 | Delta Contracting Company, LLC | $2,107,179 | +4.0% |
| 3 | VuCon, LLC | $2,552,172 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ford Construction Company | 2. Delta Contracting Company, LLC | 3. VuCon, LLC |
|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $30,000 | $25,000 | $100,000 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $100,000 | $296,250 | $150,000 |
| 3 | Removal of pipe (24",sta. 135+43.83 LT.) (202-02.01) | LF | 59 | $35.00 | $17.50 | $38.00 |
| 4 | Removal of pipe (12" ,sta. 153+06.13 C.) (202-02.02) | LF | 41 | $35.00 | $17.50 | $38.00 |
| 5 | Removal of pipe (24",sta. 153+10.84 LT.) (202-02.03) | LF | 40 | $35.00 | $17.50 | $38.00 |
| 6 | Road & drainage excavation (unclassified) (203-01) | CY | 7,524 | $22.00 | $24.00 | $30.00 |
| 7 | Placing and spreading topsoil (203-04) | CY | 1,406 | $14.00 | $24.00 | $8.00 |
| 8 | Undercutting (203-05) | CY | 27 | $35.00 | $50.00 | $38.00 |
| 9 | Water (203-06) | MG | 27 | $20.00 | $56.00 | $125.00 |
| 10 | Brooming & degrassing shoulders (208-01.05) | LM | 1.48 | $2,600.00 | $1,750.00 | $3,000.00 |
| 11 | Sediment removal (209-05) | CY | 51 | $32.00 | $17.00 | $190.00 |
| 12 | Temporary silt fence (with backing) (209-08.02) | LF | 160 | $5.50 | $5.00 | $7.00 |
| 13 | Temporary silt fence (without backing) (209-08.03) | LF | 1,515 | $2.00 | $2.40 | $3.00 |
| 14 | Enhanced rock check dam (209-08.08) | EACH | 4 | $1,100.00 | $1,825.00 | $1,600.00 |
| 15 | Mineral aggregate, type A base, grading D (303-01) | TON | 3,600 | $73.00 | $77.50 | $70.00 |
| 16 | Mineral aggregate, type B base, grading (C or D) (303-02) | TON | 100 | $70.00 | $58.00 | $85.00 |
| 17 | Mineral aggregate (size 57) (303-10.01) | TON | 20 | $72.00 | $53.00 | $190.00 |
| 18 | Asp. conc. mix(PG70-22) (BPMB-HM) GR. A-S (307-01.21) | TON | 516 | $202.50 | $202.50 | $255.00 |
| 19 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01) | TON | 560 | $195.35 | $195.35 | $250.00 |
| 20 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08) | TON | 532 | $196.00 | $196.00 | $250.00 |
| 21 | Bituminous material for prime coat (PC) (402-01) | TON | 8 | $1,365.00 | $1,365.00 | $1,700.00 |
| 22 | Aggregate for cover material (PC) (402-02) | TON | 26 | $58.00 | $58.00 | $75.00 |
| 23 | Trackless tack coat (403-02.01) | TON | 11 | $1,365.00 | $1,365.00 | $1,700.00 |
| 24 | Saw cutting asphalt pavement (407-20.05) | LF | 2,380 | $8.00 | $2.85 | $10.00 |
| 25 | Acs mix(PG70-22) grading D (411-02.10) | TON | 1,152 | $198.00 | $198.00 | $250.00 |
| 26 | Scoring shoulders (non-continuous) (16IN width) (411-12.02) | LM | 1.39 | $6,400.00 | $5,025.00 | $4,500.00 |
| 27 | Cold planing bituminous pavement (415-01.01) | TON | 803 | $55.85 | $55.85 | $50.00 |
| 28 | 18" concrete pipe culvert (class III) (607-03.02) | LF | 68 | $115.00 | $80.00 | $88.00 |
| 29 | 24" pipe culvert (side drain) (607-39.03) | LF | 106 | $145.00 | $60.00 | $110.00 |
| 30 | 24IN endwall (side drain) (611-07.32) | EACH | 4 | $6,500.00 | $6,500.00 | $6,000.00 |
| 31 | 18IN endwall (median drain) (611-07.73) | EACH | 2 | $10,500 | $6,000.00 | $4,500.00 |
| 32 | 18" temporary drainage pipe (621-03.02) | LF | 36 | $88.00 | $56.00 | $88.00 |
| 33 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 525 | $32.50 | $32.50 | $41.00 |
| 34 | W beam GR (type 2) MASH TL-3 (long post) (705-06.02) | LF | 1,038 | $35.50 | $35.50 | $41.00 |
| 35 | GR terminaltrailing end (type 13) MASH TL-3 (705-06.10) | EACH | 3 | $1,350.00 | $1,350.00 | $1,700.00 |
| 36 | Tangent energy absorbing term MASH TL-3 (705-06.20) | EACH | 3 | $3,300.00 | $3,300.00 | $4,100.00 |
| 37 | Removal and reset fence (property line fence) (707-06.03) | LF | 500 | $22.00 | $26.00 | $100.00 |
| 38 | High-visibility construction fence (707-08.11) | LF | 760 | $3.00 | $2.50 | $4.00 |
| 39 | Markers (concrete R.O.W. posts) (708-02.01) | EACH | 12 | $320.00 | $600.00 | $630.00 |
| 40 | Machined rip-rap (class A-3) (709-05.05) | TON | 100 | $79.00 | $75.00 | $90.00 |
| 41 | Machined rip-rap (class A-1) (709-05.06) | TON | 84 | $78.00 | $75.00 | $90.00 |
| 42 | Aggregate underdrains (with pipe) (710-02) | LF | 1,575 | $14.50 | $14.50 | $32.00 |
| 43 | Lateral underdrain (710-05) | LF | 135 | $14.00 | $14.00 | $28.00 |
| 44 | Lateral underdrain endwall (4:1) (710-06.13) | EACH | 8 | $1,100.00 | $1,100.00 | $1,900.00 |
| 45 | Traffic control (712-01) | LS | 1 | $60,000 | $34,200 | $50,000 |
| 46 | Interconnected portable barrier rail (712-02.02) | LF | 4,280 | $36.00 | $5.20 | $50.00 |
| 47 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 3 | $7,000.00 | $6,800.00 | $8,800.00 |
| 48 | Flexible drums (channelizing) (712-04.01) | EACH | 100 | $35.00 | $32.00 | $44.00 |
| 49 | Barrier rail delineator (712-04.50) | EACH | 215 | $11.27 | $10.00 | $13.00 |
| 50 | Warning lights (type C) (712-05.03) | EACH | 75 | $8.00 | $15.00 | $10.00 |
| 51 | Signs (construction) (712-06) | SF | 296 | $7.00 | $6.10 | $9.00 |
| 52 | Arrow board (type C) (712-08.03) | EACH | 2 | $1,050.00 | $815.00 | $1,300.00 |
| 53 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 4,455 | $7.00 | $7.00 | $9.00 |
| 54 | Perforated/knockout square tube post (713-11.02) | LB | 864 | $5.00 | $3.75 | $6.00 |
| 55 | Flat sheet aluminum signs (0.080" thick) (713-13.02) | SF | 268 | $18.00 | $12.00 | $23.00 |
| 56 | Removal of signs, posts and footings (713-15) | LS | 1 | $200.00 | $500.00 | $6,300.00 |
| 57 | Changeable message sign unit (713-16.01) | EACH | 2 | $9,150.00 | $4,500.00 | $4,000.00 |
| 58 | Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22) | EACH | 86 | $52.00 | $52.00 | $65.00 |
| 59 | Snowplowable raised pavement markers (BI-dir)(2 color) (716-01.23) | EACH | 68 | $52.00 | $52.00 | $65.00 |
| 60 | Removal of snowplowable reflective marker (716-01.30) | EACH | 68 | $29.81 | $12.00 | $126.00 |
| 61 | Plastic pavement marking (stop line) (716-02.05) | LF | 33 | $35.00 | $35.00 | $44.00 |
| 62 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 3 | $300.00 | $300.00 | $380.00 |
| 63 | Plastic pavement marking (8" dotted line) (716-02.08) | LF | 300 | $4.00 | $4.00 | $5.00 |
| 64 | Plastic pavement marking (8IN line) (716-02.12) | LM | 0.19 | $21,120 | $21,120 | $26,100 |
| 65 | Plastic pavement marking (straight arrow) (716-04.05) | EACH | 1 | $300.00 | $300.00 | $380.00 |
| 66 | Plastic pavement marking (yield line) (716-04.12) | SF | 57 | $38.00 | $38.00 | $48.00 |
| 67 | Painted pavement marking (6" line) (716-05.20) | LM | 1.86 | $3,650.00 | $3,650.00 | $4,600.00 |
| 68 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 1.86 | $12,500 | $12,500 | $16,000 |
| 69 | Mobilization (717-01) | LS | 1 | $150,000 | $208,695 | $165,000 |
| 70 | Geotextile (type III)(erosion control) (740-10.03) | SY | 226 | $7.00 | $5.50 | $25.00 |
| 71 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 80 | $5.00 | $20.00 | $32.00 |
| 72 | Temporary sediment tube 20IN (740-11.04) | LF | 1,825 | $5.50 | $3.95 | $7.00 |
| 73 | Temporary seeding (with mulch) (801-01.07) | UNIT | 157 | $45.00 | $30.00 | $57.00 |
| 74 | Water (seeding & sodding) (801-03) | MG | 103 | $5.00 | $30.00 | $6.00 |
| 75 | Sodding (new sod) (803-01) | SY | 8,685 | $4.50 | $4.00 | $6.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of June 26, 2026. Compiled by Mirage Metrics.