FDOT contract T6398 bid tabulation

SR 907 (ALTON RD) FROM MICHIGAN AVE TO S OF 43 ST (ED SULLIVAN DR). Let by Florida DOT on September 30, 2026, Miami-Dade, District 6. 4 bids received; low bid $75,760,761 by Ohla USA Inc.

Owner
Florida DOT
Letting
30 SEP 2026
Pay items
380
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Ohla USA Inc$75,760,761Low
2Lead Engineering Contractors, LLC$85,893,694+13%
3Ryan Southern - Civil JV, LLC.$90,596,857+20%
4Central Civil Construction Co.$119,989,623+58%
FDOT contract T6398: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Ohla USA Inc2. Lead Engineering Contractors, LLC3. Ryan Southern - Civil JV, LLC.4. Central Civil Construction Co.
0005Mobilization (0101-1)LS1$7,500,000$8,500,000$8,980,000$11,820,000
0010Maintenance of traffic (0102-1)DA1$3,500,000$2,500,000$2,700,000$24,725,802
0015Special detour- temporary pavement (0102-2200)SY1$350,000$650,000$296,800$310,492
0020Special detour- temporary earthwork/base (0102-2300)CY1$250,000$500,000$438,356$482,244
0025Traffic control officer (0102-14)HR3,600$75.00$100.00$93.75$82.50
0030Temporary highway lighting (0102-30)EACH1$1.00$215,000$212,000$226,007
0035Work zone sign (0102-60)ED612,760$0.18$0.18$0.18$0.20
0040Business sign (0102-61)EACH12$41.00$42.00$42.40$45.20
0045Temporary barrier, F&I, low profile, concrete (0102-71-13)LF8,450$0.01$44.00$44.52$47.46
0050Temporary barrier, relocate, low profile concrete (0102-71-23)LF11,945$21.00$21.00$21.20$23.00
0055Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED542,700$0.08$0.08$0.08$0.10
0060Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD95,535$0.03$0.03$0.03$0.03
0065Temporary separator, F&I remove (0102-75-1)LF9,655$19.00$19.00$19.08$21.76
0070Arrow board / advance warning arrow panel (0102-76)ED4,960$5.00$5.00$4.77$5.44
0075Temporary raised/retroreflective pavement marker, type D (0102-78-1)EACH413$5.00$6.00$5.30$5.65
0080Portable changeable message sign, temporary (0102-99)ED3,642$8.00$8.00$8.48$9.58
0085Temporary signalization and maintenance, intersection (0102-104)ED5,080$10.00$11.00$10.60$11.30
0090Temporary traffic detection and maintenance, intersection (0102-107-1)ED5,080$10.00$11.00$10.87$11.30
0095Type III barricade (0102-115)ED48,800$0.24$0.25$0.24$0.28
0100Temporary traffic signals for lane closures on way roadways (0102-120)ED320$87.00$586.00$583.27$169.51
0105Temporary raised rumble per day, includes all sets and relocations (0102-909)DA280$57.00$11.00$31.80$169.51
0110Removable tape, white, solid 6" (0102-913-21)GM0.21$6,538.50$11,000$6,996.02$11,696
0115Removable tape, white, 10'-30', 6'-10', or 2'-4' skip, 6" wide (0102-913-22)GM0.03$6,122.50$21,000$6,996.06$24,861
0120Removable tape, yellow, solid, (0102-913-31)GM0.25$26,389$12,000$27,984$13,278
0125Artificial coverings /rolled erosion control products (0104-1)SY4,129$7.00$11.00$10.60$2.84
0130Floating turbidity barrier (0104-11)LF779$30.00$31.00$14.10$56.50
0135Inlet protection system (0104-18)EACH177$444.50$125.00$135.58$174.73
0140Litter removal (0107-1)ACRE237.16$557.00$392.00$212.00$226.01
0145Mowing (0107-2)ACRE132.12$907.50$756.00$212.00$169.51
0150Monitor existing structures- inspection and settlement monitoring (0108-1)LS1$63,000$80,000$53,000$442,398
0155Monitor existing structures- vibration monitoring (0108-2)LS1$50,000$38,000$47,700$467,693
0160Clearing & grubbing (0110-1-1)ACRE1$3,500,000$2,488,000$4,000,000$1,945,546
0165Clearing & grubbing (0110-1-1)ACRE1$1,599,974$1,083,000$3,400,000$129,160
0170Removal of existing concrete (0110-4-10)SY9,688$75.00$65.00$6.42$38.66
0175Plugging water wells, non- artesian (0110-6)EACH3$12,755$53,000$13,250$14,125
0180Tree protection barrier (0110-21)LF5,150$7.00$9.00$4.51$12.43
0185Tree root and branch pruning (0110-22)EACH1$5,076.25$1,900.00$5,300.00$5,650.18
0190Remove existing bulkhead (0110-73)LF442$2,154.00$405.00$8.95$1,732.06
0195Regular excavation (0120-1)CY1,267.60$76.00$173.00$25.44$16.65
0200Embankment (0120-6)CY13,064.90$75.00$50.00$35.69$68.71
0205Geosynthetic reinforced foundation over soft soil (0145-2)SY7,457$13.00$16.00$6.12$14.39
0210Type B stabilization (0160-4)SY4,208$1.00$30.00$9.96$9.22
0215Reworking limerock base, 6" (0210-1-1)SY165$39.00$190.00$4.72$16.23
0220Reworking limerock base, 3" (0210-1-9)SY3,178$11.00$54.00$4.70$5.06
0225Optional base, base group 01 (0285-701)SY4,613$100.00$66.00$56.90$51.98
0230Optional base, base group 02 (0285-702)SY1,757$174.00$68.00$128.58$51.98
0235Optional base, base group 06 (0285-706)SY245$328.00$91.00$238.50$62.15
0240Optional base, base group 11 (0285-711)SY999$375.00$143.00$223.98$79.10
0245Drainable granular layer (#57 stone), special design, 12" (0285-772)SY2,776$89.00$150.00$14.57$59.11
0250Milling existing asphalt pavement, 3" avg depth (0327-70-4)SY15,808$5.00$6.09$5.30$9.04
0255Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY10,714$5.00$6.09$3.71$9.04
0260Milling existing asphalt pavement, 4" avg depth (0327-70-7)SY14,980$5.00$8.63$4.24$11.30
0265Superpave asphaltic conc, traffic B (0334-1-12)TN3,662.10$152.00$178.68$190.80$198.89
0270Superpave asphaltic conc, traffic C (0334-1-13)TN21,720.50$122.50$160.00$190.80$186.46
0275Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81)TN3,689.90$176.50$211.17$206.70$235.05
0280Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN2,559.70$176.50$187.82$222.60$209.06
0285Miscellaneous asphalt (0339-1)TN42.60$600.00$1,600.00$498.20$282.51
0290Geosynthetic interlayer reinforcement system, composite fiberglass (0342-1-2)SY34,288$19.00$15.00$39.21$42.14
0295Concrete class NS, gravity index 400-011 (0400-0-11)CY93.50$1,691.00$1,800.00$691.63$2,341.28
0300Concrete class IV, bridge substructure (0400-4-5)CY160.70$4,667.50$1,100.00$1,790.86$1,909.96
0305Conc class IV, bulkhead (0400-4-8)CY68.60$2,920.00$5,200.00$2,111.52$2,242.74
0310Reinforcing steel- bridge substructure (0415-1-5)LB24,103$2.00$3.00$2.44$2.59
0315Fiber reinforced polymer bars, #5 bar (0415-10-5)LF5,325$3.00$4.00$4.43$4.71
0320Inlets, curb, type 9, <10' (0425-1201)EACH5$6,029.75$15,000$9,840.44$14,215
0325Inlets, curb, type 9, J bot, <10' (0425-1203)EACH1$10,368$11,000$11,947$15,584
0330Inlets, curb, type 9, partial (0425-1205)EACH1$5,115.25$11,000$6,321.41$5,564.03
0335Inlets, curb, type 10, <10' (0425-1211)EACH34$7,182.50$14,000$11,172$15,317
0340Inlets, curb, type 10, >10' (0425-1212)EACH2$10,716$22,000$16,207$20,705
0345Inlets, curb, type 10, J bot <10' (0425-1213)EACH1$10,526$18,000$15,488$20,588
0350Inlets, curb, type P-1, <10' (0425-1311)EACH16$10,973$16,000$9,075.36$16,041
0355Inlets, curb type P-1, >10' (0425-1312)EACH8$11,925$18,000$14,478$21,541
0360Inlets, curb type P-1, partial (0425-1315)EACH2$8,416.00$11,000$5,960.24$7,160.08
0365Inlets, curb, type P-2, <10' (0425-1321)EACH6$11,994$18,000$9,789.17$16,960
0370Inlets, curb, type P-2, >10' (0425-1322)EACH1$12,549$18,000$14,603$22,287
0375Inlets, curb, type P-5, <10' (0425-1351)EACH14$8,100.50$14,000$11,211$15,214
0380Inlets, curb, type P-5, >10' (0425-1352)EACH2$10,948$18,000$17,030$20,215
0385Inlets, curb, type P-6, <10' (0425-1361)EACH7$10,159$15,000$12,210$15,690
0390Inlets, curb, type P-6, >10' (0425-1362)EACH3$10,609$20,000$16,360$20,576
0395Inlets, curb, type P-6, partial (0425-1365)EACH1$7,012.00$8,000.00$7,540.09$8,034.29
0400Inlets, curb, type J-5, <10' (0425-1451)EACH2$10,943$17,000$11,996$21,210
0405Inlets, curb, type J-5, >10' (0425-1452)EACH2$15,692$17,000$23,362$30,343
0410Inlets, curb, type J-6, <10' (0425-1461)EACH2$11,235$17,000$15,224$22,066
0415Inlets, DT bot, type C, jbot, >10' (0425-1524)EACH1$11,804$17,000$19,659$21,374
0420Inlets, DT bot, type C, modify (0425-1529)EACH49$5,322.50$4,000.00$11,103$10,636
0425Inlets, DT bot, type F, <10' (0425-1561)EACH8$6,632.50$11,000$10,787$15,781
0430Inlets, ditch bottom, type F, J bot, <10' (0425-1563)EACH6$11,715$13,000$16,851$18,898
0435Inlets, ditch bottom, type F, J bot, >10' (0425-1564)EACH5$21,163$16,000$33,310$43,399
0440Inlets, DT bot, type H, >10' (0425-1582)EACH1$13,806$18,000$27,146$31,731
0445Manholes, P-7, <10' (0425-2-41)EACH8$0.01$13,000$10,250$14,087
0450Manholes, P-7, >10' (0425-2-42)EACH2$9,838.00$18,000$14,363$21,499
0455Manholes, P-7, partial (0425-2-43)EACH4$7,645.75$6,000.00$5,638.38$6,583.18
0460Manholes, J-7, <10' (0425-2-71)EACH1$10,176$11,000$14,283$20,296
0465Manholes, J-7, >10' (0425-2-72)EACH53$17,171$21,000$26,970$36,111
0470Manhole, adjust (0425-5)EACH12$1,707.25$900.00$1,419.79$1,059.68
0475Pipe culvert,optional material,round, 12"S/CD (0430-175112)LF108$263.50$200.00$509.61$428.16
0480Pipe culvert,optional material,round, 15"S/CD (0430-175115)LF537$272.00$220.00$507.69$372.73
0485Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF4,907$263.00$250.00$577.49$362.71
0490Pipe culvert,optional material,round, 24"S/CD (0430-175124)LF1,372$296.00$300.00$747.16$402.54
0495Pipe culvert, opt material, round, 30"S/CD (0430-175130)LF1,067$1,988.00$1,700.00$1,522.70$2,098.60
0500Pipe culvert, opt material, round, 36"S/CD (0430-175136)LF217$452.50$1,900.00$937.22$600.84
0505Pipe culvert, opt material, round, 42"S/CD (0430-175142)LF1,141$627.00$1,800.00$1,077.13$548.46
0510Pipe culvert, opt material, round, 54"S/CD (0430-175154)LF3,328$763.00$2,000.00$1,249.14$778.85
0515Pipe culvert, opt material, round, 60"S/CD (0430-175160)LF616$787.00$2,000.00$1,761.77$862.45
0520Pipe culvert, opt material, round, 66"S/CD (0430-175166)LF242$919.00$2,000.00$1,969.06$964.75
0525Pipe filling and plugging- place out of service (0430-830)CY157.50$253.00$700.00$942.85$483.04
0530Trench drain, standard (0436-1-1)LF68$1,036.00$800.00$666.67$755.41
0535Deep well- open hole, 24" (0444-70-11)LF170$422.00$250.00$584.06$333.36
0540Deep well casing, 24" (0444-71-11)LF110$422.00$46.00$1.06$488.69
0545Pumping station- drainage (0448-73)LS1$9,703,930$5,000,000$7,534,645$12,190,356
0550Preformed pile holes, sheet (0455-15-40)SF50,255$0.01$25.00$0.01$5.65
0555Steel piling, HP 12 X 74 (0455-35-11)LF376$164.50$210.00$167.96$282.51
0560Anchor bar, steel (0455-87)EACH54$8,080.75$8,000.00$10,205$9,040.29
0565Auger grouted pile, 18" (0455-112-18)LF12,312$0.01$300.00$0.01$196.63
0570Sheet piling steel, temporary- critical (0455-133-2)SF35,613$0.01$31.00$40.13$53.35
0575Sheet piling steel, F&I (0455-133-3)SF30,800$106.50$44.00$90.24$115.55
0580Struct steel, miscellaneous (0460-2-15)LB1$143.00$104,000$302,844$10,124
0585Pipe handrail - guiderail, aluminum (0515-1-2)LF398$61.00$62.00$79.50$84.75
0590Pedestrian/ bicycle railing, aluminum only,42" type 1 (0515-2311)LF668$93.00$96.00$113.42$120.91
0595Bullet rail, single rail (0515-4-1)LF9$378.00$284.00$121.90$129.95
0600Bullet rail, double rail (0515-4-2)LF14$305.50$180.00$103.09$109.89
0605Concrete curb & gutter, type E (0520-1-7)LF156$31.00$54.00$49.71$34.79
0610Concrete curb & gutter, type F (0520-1-10)LF18,996$60.00$42.00$46.06$32.04
0615Concrete curb, type A (0520-2-1)LF309$23.00$39.00$29.32$25.04
0620Concrete curb, type D (0520-2-4)LF432$23.00$39.00$24.08$25.07
0625Valley gutter- concrete (0520-3)LF397$50.00$40.00$29.32$27.07
0630Traffic separator concrete- type IV, 4' wide (0520-5-41)LF1,281$136.00$151.00$56.18$89.66
0635Shoulder concrete barrier, 38" or 44" height (0521-72-40)LF392$532.00$700.00$339.20$480.00
0640Concrete sidewalk and driveways, 4" thick (0522-1)SY6,048$56.00$72.00$45.58$72.51
0645Concrete sidewalk and driveways, 6" thick (0522-2)SY3,773$124.00$85.00$56.29$92.14
0650Concrete ditch pavt, non reinforced, 3" (0524-1-1)SY124$99.00$114.00$111.68$120.68
0655Pavers, architectural, (0526-1-1)SY26$425.00$730.00$333.90$452.92
0660Detectable warnings (0527-2)SF595$36.00$60.00$27.56$40.04
0665Riprap- rubble, bank and shore (0530-3-3)TN34.50$506.00$1,600.00$621.60$163.86
0670Guardrail -roadway, general/low speed TL-2 (0536-1-0)LF500$21.00$21.00$16.96$18.08
0675Guardrail -roadway, general (0536-1-1)LF641$22.00$22.00$25.44$27.12
0680Guardrail transition to rigid barrier, F&I- index 536- 001, trailing (0536-8113)EACH3$1,720.50$1,700.00$1,817.90$1,938.01
0685Guardrail removal (0536-73)LF1,649$2.00$1.90$2.65$2.83
0690Guardrail end treatment- trailing anchorage (0536-85-20)EACH4$1,342.25$1,300.00$1,696.00$1,808.06
0695Guardrail end treatment- parallel approach terminal (0536-85-24)EACH6$3,061.25$3,000.00$3,021.00$3,220.60
0700Crash cushion, TL-2, narrow (0544-2-1)EACH1$27,012$22,000$19,266$20,538
0705Performance turf, sod (0570-1-2)SY21,315$8.00$5.00$6.42$9.04
0710Electrical power service- contribution in aid of construction (ciac), FPL (DO not bid) (0639-8130)LS1$356,000$356,000$356,000$356,000
0715Painted pavement markings, standard, white, solid, 6" (0710-11101)GM16.53$1,530.00$1,050.00$1,590.00$1,128.91
0720Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102)GM0.32$1,622.50$1,300.00$1,695.99$1,412.55
0725Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF230$1.00$1.05$0.85$1.13
0730Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF654$1.00$2.10$1.27$2.26
0735Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM0.37$670.00$785.00$699.60$847.53
0740Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM0.70$671.50$785.00$699.60$847.53
0745Painted pavement markings, standard, white, arrows (0710-11170)EACH103$31.00$79.00$31.80$84.75
0750Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM9.61$1,326.25$1,050.00$1,378.00$1,128.91
0755Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241)GM0.35$656.00$792.00$699.60$847.53
0760Pollution control structure with screen and filter, project 429193-1-52-01 (0916-438-10)EACH4$201,446$230,000$196,706$195,949
0765Partnering, DO not bid (0999-16)LS1$20,000$20,000$20,000$20,000
0770Disputes review board, meeting- DO not bid (0999-20-1)DA20$3,900.00$3,900.00$3,900.00$3,900.00
0775Disputes review board, hearing- DO not bid (0999-20-2)EACH2$4,500.00$4,500.00$4,500.00$4,500.00
0780Initial contingency amount, DO not bid (0999-25)LS1$123,900$123,900$123,900$123,900
0785Initial contingency amount, DO not bid (0999-25)LS1$21,000$21,000$21,000$21,000
0790Local agency initial amount (DO not bid) (0999-26)LS1$43,220$43,220$43,220$43,220
0795Conduit, furnish & install, directional bore (0630-2-12)LF10$29.00$30.00$29.68$31.64
0800Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH2$1,428.50$1,500.00$1,484.00$1,582.05
0805Electrical service wire, & install (0639-2-1)LF10$10.00$11.00$10.60$11.30
0810Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH100$709.00$700.00$736.70$593.27
0815Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH15$2,194.00$2,000.00$2,279.00$1,805.80
0820Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113)EACH3$2,194.00$3,000.00$2,279.00$2,205.82
0825Single column ground sign assembly, relocate (0700-1500)EACH1$433.50$500.00$450.50$189.85
0830Single column ground sign assembly, remove (0700-1600)EACH98$10.00$50.00$10.60$56.50
0835Multi-column ground sign assembly, F&I ground mount, 30.0 SF (0700-2113)EACH1$5,944.00$8,600.00$6,174.50$6,005.00
0840Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114)EACH1$6,117.25$9,600.00$6,354.70$6,181.29
0845Sign panel, relocate, UP to 12 SF (0700-3501)EACH4$433.50$180.00$450.50$108.48
0850Sign panel, remove, UP to 12 SF (0700-3601)EACH5$71.00$36.00$74.20$79.10
0855Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH30$204.00$120.00$212.00$126.56
0860Enhanced highway sign solar powered, F&I ground mount, W/eds, UP to 12 SF of static sign panels (0700-142131)EACH2$16,837$20,000$17,490$18,646
0865Tubular marker, 36" white post (0704-1-3)EACH28$97.00$135.00$100.70$146.90
0870Tubular marker, 36" yellow (0704-1-4)EACH22$97.00$135.00$100.70$146.90
0875Object marker, type 1 (0705-10-1)EACH10$357.00$365.00$371.00$392.12
0880Raised pavement marker, type B (0706-1-3)EACH1,453$4.00$5.00$4.24$5.65
0885Painted pavement markings, surface (0710-90)LS1$40,668$52,000$42,246$55,826
0890Painted pavement markings, surface (0710-90)LS1$1.00$7,600.00$0.01$8,090.86
0895Thermoplastic, standard, solid, 12" for interchange markings (0711-11103)GM0.09$12,514$9,600.00$13,432$10,622
0900Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF2,641$2.00$2.10$2.54$2.26
0905Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF1,904$4.00$3.00$3.82$3.50
0910Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF710$5.00$4.00$5.09$4.63
0915Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.35$2,306.25$1,450.00$2,438.01$1,525.55
0920Thermoplastic, standard, message or symbol (0711-11160)EACH26$122.50$210.00$127.20$226.01
0925Thermoplastic, standard, arrow (0711-11170)EACH100$82.00$105.00$84.80$113.00
0930Thermoplastic, standard, yield line (0711-11180)LF12$20.00$6.00$21.20$7.35
0935Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF78$4.00$3.00$3.82$3.50
0940Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.33$2,289.75$1,500.00$2,437.99$1,525.55
0945Thermoplastic, standard, blue, solid,6" (0711-11421)LF192$4.00$6.00$4.24$7.46
0950Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF2,219$17.00$19.00$18.02$20.34
0955Thermoplastic, preformed, white, message (0711-14160)EACH43$255.00$470.00$265.00$508.52
0960Thermoplastic, preformed, 12"X12" white elephant marking (0711-14163)GM0.04$59,864$30,000$55,968$28,194
0965Thermoplastic, preformed, white, arrow (0711-14170)EACH26$153.00$470.00$159.00$508.52
0970Thermoplastic, preformed, color route shield (0711-14660)EACH3$2,602.00$3,400.00$2,703.00$3,616.11
0975Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM5.35$5,395.00$5,300.00$5,607.40$5,666.00
0980Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.49$5,730.25$6,800.00$5,989.01$7,339.58
0985Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM1.71$1,339.75$1,600.00$1,399.20$1,689.41
0990Thermoplastic, standard-other surfaces white, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-16133)GM0.10$4,355.25$3,800.00$4,875.98$3,966.42
0995Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM3.39$5,393.25$5,200.00$5,607.40$5,666.00
1000Thermoplastic, standard-other surfaces, yellow, solid, 8" (0711-16202)GM0.01$7,206.25$8,500.00$5,988.75$7,339.57
1005Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231)GM0.61$1,340.25$1,600.00$1,399.20$1,689.41
1010Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1)SF460$4.00$4.00$4.24$4.29
1015Permanent tape, white, solid, 6" for concrete bridges (0713-103101)GM0.13$30,853$32,000$33,920$33,901
1020Permanent tape, white, 3-9 dotted, 6" wide, for concrete surfaces (0713-103171)GM0.03$8,256.00$55,000$9,433.94$65,542
1025Permanent tape, yellow, solid, for concrete bridges (0713-103201)GM0.07$29,685$64,000$33,920$65,542
1030Permanent tape, black, 3-9 dotted, 6" wide, for concrete surfaces (0713-103371)GM0.03$8,256.00$55,000$9,433.94$65,542
1035Green-colored pavement markings, bike lane (0714-10)SF1,139$17.00$4.00$18.02$20.34
1040Conduit, furnish & install, directional bore (0630-2-12)LF10,325$29.00$30.07$29.68$31.64
1045Conduit, furnish & install, mount (0630-2-15)LF200$71.00$74.00$74.20$79.10
1050Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH98$1,428.50$1,500.00$1,484.00$1,582.05
1055Pull & splice box, install (0635-2-30)EACH1$1,224.50$1,200.00$1,272.00$1,356.05
1060Junction box, furnish & install, mounted (0635-3-12)EACH2$1,224.50$1,200.00$1,272.00$1,356.05
1065Electrical power service, F&I, underground, meter by contractor (0639-1122)AS1$7,142.75$7,500.00$7,420.00$7,910.25
1070Prestressed concrete pole, type P-II service pole (0641-2-12)EACH1$2,551.00$2,600.00$2,650.00$2,825.09
1075Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF16,634$3.00$3.22$3.18$3.39
1080Lighting conductors, F&I, insulated, no 4 to no 2 (0715-1-13)LF22,606$5.00$5.00$5.30$5.65
1085Lighting conductors, remove & dispose, contractor owns (0715-1-60)LF22,208$0.10$0.10$0.11$0.11
1090Load center, F&I, secondary voltage (0715-7-11)EACH1$16,327$17,000$16,960$18,081
1095Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211)EACH22$1,071.50$1,120.00$1,113.00$1,186.54
1100Light pole complete, F&I, standard pole special foundation, 30' mounting height, 10' arm length (0715-62121)EACH2$16,837$12,000$12,190$18,646
1105Light pole complete, F&I, standard pole special foundation, 35' mounting height, 10' arm length (0715-62221)EACH1$16,837$12,000$12,190$18,646
1110Light pole complete, F&I, standard pole special foundation, 40' mounting height, 10' arm length (0715-62321)EACH36$18,367$13,000$13,250$20,341
1115Light pole complete, remove pole and foundation (0715-69000)EACH31$1,020.50$1,060.00$1,060.00$1,130.04
1120Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH84$765.50$800.00$795.00$847.53
1125Light pole complete-special design, F&I, pole top mount, aluminum, 20' (0715-516120)EACH45$13,265$8,500.00$8,374.00$14,690
1130Conduit, furnish & install, directional bore (0630-2-12)LF2,728$29.00$30.00$29.68$31.64
1135Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI4$10,204$10,000$10,600$11,300
1140Signal cable, remove- intersection (0632-7-6)PI3$510.00$500.00$530.00$565.02
1145Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH103$1,428.50$1,500.00$1,484.00$1,582.05
1150Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH4$2,551.00$2,600.00$2,650.00$2,825.09
1155Pull & splice box, install (0635-2-30)EACH5$1,224.50$1,300.00$1,272.00$1,356.05
1160Junction box, furnish & install, mounted (0635-3-12)EACH1$1,224.50$1,300.00$1,272.00$1,356.05
1165Electrical power service, F&I, underground, meter by contractor (0639-1122)AS3$7,142.75$7,500.00$7,420.00$7,910.25
1170Electrical power service, remove overhead (0639-1610)AS2$765.50$800.00$795.00$847.53
1175Electrical service wire, & install (0639-2-1)LF1,165$10.00$11.00$10.60$11.30
1180Electrical service wire, (0639-2-6)LF50$1.00$1.00$1.06$1.13
1185Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60)EACH2$2,040.75$2,100.00$2,120.00$2,260.07
1190Prestressed concrete pole, type P-II service pole (0641-2-12)EACH3$2,551.00$2,700.00$2,650.00$2,825.09
1195Aluminum signals pole, (0646-1-11)EACH17$1,836.75$1,900.00$1,908.00$2,034.06
1200Aluminum signals pole, remove (0646-1-60)EACH8$255.00$270.00$265.00$282.51
1205Steel mast arm assembly, and install, single arm 70' (0649-21-15)EACH1$112,245$120,000$116,600$124,304
1210Steel mast arm assembly- replace structural grout pad on existing pole (0649-40-4)EACH2$765.50$800.00$795.00$847.53
1215Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14)AS4$1,836.75$1,900.00$1,908.00$2,034.06
1220Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS14$1,530.50$1,600.00$1,590.00$1,695.06
1225Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12)AS3$2,040.75$2,100.00$2,120.00$2,260.07
1230Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60)AS1$255.00$260.00$265.00$282.51
1235Loop assembly, F&I, type F (0660-2106)AS12$1,530.50$1,600.00$1,590.00$1,695.06
1240Vehicle detection system- microwave, furnish & install cabinet equipment (0660-3-11)EACH3$5,102.00$5,400.00$5,300.00$5,650.18
1245Vehicle detection system- microwave, furnish & install, above ground equipment (0660-3-12)EACH3$14,286$14,900$14,840$15,821
1250Pedestrian detector, furnish & install, standard (0665-1-11)EACH10$408.00$430.00$424.00$452.02
1255Pedestrian detector, furnish & install, accessible (0665-1-12)EACH14$2,040.75$2,100.00$2,120.00$2,260.07
1260Pedestrian detector, remove- pole/pedestal to remain (0665-1-60)EACH4$51.00$54.00$53.00$56.50
1265Traffic controller assembly, F&I, caltrans W/standard lock (0670-5180)AS2$51,020$54,000$53,000$56,502
1270Traffic controller assembly, remove controller with (0670-5600)AS1$765.50$800.00$795.00$847.53
1275Cellular modem, furnish and install (0684-8-1)EACH2$2,551.00$2,600.00$2,650.00$2,825.09
1280Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH5$1,530.50$1,600.00$1,590.00$1,695.06
1285Sign panel, remove, UP to 12 SF (0700-3601)EACH5$102.00$105.00$106.00$113.00
1290Relocate trees and palms, palms, 18.1" or greater DBH, 14.0' or greater of clear trunk (0581-1292)EACH2$3,045.75$3,000.00$3,180.00$3,390.11
1295Relocate trees and palms, tree, 4.1" to 6.0" DBH (0581-1320)EACH1$5,076.25$2,000.00$5,300.00$5,650.18
1300Relocate trees and palms, tree, 6.1" to 8.0" DBH (0581-1330)EACH1$10,152$3,200.00$10,600$11,300
1305Relocate trees and palms, tree, 8.1" to 14.0" DBH (0581-1340)EACH6$11,168$5,000.00$11,660$12,430
1310Relocate trees and palms, tree, 14.1" to 16.0" DBH (0581-1350)EACH6$15,228$6,000.00$15,900$16,951
1315Irrigation system (0590-70)LS1$464,081$345,000$484,547$516,562
1320Irrigation system- modify existing system (0590-70-5)LS1$42,010$70,000$43,863$46,761
1325Relocate trees and <14' of clear trunk, sabal palm only (0581-1-7)EACH1$1,015.25$1,080.00$1,060.00$1,130.04
1330Relocate trees and palms, palms, <10.0" DBH, <14.0' of clear trunk (0581-1271)EACH28$1,015.25$1,200.00$1,060.00$1,130.04
1335Relocate trees and palms, palms, 10.0"-18.0" DBH, <14.0' of clear trunk (0581-1281)EACH54$1,015.25$885.00$1,060.00$1,130.04
1340Relocate trees and palms, palms, 10.0"-18.0" DBH, 14.0' or greater of clear trunk (0581-1282)EACH2$2,538.00$2,000.00$2,650.00$2,825.09
1345Relocate trees and palms, palms, 18.1" or greater DBH, 14.0' or greater of clear trunk (0581-1292)EACH21$4,882.75$3,000.00$5,098.09$5,434.93
1350Relocate trees and palms, tree, 3.1" to 4.0" DBH (0581-1310)EACH8$6,599.00$1,400.00$6,890.00$7,345.23
1355Relocate trees and palms, tree, 4.1" to 6.0" DBH (0581-1320)EACH19$5,984.50$2,000.00$6,248.42$6,661.27
1360Relocate trees and palms, tree, 6.1" to 8.0" DBH (0581-1330)EACH14$9,209.50$3,200.00$9,615.72$10,251
1365Relocate trees and palms, tree, 8.1" to 14.0" DBH (0581-1340)EACH16$12,690$5,000.00$13,250$14,125
1370Relocate trees and palms, tree, 14.1" to 16.0" DBH (0581-1350)EACH3$15,228$6,000.00$15,900$16,951
1375Initial contingency amount, DO not bid (0999-25)LS1$5,100.00$5,100.00$5,100.00$5,100.00
1380Local agency initial amount (DO not bid) (0999-26)LS1$1,336,010$1,336,010$1,336,010$1,336,010
1385Utility pipe,remove & dispose, 2- 4.9" (1050-16002)LF425$65.00$120.00$11.95$44.36
1390Utility pipe,remove & dispose, 5- 7.9" (1050-16003)LF1,170$65.00$73.00$32.58$63.25
1395Utility pipe,remove & dispose, 8- 19.9" (1050-16004)LF1,135$65.00$69.00$227.91$43.20
1400Utility pipe,plug & place out of service, 2- 4.9" (1050-18002)LF815$40.00$29.00$11.41$1.90
1405Utility pipe,plug & place out of service, 5- 7.9" (1050-18003)LF605$136.00$40.00$12.12$6.19
1410Utility pipe,plug & place out of service, 8-19.9" (1050-18004)LF9,340$20.00$45.00$199.25$20.37
1415Utility pipe- poly vinyl chloride, furnish & install, water/sewer, (1050-31206)LF3,775$241.00$250.00$420.10$427.56
1420Utility pipe- poly vinyl chloride, furnish & install, water/sewer, (1050-31208)LF1,286$244.50$550.00$1,187.37$515.25
1425Utility pipe- poly vinyl chloride, furnish & install, water/sewer, 10" (1050-31210)LF766$233.00$794.00$1,489.33$566.66
1430Utility pipe- poly vinyl chloride, furnish & install, water/sewer, 12" (1050-31212)LF1,188$239.50$600.00$1,119.45$722.35
1435Utility pipe- poly vinyl chloride, furnish & install, water/sewer, 15" (1050-31215)LF1,598$279.00$600.00$1,068.57$1,077.49
1440Utility pipe- poly vinyl chloride, furnish & install, water/sewer, 18" (1050-31218)LF337$341.50$1,300.00$1,945.28$1,649.92
1445Utility pipe- polyethylene, furnish & install, water/sewer, (1050-41202)LF4,555$176.00$110.00$46.42$99.73
1450Utility pipe- ductile iron/cast iron, furnish & install, water/sewer, 2" (1050-51202)LF330$237.00$350.00$49.51$100.84
1455Utility pipe- ductile iron/cast iron, furnish & install, water/sewer, 4" (1050-51204)LF415$307.50$410.00$367.40$192.17
1460Utility pipe- ductile iron/cast iron, furnish & install, water/sewer, 6" (1050-51206)LF525$268.00$425.00$344.83$235.69
1465Utility pipe- ductile iron/cast iron, furnish & install, water/sewer, 8" (1050-51208)LF2,050$284.00$400.00$400.49$460.01
1470Utility pipe- ductile iron/cast iron, furnish & install, water/sewer, 10" (1050-51210)LF20$340.50$550.00$691.02$538.75
1475Utility pipe- ductile iron/cast iron, furnish & install, water/sewer, 12" (1050-51212)LF5,145$326.00$550.00$715.65$478.05
1480Utility fittings for PVC pipe, furnish and install, cap/plug, 8" (1055-31508)EACH1$1,133.75$6,800.00$963.70$604.31
1485Utility fittings for PVC pipe, furnish and install, cap/plug, (1055-31510)EACH2$1,243.25$5,800.00$1,910.64$801.85
1490Utility fittings for PVC pipe, furnish and install, cap/plug, (1055-31512)EACH1$1,404.50$11,705$2,892.27$1,192.47
1495Utility fittings for PVC pipe, furnish and install, 8" wye (1055-31608)EACH19$1,962.50$5,000.00$2,462.95$2,813.30
1500Utility fittings for PVC pipe, furnish and install, 10" wye (1055-31610)EACH10$1,101.00$7,800.00$2,991.53$4,313.31
1505Utility fittings for PVC pipe, furnish and install, 12" wye (1055-31612)EACH17$1,243.50$11,000$4,633.41$4,402.52
1510Utility fittings for PVC pipe, furnish and install, 15" wye (1055-31615)EACH27$1,632.75$7,000.00$11,553$8,845.04
1515Utility fittings for PVC pipe, furnish and install, 18" wye (1055-31618)EACH3$1,811.00$8,800.00$10,579$17,008
1520Utility fittings for PVC pipe, furnish and install, cleanout 6" (1055-31706)EACH76$2,241.00$5,600.00$2,865.01$6,682.64
1525Utility fittings, ductile iron, furnish & install elbow, 8" (1055-51108)EACH81$1,397.00$2,800.00$1,549.81$1,176.26
1530Utility fittings, ductile iron, furnish & install elbow, (1055-51110)EACH3$1,767.50$2,900.00$1,966.80$1,509.78
1535Utility fittings, ductile iron, furnish & install elbow, (1055-51112)EACH50$2,251.25$3,440.00$2,554.53$2,090.05
1540Utility fittings, ductile iron, furnish & install tee, 8" (1055-51208)EACH2$2,196.00$3,200.00$1,773.24$1,862.27
1545Utility fittings, ductile iron, furnish & install tee, 12" (1055-51212)EACH24$2,907.50$3,900.00$4,425.42$2,552.70
1550Utility fittings, ductile iron, furnish & install reducer, 8" (1055-51308)EACH5$1,283.50$2,500.00$1,460.45$951.70
1555Utility fittings, ductile iron, furnish & install reducer, 12" (1055-51312)EACH8$1,826.75$4,900.00$1,933.14$1,614.73
1560Utility fittings, ductile iron, furnish & install, 8" (1055-51508)EACH11$1,131.00$1,965.00$962.04$659.48
1565Utility fittings, ductile iron, furnish & install, 12" (1055-51512)EACH2$1,370.25$2,500.00$2,674.57$1,055.44
1570Utility fittings, ductile iron, furnish & install cross, 8" (1055-51808)EACH1$2,628.50$3,800.00$4,506.16$3,537.21
1575Utility fittings, ductile iron, furnish & install cross, (1055-51812)EACH3$4,179.75$5,900.00$5,468.63$3,521.79
1585Utility structure, below ground, F&I, water / sewer > 80 FT3, 6.1 - 12' (1060-11222)EACH19$18,714$22,000$17,856$14,601
1587Utility structure, below ground, F&I, water / sewer > 80 FT3, > 12' (1060-11223)EACH9$8,060.00$28,000$31,935$25,706
1590Utility structure, below ground, adjust/modify (1060-15)EACH44$1,619.00$4,500.00$3,583.59$1,552.46
1595Utility structure, below ground, remove&dispose contractor takes ownership (1060-16)EACH17$2,194.75$4,500.00$3,452.90$1,660.47
1600Utility auxiliary items, 8" concrete slab for ground cover less than 2.5' (1070-1-1)SF408$88.00$40.00$22.66$40.19
1605Utility fixture, valve/meter box, furnish & install, 2" (1080-21102)EACH154$3,803.75$5,000.00$3,021.32$6,835.11
1610Utility fixture, valve/meter box, remove (1080-21600)EACH104$780.50$400.00$663.17$684.85
1615Utility fixture- tapping saddle/sleeve, furnish & 2" (1080-23102)EACH1$3,775.00$2,000.00$1,572.11$2,639.84
1620Utility fixture- tapping saddle/sleeve, furnish & 4" (1080-23104)EACH4$8,177.00$2,100.00$6,292.13$9,854.72
1625Utility fixture- tapping saddle/sleeve, furnish & 6" (1080-23106)EACH4$8,485.50$2,500.00$9,167.02$11,929
1630Utility fixture- tapping saddle/sleeve, furnish & 8" (1080-23108)EACH10$11,189$8,000.00$12,847$14,057
1635Utility fixture- tapping saddle/sleeve, furnish & 12" (1080-23112)EACH2$14,457$12,000$19,779$21,884
1640Utility fixture, valve assembly, furnish and install, 3" (1080-24103)EACH1$3,295.25$3,200.00$3,687.89$2,805.92
1645Utility fixture, valve assembly, furnish and install, 4" (1080-24104)EACH6$3,294.00$3,500.00$3,740.59$2,947.33
1650Utility fixture, valve assembly, furnish and install, 6" (1080-24106)EACH13$3,881.75$3,900.00$4,014.15$3,720.75
1655Utility fixture, valve assembly, furnish and install, 8" (1080-24108)EACH18$5,167.75$5,900.00$4,360.01$4,882.52
1660Utility fixture, valve assembly, furnish and install, 10" (1080-24110)EACH1$8,154.50$6,500.00$6,887.51$6,427.18
1665Utility fixture, valve assembly, furnish and install, 12" (1080-24112)EACH24$8,648.75$7,800.00$7,809.82$8,200.95
1670Utility fixture, valve assembly, adjust/modify (1080-24500)EACH39$1,522.25$1,200.00$1,848.18$952.89
1675Utility fixture, vac/air furnish & install 2" (1080-26102)EACH19$4,742.50$4,500.00$1,520.43$17,298
1680Lift station, sanitary sewer (1501-1)EACH1$2,080,924$1,800,000$386,201$3,307,579
1685Lift station, sewer bypass system (1501-3)LS1$277,475$565,000$117,972$1,893,396
1690Fire hydrant, F&I, standard, 2 hose, 1PUMPER, 6" (1644-113-08)EACH12$10,993$15,000$5,594.27$11,829
1695Fire hydrant, remove (1644-900)EACH12$2,021.00$1,100.00$1,003.82$1,937.84
1700Itsfm subsurface documentation- project length (0611-1-1)MI1.73$4,079.25$4,300.00$4,240.00$4,520.14
1705Itsfm location documentation- ITS site (0611-2-2)EACH2$2,245.00$2,300.00$2,332.00$2,486.07
1710Conduit, furnish & install, open trench (0630-2-11)LF945$22.00$25.00$23.32$24.86
1715Conduit, furnish & install, directional bore (0630-2-12)LF1,925$37.00$38.00$38.16$40.68
1720Conduit, furnish & install, aboveground (0630-2-14)LF120$51.00$50.00$53.00$56.50
1725Conduit, furnish & install, mount (0630-2-15)LF640$71.00$74.00$74.20$79.10
1730Fiber optic cable, F&I, underground,2-12 fibers (0633-1121)LF3,835$4.00$4.00$4.24$4.52
1735Fiber optic cable, remove, overhead (0633-1610)LF30$2.00$2.00$2.54$2.71
1740Fiber optic cable, remove, underground (0633-1620)LF90$2.00$2.00$2.54$2.71
1745Fiber optic connection, install, splice (0633-2-31)EACH20$61.00$64.44$63.60$67.80
1750Fiber optic connection hardware, F&I, splice enclosure (0633-3-11)EACH1$1,581.75$1,600.00$1,643.00$1,751.56
1755Fiber optic connection hardware, F&I, splice tray (0633-3-12)EACH1$67.00$70.00$69.96$74.58
1760Fiber optic connection hardware, F&I, buffer tube fan out kit (0633-3-14)EACH1$102.00$100.00$106.00$113.00
1765Fiber optic connection hardware, F&I, preterminated patch panel (0633-3-15)EACH2$2,449.00$2,500.00$2,544.00$2,712.08
1770Fiber optic connection hardware, F&I, connector panel (0633-3-17)EACH1$117.50$122.00$121.90$129.95
1775Fiber optic cable locator (0633-6)DA1,200$51.00$54.00$53.00$56.50
1780Multi-conductor cable, furnish & install, cat 6 (0633-8-11)LF310$10.00$10.00$10.60$11.30
1785Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH11$1,428.50$1,400.00$1,484.00$1,582.05
1790Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH14$2,551.00$2,600.00$2,650.00$2,825.09
1795Junction box, furnish & install, mounted (0635-3-12)EACH4$1,224.50$1,300.00$1,272.00$1,356.05
1800Electrical power service, F&I, underground, meter by contractor (0639-1122)AS1$7,653.00$8,000.00$7,950.00$8,475.27
1805Electrical power service, F&I, underground, meter not required (0639-1123)AS1$7,142.75$7,400.00$7,420.00$8,475.27
1810Electrical power service, remove underground (0639-1620)AS1$765.50$800.00$795.00$847.53
1815Electrical service wire, & install (0639-2-1)LF1,405$31.00$32.22$31.80$33.90
1820Electrical service wire, (0639-2-6)LF595$1.00$1.00$1.06$1.13
1825Prestressed concrete pole, type P-II service pole (0641-2-12)EACH2$2,551.00$2,600.00$2,650.00$2,825.09
1830Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60)EACH1$765.50$800.00$795.00$847.53
1835Concrete CCTV pole, furnish & install with lowering device, (0641-3163)EACH1$56,122$58,000$58,300$62,152
1838Aluminum pole- index 695-001, remove (0646-2600)EACH1$5,102.00$1,500.00$2,120.00$565.02
1840ITS cabinet, F&I W/riser, ground mount W/sunshield, 334, 66" H X W X 30" D (0676-2243)EACH1$15,306$16,000$15,900$16,951
1845ITS cabinet- adjust/modify (0676-2500)EACH1$5,102.00$5,000.00$5,300.00$5,650.18
1850ITS cabinet- remove (0676-2600)EACH1$765.50$800.00$795.00$847.53
1855Small equipment enclosure, furnish and install, less than 10"W X 13"H X 11" D (0676-3-10)EACH1$1,020.50$1,066.00$1,060.00$1,130.04
1860ITS CCTV camera, non- pressurized, IP, high definition (0682-1173)EACH1$7,653.00$8,000.00$7,950.00$8,475.27
1865ITS CCTV camera, remove & disposal (0682-1600)EACH1$510.00$530.00$530.00$565.02
1870Managed field ethernet switch, furnish & install (0684-1-1)EACH1$5,102.00$5,300.00$5,300.00$5,650.18
1875Uninterruptible power supply, furnish and install, line interactive (0685-1-11)EACH1$7,142.75$7,500.00$7,420.00$7,910.25
1880Remote power management rpmu, furnish and install (0685-2-1)EACH1$1,020.50$1,060.00$1,060.00$1,130.04
1885Front access dynamic message sign, furnish & install- W/UPS, full color, 101-200 SF (0700-8136)EACH1$117,347$122,000$121,900$129,954
1890DMS support structure, cantilever, 41-50 FT (0700-10124)EACH1$219,388$210,000$212,000$242,958
1893DMS support structure, (0700-10600)EACH1$15,306$15,000$31,800$28,251
FDOT contract T6398: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of September 30, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy