FDOT contract T7595 bid tabulation

SR 580 (W BUSCH BLVD) AND GUNN HWY FROM N DALE MABRY HWY TO. Let by Florida DOT on May 20, 2026, Hillsborough, District 7. 8 bids received; low bid $12,762,535 by C.W. Roberts Contracting, Inc..

Owner
Florida DOT
Letting
20 MAY 2026
Pay items
208
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1C.W. Roberts Contracting, Inc.$12,762,535Low
2Hubbard Construction Company$12,835,551+1.0%
3PCS Civil, Inc.$13,291,738+4.0%
4Blacktip Services Incorporated$13,429,834+5.0%
5Preferred Materials Inc.$13,603,764+7.0%
6Burgess Civil, LLC$14,371,815+13%
7De Moya Contracting LLC$15,124,913+19%
8Ajax Paving Industries of Florida LLC$15,187,558+19%
FDOT contract T7595: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. C.W. Roberts Contracting, Inc.2. Hubbard Construction Company3. PCS Civil, Inc.4. Blacktip Services Incorporated5. Preferred Materials Inc.6. Burgess Civil, LLC
0005Mobilization (0101-1)LS1$260,000$740,697$1,002,500$500,000$1,226,750$704,598
0010Mobilization (0101-1)LS1$52,000$50,000$59,900$500,000$200,000$124,341
0015Maintenance of traffic (0102-1)DA1$190,000$329,528$425,000$240,000$473,100$357,015
0020Maintenance of traffic (0102-1)DA1$52,560$35,000$45,000$124,000$100,000$39,657
0025Pedestrian or bicycle special detour (0102-4-1)SY1$4,604.43$4,829.75$14,500$9,000.00$8,600.00$3,621.07
0030Traffic control officer (0102-14)HR1,236$95.15$93.02$75.00$85.00$85.22$90.10
0035Work zone sign (0102-60)ED26,351$0.20$0.21$0.25$0.25$0.20$0.21
0040Business sign (0102-61)EACH29$43.40$44.44$40.00$40.00$42.61$43.52
0045Temporary barrier, F&I, low profile, concrete (0102-71-13)LF1,752$43.00$42.22$42.00$84.00$40.48$43.09
0050Temporary barrier, relocate, low profile concrete (0102-71-23)LF1,140$19.20$18.89$9.00$25.00$8.52$19.28
0055Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED31,510$0.10$0.10$0.13$0.11$0.10$0.10
0060Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD4,242$0.05$0.04$0.07$0.07$0.04$0.04
0065Arrow board / advance warning arrow panel (0102-76)ED1,094$4.35$4.44$6.00$5.30$4.26$4.35
0070Portable changeable message sign, temporary (0102-99)ED1,562$9.75$10.00$13.00$10.50$9.59$9.79
0075Temporary signalization and maintenance, intersection (0102-104)ED2,600$8.25$8.13$23.00$27.50$7.80$21.41
0080Temporary traffic detection and maintenance, intersection (0102-107-1)ED2,600$22.95$22.67$23.00$25.67$21.73$4.56
0085Existing ITS maintenance (0102-112)DA260$161.90$159.96$82.00$32.99$153.36$106.00
0090Type III barricade (0102-115)ED176$0.40$0.39$0.35$0.33$0.37$0.38
0095Radar speed display unit (0102-150-2)ED520$5.45$5.56$6.00$5.40$5.33$5.44
0100Sediment barrier (0104-10-3)LF7,342$1.25$1.09$1.00$3.81$3.24$2.22
0105Soil tracking prevention device (0104-15)EACH1$1,089.90$1,118.03$2,850.00$900.00$6,593.92$2,650.00
0110Inlet protection system (0104-18)EACH92$136.25$135.47$175.00$50.00$208.15$152.64
0115Litter removal (0107-1)ACRE141.60$64.50$110.57$125.00$90.00$79.89$64.66
0120Mowing (0107-2)ACRE63.40$115.20$110.57$275.00$90.00$159.78$115.54
0125Monitor existing structures- vibration monitoring (0108-2)LS1$15,856$16,416$6,250.00$2,500.00$57,063$30,740
0130Clearing & grubbing (0110-1-1)ACRE1$240,000$98,158$95,000$90,500$682,301$127,428
0135Clearing & grubbing (0110-1-1)ACRE1$210,000$98,158$27,500$78,000$190,746$14,159
0140Removal of existing concrete (0110-4-10)SY5,763$65.55$69.95$25.00$62.00$23.56$37.23
0145Embankment (0120-6)CY1,119.50$35.60$75.59$17.00$67.00$52.58$63.85
0147Regular excavation (3-R projects only) (0120-71)LS1$37,542$196,317$42,500$156,000$21,153$46,305
0150Optional base, base group 15 (0285-715)SY1,282$84.55$61.79$72.00$72.00$104.41$106.84
0155Milling existing asphalt pavement, 2" avg depth (0327-70-5)SY59,249$1.85$1.56$2.10$2.16$2.00$3.91
0160Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY68,806$2.25$2.46$2.25$3.19$1.93$6.75
0165Milling existing asphalt pavement, 5 1/2" avg depth (0327-70-18)SY7,673$6.25$5.23$6.75$7.10$6.02$12.71
0170Superpave asphaltic conc, traffic E (0334-1-15)TN4,853.10$150.30$130.37$145.00$150.31$137.05$192.43
0175Asphalt concrete friction course,traffic E, FC-12.5, PG (0337-7-88)TN10,845.90$163.25$156.14$190.00$179.51$174.88$206.94
0180Miscellaneous asphalt (0339-1)TN59.20$300.70$464.84$225.00$412.00$346.99$392.86
0185Concrete class NS, gravity index 400-011 (0400-0-11)CY71.10$3,289.30$3,102.71$1,325.00$2,750.00$1,278.24$6,132.28
0190Inlets, curb type P-1, partial (0425-1315)EACH1$9,943.85$8,687.57$7,300.00$7,700.00$6,779.69$5,076.16
0195Inlets, curb, type P-2, partial (0425-1325)EACH1$9,943.85$8,687.57$7,775.00$7,700.00$9,190.38$6,647.18
0200Inlets, curb, type P-3, <10' (0425-1331)EACH2$12,268$10,718$10,250$9,500.00$10,676$8,290.53
0205Inlets, curb, type P-5, <10' (0425-1351)EACH4$12,268$10,718$8,675.00$9,500.00$10,387$10,245
0210Inlets, curb, type P-5, partial (0425-1355)EACH9$9,943.85$8,687.57$4,300.00$7,700.00$8,029.20$6,951.06
0215Inlets, curb, type P-6, <10' (0425-1361)EACH1$12,268$10,718$9,550.00$9,500.00$10,964$11,636
0220Inlets, curb, type 7, <10' (0425-1471)EACH3$12,268$10,718$6,200.00$9,500.00$15,348$16,610
0225Inlets, gutter, type V, partial (0425-1715)EACH1$9,943.85$8,687.57$2,700.00$7,700.00$14,143$8,042.17
0230Inlets, closed flume (0425-1910)EACH1$8,523.30$7,446.49$11,750$6,600.00$9,127.46$2,943.74
0235Manholes, P-8, partial (0425-2-63)EACH4$9,943.85$8,687.58$2,750.00$7,700.00$12,845$6,277.84
0240Manhole, adjust (0425-5)EACH15$2,389.10$2,087.27$1,750.00$8,550.00$1,325.05$308.22
0245Desilting pipe, 0 - 24" (0430-94-1)LF1,282$7.05$8.98$7.50$8.64$8.52$11.02
0250Pipe culvert, optional material, round, 30"SD (0430-174130)LF20$424.90$371.20$250.00$329.00$383.85$250.92
0255Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF1,584$424.90$371.20$225.00$329.00$232.30$506.73
0260Pipe culvert,optional material,other-elip/arch, (0430-175218)LF14$424.90$371.20$275.00$329.00$296.49$269.62
0265Mitered end section, optional - elliptical / arch, 18" CD (0430-982625)EACH1$1,775.70$1,551.36$4,975.00$1,375.00$3,569.23$2,663.98
0270Mitered end section , optional round, 30" SD (0430-984133)EACH2$1,775.70$1,551.35$9,825.00$1,375.00$9,296.17$7,846.06
0275Pipe liner, cured in place, 15" (0431-1115)LF342$179.05$117.86$195.00$113.40$111.85$174.98
0280Pipe liner, cured in place, 18" (0431-1118)LF504$109.50$123.47$130.00$118.80$117.17$107.02
0285Pipe liner, cured in place, 24" (0431-1124)LF287$142.60$145.92$165.00$140.40$138.48$139.35
0290Pipe handrail - guiderail, steel (0515-1-1)LF338$118.10$72.23$75.00$82.08$83.19$69.96
0295Concrete curb & gutter, type E (0520-1-7)LF4,980$65.90$62.16$68.00$55.09$51.13$73.11
0300Concrete curb & gutter, type F (0520-1-10)LF3,504$65.90$62.16$75.00$55.09$48.51$57.37
0305Concrete curb, type A (0520-2-1)LF40$31.25$29.46$100.00$26.11$100.25$46.85
0310Traffic separator concrete- type I, 4' wide (0520-5-11)LF7,777$52.65$49.64$41.00$44.00$42.65$88.56
0315Concrete traffic separator, special- variable width (0520-70)SY2,602$100.70$95.01$90.00$84.21$93.08$210.02
0320Shoulder concrete barrier, 38" or 44" height (0521-72-40)LF302$442.55$417.45$250.00$370.00$436.73$745.73
0325Concrete sidewalk and driveways, 4" thick (0522-1)SY2,009$70.10$66.09$70.00$58.58$64.39$108.58
0330Concrete sidewalk and driveways, 6" thick (0522-2)SY1,638$88.85$83.82$105.00$74.29$131.03$132.52
0335Bus shelter pad- concrete (0522-4)SY62$88.85$83.82$265.00$74.29$138.74$164.99
0340Concrete slope pavement,non reinforced, 3" (0524-2-1)SY65$149.50$141.03$225.00$125.00$136.57$363.14
0345Detectable warnings (0527-2)SF451$31.70$41.75$45.00$37.00$31.71$31.80
0350Guardrail -roadway, general (0536-1-1)LF263$27.25$25.32$25.00$28.08$26.63$28.48
0355Guardrail removal (0536-73)LF576$2.20$2.04$3.75$5.40$2.13$2.28
0360Guardrail end treatment- trailing anchorage (0536-85-20)EACH1$2,179.25$1,584.74$1,550.00$2,052.00$2,130.40$2,278.34
0365Guardrail end treatment- parallel approach terminal (0536-85-24)EACH1$3,595.75$3,554.19$3,325.00$3,996.00$3,515.17$3,759.27
0370Fencing, type B, 5.1-6.0, reset existing (0550-10228)LF606$21.30$19.70$17.00$19.44$21.14$45.59
0375Performance turf, sod (0570-1-2)SY4,389$9.15$7.63$7.00$4.25$5.53$6.27
0380Conduit, furnish & install, directional bore (0630-2-12)LF437$54.05$53.41$62.50$19.12$51.20$55.12
0385Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH9$1,508.80$1,490.96$1,475.00$2,459.16$1,429.40$1,064.56
0390Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1)EACH20$2,698.85$2,666.99$3,050.00$3,508.92$2,556.88$2,322.04
0395Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12)EACH20$3,284.80$3,246.03$2,875.00$3,823.20$3,112.01$2,291.51
0400Traffic monitoring site cabinet, furnish & install, type 3, pedestal mount (0695-7132)EACH2$7,835.00$7,742.47$9,950.00$6,507.22$7,422.80$8,253.27
0405Traffic monitoring site cabinet, remove existing cabinet (0695-7600)EACH2$986.10$974.43$700.00$1,942.06$934.20$805.92
0410Painted pavement markings, standard, white, solid, 6" (0710-11101)GM12.84$1,750.90$1,767.78$1,655.00$1,728.00$1,703.39$1,483.19
0415Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102)GM2.57$2,334.15$2,356.12$2,225.00$2,303.64$2,270.31$1,588.76
0420Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF6,104$1.20$1.22$1.15$1.19$1.17$0.80
0425Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124)LF2,334$1.30$1.33$1.25$1.30$1.28$1.33
0430Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF5,517$1.40$1.44$1.40$1.40$1.38$1.59
0435Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM8.64$547.15$552.35$525.00$540.00$532.23$741.48
0440Painted pavement marking, standard,white, 3'-9' skip drop line and approach to toll 12" wide, (0710-11133)GM0.09$1,094.25$1,081.41$1,025.00$1,080.00$1,041.96$1,451.74
0445Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM1.02$711.30$712.21$675.00$702.00$686.27$735.45
0450Painted pavement markings, standard, white, message or symbol (0710-11160)EACH24$38.30$38.69$36.25$37.80$37.28$68.90
0455Painted pavement markings, standard, white, arrows (0710-11170)EACH160$38.30$38.69$36.25$37.80$37.28$37.10
0460Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM9.00$1,750.90$1,768.15$1,655.00$1,728.00$1,703.75$1,483.51
0465Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224)LF710$1.30$1.33$1.25$1.30$1.28$1.33
0470Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241)GM0.53$711.30$714.50$715.00$702.00$688.48$737.82
0485Initial contingency amount, DO not bid (0999-25)LS1$136,000$136,000$136,000$136,000$136,000$136,000
0490Initial contingency amount, DO not bid (0999-25)LS1$10,000$10,000$10,000$10,000$10,000$10,000
0495Midblock crosswalk: rectangular rapid flashing beacon, furnish & install- complete sign assy- single direction (0654-2-21)AS4$15,153$14,974$12,900$14,900$11,717$9,328.43
0500Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH159$475.70$499.98$575.00$610.20$479.34$477.00
0505Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH17$2,114.15$2,222.15$2,175.00$2,430.00$2,130.40$2,120.00
0510Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113)EACH2$2,642.70$2,777.69$2,825.00$3,780.00$2,663.01$2,650.00
0515Single column ground sign assembly, relocate (0700-1500)EACH9$370.00$388.88$300.00$324.00$372.82$371.00
0520Single column ground sign assembly, remove (0700-1600)EACH104$26.45$27.78$33.00$70.20$26.63$26.50
0525Single column ground sign assembly, F&I cantilever mount, 20.1-30.0 SF (0700-1913)EACH3$3,171.25$3,333.23$5,000.00$3,510.00$3,195.60$3,180.00
0530Multi-column ground sign assembly, F&I ground mount, 30.0 SF (0700-2113)EACH2$5,708.25$5,999.81$6,600.00$5,940.00$5,752.09$5,724.00
0535Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114)EACH1$7,928.10$8,333.06$8,225.00$8,910.00$7,989.01$7,950.00
0540Multi-column ground sign assembly, F&I ground mount, 100.0 SF (0700-2115)EACH1$9,513.75$9,999.68$11,175$10,530$9,586.81$9,540.00
0545Multi-column ground sign assembly, remove (0700-2600)EACH4$1,585.60$1,666.61$1,250.00$1,620.00$1,597.80$1,590.00
0550Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH5$317.10$333.32$255.00$351.00$319.56$318.00
0555Sign panel, furnish & install ground mount, 21-30 SF (0700-3103)EACH9$528.55$555.54$1,075.00$1,080.00$532.60$530.00
0560Sign panel, furnish & install ground mount, 31-50 SF (0700-3104)EACH1$1,057.10$1,111.08$1,885.00$1,836.00$1,065.20$1,060.00
0565Sign panel, furnish & install overhead mount, 12-20 SF (0700-3202)EACH1$2,219.90$2,333.26$725.00$1,080.00$2,236.93$2,226.00
0570Sign panel, furnish & install overhead mount, 51-100 SF (0700-3205)EACH2$3,171.25$3,333.23$2,750.00$4,860.00$3,195.61$3,180.00
0575Sign panel, furnish & install overhead mount, 101-200 SF (0700-3206)EACH3$5,602.55$5,888.70$4,755.00$8,100.00$5,645.57$5,618.00
0580Sign panel, remove, UP to 12 SF (0700-3601)EACH5$26.45$27.78$60.00$37.80$26.63$26.50
0585Sign panel, remove, 12-20 SF (0700-3602)EACH1$105.70$111.10$90.00$70.20$106.52$106.00
0590Sign panel, remove, 21-30 SF (0700-3603)EACH9$158.55$166.66$235.00$135.00$159.78$159.00
0595Sign panel, remove, 31-50 SF (0700-3604)EACH1$317.15$333.32$230.00$324.00$319.56$318.00
0600Sign panel, remove, 51-100 SF lighting (0700-3625)EACH2$1,268.50$1,333.29$735.00$621.00$1,278.24$1,272.00
0605Sign panel, remove, 101-200 SF with lighting (0700-3626)EACH3$1,268.50$1,333.29$1,175.00$1,080.00$1,278.24$1,272.00
0610Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH14$105.70$111.11$90.00$124.20$106.52$106.00
0615Tubular marker, 36" yellow (0704-1-4)EACH23$218.85$105.55$210.00$216.00$101.19$100.70
0620Object marker, type 3 (0705-10-3)EACH13$218.85$333.32$210.00$216.00$319.56$318.00
0625Raised pavement marker, type B (0706-1-3)EACH2,393$5.45$5.53$5.25$5.40$5.33$5.30
0630Painted pavement markings, durable paint, yellow, island nose (0710-12290)SF102$4.40$4.42$4.25$4.32$4.26$10.60
0635Painted pavement markings, surface (0710-90)LS1$80,441$81,262$76,050$81,333$78,302$95,188
0640Painted pavement markings, surface (0710-90)LS1$4,232.80$4,275.93$4,000.00$4,177.44$4,120.20$5,300.00
0645Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF6,104$3.30$3.32$3.25$3.24$3.20$3.71
0650Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF2,334$4.90$4.97$4.75$4.86$4.79$4.77
0655Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF5,517$6.60$6.63$6.25$6.48$6.39$6.36
0660Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.95$1,783.70$1,786.70$1,700.00$1,760.40$1,721.64$3,153.16
0665Thermoplastic, standard, message or symbol (0711-11160)EACH24$78.80$79.59$75.00$77.76$76.69$212.00
0670Thermoplastic, standard, arrow (0711-11170)EACH160$58.00$58.59$55.00$57.24$56.46$84.80
0675Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF710$4.40$4.42$4.25$4.32$4.26$5.30
0680Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.55$1,783.75$1,792.13$1,675.00$1,760.40$1,726.87$3,162.75
0685Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF4,120$16.35$16.50$15.50$16.12$15.90$16.96
0690Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM11.85$4,749.30$4,795.69$4,500.00$4,687.20$4,621.02$5,297.76
0695Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM2.57$6,331.65$6,391.24$6,000.00$6,248.88$6,158.46$6,143.22
0700Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM7.65$1,187.30$1,198.96$1,125.00$1,171.80$1,155.29$2,543.00
0705Thermoplastic, standard-other surfaces white, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-16133)GM0.09$2,374.60$2,346.63$2,200.00$2,343.60$2,261.20$5,184.78
0710Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM8.04$4,213.10$4,254.98$4,000.00$4,158.00$4,100.00$5,298.68
0715Conduit, furnish & install, open trench (0630-2-11)LF184$21.25$20.98$19.50$19.75$20.11$18.34
0720Conduit, furnish & install, directional bore (0630-2-12)LF56$48.65$48.07$30.50$15.29$46.08$71.87
0725Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH3$2,425.90$2,397.28$1,875.00$2,459.16$2,298.30$1,064.56
0730Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF690$3.40$3.36$3.00$2.98$3.22$3.18
0735Luminaire & bracket arm- aluminum, furnish & install new luminaire and arm on new/existing pole (0715-5-31)EACH8$3,603.50$3,560.94$2,075.00$7,312.04$3,413.92$3,235.44
0740Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211)EACH13$1,480.10$1,462.60$1,025.00$2,784.46$1,402.21$1,334.65
0745Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 12' arm length (0715-61342)EACH1$13,522$13,362$14,400$10,546$12,810$8,224.96
0750Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH9$816.45$806.80$855.00$1,469.99$773.49$860.83
0755Conduit, furnish & install, open trench (0630-2-11)LF312$229.45$226.76$37.25$19.75$217.40$14.31
0760Conduit, furnish & install, directional bore (0630-2-12)LF877$60.50$59.81$45.50$18.48$57.34$31.69
0765Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI6$17,309$17,105$19,550$19,367$16,398$15,585
0770Signal cable- repair/replace/other, furnish & install (0632-7-2)LF95$7.95$7.87$5.25$15.21$7.54$10.28
0775Signal cable, remove- intersection (0632-7-6)PI2$1,774.90$1,753.96$900.00$7,768.23$1,681.54$805.92
0780Span wire assembly, F&I, single point, box or drop box (0634-4143)PI1$9,878.35$9,761.71$12,100$12,952$9,358.67$4,967.90
0785Span wire assembly, F&I, two point, diagonal (0634-4152)PI3$7,715.50$7,624.38$10,050$10,360$7,309.59$6,176.73
0790Span wire assembly, F&I, two point, box or drop box (0634-4153)PI3$15,979$15,791$19,750$12,693$15,139$6,176.73
0795Span wire assembly, remove- poles remain (0634-4600)PI4$2,366.55$2,338.60$2,125.00$5,826.18$2,242.05$805.92
0800Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH38$1,508.80$1,490.96$1,650.00$2,459.16$1,429.40$1,064.56
0805Electrical power service, F&I, underground, meter by contractor (0639-1122)AS1$4,239.15$4,189.11$9,775.00$5,959.66$4,016.15$7,204.50
0810Electrical service wire, & install (0639-2-1)LF6$24.45$24.16$13.50$14.12$23.16$31.69
0815Electrical service disconnect, F&I, pole mount (0639-3-11)EACH1$1,797.90$1,776.67$1,950.00$1,943.03$1,703.32$3,403.45
0820Prestressed concrete pole, type P-II service pole (0641-2-12)EACH1$3,193.70$3,156.02$2,600.00$2,622.94$3,025.72$4,163.57
0825Prestressed concrete pole, type P-VII (0641-2-17)EACH4$44,104$43,583$23,200$25,997$41,784$24,107
0830Prestressed concrete pole, type P-VIII (0641-2-18)EACH4$45,230$44,696$26,825$26,904$42,850$26,811
0835Prestressed concrete pole, complete pole removal- pole 30' and greater (0641-2-80)EACH6$28,790$28,450$11,575$10,924$27,275$4,835.30
0840Aluminum signals pole, (0646-1-11)EACH29$3,149.70$3,112.50$3,250.00$5,187.89$2,983.99$2,355.00
0845Aluminum signals pole, remove (0646-1-60)EACH13$591.65$584.65$250.00$1,942.06$560.51$604.41
0850Steel strain pole, F&I, type PS- (0649-1-14)EACH4$69,730$68,907$46,500$54,177$66,062$64,203
0855Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14)AS47$2,401.05$2,372.69$2,475.00$2,449.77$2,274.73$1,903.34
0860Vehicular traffic signal, furnish & install aluminum, 4 section, 1 way (0650-1-16)AS5$2,280.40$2,253.49$2,375.00$3,250.21$2,160.45$1,882.14
0865Vehicular traffic signal, relocate- includes removal reinstallation (0650-1-70)AS43$869.30$859.01$1,650.00$3,122.23$823.54$906.51
0870Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- black with reflect border (0650-2102)EACH35$675.90$667.91$675.00$1,230.23$640.34$466.72
0875Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS29$1,118.20$1,104.99$1,400.00$746.90$1,059.36$825.00
0880Loop detector, inductive, F&I, type 5, 2CHANNEL, solid state, shelf mounted (0660-1105)EACH12$870.65$860.37$1,100.00$841.91$824.85$500.32
0885Loop assembly, F&I, type F (0660-2106)AS14$2,189.85$2,164.00$2,350.00$3,519.83$2,074.65$2,244.13
0890Vehicle detection system- microwave, furnish & install cabinet equipment (0660-3-11)EACH7$10,704$10,578$11,200$12,087$10,141$9,993.57
0895Vehicle detection system- microwave, furnish & install, above ground equipment (0660-3-12)EACH7$11,867$11,727$12,050$13,821$11,243$9,788.57
0900Vehicle detection system- furnish & install cabinet equipment (0660-4-11)EACH22$10,765$10,638$34,650$27,933$10,199$10,650
0905Vehicle detection system- furnish & install above ground equipment (0660-4-12)EACH22$8,344.15$8,245.62$13,650$13,075$7,905.18$8,604.66
0910Pedestrian detector, furnish & install, standard (0665-1-11)EACH29$577.30$570.47$450.00$450.12$546.92$407.89
0915Traffic controller assembly, F&I, NEMA W/standard lock (0670-5160)AS1$64,380$63,620$70,300$46,847$60,993$56,276
0920Uninterruptible power supply, furnish and install, line interactive (0685-1-11)EACH1$16,842$16,643$18,750$15,058$15,956$3,587.89
0925Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH5$997.55$985.78$1,100.00$1,239.30$945.08$1,048.02
0930Internally illuminated sign, furnish & install overhead mount, UP to 12 SF (0700-5-21)EACH2$6,346.10$6,271.19$10,575$4,326.70$6,012.27$3,112.90
0935Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22)EACH12$6,679.90$6,601.04$8,575.00$5,226.93$6,328.50$3,272.96
0940Enhanced highway sign AC powered, F&I overhead blank out sign <12 SF (0700-141360)EACH4$7,825.40$7,733.04$10,050$7,837.89$7,413.76$6,232.38
0945Enhanced highway sign AC powered, relocate - overhead mount (0700-141803)EACH2$1,549.00$1,530.70$2,650.00$7,450.06$1,467.50$944.78
0950Itsfm subsurface documentation- project length (0611-1-1)MI3.70$4,915.30$4,857.24$5,600.00$4,167.29$4,656.70$4,380.45
0955Itsfm location documentation- intersection (0611-2-1)EACH7$3,577.50$3,535.24$4,075.00$3,122.28$3,389.28$3,188.16
0960Conduit, furnish & install, open trench (0630-2-11)LF5,600$42.85$42.33$35.50$25.25$40.58$29.04
0965Conduit, furnish & install, directional bore (0630-2-12)LF9,695$45.65$45.10$72.50$30.22$43.24$45.05
0970Fiber optic cable, F&I, underground,2-12 fibers (0633-1121)LF1,385$5.50$5.42$6.25$4.65$5.20$4.56
0975Fiber optic cable, F&I, underground, 97 - 144 fibers (0633-1124)LF19,225$6.55$6.47$7.50$6.37$6.20$5.51
0980Fiber optic cable, relocate, underground (0633-1420)LF400$4.50$4.46$5.25$3.82$4.27$3.82
0985Fiber optic cable, remove, underground (0633-1620)LF1,140$1.90$1.86$2.25$1.59$1.78$1.59
0990Fiber optic connection, install, splice (0633-2-31)EACH36$67.65$66.84$77.00$57.35$64.08$56.07
0995Fiber optic connection hardware, F&I, splice enclosure (0633-3-11)EACH9$1,924.00$1,901.30$2,200.00$1,631.23$1,822.80$1,592.23
1000Fiber optic connection hardware, F&I, splice tray (0633-3-12)EACH9$75.15$74.26$85.50$63.72$71.20$62.22
1005Fiber optic connection hardware, F&I, preterminated patch panel (0633-3-15)EACH7$2,818.40$2,785.11$3,200.00$2,389.50$2,670.12$2,332.32
1010Telephone cable, remove (0633-4-16)LF4,760$4.95$4.88$1.25$4.86$4.68$0.11
1015Fiber optic cable locator (0633-6)DA260$187.90$185.67$265.00$127.44$178.01$21.20
1020Multi-conductor cable, furnish & install, cat 6 (0633-8-11)LF420$8.80$8.67$5.50$1.94$8.31$4.56
1025Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH23$2,494.10$2,464.64$2,775.00$4,275.18$2,362.88$2,436.41
1030Pull & splice box, F&I, 30" X 60" rectangular or 36" round size (0635-2-13)EACH6$6,210.50$6,137.20$6,775.00$5,516.75$5,883.81$5,636.34
1035ITS CCTV camera, non- pressurized, IP, high definition (0682-1173)EACH7$16,031$15,842$6,525.00$8,921.99$15,188$14,195
1040Managed field ethernet switch, furnish & install (0684-1-1)EACH7$6,606.30$6,528.31$5,150.00$4,101.35$6,258.77$4,778.16
1045Wireless communication system device, remove (0684-6-6)EACH3$338.20$334.21$295.00$971.03$320.41$299.56
FDOT contract T7595: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of May 20, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy