TDOT contract CN262059 bid tabulation
The repair of the bridges on s.r. 127 over bradley creek at l.m. 6.21 and l.m. 9.76, including grading, drainage, and paving. Let by Tennessee DOT on August 14, 2026, Coffee County. 5 bids received; low bid $5,131,459 by Jones Bros. Contractors, LLC.
- Owner
- Tennessee DOT
- Letting
- 14 AUG 2026
- Pay items
- 191
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Jones Bros. Contractors, LLC | $5,131,459 | Low |
| 2 | Mid-State Construction Company, Inc. | $5,809,350 | +13% |
| 3 | Dement Construction Group, LLC | $6,079,095 | +18% |
| 4 | Capital City Construction Services, LLC | $6,271,027 | +22% |
| 5 | Bell & Associates Construction, LLC | $7,247,661 | +41% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Jones Bros. Contractors, LLC | 2. Mid-State Construction Company, Inc. | 3. Dement Construction Group, LLC | 4. Capital City Construction Services, LLC | 5. Bell & Associates Construction, LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $50,000 | $98,362 | $75,000 | $77,314 | $75,000 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $40,000 | $123,001 | $245,000 | $52,041 | $85,000 |
| 3 | Removal of pipe (15" RCP, sta. 103+82.63 22.96 LT.) (202-02.01) | LF | 27 | $15.00 | $30.75 | $28.00 | $41.30 | $45.00 |
| 4 | Removal of pipe (18" RCP, sta. 103+97.88 22.57 RT.) (202-02.02) | LF | 42 | $15.00 | $30.75 | $28.00 | $41.30 | $40.00 |
| 5 | Removal of pipe (18" RCP, sta. 9+92.74 33.41 RT.) (202-02.03) | LF | 29 | $15.00 | $30.75 | $30.00 | $41.30 | $45.00 |
| 6 | Removal of pipe (6" PVC, sta. 10+50 RT.) (202-02.04) | LF | 104 | $5.00 | $30.75 | $28.00 | $41.30 | $35.00 |
| 7 | Road & drainage excavation (unclassified) (203-01) | CY | 1,604 | $40.00 | $34.20 | $45.00 | $59.98 | $70.00 |
| 8 | Road & drainage excavation (stream mitigation) (203-01.13) | CY | 3,500 | $30.00 | $34.20 | $50.00 | $57.07 | $40.00 |
| 9 | Borrow excavation (unclassified) (203-03) | CY | 611 | $40.00 | $36.48 | $45.00 | $52.69 | $90.00 |
| 10 | Placing and spreading topsoil (203-04) | CY | 692 | $35.00 | $30.78 | $25.00 | $38.46 | $50.00 |
| 11 | Water (203-06) | MG | 27 | $10.00 | $114.00 | $10.00 | $15.00 | $50.00 |
| 12 | Natural streambed material(removal-storage-placement) (203-20.02) | CY | 1,600 | $28.00 | $13.68 | $50.00 | $60.13 | $44.00 |
| 13 | Construction of haul road (203-50) | LS | 1 | $1,000.00 | $151,379 | $135,000 | $145,470 | $115,300 |
| 14 | 18" temporary slope drain (209-02.07) | LF | 183 | $25.00 | $27.93 | $25.00 | $66.92 | $80.00 |
| 15 | Stream mitigation-coconut fiber rolls (209-03.31) | LF | 145 | $55.00 | $28.50 | $125.00 | $20.73 | $60.00 |
| 16 | Stream mitigation - live brush layering (209-03.42) | LF | 145 | $272.00 | $171.00 | $155.00 | $65.66 | $300.00 |
| 17 | Placing native stone in new channel (209-03.66) | SY | 200 | $100.00 | $57.00 | $92.00 | $61.23 | $110.00 |
| 18 | Stream mitigation – wood toe W/reinforced earth (209-03.67) | LF | 145 | $220.00 | $228.00 | $165.00 | $84.46 | $240.00 |
| 19 | Protected area marker (white with decal) (209-03.99) | EACH | 16 | $180.00 | $285.00 | $255.00 | $183.67 | $300.00 |
| 20 | Sediment removal (209-05) | CY | 44 | $20.00 | $24.60 | $25.00 | $139.16 | $10.00 |
| 21 | Temporary silt fence (with backing) (209-08.02) | LF | 7,318 | $4.00 | $5.68 | $4.98 | $4.08 | $5.00 |
| 22 | Rock check dam (209-08.07) | EACH | 4 | $800.00 | $792.87 | $695.50 | $714.29 | $750.00 |
| 23 | Enhanced rock check dam (209-08.08) | EACH | 11 | $1,000.00 | $969.00 | $850.00 | $714.29 | $900.00 |
| 24 | Sandbags (209-09.01) | BAG | 2,113 | $5.00 | $0.10 | $16.00 | $6.12 | $3.00 |
| 25 | Sediment filter bag(15' X 10') (209-09.04) | EACH | 10 | $600.00 | $423.12 | $775.00 | $326.53 | $450.00 |
| 26 | Polyethylene sheeting (6 mil. minimum) (209-20.03) | SY | 24 | $8.00 | $11.40 | $20.00 | $4.00 | $12.00 |
| 27 | Temporary in stream diversion (209-65.04) | LF | 1,087 | $30.00 | $54.87 | $60.00 | $56.33 | $100.00 |
| 28 | Mineral aggregate, type A base, grading D (303-01) | TON | 2,321 | $47.00 | $35.91 | $31.48 | $47.59 | $45.00 |
| 29 | Mineral aggregate (size 57) (303-10.01) | TON | 28 | $75.00 | $54.12 | $80.00 | $136.99 | $95.00 |
| 30 | Mineral aggregate (size 57) (303-10.04) | TON | 1,200 | $55.00 | $44.64 | $50.00 | $67.01 | $55.00 |
| 31 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01) | TON | 56 | $186.00 | $427.50 | $375.00 | $663.27 | $450.00 |
| 32 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 163 | $188.00 | $250.80 | $220.00 | $239.80 | $250.00 |
| 33 | Bituminous material for tack coat (TC) (403-01) | TON | 3 | $1,050.00 | $1,197.00 | $1,050.00 | $2,040.82 | $1,100.00 |
| 34 | Saw cutting asphalt pavement (407-20.05) | LF | 1,822 | $8.00 | $9.12 | $10.00 | $3.57 | $3.75 |
| 35 | Acs mix(PG64-22) grading D (411-01.10) | TON | 431 | $203.00 | $250.80 | $230.00 | $255.10 | $230.00 |
| 36 | Scoring for rumble stripe (non-continuous) (4IN width) (411-12.04) | LM | 0.70 | $12,700 | $1,711.14 | $1,500.00 | $5,102.04 | $1,500.00 |
| 37 | Cold planing bituminous pavement (415-01.02) | SY | 5,133 | $7.45 | $6.84 | $6.00 | $5.10 | $6.50 |
| 38 | 18" pipe culvert (side drain) (607-39.02) | LF | 24 | $80.00 | $85.50 | $57.00 | $140.74 | $70.00 |
| 39 | 24" pipe culvert (side drain) (607-39.03) | LF | 89 | $100.00 | $108.30 | $71.00 | $158.07 | $125.00 |
| 40 | Class A concrete (pipe endwalls) (611-07.01) | CY | 1.50 | $3,000.00 | $2,850.00 | $2,000.00 | $3,468.70 | $6,500.00 |
| 41 | Steel bar reinforcement (pipe endwalls) (611-07.02) | LB | 70 | $1.40 | $3.42 | $10.00 | $0.99 | $3.00 |
| 42 | 18IN endwall (side drain) (611-07.31) | EACH | 2 | $5,000.00 | $5,130.00 | $8,000.00 | $8,859.75 | $7,100.00 |
| 43 | 24IN endwall (side drain) (611-07.32) | EACH | 3 | $6,400.00 | $6,270.00 | $8,000.00 | $10,274 | $10,000 |
| 44 | 18" temporary drainage pipe (621-03.02) | LF | 428 | $25.00 | $54.72 | $30.00 | $47.36 | $100.00 |
| 45 | 24" temporary drainage pipe (621-03.03) | LF | 184 | $45.00 | $71.82 | $30.00 | $58.28 | $100.00 |
| 46 | 36" temporary drainage pipe (621-03.05) | LF | 138 | $60.00 | $117.42 | $30.00 | $75.62 | $130.00 |
| 47 | Earth pad for type 38 GR end treatment (705-04.09) | EACH | 8 | $1,000.00 | $1,140.00 | $1,000.00 | $1,020.41 | $1,050.00 |
| 48 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 856.25 | $25.00 | $31.35 | $27.50 | $28.06 | $30.00 |
| 49 | GR terminal (in-inline) MASH TL-3 (705-06.11) | EACH | 2 | $1,000.00 | $1,710.00 | $1,500.00 | $1,530.61 | $1,600.00 |
| 50 | Tangent energy absorbing term MASH TL-3 (705-06.20) | EACH | 8 | $3,200.00 | $3,705.00 | $3,250.00 | $3,316.33 | $3,350.00 |
| 51 | Thrie beam bridge transition MASH TL-3 (705-06.25) | EACH | 8 | $2,900.00 | $3,420.00 | $3,000.00 | $3,061.22 | $3,200.00 |
| 52 | Guardrail removed (706-01) | LF | 840 | $2.00 | $1.14 | $1.00 | $1.02 | $1.00 |
| 53 | Radius rail (706-06.03) | LF | 45 | $27.00 | $33.63 | $29.50 | $30.10 | $32.00 |
| 54 | Rounded end element (706-10.26) | EACH | 2 | $100.00 | $114.00 | $100.00 | $102.04 | $105.00 |
| 55 | Removal of fence (combination of woven wire and wooded) (707-06.01) | LF | 1,250 | $4.00 | $15.54 | $6.00 | $9.80 | $8.00 |
| 56 | High-visibility construction fence (707-08.11) | LF | 2,894 | $2.50 | $2.85 | $2.50 | $2.55 | $2.75 |
| 57 | Markers (concrete R.O.W. posts) (708-02.01) | EACH | 32 | $300.00 | $292.17 | $320.00 | $500.00 | $800.00 |
| 58 | Machined rip-rap (class A-3) (709-05.05) | TON | 200 | $56.00 | $43.45 | $55.00 | $109.31 | $80.00 |
| 59 | Machined rip-rap (class A-1) (709-05.06) | TON | 207 | $56.00 | $50.12 | $55.00 | $107.23 | $80.00 |
| 60 | Machined rip-rap (class B) (709-05.08) | TON | 1,226 | $50.00 | $45.67 | $55.00 | $98.02 | $75.00 |
| 61 | Machined rip-rap (class C) (709-05.09) | TON | 1,419 | $50.00 | $45.65 | $55.00 | $91.22 | $75.00 |
| 62 | Rock riffles (709-05.81) | LS | 1 | $34,600 | $31,350 | $50,000 | $37,924 | $36,000 |
| 63 | Traffic control (712-01) | LS | 1 | $50,000 | $54,580 | $75,000 | $21,429 | $30,000 |
| 64 | Portable barrier rail (MASH TL-3) (712-02.10) | LF | 380 | $55.00 | $68.40 | $60.00 | $57.61 | $95.00 |
| 65 | Portable barrier rail, reduced deflection (MASH TL-3) (712-02.12) | LF | 440 | $70.00 | $68.40 | $100.00 | $57.61 | $145.00 |
| 66 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 2 | $6,105.00 | $6,959.70 | $6,105.00 | $6,229.59 | $6,700.00 |
| 67 | Flexible drums (channelizing) (712-04.01) | EACH | 60 | $24.00 | $27.36 | $24.00 | $24.49 | $25.00 |
| 68 | Barrier rail delineator (712-04.50) | EACH | 25 | $13.00 | $14.82 | $13.00 | $13.27 | $14.00 |
| 69 | Warning lights (type A) (712-05.01) | EACH | 8 | $22.00 | $25.08 | $22.00 | $22.45 | $22.00 |
| 70 | Signs (construction) (712-06) | SF | 1,321 | $6.98 | $7.96 | $6.98 | $7.12 | $7.75 |
| 71 | Temporary barricades (type III) (712-07.03) | LF | 72 | $24.00 | $27.36 | $24.00 | $24.49 | $26.00 |
| 72 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 3,270 | $3.05 | $4.56 | $4.00 | $5.10 | $4.00 |
| 73 | Removable pavement marking (stop line) (712-09.04) | LF | 24 | $9.00 | $28.50 | $25.00 | $30.61 | $26.00 |
| 74 | Removable pavement marking (6" line) (712-09.08) | LF | 4,000 | $2.58 | $3.99 | $3.50 | $4.08 | $3.75 |
| 75 | "U" section steel posts (713-11.01) | LB | 46 | $3.32 | $3.78 | $3.32 | $3.39 | $3.50 |
| 76 | Flat sheet aluminum signs (0.100" thick) (713-13.03) | SF | 10 | $16.32 | $18.61 | $16.32 | $16.65 | $18.00 |
| 77 | Removal of signs, posts and footings (713-15) | LS | 1 | $100.00 | $114.00 | $100.00 | $102.04 | $110.00 |
| 78 | Changeable message sign unit (713-16.01) | EACH | 4 | $5,495.00 | $6,264.30 | $5,495.00 | $5,607.14 | $6,000.00 |
| 79 | Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22) | EACH | 40 | $37.00 | $68.40 | $60.00 | $102.04 | $65.00 |
| 80 | Removal of snowplowable reflective marker (716-01.30) | EACH | 13 | $10.00 | $28.50 | $25.00 | $51.02 | $25.00 |
| 81 | Removal of pavement marking (line) (716-08.20) | LM | 2 | $5,280.00 | $3,420.00 | $3,000.00 | $5,102.04 | $3,200.00 |
| 82 | Wet reflective pavement marking(6" line) (716-09.03) | LM | 0.20 | $18,000 | $39,330 | $34,500 | $61,224 | $36,000 |
| 83 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 2 | $6,700.00 | $10,830 | $9,500.00 | $8,163.27 | $10,500 |
| 84 | Mobilization (717-01) | LS | 1 | $500,000 | $576,307 | $607,161 | $184,200 | $717,500 |
| 85 | Temporary traffic signal system (730-40.02) | LS | 1 | $95,000 | $117,042 | $84,500 | $111,225 | $65,000 |
| 86 | Geogrid reinforcement type 2 (740-07.04) | SY | 1,836 | $4.00 | $6.37 | $5.50 | $6.00 | $5.00 |
| 87 | Geotextile (type III)(erosion control) (740-10.03) | SY | 713 | $4.00 | $3.42 | $4.00 | $3.47 | $5.00 |
| 88 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 924 | $5.00 | $7.04 | $5.50 | $3.83 | $5.00 |
| 89 | Temporary sediment tube 20IN (740-11.04) | LF | 1,966 | $4.15 | $4.56 | $4.00 | $4.23 | $4.50 |
| 90 | 6IN dia PVC pipe (790-42.11) | LF | 127 | $20.00 | $44.46 | $50.00 | $35.00 | $72.00 |
| 91 | Seeding (with mulch) (801-01) | UNIT | 39 | $58.00 | $142.50 | $50.00 | $59.18 | $110.00 |
| 92 | Temporary seeding (with mulch) (801-01.07) | UNIT | 133 | $30.00 | $45.60 | $33.50 | $30.61 | $34.00 |
| 93 | Grass seed mix (ripzn/FLPL) W/mulch (801-01.35) | UNIT | 17 | $99.00 | $456.00 | $100.00 | $101.02 | $138.00 |
| 94 | Special wetland seed mixture (801-01.36) | UNIT | 2 | $400.00 | $256.50 | $225.00 | $408.16 | $250.00 |
| 95 | Natve seed MX final stablizatn of slopes (801-01.38) | UNIT | 6 | $140.00 | $228.00 | $200.00 | $142.86 | $220.00 |
| 96 | Seeding (without mulch) (801-02) | UNIT | 30 | $32.00 | $35.91 | $31.50 | $32.65 | $35.00 |
| 97 | Water (seeding & sodding) (801-03) | MG | 22 | $100.00 | $114.00 | $100.00 | $102.04 | $110.00 |
| 98 | Cuttings: salix nigra (18IN-24IN length) (802-02.30) | EACH | 35 | $8.90 | $12.35 | $10.83 | $9.08 | $11.00 |
| 99 | Cuttings: salix sericea (18IN-24IN) (802-02.31) | EACH | 35 | $8.90 | $12.35 | $10.83 | $9.08 | $11.00 |
| 100 | Cuttings: cornus amomum (18IN-24IN) (802-02.32) | EACH | 35 | $8.90 | $21.95 | $19.25 | $9.08 | $11.00 |
| 101 | Cuttings: sambucus canadensis (18IN-24IN) (802-02.33) | EACH | 35 | $8.90 | $12.35 | $10.83 | $9.08 | $11.00 |
| 102 | Acer negundo (box elder seedlng B.R.) (802-12.01) | EACH | 50 | $12.00 | $12.35 | $10.83 | $12.24 | $13.00 |
| 103 | Acer rubrum (red maple seedlng B.R.) (802-12.02) | EACH | 4 | $12.00 | $12.35 | $10.83 | $12.24 | $12.00 |
| 104 | Acer saccharinum (silver maple seedlng B.R.) (802-12.03) | EACH | 4 | $12.00 | $12.35 | $10.83 | $12.24 | $12.00 |
| 105 | Betula nigra (river birch seedlng B.R.) (802-12.07) | EACH | 46 | $12.00 | $12.35 | $10.83 | $12.24 | $13.00 |
| 106 | Diospyros virginiana (persimmon seedlng B.R.) (802-12.14) | EACH | 46 | $12.00 | $12.35 | $10.83 | $12.24 | $13.00 |
| 107 | Fraxinus pennsylvanica (green ash seedlng B.R.) (802-12.16) | EACH | 30 | $12.00 | $12.35 | $10.83 | $12.24 | $13.00 |
| 108 | Juglans nigra (black walnut seedlng B.R.) (802-12.17) | EACH | 46 | $12.00 | $12.35 | $10.83 | $12.24 | $13.00 |
| 109 | Liquidamber styraciflua (sweetgum seedlng B.R.) (802-12.18) | EACH | 4 | $12.00 | $12.35 | $10.83 | $12.24 | $12.00 |
| 110 | Liriodendron tulipifera (tulip poplar seedlng B.R.) (802-12.19) | EACH | 46 | $12.00 | $12.35 | $10.83 | $12.24 | $13.00 |
| 111 | Nyssa aquatica (swamp tupelo seedlng B.R.) (802-12.20) | EACH | 4 | $12.00 | $12.35 | $10.83 | $12.24 | $12.00 |
| 112 | Platanus occidentalis (sycamore seedlng B.R.) (802-12.26) | EACH | 46 | $12.00 | $12.35 | $10.83 | $12.24 | $17.00 |
| 113 | Quercus bicolor (swamp white oak seedlng B.R.) (802-12.30) | EACH | 4 | $12.00 | $12.35 | $10.83 | $12.24 | $12.00 |
| 114 | Quercus phellos (willow oak seedlng B.R.) (802-12.38) | EACH | 46 | $12.00 | $12.35 | $10.83 | $12.24 | $13.00 |
| 115 | Carpinus caroliniana (american hornbeam seedling B.R.) (802-12.45) | EACH | 30 | $12.00 | $12.35 | $10.83 | $12.24 | $14.00 |
| 116 | Cornus amomum (silky dogwood SDLNG bare root) (802-13.54) | EACH | 30 | $12.00 | $12.35 | $10.83 | $12.24 | $14.00 |
| 117 | Hamamelis virginiana (witch hazel SDLNG bare root) (802-13.55) | EACH | 30 | $12.00 | $12.35 | $10.83 | $12.24 | $14.00 |
| 118 | Lindera benzoin (spicebush SDLNG bare root) (802-13.59) | EACH | 30 | $12.00 | $12.35 | $10.83 | $12.24 | $14.00 |
| 119 | Sodding (new sod) (803-01) | SY | 1,720 | $7.10 | $6.84 | $6.00 | $7.24 | $6.50 |
| 120 | Turf reinforcement mat (class III) (805-01.03) | SY | 214.20 | $9.40 | $5.69 | $4.99 | $9.59 | $5.50 |
| 121 | Erosion control blanket (type II) (805-12.02) | SY | 2,029 | $1.00 | $1.25 | $1.10 | $1.02 | $1.25 |
| 122 | 700 gram coir fiber erosion blanket (805-12.08) | SY | 970 | $4.70 | $11.40 | $7.50 | $4.80 | $12.00 |
| 123 | Removal of structures (bridge no. 16-SR127-06.21) (202-04.01) | LS | 1 | $85,000 | $93,388 | $50,000 | $170,250 | $125,000 |
| 124 | Removal of structures (bridge no. 16-SR127-09.76) (202-04.02) | LS | 1 | $85,000 | $130,643 | $125,000 | $160,875 | $110,000 |
| 125 | Dry excavation (bridges) (204-02.01) | CY | 2,095 | $35.00 | $53.36 | $38.00 | $42.45 | $70.00 |
| 126 | Core drilling for piles(rock) (204-14) | LF | 70 | $850.00 | $342.00 | $300.00 | $361.22 | $425.00 |
| 127 | Core drilling for piles(soil) (204-15) | LF | 92 | $790.00 | $342.00 | $300.00 | $271.43 | $420.00 |
| 128 | Granular backfill (bridges) (303-01.02) | TON | 72 | $75.00 | $47.21 | $100.00 | $150.68 | $60.00 |
| 129 | Epoxy coated reinforcing steel (604-02.03) | LB | 64,606 | $2.00 | $2.41 | $1.90 | $1.52 | $2.25 |
| 130 | Class A concrete (bridges) (604-03.01) | CY | 143 | $1,300.00 | $1,321.03 | $1,100.00 | $1,655.44 | $1,850.00 |
| 131 | Pavement @ bridge ends (604-03.04) | SY | 434 | $430.00 | $421.16 | $425.00 | $495.81 | $550.00 |
| 132 | Class DS concrete (604-03.32) | CY | 186 | $1,500.00 | $1,417.92 | $1,500.00 | $1,365.89 | $1,900.00 |
| 133 | Applied texture finish (new structures) (604-04.01) | SY | 780 | $20.00 | $18.24 | $16.00 | $15.00 | $17.00 |
| 134 | Bridge deck grooving (mechanical) (604-05.31) | SY | 1,110 | $10.00 | $8.41 | $7.38 | $7.53 | $9.00 |
| 135 | Remove existing wearing surface (604-10.14) | LS | 1 | $57,500 | $43,320 | $45,000 | $18,750 | $50,000 |
| 136 | Steel piles (12 inch) (606-03.03) | LF | 857 | $100.00 | $139.42 | $70.00 | $177.55 | $150.00 |
| 137 | Pile tips (steel piles, 12 inch) (606-03.06) | EACH | 14 | $165.00 | $388.11 | $225.00 | $240.63 | $240.00 |
| 138 | Prestressed concrete box beam (33" X 36") (615-02.05) | LF | 700 | $502.00 | $509.91 | $475.00 | $491.13 | $450.00 |
| 139 | Concrete railing (620-06) | LF | 374 | $200.00 | $166.55 | $350.00 | $310.19 | $575.00 |
| 140 | Temporary shoring (bridge no. 16-SR127-06.21) (621-05.10) | LS | 1 | $25,000 | $30,750 | $100,000 | $50,000 | $125,000 |
| 141 | 6" perforated pipe with vertical drain system (710-09.01) | LF | 230 | $50.00 | $45.39 | $45.00 | $60.00 | $60.00 |
| 142 | 6" pipe underdrain (710-09.02) | LF | 136 | $18.00 | $31.92 | $25.00 | $30.00 | $30.00 |
| 143 | 2IN steel gas main (791-01.02) | LF | 10 | $729.00 | $831.06 | $650.00 | $663.27 | $720.00 |
| 144 | 6IN steel gas main (791-01.05) | LF | 600 | $98.00 | $111.72 | $290.00 | $295.92 | $320.00 |
| 145 | HDD 6IN steel pipe - unconsolidated (791-04.23) | LF | 1,005 | $260.00 | $296.40 | $435.00 | $443.88 | $480.00 |
| 146 | Connect to 6IN EX. STL main W/ stopple (791-06.33) | EACH | 6 | $21,200 | $24,168 | $27,000 | $27,551 | $28,000 |
| 147 | 2IN steel gas valve assembly (791-07.09) | EACH | 2 | $5,250.00 | $5,985.00 | $4,500.00 | $4,591.84 | $4,750.00 |
| 148 | 6IN steel gas valve assembly (791-07.11) | EACH | 3 | $36,750 | $41,895 | $43,000 | $43,878 | $47,750 |
| 149 | Pole 35FT class 4 wood (793-01.07) | EACH | 2 | $975.00 | $1,111.50 | $3,500.00 | $4,122.45 | $3,800.00 |
| 150 | Anchor 3/4IN (793-01.40) | EACH | 6 | $487.50 | $555.75 | $800.00 | $942.86 | $875.00 |
| 151 | Install pole number (793-01.99) | EACH | 1 | $63.00 | $71.82 | $120.00 | $201.02 | $130.00 |
| 152 | Guy wire 10M or 3/8IN (793-02.08) | EACH | 10 | $142.50 | $162.45 | $275.00 | $387.76 | $305.00 |
| 153 | Install guy guard (793-02.99) | EACH | 8 | $28.20 | $32.15 | $90.00 | $95.41 | $100.00 |
| 154 | 10M strand (793-03.03) | LF | 2,868 | $3.45 | $3.93 | $3.95 | $5.82 | $4.50 |
| 155 | Install strand bond (793-03.40) | EACH | 6 | $34.80 | $39.67 | $50.00 | $189.80 | $55.00 |
| 156 | Relash/delash cable (793-04.01) | LF | 1,400 | $2.03 | $2.31 | $3.26 | $4.69 | $3.50 |
| 157 | Aerial splice closure (793-04.07) | EACH | 7 | $900.00 | $1,026.00 | $850.00 | $1,076.53 | $943.00 |
| 158 | Aerial splice closure (3M) (793-04.13) | EACH | 7 | $1,702.50 | $1,940.85 | $1,000.00 | $1,306.12 | $1,100.00 |
| 159 | 96 fiber(material only) (793-07.05) | LF | 1,100 | $2.61 | $2.98 | $2.23 | $2.81 | $2.50 |
| 160 | 144 fiber(material only) (793-07.07) | LF | 2,734 | $3.19 | $3.64 | $3.01 | $3.83 | $3.50 |
| 161 | 192 fiber(material only) (793-07.08) | LF | 2,734 | $4.43 | $5.05 | $2.89 | $4.08 | $3.20 |
| 162 | 288 fiber(material only) (793-07.10) | LF | 2,200 | $5.25 | $5.99 | $3.39 | $4.85 | $3.75 |
| 163 | 108-144 fiber(installation only) (793-07.17) | LF | 3,268 | $2.33 | $2.66 | $3.12 | $4.08 | $3.50 |
| 164 | 192-216 fiber(installation only) (793-07.18) | LF | 1,734 | $2.63 | $3.00 | $3.12 | $4.08 | $3.50 |
| 165 | Single fiber optic cable splice (793-07.25) | EACH | 6 | $52.50 | $59.85 | $50.00 | $98.98 | $55.50 |
| 166 | 120 fiber(material only) (793-07.26) | LF | 1,634 | $3.19 | $3.64 | $3.01 | $3.47 | $3.50 |
| 167 | Hot splice existing fiber cables (793-07.41) | EACH | 2,424 | $37.65 | $42.92 | $46.60 | $72.45 | $50.00 |
| 168 | Install fiber storage bracket (793-07.90) | EACH | 22 | $142.50 | $162.45 | $235.00 | $322.45 | $260.00 |
| 169 | Rearrange existing fiber storage bracket (793-07.91) | EACH | 2 | $96.75 | $110.30 | $100.00 | $126.53 | $111.00 |
| 170 | Buried cable @ 36IN depth (793-10.02) | LF | 4,400 | $5.63 | $6.42 | $5.90 | $17.35 | $6.50 |
| 171 | Buried riser guard (793-11.13) | EACH | 20 | $236.25 | $269.33 | $300.00 | $408.16 | $333.00 |
| 172 | 2 pair buried drop (793-11.14) | LF | 950 | $8.10 | $9.23 | $5.09 | $7.35 | $5.00 |
| 173 | Rearrange existing splice case (793-11.50) | EACH | 2 | $525.00 | $598.50 | $250.00 | $318.37 | $277.00 |
| 174 | Transfer cable attachment (793-15.01) | EACH | 22 | $139.80 | $159.37 | $325.00 | $254.08 | $360.00 |
| 175 | Transfer drop attachment (793-15.02) | EACH | 1 | $46.50 | $53.01 | $215.00 | $282.65 | $238.00 |
| 176 | HDD 2IN PVC casing in rock (793-15.21) | LF | 200 | $209.50 | $238.83 | $115.00 | $135.71 | $128.00 |
| 177 | Directional bore 2IN/flex sleeve (793-16.02) | LF | 400 | $33.30 | $37.96 | $37.00 | $69.90 | $41.00 |
| 178 | Remove aerial cable and wire (793-98.01) | LF | 5,356 | $1.20 | $1.37 | $1.41 | $2.04 | $1.50 |
| 179 | Remove poles all sizes (793-98.04) | EACH | 10 | $120.00 | $136.80 | $360.00 | $556.12 | $400.00 |
| 180 | Remove anchor (any size) (793-98.08) | EACH | 3 | $48.00 | $54.72 | $95.00 | $126.53 | $106.00 |
| 181 | Remove down guy (793-98.09) | EACH | 10 | $36.00 | $41.04 | $95.00 | $126.53 | $106.00 |
| 182 | Trim utility right-of-way (793-98.21) | LF | 200 | $6.00 | $6.84 | $9.94 | $14.29 | $11.00 |
| 183 | 4IN dip slip joint water line (795-01.02) | LF | 700 | $140.00 | $159.60 | $84.00 | $160.20 | $200.00 |
| 184 | 6IN dip slip joint water line (795-01.04) | LF | 620 | $140.00 | $159.60 | $72.00 | $153.06 | $184.00 |
| 185 | Bore/jack 12IN steel casing pipe-rock. (795-05.77) | LF | 120 | $600.00 | $684.00 | $822.00 | $1,035.71 | $1,620.00 |
| 186 | 4IN gate valve assembly (795-08.03) | EACH | 2 | $3,100.00 | $3,534.00 | $1,843.00 | $1,887.76 | $4,196.00 |
| 187 | 6IN gate valve assembly (795-08.04) | EACH | 2 | $3,700.00 | $4,218.00 | $2,378.00 | $2,489.80 | $4,830.00 |
| 188 | 3/4IN service pipe (795-09.37) | LF | 150 | $40.00 | $45.60 | $41.00 | $63.27 | $160.00 |
| 189 | DI fittings (795-13.01) | LB | 1,500 | $12.00 | $13.68 | $12.00 | $15.31 | $15.31 |
| 190 | Class B concrete (795-14.02) | CY | 25 | $350.00 | $399.00 | $413.00 | $306.12 | $550.00 |
| 191 | Relocate/reconnect 3/4IN water meter assembly (795-16.16) | EACH | 3 | $3,000.00 | $3,420.00 | $1,293.00 | $1,387.76 | $1,430.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of August 14, 2026. Compiled by Mirage Metrics.