TDOT contract CN264057 bid tabulation
The grading, drainage, and paving on a s.i.a. route serving packaging corporation of america, including construction of turn lanes on s.r. 57. Let by Tennessee DOT on October 2, 2026, Hardin County. 5 bids received; low bid $2,998,959 by Delta Contracting Company, LLC.
- Owner
- Tennessee DOT
- Letting
- 02 OCT 2026
- Pay items
- 105
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Delta Contracting Company, LLC | $2,998,959 | Low |
| 2 | VuCon, LLC | $3,710,545 | +24% |
| 3 | Kenneth Rich Construction Company, Inc. | $3,921,558 | +31% |
| 4 | Jones Bros. Contractors, LLC | $4,134,819 | +38% |
| 5 | Volunteer Bridge Construction, Inc. | $4,950,805 | +65% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Delta Contracting Company, LLC | 2. VuCon, LLC | 3. Kenneth Rich Construction Company, Inc. | 4. Jones Bros. Contractors, LLC | 5. Volunteer Bridge Construction, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $38,000 | $55,000 | $32,340 | $90,000 | $50,000 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $109,600 | $120,000 | $98,175 | $75,000 | $200,000 |
| 3 | Removal of structures and obstructions (202-01) | LS | 1 | $1,100.00 | $6,050.00 | $3,902.25 | $35,000 | $30,000 |
| 4 | Removal of pipe (8", 211+19) (202-02.01) | LF | 22 | $25.00 | $49.00 | $17.33 | $40.00 | $50.00 |
| 5 | Water well abandonment (202-13) | EACH | 1 | $5,000.00 | $28,000 | $6,615.00 | $14,500 | $8,000.00 |
| 6 | Road & drainage excavation (unclassified) (203-01) | CY | 66,183 | $10.30 | $9.00 | $10.15 | $14.15 | $12.00 |
| 7 | Borrow excavation (unclassified) (203-03) | CY | 5,946 | $0.10 | $11.00 | $1.04 | $1.00 | $20.00 |
| 8 | Placing and spreading topsoil (203-04) | CY | 2,572 | $8.75 | $7.00 | $5.78 | $13.25 | $25.00 |
| 9 | Water (203-06) | MG | 96 | $25.00 | $40.00 | $19.64 | $10.00 | $100.00 |
| 10 | Furnishing & spreading topsoil (203-07) | CY | 1,230 | $9.00 | $23.00 | $28.49 | $13.25 | $50.00 |
| 11 | Channel substrate (203-20.01) | CY | 16 | $300.00 | $165.00 | $18.49 | $250.00 | $175.00 |
| 12 | Foundation fill material (204-08) | CY | 11 | $250.00 | $115.00 | $36.96 | $115.00 | $250.00 |
| 13 | Backfill material (flowable fill) (204-08.01) | CY | 9 | $425.00 | $470.00 | $265.09 | $425.00 | $400.00 |
| 14 | Brooming & degrassing shoulders (208-01.05) | LM | 0.20 | $2,000.00 | $5,500.00 | $44,100 | $1,500.00 | $5,000.00 |
| 15 | 12" temporary slope drain (209-02.05) | LF | 65 | $13.00 | $38.00 | $31.84 | $20.00 | $100.00 |
| 16 | Filter sock (24 inch) (209-03.23) | LF | 2,950 | $10.00 | $11.00 | $19.61 | $10.00 | $15.00 |
| 17 | Sediment removal (209-05) | CY | 302 | $9.00 | $28.00 | $28.88 | $15.00 | $2.00 |
| 18 | Temporary silt fence (with backing) (209-08.02) | LF | 4,436 | $5.50 | $6.00 | $6.83 | $5.50 | $7.50 |
| 19 | Temporary silt fence (without backing) (209-08.03) | LF | 2,706 | $2.50 | $3.00 | $4.73 | $2.50 | $4.50 |
| 20 | Rock check dam (209-08.07) | EACH | 10 | $1,000.00 | $1,500.00 | $472.68 | $950.00 | $1,500.00 |
| 21 | Enhanced rock check dam (209-08.08) | EACH | 13 | $1,500.00 | $1,700.00 | $709.03 | $1,050.00 | $2,500.00 |
| 22 | Sandbags (209-09.01) | BAG | 1,975 | $2.75 | $6.00 | $12.23 | $6.00 | $10.00 |
| 23 | Sediment filter bag (15' X 15') (209-09.03) | EACH | 3 | $500.00 | $5,000.00 | $1,222.57 | $825.00 | $500.00 |
| 24 | Polyethylene sheeting (10 mil.) (209-20.04) | SY | 1,235 | $2.00 | $6.00 | $6.78 | $4.00 | $8.00 |
| 25 | Temporary diversion channel (209-65.03) | LF | 235 | $5.00 | $97.00 | $10.40 | $82.00 | $175.00 |
| 26 | Mineral aggregate, type A base, grading D (303-01) | TON | 6,700 | $38.00 | $46.00 | $39.97 | $48.00 | $50.00 |
| 27 | Granular backfill (roadway) (303-01.01) | TON | 192 | $50.00 | $70.00 | $43.59 | $45.00 | $50.00 |
| 28 | Mineral aggregate, type B base, grading (C or D) (303-02) | TON | 200 | $35.00 | $55.00 | $38.52 | $48.00 | $50.00 |
| 29 | Mineral aggregate (size 57) (303-10.01) | TON | 56 | $45.00 | $110.00 | $42.43 | $58.00 | $60.00 |
| 30 | Asp. conc. mix(PG70-22) (BPMB-HM) GR. A-S (307-01.21) | TON | 970 | $133.00 | $147.00 | $139.65 | $150.00 | $140.00 |
| 31 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01) | TON | 1,670 | $142.00 | $156.00 | $149.10 | $140.00 | $146.00 |
| 32 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08) | TON | 1,410 | $156.00 | $172.00 | $163.80 | $160.00 | $160.00 |
| 33 | Bituminous material for tack coat (TC) (403-01) | TON | 11 | $225.00 | $248.00 | $236.25 | $780.00 | $1,000.00 |
| 34 | Saw cutting asphalt pavement (407-20.05) | LF | 1,100 | $4.09 | $8.00 | $12.60 | $3.50 | $12.00 |
| 35 | Acs mix(PG70-22) grading D (411-02.10) | TON | 740 | $192.00 | $212.00 | $201.60 | $170.00 | $200.00 |
| 36 | Scoring shoulders (non-continuous) (16IN width) (411-12.02) | LM | 0.40 | $15,000 | $30,000 | $24,386 | $23,225 | $25,000 |
| 37 | Cold planing bituminous pavement (415-01.02) | SY | 3,735 | $4.00 | $4.50 | $4.20 | $11.15 | $25.00 |
| 38 | Class A concrete (box bridges) (604-02.01) | CY | 70 | $894.00 | $717.00 | $3,288.01 | $1,300.00 | $2,000.00 |
| 39 | Steel bar reinforcement (box bridges) (604-02.02) | LB | 12,587 | $2.50 | $2.00 | $1.16 | $2.75 | $3.50 |
| 40 | 18" concrete pipe culvert (class III) (607-03.02) | LF | 152 | $80.00 | $80.00 | $58.83 | $110.00 | $80.00 |
| 41 | 30" concrete pipe culvert (class IV) trenchless (607-06.10) | LF | 124 | $1,200.00 | $1,700.00 | $2,320.44 | $1,400.00 | $1,700.00 |
| 42 | 72" concrete pipe culvert (class III) (607-13.03) | LF | 152 | $400.00 | $367.00 | $509.46 | $545.00 | $700.00 |
| 43 | Spring drain box, type 1 (611-02.01) | EACH | 1 | $3,800.00 | $2,915.00 | $8,281.93 | $8,500.00 | $6,000.00 |
| 44 | Class A concrete (pipe endwalls) (611-07.01) | CY | 34 | $1,275.00 | $715.00 | $1,047.56 | $2,150.00 | $2,000.00 |
| 45 | Steel bar reinforcement (pipe endwalls) (611-07.02) | LB | 2,230 | $2.50 | $2.00 | $3.41 | $6.25 | $5.00 |
| 46 | 18IN endwall (cross drain) 4:1 (611-07.55) | EACH | 2 | $3,800.00 | $3,150.00 | $2,927.71 | $2,200.00 | $5,500.00 |
| 47 | 24IN endwall (cross drain) 3:1 (611-07.57) | EACH | 1 | $4,200.00 | $3,550.00 | $3,264.46 | $2,600.00 | $7,500.00 |
| 48 | 48IN endwall (cross drain) 3:1 (611-07.69) | EACH | 2 | $6,000.00 | $8,300.00 | $8,853.66 | $13,000 | $10,000 |
| 49 | 18" temporary drainage pipe (621-03.02) | LF | 36 | $30.00 | $68.00 | $43.95 | $40.00 | $120.00 |
| 50 | 48" temporary drainage pipe (621-03.07) | LF | 70 | $100.00 | $144.00 | $215.00 | $135.00 | $300.00 |
| 51 | Earth pad for guard rail end treatment (705-04.10) | EACH | 2 | $975.00 | $2,000.00 | $346.50 | $1,875.00 | $2,000.00 |
| 52 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 575 | $36.00 | $33.00 | $30.19 | $28.75 | $40.00 |
| 53 | W beam GR (type 2) MASH TL-3 (long post) (705-06.02) | LF | 287.50 | $38.75 | $36.50 | $39.11 | $37.25 | $45.00 |
| 54 | GR terminal (energy absorbing) MASH TL-2 (705-06.30) | EACH | 8 | $3,300.00 | $3,700.00 | $2,835.00 | $2,700.00 | $3,500.00 |
| 55 | Radius rail (706-06.03) | LF | 75 | $48.00 | $46.00 | $38.59 | $36.75 | $55.00 |
| 56 | High-visibility construction fence (707-08.11) | LF | 1,290 | $2.50 | $3.00 | $0.84 | $2.50 | $4.50 |
| 57 | Markers (concrete R.O.W. posts) (708-02.01) | EACH | 8 | $400.00 | $550.00 | $420.00 | $350.00 | $400.00 |
| 58 | Machined rip-rap (class A-3) (709-05.05) | TON | 270 | $50.00 | $78.00 | $55.37 | $70.00 | $60.00 |
| 59 | Machined rip-rap (class A-1) (709-05.06) | TON | 320 | $50.00 | $69.00 | $55.37 | $70.00 | $60.00 |
| 60 | Machined rip-rap (class B) (709-05.08) | TON | 93 | $50.00 | $66.00 | $56.40 | $70.00 | $60.00 |
| 61 | Machined rip-rap (class C) (709-05.09) | TON | 102 | $50.00 | $83.00 | $65.64 | $70.00 | $60.00 |
| 62 | Aggregate underdrains (with pipe) (710-02) | LF | 2,820 | $14.75 | $16.50 | $29.41 | $14.75 | $125.00 |
| 63 | Filter cloth underdrain (with pipe) (710-04) | LF | 1,240 | $18.25 | $20.00 | $49.02 | $18.25 | $60.00 |
| 64 | Lateral underdrain (710-05) | LF | 220 | $14.25 | $16.00 | $42.11 | $14.25 | $65.00 |
| 65 | Lateral underdrain endwall (4:1) (710-06.13) | EACH | 15 | $1,125.00 | $1,250.00 | $1,569.07 | $1,125.00 | $4,500.00 |
| 66 | Lateral underdrain endwall (5:1) (710-06.14) | EACH | 5 | $1,125.00 | $1,250.00 | $864.81 | $1,125.00 | $4,500.00 |
| 67 | Traffic control (712-01) | LS | 1 | $30,050 | $35,000 | $68,250 | $150,000 | $125,000 |
| 68 | Portable barrier rail, reduced deflection (MASH TL-3) (712-02.12) | LF | 1,000 | $5.00 | $120.00 | $63.00 | $85.00 | $160.00 |
| 69 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 2 | $750.00 | $6,615.00 | $5,040.00 | $4,800.00 | $6,000.00 |
| 70 | Flexible drums (channelizing) (712-04.01) | EACH | 60 | $35.00 | $31.00 | $36.75 | $35.00 | $50.00 |
| 71 | Barrier rail delineator (712-04.50) | EACH | 75 | $10.00 | $11.00 | $10.50 | $10.00 | $15.00 |
| 72 | Warning lights (type A) (712-05.01) | EACH | 12 | $10.00 | $17.00 | $10.50 | $10.00 | $15.00 |
| 73 | Warning lights (type C) (712-05.03) | EACH | 20 | $10.00 | $17.00 | $10.50 | $10.00 | $15.00 |
| 74 | Signs (construction) (712-06) | SF | 136 | $6.00 | $8.00 | $6.30 | $6.00 | $16.00 |
| 75 | Removable pavement marking (6" line) (712-09.08) | LF | 4,400 | $6.00 | $7.00 | $7.35 | $6.00 | $7.50 |
| 76 | Sign post delineation enhancement (713-02.21) | LF | 43 | $5.50 | $4.00 | $5.78 | $5.50 | $7.50 |
| 77 | Perforated/knockout square tube post (713-11.02) | LB | 241 | $4.00 | $4.00 | $4.20 | $4.00 | $6.25 |
| 78 | Flat sheet aluminum signs (0.080" thick) (713-13.02) | SF | 9 | $14.00 | $13.00 | $14.70 | $14.00 | $17.00 |
| 79 | Flat sheet aluminum signs (0.100" thick) (713-13.03) | SF | 52.50 | $14.50 | $14.00 | $15.23 | $14.50 | $17.50 |
| 80 | Changeable message sign unit (713-16.01) | EACH | 2 | $5,000.00 | $5,000.00 | $5,250.00 | $5,000.00 | $7,000.00 |
| 81 | Dead end sign and support (713-16.06) | EACH | 1 | $175.00 | $440.00 | $183.75 | $175.00 | $17.00 |
| 82 | End of roadway sign and support (713-16.07) | EACH | 4 | $150.00 | $331.00 | $157.50 | $150.00 | $200.00 |
| 83 | Railroad advance warning sign and support (713-16.09) | EACH | 1 | $225.00 | $440.00 | $236.25 | $225.00 | $400.00 |
| 84 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 95 | $62.00 | $69.00 | $67.20 | $62.00 | $68.00 |
| 85 | Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22) | EACH | 10 | $62.00 | $69.00 | $67.20 | $62.00 | $68.00 |
| 86 | Plastic pavement marking(channelization striping) (716-02.04) | SY | 52 | $48.00 | $53.00 | $52.50 | $48.00 | $52.00 |
| 87 | Plastic pavement marking (stop line) (716-02.05) | LF | 66 | $35.00 | $39.00 | $38.85 | $35.00 | $38.00 |
| 88 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 8 | $250.00 | $280.00 | $273.00 | $250.00 | $300.00 |
| 89 | Plastic pavement marking (8" dotted line) (716-02.08) | LF | 200 | $4.00 | $5.00 | $4.73 | $4.00 | $6.00 |
| 90 | Plastic word pavement marking (RXR) (716-03.02) | EACH | 1 | $1,500.00 | $1,700.00 | $1,680.00 | $1,500.00 | $2,000.00 |
| 91 | Painted pavement marking (4" line) (716-05.01) | LM | 1 | $3,500.00 | $3,850.00 | $3,780.00 | $3,500.00 | $4,500.00 |
| 92 | Painted pavement marking (6" line) (716-05.20) | LM | 0.80 | $3,500.00 | $3,850.00 | $3,780.00 | $3,500.00 | $4,500.00 |
| 93 | Painted pavement marking(4"dotted line) (716-05.21) | LF | 535 | $2.00 | $3.00 | $2.63 | $2.00 | $3.00 |
| 94 | Removal of pavement marking (line) (716-08.20) | LM | 0.80 | $5,100.00 | $5,700.00 | $5,460.00 | $5,100.00 | $6,200.00 |
| 95 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 1.20 | $9,800.00 | $11,000 | $10,395 | $9,800.00 | $11,000 |
| 96 | Mobilization (717-01) | LS | 1 | $94,278 | $315,000 | $254,100 | $410,000 | $150,000 |
| 97 | Geotextile (type III)(erosion control) (740-10.03) | SY | 1,129 | $2.00 | $11.00 | $8.54 | $3.75 | $15.00 |
| 98 | Temporary sediment tube 24IN (740-11.05) | LF | 5,165 | $7.00 | $8.00 | $24.72 | $7.00 | $9.00 |
| 99 | Temporary seeding (with mulch) (801-01.07) | UNIT | 672 | $30.00 | $33.00 | $54.81 | $30.00 | $40.00 |
| 100 | Natve seed MX final stablizatn of slopes (801-01.38) | UNIT | 9 | $300.00 | $331.00 | $210.00 | $300.00 | $400.00 |
| 101 | Seeding (without mulch) (801-02) | UNIT | 3 | $100.00 | $110.00 | $105.00 | $100.00 | $200.00 |
| 102 | Fertilizer (801-02.15) | TON | 10 | $500.00 | $550.00 | $525.00 | $500.00 | $600.00 |
| 103 | Water (seeding & sodding) (801-03) | MG | 374 | $1.00 | $1.00 | $19.95 | $1.00 | $125.00 |
| 104 | Sodding (new sod) (803-01) | SY | 26,640 | $3.75 | $4.00 | $3.94 | $3.75 | $4.75 |
| 105 | Turf reinforcement mat (class I) (805-01.01) | SY | 42 | $20.00 | $22.00 | $21.00 | $20.00 | $35.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of October 2, 2026. Compiled by Mirage Metrics.