TDOT contract CNZ271 bid tabulation
The grading, drainage, signals, and paving on u.s. 11e (s.r. 34) at the intersection of stockyard road and precision boulevard (l.m. 4.89 - l.m. 5.49), and construction of a s.i.a. route serving appalachian producers. Let by Tennessee DOT on October 3, 2025, Washington County. 3 bids received; low bid $3,283,917 by Baker's Construction Services, Inc..
- Owner
- Tennessee DOT
- Letting
- 03 OCT 2025
- Pay items
- 93
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Baker's Construction Services, Inc. | $3,283,917 | Low |
| 2 | Adams Contracting, LLC | $3,641,946 | +11% |
| 3 | Summers-Taylor, Inc. | $4,220,636 | +29% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Baker's Construction Services, Inc. | 2. Adams Contracting, LLC | 3. Summers-Taylor, Inc. |
|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $52,744 | $40,000 | $22,100 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $130,366 | $150,000 | $98,800 |
| 3 | Road & drainage excavation (unclassified) (203-01) | CY | 24,188 | $22.22 | $30.00 | $52.50 |
| 4 | Borrow excavation (graded solid rock) (203-02.01) | TON | 270 | $68.81 | $90.00 | $91.00 |
| 5 | Placing and spreading topsoil (203-04) | CY | 966 | $20.76 | $28.00 | $33.50 |
| 6 | Water (203-06) | MG | 15 | $23.30 | $100.00 | $17.00 |
| 7 | Sediment removal (209-05) | CY | 200 | $50.09 | $10.00 | $40.00 |
| 8 | Rock check dam (209-08.07) | EACH | 99 | $630.20 | $985.00 | $593.00 |
| 9 | Enhanced rock check dam (209-08.08) | EACH | 8 | $850.45 | $1,500.00 | $1,050.00 |
| 10 | Catch basin protection (type D) (209-40.33) | EACH | 1 | $398.45 | $1,250.00 | $722.00 |
| 11 | Mineral aggregate, type A base, grading D (303-01) | TON | 5,441 | $55.83 | $70.00 | $66.25 |
| 12 | Mineral aggregate (size 57) (303-10.01) | TON | 130 | $77.77 | $125.00 | $86.50 |
| 13 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01) | TON | 810 | $218.90 | $210.00 | $199.00 |
| 14 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 641 | $225.50 | $217.00 | $205.00 |
| 15 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01) | TON | 175 | $328.90 | $317.00 | $299.00 |
| 16 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08) | TON | 135 | $317.90 | $306.00 | $289.00 |
| 17 | Bituminous material for prime coat (PC) (402-01) | TON | 19 | $2,420.00 | $2,300.00 | $2,200.00 |
| 18 | Aggregate for cover material (PC) (402-02) | TON | 75 | $137.50 | $130.00 | $125.00 |
| 19 | Bituminous material for tack coat (TC) (403-01) | TON | 5 | $1,512.50 | $1,400.00 | $1,375.00 |
| 20 | Acs mix(PG64-22) grading D (411-01.10) | TON | 393 | $273.90 | $260.00 | $249.00 |
| 21 | Acs mix(PG70-22) grading D (411-02.10) | TON | 1,450 | $231.00 | $220.00 | $210.00 |
| 22 | Scoring shoulders (non-continuous) (16IN width) (411-12.02) | LM | 0.50 | $3,300.00 | $20,000 | $22,741 |
| 23 | Cold planing bituminous pavement (415-01.01) | TON | 660 | $86.90 | $84.00 | $79.00 |
| 24 | Cold planing bituminous pavement (415-01.02) | SY | 20 | $82.50 | $80.00 | $75.00 |
| 25 | 18" pipe culvert (607-03.30) | LF | 194 | $226.52 | $130.00 | $241.00 |
| 26 | Class A concrete (pipe endwalls) (611-07.01) | CY | 2 | $3,563.90 | $3,500.00 | $3,990.00 |
| 27 | Steel bar reinforcement (pipe endwalls) (611-07.02) | LB | 90 | $9.32 | $6.75 | $0.95 |
| 28 | 18IN endwall (cross drain) 4:1 (611-07.55) | EACH | 1 | $3,218.58 | $3,800.00 | $3,200.00 |
| 29 | Markers (concrete R.O.W. posts) (708-02.01) | EACH | 24 | $543.91 | $550.00 | $632.00 |
| 30 | Machined rip-rap (class A-3) (709-05.05) | TON | 250 | $73.60 | $85.00 | $89.00 |
| 31 | Machined rip-rap (class A-1) (709-05.06) | TON | 100 | $73.47 | $85.00 | $127.00 |
| 32 | Traffic control (712-01) | LS | 1 | $85,552 | $125,000 | $94,500 |
| 33 | Interconnected portable barrier rail (712-02.02) | LF | 1,200 | $73.53 | $50.00 | $130.00 |
| 34 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 3 | $10,375 | $10,900 | $12,000 |
| 35 | Flexible drums (channelizing) (712-04.01) | EACH | 170 | $40.85 | $34.00 | $34.00 |
| 36 | Warning lights (type A) (712-05.01) | EACH | 18 | $30.80 | $30.00 | $30.00 |
| 37 | Warning lights (type C) (712-05.03) | EACH | 65 | $30.80 | $30.00 | $30.00 |
| 38 | Signs (construction) (712-06) | SF | 665 | $10.71 | $7.75 | $7.70 |
| 39 | Temporary barricades (type III) (712-07.03) | LF | 150 | $24.50 | $17.00 | $17.00 |
| 40 | Arrow board (type C) (712-08.03) | EACH | 4 | $2,785.94 | $1,300.00 | $1,270.00 |
| 41 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 1,120 | $4.57 | $4.25 | $5.10 |
| 42 | Perforated/knockout square tube post (713-11.02) | LB | 425 | $5.50 | $5.50 | $5.30 |
| 43 | Flat sheet aluminum signs (0.080" thick) (713-13.02) | SF | 25 | $16.34 | $16.00 | $15.50 |
| 44 | Flat sheet aluminum signs (0.100" thick) (713-13.03) | SF | 61 | $17.05 | $17.00 | $16.50 |
| 45 | Street name sign (rigid 0.100IN thick (713-14.21) | SF | 79 | $61.60 | $105.00 | $119.00 |
| 46 | Removal of signs, posts and footings (713-15) | LS | 1 | $550.00 | $530.00 | $526.00 |
| 47 | Suspended flat sheet aluminum sign (0.080" thick) (713-15.07) | EACH | 2 | $1,540.00 | $600.00 | $631.00 |
| 48 | Changeable message sign unit (713-16.01) | EACH | 4 | $8,801.01 | $6,700.00 | $8,700.00 |
| 49 | Signs (stop sign) (713-16.20) | EACH | 1 | $567.87 | $320.00 | $316.00 |
| 50 | Signs (speed limit sign) (713-16.21) | EACH | 1 | $918.74 | $320.00 | $316.00 |
| 51 | Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22) | EACH | 30 | $52.25 | $51.00 | $52.50 |
| 52 | Snowplowable raised pavement markers (BI-dir)(2 color) (716-01.23) | EACH | 110 | $52.25 | $51.00 | $52.50 |
| 53 | Plastic pavement marking(channelization striping) (716-02.04) | SY | 30 | $33.00 | $32.00 | $35.50 |
| 54 | Plastic pavement marking (stop line) (716-02.05) | LF | 135 | $12.65 | $13.00 | $15.50 |
| 55 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 13 | $192.50 | $190.00 | $223.00 |
| 56 | Plastic pavement marking (8" dotted line) (716-02.08) | LF | 1,200 | $2.48 | $2.50 | $2.25 |
| 57 | Plastic pavement marking (straight-turn arrow) (716-04.01) | EACH | 2 | $214.50 | $210.00 | $287.00 |
| 58 | Plastic pavement marking (straight arrow) (716-04.05) | EACH | 1 | $165.00 | $160.00 | $223.00 |
| 59 | Plastic pavement marking (yield line) (716-04.12) | SF | 12 | $19.25 | $19.00 | $32.00 |
| 60 | Painted pavement marking (4" line) (716-05.01) | LM | 3 | $1,100.00 | $1,100.00 | $3,190.00 |
| 61 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 2 | $7,425.00 | $7,200.00 | $9,560.00 |
| 62 | Enhanced flat line thermo (12IN line) (716-12.09) | LF | 400 | $4.92 | $4.25 | $2.85 |
| 63 | Mobilization (717-01) | LS | 1 | $211,098 | $350,000 | $389,700 |
| 64 | Signal head assembly (130 A3 with backplate) (730-02.03) | EACH | 2 | $2,530.00 | $2,100.00 | $2,450.00 |
| 65 | Signal head assembly (130 with backplate) (730-02.09) | EACH | 4 | $3,080.00 | $2,100.00 | $2,430.00 |
| 66 | Signal head assembly (140 A1 with backplate) (730-02.14) | EACH | 2 | $3,575.00 | $2,500.00 | $2,900.00 |
| 67 | Signal head assembly (150 A2H with backplate) (730-02.17) | EACH | 2 | $3,630.00 | $3,200.00 | $3,700.00 |
| 68 | Install pull box (type B) (730-03.21) | EACH | 14 | $3,850.00 | $1,450.00 | $1,610.00 |
| 69 | Electrical service connection (730-05.01) | EACH | 1 | $4,950.00 | $10,000 | $10,800 |
| 70 | Signal cable - 5 conductor (730-08.02) | LF | 2,362 | $2.78 | $3.30 | $3.75 |
| 71 | Signal cable - 7 conductor (730-08.03) | LF | 1,034 | $3.25 | $3.80 | $4.35 |
| 72 | Conduit 2" diameter (PVC schedule 40) (730-12.02) | LF | 1,301 | $13.42 | $11.25 | $13.00 |
| 73 | Conduit 2" diameter (directional bore) (730-12.23) | LF | 312 | $16.72 | $41.00 | $47.00 |
| 74 | Conduit 3" diameter (directional bore) (730-12.24) | LF | 125 | $18.10 | $54.00 | $61.00 |
| 75 | Vehicle detector (radar - stop line) (730-13.12) | EACH | 4 | $11,550 | $11,000 | $12,000 |
| 76 | Vehicle detector (radar - advance) (730-13.13) | EACH | 2 | $11,550 | $14,000 | $15,700 |
| 77 | Cabinet (atc) (730-15.07) | EACH | 1 | $46,750 | $23,000 | $26,000 |
| 78 | Controller (atc) (730-16.04) | EACH | 1 | $13,200 | $6,000.00 | $6,890.00 |
| 79 | Cantilever signal support (1 arm @ 50') (730-25.01) | EACH | 1 | $33,000 | $30,000 | $33,900 |
| 80 | Cantilever signal support (1 arm @ 55') (730-25.07) | EACH | 1 | $33,550 | $34,000 | $39,800 |
| 81 | Cantilever signal support (1 arm @ 75') (730-25.15) | EACH | 1 | $50,600 | $58,000 | $66,200 |
| 82 | Cantilever signal support (1 arm @ 80') (730-25.16) | EACH | 1 | $55,565 | $61,000 | $70,400 |
| 83 | Flashing warning beacon (amber) (730-26.08) | EACH | 4 | $5,500.00 | $1,200.00 | $1,390.00 |
| 84 | Geotextile (type III)(erosion control) (740-10.03) | SY | 428 | $7.00 | $3.00 | $9.20 |
| 85 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 210 | $7.00 | $3.00 | $34.50 |
| 86 | Temporary sediment tube 12IN (740-11.02) | LF | 8,400 | $4.40 | $5.00 | $4.10 |
| 87 | Temporary sediment tube 18IN (740-11.03) | LF | 500 | $4.95 | $5.30 | $4.75 |
| 88 | Seeding (with mulch) (801-01) | UNIT | 10 | $66.00 | $110.00 | $72.00 |
| 89 | Temporary seeding (with mulch) (801-01.07) | UNIT | 65 | $44.00 | $51.00 | $48.00 |
| 90 | Seeding (without mulch) (801-02) | UNIT | 64 | $27.50 | $39.00 | $30.00 |
| 91 | Water (seeding & sodding) (801-03) | MG | 13 | $55.00 | $270.00 | $60.00 |
| 92 | Erosion control blanket (type I) (805-12.01) | SY | 5,350 | $1.54 | $2.00 | $1.65 |
| 93 | Erosion control blanket (type II) (805-12.02) | SY | 1,000 | $1.93 | $2.25 | $2.10 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of October 3, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.