FDOT contract T7583 bid tabulation
SR 56 AND CR 581 (BRUCE B DOWNS BLVD) FROM BRUCE B DOWNS BL. Let by Florida DOT on February 25, 2026, Pasco, District 7. 5 bids received; low bid $19,729,686 by Preferred Materials Inc..
- Owner
- Florida DOT
- Letting
- 25 FEB 2026
- Pay items
- 221
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Preferred Materials Inc. | $19,729,686 | Low |
| 2 | C.W. Roberts Contracting, Inc. | $19,822,783 | 0.0% |
| 3 | Superior Asphalt, Inc. | $20,549,001 | +4.0% |
| 4 | Ajax Paving Industries of Florida LLC | $22,384,541 | +13% |
| 5 | Hubbard Construction Company | $24,280,726 | +23% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Preferred Materials Inc. | 2. C.W. Roberts Contracting, Inc. | 3. Superior Asphalt, Inc. | 4. Ajax Paving Industries of Florida LLC | 5. Hubbard Construction Company |
|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $437,100 | $808,663 | $734,798 | $561,077 | $681,367 |
| 0010 | Mobilization (0101-1) | LS | 1 | $160,750 | $521,169 | $475,000 | $76,721 | $413,249 |
| 0015 | Maintenance of traffic (0102-1) | DA | 1 | $605,000 | $357,446 | $415,550 | $880,476 | $896,702 |
| 0020 | Maintenance of traffic (0102-1) | DA | 1 | $22,395 | $238,297 | $225,000 | $378,075 | $543,850 |
| 0025 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $23,656 | $14,947 | $14,935 | $7,869.35 | $16,547 |
| 0030 | Pedestrian escort/flagger (0102-5) | HR | 672 | $14.52 | $32.13 | $21.50 | $64.07 | $42.66 |
| 0035 | Traffic control officer (0102-14) | HR | 2,022 | $82.94 | $0.11 | $102.00 | $112.13 | $105.43 |
| 0040 | Work zone sign (0102-60) | ED | 33,631 | $0.21 | $0.22 | $0.25 | $0.20 | $0.24 |
| 0045 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 573 | $38.36 | $58.41 | $44.00 | $39.51 | $44.00 |
| 0050 | Temporary barrier, F&I, anchored (0102-71-15) | LF | 483 | $35.25 | $53.68 | $38.65 | $36.31 | $40.44 |
| 0055 | Temporary barrier, relocate, low profile concrete (0102-71-23) | LF | 138 | $16.59 | $25.26 | $12.90 | $17.09 | $19.03 |
| 0060 | Temporary barrier, relocate, anchored (0102-71-25) | LF | 590 | $16.59 | $25.26 | $15.60 | $17.09 | $19.03 |
| 0065 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 125,588 | $0.09 | $0.01 | $0.15 | $0.10 | $0.11 |
| 0070 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 6,006 | $0.04 | $0.04 | $0.05 | $0.03 | $0.05 |
| 0075 | Arrow board / advance warning arrow panel (0102-76) | ED | 960 | $5.18 | $5.48 | $5.15 | $5.34 | $5.95 |
| 0080 | Temporary crash cushion, redirective option (0102-89-1) | LO | 8 | $829.45 | $876.38 | $1,170.00 | $854.29 | $951.44 |
| 0085 | Portable changeable message sign, temporary (0102-99) | ED | 2,004 | $11.40 | $12.05 | $11.50 | $9.61 | $13.08 |
| 0090 | Temporary signalization and maintenance, intersection (0102-104) | ED | 2,560 | $25.92 | $16.01 | $26.00 | $26.70 | $10.48 |
| 0095 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 2,560 | $25.92 | $20.56 | $26.00 | $26.70 | $12.32 |
| 0100 | Existing ITS maintenance (0102-112) | DA | 640 | $188.18 | $132.28 | $185.00 | $193.82 | $89.44 |
| 0105 | Type III barricade (0102-115) | ED | 540 | $0.31 | $0.33 | $0.30 | $0.25 | $0.36 |
| 0110 | Portable regulatory, sign (0102-150-1) | ED | 640 | $5.18 | $5.48 | $4.55 | $5.34 | $5.95 |
| 0115 | Radar speed display unit (0102-150-2) | ED | 640 | $5.18 | $5.48 | $4.85 | $5.34 | $5.95 |
| 0120 | Removable tape, white, solid 6" (0102-913-21) | GM | 0.70 | $9,821.60 | $10,606 | $10,735 | $10,679 | $11,799 |
| 0125 | Removable tape, white, 10'-30', 6'-10', or 2'-4' skip, 6" wide (0102-913-22) | GM | 0.19 | $3,046.29 | $3,414.02 | $2,415.00 | $2,402.70 | $2,607.53 |
| 0130 | Removable tape, white, 24" stop bar (0102-913-23) | LF | 1,424 | $4.15 | $4.42 | $9.70 | $9.61 | $10.65 |
| 0135 | Removable tape, white, 12" crosswalk (0102-913-24) | LF | 1,627 | $2.07 | $2.21 | $4.85 | $4.81 | $5.32 |
| 0140 | Removable tape, white, symbol or arrow (0102-913-29) | EACH | 16 | $518.40 | $551.93 | $270.00 | $270.17 | $299.37 |
| 0145 | Sediment barrier (0104-10-3) | LF | 3,057 | $1.35 | $1.59 | $1.35 | $1.60 | $2.96 |
| 0150 | Soil tracking prevention device (0104-15) | EACH | 2 | $4,769.31 | $1,137.57 | $2,950.00 | $0.00 | $6,850.40 |
| 0155 | Inlet protection system (0104-18) | EACH | 227 | $155.52 | $142.86 | $134.20 | $144.16 | $209.52 |
| 0160 | Litter removal (0107-1) | ACRE | 1,030.49 | $23.79 | $24.98 | $24.50 | $24.51 | $27.29 |
| 0165 | Mowing (0107-2) | ACRE | 1,030.49 | $61.96 | $65.05 | $65.00 | $63.82 | $71.07 |
| 0170 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $231,138 | $169,578 | $212,800 | $39,514 | $240,364 |
| 0175 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $27,954 | $22,610 | $28,385 | $12,904 | $32,065 |
| 0180 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $43,470 | $90,442 | $7,250.00 | $6,130.73 | $37,478 |
| 0185 | Removal of existing concrete (0110-4-10) | SY | 1,247 | $26.65 | $27.61 | $27.00 | $43.64 | $30.57 |
| 0190 | Regular excavation (0120-1) | CY | 385.20 | $28.57 | $29.61 | $29.00 | $153.79 | $32.78 |
| 0195 | Embankment (0120-6) | CY | 276.40 | $36.32 | $37.63 | $37.00 | $209.57 | $41.66 |
| 0200 | Type B stabilization (0160-4) | SY | 3,060 | $26.42 | $27.37 | $26.00 | $25.41 | $30.30 |
| 0205 | Optional base, base group 01 (0285-701) | SY | 59 | $48.52 | $50.28 | $103.77 | $346.35 | $285.86 |
| 0210 | Optional base, base group 06 (0285-706) | SY | 763 | $56.11 | $58.14 | $55.15 | $49.38 | $41.47 |
| 0215 | Optional base, base group 09 (0285-709) | SY | 749 | $69.19 | $71.69 | $74.20 | $55.62 | $59.51 |
| 0220 | Optional base, base group 11 (0285-711) | SY | 392 | $86.28 | $94.78 | $162.00 | $80.46 | $117.01 |
| 0225 | Milling existing asphalt pavement, 3 1/2" avg depth (0327-70-2) | SY | 67,828 | $3.72 | $3.34 | $1.20 | $4.95 | $4.51 |
| 0230 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 17,652 | $3.94 | $2.13 | $1.65 | $5.59 | $2.87 |
| 0235 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 68,693 | $3.65 | $5.81 | $2.15 | $5.53 | $7.82 |
| 0240 | Milling existing asphalt pavement, 2 1/4" avg depth (0327-70-11) | SY | 51,740 | $3.32 | $3.28 | $2.30 | $3.53 | $4.34 |
| 0245 | Milling existing asphalt pavement, 2 3/4" avg depth (0327-70-15) | SY | 146,090 | $3.00 | $2.07 | $1.60 | $3.57 | $2.86 |
| 0250 | Milling existing asphalt pavement, 3 3/4" avg depth (0327-70-20) | SY | 145,803 | $3.67 | $3.79 | $1.65 | $4.58 | $5.06 |
| 0255 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 55,159.70 | $109.60 | $103.68 | $127.75 | $129.59 | $129.34 |
| 0260 | Asphalt concrete friction course, inc bit, FC-5, PG 76-22 (0337-7-25) | TN | 13,839.10 | $219.00 | $207.93 | $223.85 | $225.00 | $242.10 |
| 0265 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 11,723.10 | $170.00 | $161.40 | $153.35 | $193.91 | $193.26 |
| 0270 | Miscellaneous asphalt (0339-1) | TN | 18.90 | $404.24 | $376.84 | $486.50 | $460.75 | $436.18 |
| 0275 | Plain cement concrete 8.5" (0350-3-6) | SY | 59 | $218.39 | $226.29 | $220.90 | $160.18 | $250.51 |
| 0280 | Inlets, curb, type 9, <10' (0425-1201) | EACH | 6 | $6,733.12 | $6,976.72 | $6,810.00 | $11,233 | $7,723.44 |
| 0285 | Manhole, adjust (0425-5) | EACH | 8 | $1,049.11 | $341.16 | $1,060.00 | $142.83 | $1,203.42 |
| 0290 | Manhole, adjust, utilities (0425-5-1) | EACH | 4 | $1,022.34 | $341.17 | $1,035.00 | $142.83 | $1,172.71 |
| 0295 | Valve boxes, adjust (0425-6) | EACH | 21 | $651.34 | $207.68 | $660.00 | $85.70 | $747.14 |
| 0300 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 6 | $265.08 | $274.67 | $268.00 | $1,092.14 | $304.07 |
| 0305 | Pipe culvert,optional material,other-elip/arch, (0430-175218) | LF | 216 | $202.17 | $209.48 | $204.50 | $332.61 | $231.90 |
| 0310 | Mitered end sect, optional - elliptical / arch, 18" SD (0430-984625) | EACH | 2 | $2,938.13 | $3,044.43 | $2,970.00 | $4,078.96 | $3,370.28 |
| 0315 | Concrete curb & gutter, type E (0520-1-7) | LF | 1,309 | $50.89 | $52.73 | $72.00 | $48.60 | $58.37 |
| 0320 | Concrete curb & gutter, type F (0520-1-10) | LF | 893 | $52.21 | $54.10 | $74.25 | $47.54 | $59.89 |
| 0325 | Concrete curb, type D (0520-2-4) | LF | 487 | $31.08 | $32.21 | $55.00 | $37.38 | $35.66 |
| 0330 | Concrete curb, type RA (0520-2-8) | LF | 200 | $58.83 | $60.96 | $89.50 | $37.38 | $67.48 |
| 0335 | Traffic separator concrete- type IV, 8.5' wide (0520-5-46) | LF | 239 | $119.96 | $124.30 | $214.00 | $195.60 | $137.60 |
| 0340 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 1,088 | $65.54 | $67.91 | $66.30 | $67.28 | $75.18 |
| 0345 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 731 | $101.57 | $105.24 | $102.75 | $86.50 | $116.50 |
| 0350 | Detectable warnings (0527-2) | SF | 446 | $33.00 | $34.20 | $22.50 | $26.70 | $37.86 |
| 0355 | Guardrail -roadway, general (0536-1-1) | LF | 435 | $26.35 | $27.46 | $26.65 | $27.13 | $30.22 |
| 0360 | Pipe rail for guardrail (0536-6) | LF | 263 | $5.79 | $6.03 | $5.85 | $5.96 | $6.64 |
| 0365 | Special guardrail post- special steel post for concrete structure mount (0536-7-2) | EACH | 4 | $292.03 | $304.37 | $295.00 | $300.78 | $334.98 |
| 0370 | Guardrail removal (0536-73) | LF | 789 | $3.06 | $3.19 | $3.10 | $3.15 | $3.51 |
| 0375 | Guardrail end treatment- trailing anchorage (0536-85-20) | EACH | 1 | $1,659.20 | $1,729.33 | $1,680.00 | $1,708.91 | $1,903.24 |
| 0380 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 6 | $3,280.40 | $3,419.07 | $3,320.00 | $3,378.67 | $3,762.89 |
| 0385 | Performance turf, sod (0570-1-2) | SY | 28,873 | $3.86 | $3.63 | $6.80 | $5.19 | $3.48 |
| 0390 | Conduit, furnish & install, open trench (0630-2-11) | LF | 68 | $23.85 | $27.88 | $69.25 | $24.56 | $78.51 |
| 0395 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 14 | $67.39 | $30.00 | $210.00 | $69.41 | $238.91 |
| 0400 | Pull & splice box, F&I, 17" X 30" cover size (0635-2-14) | EACH | 6 | $36.29 | $1,662.17 | $1,635.00 | $37.38 | $1,851.12 |
| 0405 | Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1) | EACH | 18 | $2,815.19 | $2,301.22 | $2,485.00 | $2,899.52 | $2,816.88 |
| 0410 | Traffic monitoring site speed/classification unit, furnish & install, volume speed and classification (0695-3-11) | AS | 5 | $19,315 | $7,220.12 | $9,560.00 | $19,893 | $10,842 |
| 0415 | Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12) | EACH | 18 | $2,558.84 | $2,983.37 | $2,340.00 | $2,635.49 | $2,654.31 |
| 0420 | Traffic monitoring site cabinet, F&I, type 3, 2 pane back, pedestal mount (0695-7162) | EACH | 5 | $6,424.66 | $7,387.62 | $7,085.00 | $6,617.13 | $8,032.40 |
| 0425 | Raised pavement marker, type B (0706-1-3) | EACH | 4,355 | $4.15 | $4.42 | $3.85 | $3.93 | $4.35 |
| 0430 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 14.47 | $1,450.93 | $1,545.83 | $1,700.00 | $1,735.28 | $1,922.06 |
| 0435 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 8,340 | $0.78 | $0.83 | $1.60 | $1.60 | $1.77 |
| 0440 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 3,124 | $1.30 | $1.38 | $1.70 | $1.71 | $1.89 |
| 0445 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 8,608 | $1.56 | $1.66 | $1.80 | $1.82 | $2.01 |
| 0450 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 12.54 | $725.76 | $772.70 | $510.00 | $517.92 | $573.90 |
| 0455 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 1.58 | $725.77 | $772.70 | $655.50 | $667.42 | $739.55 |
| 0460 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 18 | $62.21 | $66.23 | $36.70 | $37.38 | $41.42 |
| 0465 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 361 | $36.29 | $38.64 | $31.50 | $32.04 | $35.50 |
| 0470 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 6.82 | $1,449.61 | $1,545.63 | $1,705.00 | $1,735.28 | $1,920.31 |
| 0475 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 485 | $1.30 | $1.38 | $1.70 | $1.71 | $1.89 |
| 0480 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.47 | $722.69 | $785.81 | $655.50 | $667.42 | $736.44 |
| 0485 | Directional indicators (0919-528100) | SF | 80 | $33.00 | $95.24 | $94.40 | $96.11 | $107.99 |
| 0490 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $80,000 | $80,000 | $80,000 | $80,000 | $80,000 |
| 0495 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $10,000 | $10,000 | $10,000 | $10,000 | $10,000 |
| 0500 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $60,000 | $60,000 | $60,000 | $60,000 | $60,000 |
| 0505 | Ground-in rumble strips, 8" sinusoidal (0546-72-3) | GM | 14.13 | $1,975.47 | $3,124.67 | $1,180.00 | $1,201.35 | $2,736.31 |
| 0510 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 160 | $497.67 | $513.07 | $500.00 | $512.58 | $621.23 |
| 0515 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 42 | $2,073.61 | $2,137.78 | $1,780.00 | $2,135.73 | $2,603.25 |
| 0520 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 1 | $2,592.02 | $2,672.22 | $2,600.00 | $2,669.66 | $3,313.22 |
| 0525 | Single column ground sign assembly, relocate (0700-1500) | EACH | 1 | $336.96 | $347.39 | $375.00 | $347.06 | $236.66 |
| 0530 | Single column ground sign assembly, remove (0700-1600) | EACH | 139 | $20.74 | $21.38 | $62.00 | $21.36 | $76.91 |
| 0535 | Single column ground sign assembly, F&I cantilever mount, 20.1-30.0 SF (0700-1913) | EACH | 2 | $3,836.18 | $3,954.90 | $4,130.00 | $3,951.10 | $6,508.12 |
| 0540 | Single column ground sign assembly, F&I cantilever mount, 30.1+ SF (0700-1914) | EACH | 3 | $4,147.22 | $4,275.56 | $4,450.00 | $4,271.46 | $6,508.12 |
| 0545 | Multi-column ground sign assembly, F&I ground mount, 20.0 SF (0700-2112) | EACH | 1 | $13,997 | $14,430 | $8,960.00 | $14,416 | $5,916.48 |
| 0550 | Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114) | EACH | 1 | $7,776.05 | $8,016.68 | $7,800.00 | $8,008.99 | $8,578.89 |
| 0555 | Sign panel, furnish & install ground mount, 12-20 SF (0700-3102) | EACH | 7 | $466.56 | $481.00 | $795.00 | $480.54 | $692.23 |
| 0560 | Sign panel, furnish & install overhead mount, 101-200 SF (0700-3206) | EACH | 1 | $5,702.43 | $5,878.90 | $7,550.00 | $5,873.26 | $5,916.48 |
| 0565 | Sign panel, relocate, UP to 12 SF (0700-3501) | EACH | 1 | $103.68 | $106.89 | $188.00 | $106.79 | $82.84 |
| 0570 | Sign panel, remove, 12-20 SF (0700-3602) | EACH | 7 | $20.74 | $21.38 | $188.00 | $21.36 | $53.25 |
| 0575 | Retroreflective sign strip- furnish and install, 2' (0700-13-12) | EACH | 36 | $82.94 | $85.51 | $92.00 | $85.43 | $59.16 |
| 0580 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 42 | $93.31 | $96.20 | $107.00 | $96.11 | $130.16 |
| 0585 | Tubular marker, 36" white post (0704-1-3) | EACH | 22 | $207.36 | $220.77 | $213.00 | $213.57 | $189.33 |
| 0590 | Tubular marker, 36" yellow (0704-1-4) | EACH | 38 | $207.36 | $220.77 | $213.00 | $213.57 | $189.33 |
| 0595 | Object marker, type 2 (0705-10-2) | EACH | 59 | $103.68 | $106.89 | $155.00 | $106.79 | $207.08 |
| 0600 | Raised pavement marker, type B (0706-1-3) | EACH | 10,829 | $4.15 | $4.42 | $4.20 | $4.27 | $4.73 |
| 0605 | Painted pavement markings, standard, white, island nose (0710-11190) | SF | 29 | $3.11 | $3.31 | $4.20 | $4.27 | $4.73 |
| 0610 | Painted pavement markings, standard, yellow, island nose (0710-11290) | SF | 328 | $3.11 | $3.31 | $4.20 | $4.27 | $4.73 |
| 0615 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 1,260 | $5.18 | $5.52 | $4.40 | $4.43 | $4.91 |
| 0620 | Painted pavement markings, surface (0710-90) | LS | 1 | $82,219 | $87,536 | $80,825 | $76,788 | $85,088 |
| 0625 | Painted pavement markings, surface (0710-90) | LS | 1 | $15,448 | $16,448 | $10,635 | $10,783 | $11,949 |
| 0630 | Painted pavement markings, surface (0710-90) | LS | 1 | $86,470 | $92,062 | $65,970 | $66,907 | $74,139 |
| 0635 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 11,247 | $4.15 | $4.42 | $3.15 | $3.19 | $3.54 |
| 0640 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 7,631 | $4.67 | $4.97 | $4.75 | $4.79 | $5.31 |
| 0645 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 7,288 | $5.18 | $5.52 | $6.30 | $6.39 | $7.08 |
| 0650 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 3.44 | $3,105.89 | $3,316.40 | $1,760.00 | $1,783.34 | $1,973.23 |
| 0655 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 25 | $233.28 | $248.37 | $83.00 | $84.36 | $93.48 |
| 0660 | Thermoplastic, standard, arrow (0711-11170) | EACH | 807 | $82.94 | $88.31 | $62.00 | $63.00 | $69.81 |
| 0665 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 2,300 | $7.26 | $7.73 | $4.35 | $4.38 | $4.85 |
| 0670 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.47 | $4,645.85 | $5,051.57 | $1,760.00 | $1,783.34 | $1,967.73 |
| 0675 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 5,084 | $14.52 | $15.45 | $15.00 | $15.36 | $17.02 |
| 0680 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 74 | $196.99 | $209.73 | $195.00 | $197.56 | $218.91 |
| 0685 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 73 | $103.68 | $110.39 | $82.00 | $83.29 | $92.30 |
| 0690 | Thermoplastic, preformed, white with black contrast, arrow on concrete surface (0711-14570) | EACH | 2 | $518.41 | $551.93 | $980.00 | $995.25 | $1,102.84 |
| 0695 | Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101) | GM | 25.13 | $5,596.97 | $5,961.33 | $6,555.00 | $6,648.53 | $7,364.84 |
| 0700 | Thermoplastic, standard-open graded asphalt surfaces, solid, 8" (0711-15102) | GM | 1.21 | $6,205.45 | $6,606.78 | $8,740.00 | $8,865.42 | $9,799.41 |
| 0705 | Thermoplastic, standard-open graded asphalt surfaces, skip, 6",10-30 skip or 3-9 lane (0711-15131) | GM | 19.25 | $3,109.29 | $3,312.10 | $1,640.00 | $1,662.67 | $1,841.72 |
| 0710 | Thermoplastic, standard-open graded asphalt surfaces, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-15133) | GM | 0.32 | $6,144.04 | $6,745.80 | $3,280.00 | $3,324.27 | $3,638.15 |
| 0715 | Thermoplastic, standard-open graded asphalt surfaces, 6", 6-10 dotted managed lane marking (0711-15171) | GM | 0.99 | $3,082.11 | $3,314.93 | $2,460.00 | $2,493.47 | $2,737.85 |
| 0720 | Thermoplastic, standard-open graded asphalt surfaces, yellow, solid, 6" (0711-15201) | GM | 14.08 | $5,598.75 | $5,960.85 | $6,015.00 | $6,097.51 | $6,756.61 |
| 0725 | Thermoplastic, standard-open graded asphalt surfaces, yellow, skip, 6" (0711-15231) | GM | 0.64 | $3,091.10 | $3,342.44 | $1,500.00 | $1,524.91 | $1,679.24 |
| 0730 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 5.20 | $5,176.05 | $5,521.43 | $4,665.00 | $4,728.51 | $5,231.56 |
| 0735 | Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102) | GM | 0.89 | $5,702.44 | $6,071.24 | $6,215.00 | $6,304.68 | $6,986.17 |
| 0740 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 3.56 | $2,586.91 | $2,761.98 | $1,165.00 | $1,182.13 | $1,307.33 |
| 0745 | Thermoplastic, standard other surfaces, white, 6", 6-10 dotted managed lane marking (0711-16171) | GM | 0.39 | $2,592.03 | $2,759.64 | $1,760.00 | $1,783.34 | $1,976.10 |
| 0750 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 2.28 | $5,184.03 | $5,519.31 | $4,285.00 | $4,346.21 | $4,816.00 |
| 0755 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 0.17 | $2,576.84 | $2,743.51 | $1,070.00 | $1,087.09 | $1,197.54 |
| 0760 | Permanent tape, white, solid, 6" for concrete bridges (0713-103101) | GM | 0.04 | $26,661 | $37,847 | $52,000 | $52,806 | $50,155 |
| 0765 | Permanent tape, white, solid W/contrast, 6" primary line width, for concrete surfaces (0713-103121) | GM | 0.04 | $53,321 | $56,770 | $84,800 | $86,017 | $81,698 |
| 0770 | Preformed/permanent tape, remove (0713-107) | SF | 184 | $20.22 | $21.53 | $3.15 | $3.20 | $3.55 |
| 0775 | Conduit, furnish & install, open trench (0630-2-11) | LF | 661 | $10.89 | $10.78 | $18.00 | $11.21 | $29.36 |
| 0780 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 2,224 | $32.05 | $26.17 | $38.00 | $33.01 | $33.82 |
| 0785 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 31 | $1,623.88 | $1,434.31 | $1,580.00 | $1,672.52 | $2,774.66 |
| 0790 | Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60) | EACH | 1 | $543.29 | $636.55 | $625.00 | $559.56 | $417.20 |
| 0795 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 13,295 | $3.01 | $2.12 | $2.80 | $3.10 | $2.75 |
| 0800 | Lighting conductors, remove & dispose, contractor owns (0715-1-60) | LF | 789 | $0.78 | $0.95 | $0.65 | $0.80 | $0.52 |
| 0805 | Luminaire & bracket arm, install (0715-5-30) | EACH | 4 | $1,087.61 | $968.09 | $2,315.00 | $1,120.19 | $1,421.75 |
| 0810 | Load center, F&I, secondary voltage (0715-7-11) | EACH | 4 | $20,431 | $11,926 | $16,280 | $21,043 | $22,080 |
| 0815 | Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211) | EACH | 4 | $2,524.11 | $2,074.60 | $2,100.00 | $2,599.72 | $2,373.68 |
| 0820 | Light pole complete, F&I, standard pole standard foundation, 35' mounting height, 12' arm length (0715-61242) | EACH | 4 | $9,885.75 | $8,224.87 | $10,500 | $10,182 | $12,899 |
| 0825 | Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 12' arm length (0715-61342) | EACH | 7 | $9,859.41 | $8,740.57 | $10,700 | $10,155 | $13,095 |
| 0830 | Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 15' arm length (0715-61352) | EACH | 6 | $10,248 | $7,822.36 | $10,370 | $10,555 | $11,139 |
| 0835 | Light pole complete, F&I, standard pole special foundation, 40' mounting height, 12' arm length (0715-62342) | EACH | 5 | $14,741 | $10,712 | $10,500 | $15,182 | $13,815 |
| 0840 | Light pole complete, F&I, utility conflict pole special foundation, 40' mounting height, 16' arm length (0715-66366) | EACH | 2 | $9,223.43 | $11,917 | $11,400 | $9,499.74 | $15,423 |
| 0845 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 34 | $888.49 | $765.43 | $775.00 | $915.11 | $863.60 |
| 0850 | Light pole complete- special design, F&I, single arm mount, aluminum, 30' (0715-511130) | EACH | 2 | $14,227 | $10,077 | $10,000 | $14,653 | $13,381 |
| 0855 | Itsfm location documentation- intersection (0611-2-1) | EACH | 9 | $2,594.61 | $2,941.29 | $3,170.00 | $2,672.33 | $3,617.19 |
| 0860 | Conduit, furnish & install, open trench (0630-2-11) | LF | 384 | $19.96 | $15.11 | $21.75 | $20.56 | $45.30 |
| 0865 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 1,823 | $21.67 | $32.41 | $41.25 | $22.32 | $50.87 |
| 0870 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 5 | $11,742 | $26,603 | $12,600 | $12,094 | $17,742 |
| 0875 | Signal cable, remove- intersection (0632-7-6) | PI | 5 | $1,036.81 | $973.74 | $2,500.00 | $1,067.87 | $2,503.25 |
| 0880 | Fiber optic cable locator (0633-6) | DA | 320 | $142.56 | $228.72 | $172.00 | $146.83 | $198.74 |
| 0885 | Span wire assembly, F&I, two point, box or drop box (0634-4153) | PI | 4 | $13,954 | $18,203 | $11,000 | $14,372 | $55,615 |
| 0890 | Span wire assembly, remove- poles remain (0634-4600) | PI | 4 | $1,555.21 | $11,789 | $2,500.00 | $1,601.80 | $7,509.77 |
| 0895 | Pull & splice box, F&I, 17" X 30" cover size (0635-2-14) | EACH | 23 | $2,041.51 | $1,862.71 | $1,760.00 | $2,102.67 | $1,851.12 |
| 0900 | Aluminum signals pole, (0646-1-11) | EACH | 15 | $3,059.17 | $2,506.68 | $2,790.00 | $3,150.81 | $3,215.38 |
| 0905 | Aluminum signals pole, remove (0646-1-60) | EACH | 7 | $544.32 | $258.50 | $500.00 | $560.63 | $834.41 |
| 0910 | Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14) | AS | 85 | $1,989.60 | $2,068.57 | $2,195.00 | $2,049.20 | $2,765.36 |
| 0915 | Vehicular traffic signal, furnish & install aluminum, 5 section cluster, 1 way (0650-1-19) | AS | 12 | $2,411.04 | $2,959.00 | $3,275.00 | $2,483.27 | $3,922.23 |
| 0920 | Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109) | EACH | 9 | $743.57 | $486.55 | $600.00 | $765.84 | $714.94 |
| 0925 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 14 | $1,143.03 | $914.18 | $1,025.00 | $1,177.27 | $1,078.48 |
| 0930 | Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12) | AS | 1 | $1,848.46 | $1,585.85 | $1,970.00 | $1,903.83 | $2,078.17 |
| 0935 | Loop detector inductive, F&I, type 9 (0660-1109) | EACH | 21 | $880.51 | $417.65 | $420.00 | $906.89 | $374.83 |
| 0940 | Loop detector inductive, remove- cabinet to remain (0660-1600) | EACH | 55 | $41.47 | $86.23 | $125.00 | $42.71 | $26.08 |
| 0945 | Loop assembly, F&I, type B (0660-2102) | AS | 39 | $1,739.76 | $2,117.70 | $1,875.00 | $1,791.88 | $2,340.41 |
| 0950 | Vehicle detection system - microwave, remove, complete system (0660-3-60) | EACH | 1 | $1,529.29 | $326.32 | $1,000.00 | $1,575.10 | $1,877.45 |
| 0955 | Vehicle detection system- furnish & install cabinet equipment (0660-4-11) | EACH | 5 | $26,000 | $29,459 | $27,700 | $26,779 | $31,534 |
| 0960 | Vehicle detection system- furnish & install above ground equipment (0660-4-12) | EACH | 14 | $7,114.50 | $7,039.28 | $6,400.00 | $7,327.63 | $7,343.66 |
| 0965 | Vehicle detection system- adjust/modify cabinet (0660-4-51) | EACH | 3 | $1,995.85 | $312.83 | $1,880.00 | $2,055.64 | $1,251.63 |
| 0970 | Vehicle detection system- remove cabinet equipment (0660-4-61) | EACH | 2 | $1,036.81 | $485.03 | $375.00 | $1,067.87 | $417.21 |
| 0975 | Vehicle detection system- remove above ground (0660-4-62) | EACH | 6 | $1,016.07 | $806.70 | $625.00 | $1,046.51 | $417.21 |
| 0980 | Signal priority & preemption system, adjust/modify (0663-1500) | EACH | 3 | $2,695.70 | $951.59 | $1,890.00 | $2,776.45 | $5,055.16 |
| 0985 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 15 | $369.81 | $348.32 | $420.00 | $380.89 | $610.63 |
| 0990 | Traffic controller, modify (0671-2-40) | EACH | 8 | $4,769.31 | $5,200.80 | $3,240.00 | $4,912.18 | $2,349.35 |
| 0995 | Traffic signal controller cabinet, adjust/modify (0676-1500) | EACH | 9 | $2,661.48 | $2,200.63 | $3,570.00 | $2,741.21 | $2,094.16 |
| 1000 | ITS CCTV camera, pressurized, high definition (0682-1163) | EACH | 1 | $9,982.66 | $6,971.23 | $9,625.00 | $10,282 | $10,955 |
| 1005 | Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201) | EACH | 6 | $944.54 | $1,146.87 | $1,215.00 | $972.84 | $1,140.25 |
| 1010 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 2 | $259.20 | $252.08 | $94.00 | $266.97 | $208.60 |
| 1015 | Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22) | EACH | 22 | $5,905.52 | $8,683.19 | $4,940.00 | $6,082.44 | $8,090.87 |
| 1020 | Internally illuminated sign, remove (0700-5-60) | EACH | 21 | $466.56 | $878.11 | $500.00 | $480.54 | $625.81 |
| 1025 | Enhanced highway sign AC powered, F&I overhead blank out sign <12 SF (0700-141360) | EACH | 1 | $8,698.28 | $8,099.15 | $8,395.00 | $8,958.86 | $9,417.74 |
| 1030 | Itsfm subsurface documentation- project length (0611-1-1) | MI | 1.68 | $3,183.84 | $4,319.87 | $3,100.00 | $3,271.41 | $4,422.75 |
| 1035 | Conduit, furnish & install, open trench (0630-2-11) | LF | 6,694 | $21.67 | $27.04 | $27.00 | $22.32 | $39.89 |
| 1040 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 2,170 | $30.22 | $36.24 | $44.00 | $31.13 | $58.86 |
| 1045 | Fiber optic cable, F&I, underground,2-12 fibers (0633-1121) | LF | 117 | $4.28 | $4.85 | $4.50 | $4.41 | $5.96 |
| 1050 | Fiber optic cable, F&I, underground, 97 - 144 fibers (0633-1124) | LF | 9,964 | $5.65 | $6.40 | $6.00 | $5.82 | $7.87 |
| 1055 | Fiber optic connection, install, splice (0633-2-31) | EACH | 292 | $51.32 | $60.76 | $55.00 | $52.86 | $71.55 |
| 1060 | Fiber optic connection, install, termination (0633-2-32) | EACH | 12 | $85.54 | $96.96 | $90.00 | $88.10 | $119.25 |
| 1065 | Fiber optic connection hardware, F&I, splice (0633-3-11) | EACH | 1 | $1,476.93 | $1,706.60 | $1,720.00 | $1,521.18 | $2,059.01 |
| 1070 | Fiber optic connection hardware, F&I, splice tray (0633-3-12) | EACH | 27 | $57.02 | $96.96 | $55.00 | $58.73 | $79.49 |
| 1075 | Fiber optic connection hardware, F&I, buffer tube fan out kit (0633-3-14) | EACH | 1 | $96.94 | $90.51 | $105.00 | $99.85 | $135.16 |
| 1080 | Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16) | EACH | 1 | $1,397.10 | $1,680.74 | $1,650.00 | $1,438.95 | $1,947.71 |
| 1085 | Fiber optic connection hardware, adjust/modify splice enclosure (0633-3-51) | EACH | 2 | $883.88 | $1,001.98 | $965.00 | $910.36 | $2,464.46 |
| 1090 | Fiber optic cable locator (0633-6) | DA | 320 | $142.56 | $228.72 | $170.00 | $146.83 | $198.74 |
| 1095 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 16 | $2,745.56 | $2,424.89 | $3,090.00 | $2,827.81 | $2,948.85 |
| 1100 | Pull & splice box, F&I, 30" X 60" rectangular or 36" round size (0635-2-13) | EACH | 1 | $5,843.29 | $7,007.49 | $6,685.00 | $6,018.34 | $6,756.44 |
| 1105 | Managed field ethernet switch, furnish & install (0684-1-1) | EACH | 1 | $24,012 | $5,162.11 | $8,940.00 | $24,731 | $11,026 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of February 25, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.