TDOT contract CN263059 bid tabulation
The grading, drainage, and paving on i-40 from approximately 0.5 miles west and east of the s.r. 48 overpass (l.m. 2.25 in hickman county to l.m. 0.6 in dickson county), including repair on the s.r. 48 bridge over i-40. Let by Tennessee DOT on June 26, 2026, Dickson And Hickman Counties. 3 bids received; low bid $11,860,693 by Jones Bros. Contractors, LLC.
- Owner
- Tennessee DOT
- Letting
- 26 JUN 2026
- Pay items
- 141
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Jones Bros. Contractors, LLC | $11,860,693 | Low |
| 2 | Civil Constructors, LLC | $12,720,913 | +7.0% |
| 3 | Eubank Asphalt Paving & Sealing, LLC | $12,726,920 | +7.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Jones Bros. Contractors, LLC | 2. Civil Constructors, LLC | 3. Eubank Asphalt Paving & Sealing, LLC |
|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $74,000 | $41,320 | $75,000 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $450,000 | $196,376 | $225,000 |
| 3 | Removal of structures (concrete ditch, sta. varies) (202-04.01) | LS | 1 | $30,000 | $32,840 | $8,500.00 |
| 4 | Road & drainage excavation (unclassified) (203-01) | CY | 70,200 | $22.75 | $30.35 | $20.00 |
| 5 | Placing and spreading topsoil (203-04) | CY | 6,677 | $21.00 | $22.85 | $14.00 |
| 6 | Water (203-06) | MG | 481 | $10.00 | $13.35 | $25.00 |
| 7 | Channel substrate (203-20.01) | CY | 0.60 | $250.00 | $2,790.00 | $500.00 |
| 8 | Construction of haul road (203-50) | LS | 1 | $125,000 | $518,660 | $150,000 |
| 9 | Backfill material (flowable fill) (204-08.01) | CY | 188 | $275.00 | $333.00 | $400.00 |
| 10 | Brooming & degrassing shoulders (208-01.05) | LM | 2.20 | $1,850.00 | $4,610.00 | $2,000.00 |
| 11 | 18" temporary slope drain (209-02.07) | LF | 1,006 | $30.00 | $47.10 | $35.00 |
| 12 | Sediment removal (209-05) | CY | 813 | $26.50 | $21.20 | $20.00 |
| 13 | Temporary silt fence (with backing) (209-08.02) | LF | 6,028 | $5.40 | $6.60 | $6.00 |
| 14 | Rock check dam (209-08.07) | EACH | 91 | $750.00 | $814.00 | $500.00 |
| 15 | Enhanced rock check dam (209-08.08) | EACH | 11 | $750.00 | $814.00 | $1,000.00 |
| 16 | Sediment filter bag(15' X 10') (209-09.04) | EACH | 2 | $800.00 | $495.00 | $750.00 |
| 17 | Catch basin protection (type B) (209-40.31) | EACH | 2 | $900.00 | $1,020.00 | $1,000.00 |
| 18 | Catch basin protection (type D) (209-40.33) | EACH | 1 | $800.00 | $159.00 | $1,000.00 |
| 19 | Temporary diversion channel (209-65.03) | LF | 142 | $42.00 | $8.35 | $90.00 |
| 20 | Mineral aggregate, type A base, grading D (303-01) | TON | 18,970 | $48.00 | $33.90 | $40.00 |
| 21 | Granular backfill (bridges) (303-01.02) | TON | 2 | $500.00 | $206.00 | $100.00 |
| 22 | Mineral aggregate (size 57) (303-10.01) | TON | 52 | $85.00 | $67.00 | $72.00 |
| 23 | Asp. conc. mix(PG76-22) (BPMB-HM) GR. A-S (307-01.22) | TON | 741 | $213.00 | $195.00 | $140.00 |
| 24 | Asphalt concrete mix (PG76-22) (BPMB-HM) grading A (307-03.01) | TON | 809 | $195.00 | $186.00 | $142.00 |
| 25 | Asphalt concrete mix (PG76-22) (BPMB-HM) grading B-M2 (307-03.08) | TON | 2,930 | $150.00 | $189.00 | $140.00 |
| 26 | Treated permeable base (313-03) | SY | 2,645 | $40.00 | $53.05 | $34.00 |
| 27 | Bituminous material for prime coat (PC) (402-01) | TON | 29 | $800.00 | $1,530.00 | $800.00 |
| 28 | Aggregate for cover material (PC) (402-02) | TON | 102 | $80.00 | $100.00 | $50.00 |
| 29 | Bituminous material for tack coat (TC) (403-01) | TON | 9.50 | $800.00 | $1,300.00 | $1,000.00 |
| 30 | Saw cutting asphalt pavement (407-20.05) | LF | 4,090 | $3.00 | $5.20 | $5.00 |
| 31 | Acs mix(PG70-22) grading D (411-02.10) | TON | 11 | $425.00 | $354.00 | $175.00 |
| 32 | Acs mix(PG76-22) grading D (411-03.10) | TON | 1,451 | $195.00 | $200.00 | $170.00 |
| 33 | Scoring shoulders (continuous) (16IN width) (411-12.01) | LM | 1.80 | $3,425.00 | $3,360.00 | $2,000.00 |
| 34 | Cold planing bituminous pavement (415-01.01) | TON | 233 | $170.00 | $218.00 | $45.00 |
| 35 | Portland cement concrete pavement (plain) 9" (501-01.02) | SY | 1,600 | $145.00 | $167.00 | $188.00 |
| 36 | Full depth PCC pavement repair (502-03.20) | CY | 44 | $1,300.00 | $855.00 | $1,100.00 |
| 37 | Sawing concrete pavement (full depth) (502-04.01) | LF | 1,019 | $20.00 | $16.50 | $9.00 |
| 38 | Load transfer dowels (502-04.02) | EACH | 60 | $25.00 | $23.60 | $22.00 |
| 39 | Transverse tie-bars (502-04.03) | EACH | 95 | $19.00 | $130.00 | $17.50 |
| 40 | Sealing random cracks (silicone sealant) (502-08.07) | LF | 56 | $25.00 | $9.45 | $5.00 |
| 41 | 18" concrete pipe culvert (class III) (607-03.02) | LF | 5 | $500.00 | $1,330.00 | $350.00 |
| 42 | 24" concrete pipe culvert (class III) (607-05.02) | LF | 32 | $600.00 | $315.00 | $300.00 |
| 43 | 48" concrete pipe culvert (class IV) trenchless (607-09.10) | LF | 581 | $4,050.00 | $3,250.00 | $4,150.00 |
| 44 | Manholes, > 24' - 28' depth (611-01.07) | EACH | 1 | $35,000 | $35,050 | $75,000 |
| 45 | Class A concrete (pipe endwalls) (611-07.01) | CY | 36 | $1,175.00 | $1,660.00 | $2,100.00 |
| 46 | Steel bar reinforcement (pipe endwalls) (611-07.02) | LB | 2,000 | $2.00 | $8.35 | $2.60 |
| 47 | 24" temporary drainage pipe (621-03.03) | LF | 200 | $60.00 | $93.60 | $120.00 |
| 48 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 2,376 | $24.50 | $35.75 | $33.00 |
| 49 | W beam GR (type 2) MASH TL-3 (long post) (705-06.02) | LF | 684 | $30.00 | $48.20 | $40.00 |
| 50 | GR terminaltrailing end (type 13) MASH TL-3 (705-06.10) | EACH | 2 | $2,000.00 | $1,930.00 | $1,625.00 |
| 51 | Tangent energy absorbing term MASH TL-3 (705-06.20) | EACH | 3 | $3,100.00 | $3,970.00 | $3,400.00 |
| 52 | Guardrail removed (706-01) | LF | 1,934 | $0.50 | $2.35 | $2.00 |
| 53 | Chain link fence (6 foot) (707-01.11) | LF | 840 | $20.00 | $23.60 | $28.00 |
| 54 | End & corner post assembly(chain-link fence 6') (707-01.12) | EACH | 6 | $375.00 | $442.00 | $500.00 |
| 55 | Removal of fence (woven wire) (707-06.01) | LF | 960 | $7.00 | $8.25 | $3.00 |
| 56 | High-visibility construction fence (707-08.11) | LF | 652 | $4.00 | $3.20 | $5.00 |
| 57 | Machined rip-rap (class A-3) (709-05.05) | TON | 220 | $67.00 | $83.90 | $90.00 |
| 58 | Machined rip-rap (class B) (709-05.08) | TON | 619 | $67.00 | $61.25 | $90.00 |
| 59 | Aggregate underdrains (with pipe) (710-02) | LF | 5,828 | $12.50 | $13.05 | $13.00 |
| 60 | Lateral underdrain (710-05) | LF | 555 | $12.00 | $13.85 | $14.00 |
| 61 | Lateral underdrain endwall (2:1) (710-06.11) | EACH | 11 | $1,250.00 | $1,420.00 | $1,200.00 |
| 62 | Lateral underdrain endwall (3:1) (710-06.12) | EACH | 1 | $1,250.00 | $1,180.00 | $1,200.00 |
| 63 | Lateral underdrain endwall (4:1) (710-06.13) | EACH | 2 | $1,250.00 | $1,180.00 | $1,200.00 |
| 64 | Lateral underdrain endwall (6:1) (710-06.15) | EACH | 23 | $1,250.00 | $943.00 | $1,200.00 |
| 65 | Traffic control (712-01) | LS | 1 | $150,000 | $75,560 | $450,000 |
| 66 | Portable barrier rail (MASH TL-3) (712-02.10) | LF | 17,942 | $30.00 | $64.30 | $95.00 |
| 67 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 7 | $5,340.00 | $6,300.00 | $8,000.00 |
| 68 | Flexible drums (channelizing) (712-04.01) | EACH | 760 | $29.00 | $34.20 | $60.00 |
| 69 | Barrier rail delineator (712-04.50) | EACH | 1,794 | $15.00 | $17.70 | $15.00 |
| 70 | Warning lights (type A) (712-05.01) | EACH | 4 | $30.00 | $35.40 | $25.00 |
| 71 | Signs (construction) (712-06) | SF | 1,541 | $7.00 | $8.25 | $9.00 |
| 72 | Temporary barricades (type III) (712-07.03) | LF | 48 | $25.00 | $29.50 | $20.00 |
| 73 | Arrow board (type C) (712-08.03) | EACH | 2 | $1,200.00 | $1,420.00 | $2,500.00 |
| 74 | Speed feedback sign assembly (712-08.08) | EACH | 2 | $5,000.00 | $5,900.00 | $7,500.00 |
| 75 | Digital speed limit sign assembly (712-08.09) | EACH | 4 | $5,000.00 | $5,900.00 | $7,500.00 |
| 76 | Queue protection truck (712-08.12) | DAY | 12 | $1,150.00 | $1,360.00 | $1,500.00 |
| 77 | Portable queue warning system (712-08.14) | DAY | 12 | $1,700.00 | $2,000.00 | $2,500.00 |
| 78 | Removable pavement marking (6" line) (712-09.08) | LF | 124,800 | $3.75 | $4.40 | $4.50 |
| 79 | Flexible delineator (white) (713-02.14) | EACH | 32 | $57.00 | $86.90 | $69.00 |
| 80 | "U" section steel posts (713-11.01) | LB | 757 | $3.32 | $5.05 | $4.00 |
| 81 | U post slip base (713-11.22) | EACH | 12 | $252.70 | $146.00 | $116.00 |
| 82 | Flat sheet aluminum signs (0.080" thick) (713-13.02) | SF | 118 | $15.10 | $24.55 | $19.50 |
| 83 | Flat sheet aluminum signs (0.100" thick) (713-13.03) | SF | 32 | $15.10 | $27.10 | $21.50 |
| 84 | Extruded aluminum panel signs (713-14) | SF | 40 | $28.04 | $55.45 | $44.00 |
| 85 | Removal of signs, posts and footings (713-15) | LS | 1 | $50.00 | $2,610.00 | $2,075.00 |
| 86 | Removal & relocation of sign & support (713-15.02) | EACH | 18 | $950.00 | $1,110.00 | $880.00 |
| 87 | Changeable message sign unit (713-16.01) | EACH | 4 | $5,300.00 | $6,250.00 | $10,000 |
| 88 | Jacked or bored conduit (714-03) | LF | 325 | $25.42 | $30.00 | $80.00 |
| 89 | Direct burial conduit (2" PVC, schedule 40) (714-03.01) | LF | 8,605 | $16.35 | $19.30 | $22.00 |
| 90 | Pull boxes (type C) (714-05.04) | EACH | 25 | $1,467.96 | $1,730.00 | $1,200.00 |
| 91 | Cable (1/C # 10 AWG) (714-06.03) | LF | 4,940 | $1.40 | $1.65 | $1.30 |
| 92 | Cable (1/C # 8 AWG) (714-06.04) | LF | 2,000 | $2.03 | $2.40 | $1.70 |
| 93 | Cable (1/C # 6 AWG) (714-06.05) | LF | 16,045 | $2.86 | $3.35 | $1.90 |
| 94 | Light standards (40' aluminum) (714-08.09) | EACH | 21 | $5,621.98 | $6,630.00 | $5,700.00 |
| 95 | Light standards (120' high mast) (714-08.10) | EACH | 4 | $39,164 | $46,180 | $64,260 |
| 96 | Foundation (only) for light standard (714-08.20) | EACH | 21 | $3,148.16 | $3,710.00 | $2,200.00 |
| 97 | Foundation (only) for high mast light standard (714-08.46) | EACH | 4 | $15,797 | $18,630 | $20,000 |
| 98 | Luminaires (155 watt LED offset) (714-09.09) | EACH | 21 | $1,207.58 | $1,420.00 | $1,562.00 |
| 99 | Luminaires (295 watt LED high mast with 90 degree shield) (714-09.10) | EACH | 22 | $1,420.25 | $1,670.00 | $1,736.00 |
| 100 | Control center (no. 1) (714-12.01) | LS | 1 | $16,250 | $19,160 | $13,680 |
| 101 | Control center (no. 2) (714-12.02) | LS | 1 | $16,250 | $19,160 | $13,680 |
| 102 | Electrical connection (control center no. 1) (714-25.01) | LS | 1 | $3,250.00 | $3,830.00 | $5,200.00 |
| 103 | Electrical connection (control center no. 2) (714-25.02) | LS | 1 | $3,250.00 | $3,830.00 | $5,200.00 |
| 104 | Raised PVMT markers (BI-directional) (1 color lens) (716-01.11) | EACH | 1,686 | $10.00 | $11.80 | $15.00 |
| 105 | Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22) | EACH | 84 | $40.00 | $47.15 | $50.00 |
| 106 | Snowplowable raised pavement markers (BI-dir)(2 color) (716-01.23) | EACH | 133 | $40.00 | $47.15 | $50.00 |
| 107 | Plastic pavement marking (stop line) (716-02.05) | LF | 100 | $25.00 | $29.50 | $25.00 |
| 108 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 4 | $200.00 | $236.00 | $275.00 |
| 109 | Plastic pavement marking (24" barrier line) (716-02.07) | LF | 534 | $12.00 | $14.15 | $15.00 |
| 110 | Plastic pavement marking (lane reduction arrow) (716-04.14) | EACH | 4 | $500.00 | $590.00 | $800.00 |
| 111 | Painted pavement marking (6" line) (716-05.20) | LM | 3.60 | $2,500.00 | $2,950.00 | $1,300.00 |
| 112 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 1.80 | $8,500.00 | $10,020 | $7,800.00 |
| 113 | Enhanced flatline thermo PVMT MRKNG (8IN barrier line) (716-12.03) | LF | 1,450 | $2.00 | $2.35 | $4.00 |
| 114 | Enhanced flatline thermo PVMT MRKNG (6IN dotted line) (716-12.05) | LF | 1,281 | $2.00 | $2.35 | $3.00 |
| 115 | Preformed permanent tape (6IN line) (716-15.10) | LF | 1,269 | $8.00 | $9.45 | $8.00 |
| 116 | Mobilization (717-01) | LS | 1 | $1,090,000 | $524,150 | $780,000 |
| 117 | Geotextile (type III)(erosion control) (740-10.03) | SY | 678 | $3.00 | $4.60 | $5.00 |
| 118 | Temporary sediment tube 18IN (740-11.03) | LF | 18,545 | $3.70 | $4.60 | $4.50 |
| 119 | Seeding (with mulch) (801-01) | UNIT | 451 | $45.00 | $61.30 | $85.00 |
| 120 | Temporary seeding (with mulch) (801-01.07) | UNIT | 451 | $40.00 | $54.25 | $80.00 |
| 121 | Grass seed mix (ripzn/FLPL) W/mulch (801-01.35) | UNIT | 9 | $300.00 | $105.00 | $220.00 |
| 122 | Water (seeding & sodding) (801-03) | MG | 90 | $100.00 | $189.00 | $55.00 |
| 123 | Acer negundo (box elder seedlng B.R.) (802-12.01) | EACH | 44 | $20.00 | $18.85 | $50.00 |
| 124 | Acer rubrum (red maple seedlng B.R.) (802-12.02) | EACH | 44 | $20.00 | $18.85 | $50.00 |
| 125 | Fraxinus pennsylvanica (green ash seedlng B.R.) (802-12.16) | EACH | 44 | $20.00 | $18.85 | $50.00 |
| 126 | Liriodendron tulipifera (tulip poplar seedlng B.R.) (802-12.19) | EACH | 44 | $20.00 | $18.85 | $50.00 |
| 127 | Platanus occidentalis (sycamore seedlng B.R.) (802-12.26) | EACH | 44 | $20.00 | $18.85 | $50.00 |
| 128 | Salix nigra (black willow 3FT live stakes) (802-16.01) | EACH | 44 | $15.00 | $17.70 | $50.00 |
| 129 | Erosion control blanket (type I) (805-12.01) | SY | 36,437 | $1.25 | $1.55 | $1.35 |
| 130 | Bearing device (repair) (602-10.12) | LS | 1 | $5,000.00 | $29,480 | $21,650 |
| 131 | Jacking steel spans (602-10.19) | LS | 1 | $122,000 | $206,370 | $52,100 |
| 132 | Repaint existing bearings (603-02.15) | LS | 1 | $40,000 | $47,170 | $24,300 |
| 133 | Bridge end drains(12 inch) (604-04.05) | EACH | 1 | $1,000.00 | $7,670.00 | $21,700 |
| 134 | Concrete (604-10.05) | SF | 200 | $570.00 | $943.00 | $300.00 |
| 135 | Bridge deck repairs (full depth of slab) (604-10.30) | SY | 9 | $1,800.00 | $4,130.00 | $1,152.00 |
| 136 | Expansion joint repairs (type A) (604-10.32) | LF | 69 | $1,800.00 | $2,590.00 | $1,231.00 |
| 137 | Bridge deck repairs (partial depth of slab) (604-10.50) | SY | 10 | $1,400.00 | $2,360.00 | $1,012.00 |
| 138 | Concrete repairs (604-10.54) | SF | 20 | $570.00 | $943.00 | $348.00 |
| 139 | Riser block repair (604-10.78) | EACH | 1 | $5,000.00 | $11,790 | $2,982.00 |
| 140 | 12" pipe drain (bridge drain) (610-07.01) | LF | 70 | $50.00 | $58.95 | $180.00 |
| 141 | Type 2 thin epoxy overlay (low-mod epoxy) (617-04.02) | SY | 752 | $77.50 | $106.00 | $80.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of June 26, 2026. Compiled by Mirage Metrics.