TDOT contract CN264037 bid tabulation
The grading, drainage, and paving on s.r. 22 and cates landing road serving project sonic. Let by Tennessee DOT on June 26, 2026, Lake County. 1 bid received; low bid $4,125,618 by Ford Construction Company.
- Owner
- Tennessee DOT
- Letting
- 26 JUN 2026
- Pay items
- 84
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ford Construction Company | $4,125,618 | Low |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ford Construction Company |
|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $50,000 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $29,000 |
| 3 | Removal of structures and obstructions (202-01) | LS | 1 | $20,000 |
| 4 | Removal of structures and obstructions (202-01.01) | LS | 1 | $20,000 |
| 5 | Removal of structures & obstructions (temporary run-around) (202-01.56) | LS | 1 | $38,000 |
| 6 | Removal of structures (port of cates sign W/ lights, sta.119+50) (202-04.01) | LS | 1 | $800.00 |
| 7 | Road & drainage excavation (unclassified) (203-01) | CY | 8,336 | $20.00 |
| 8 | Water (203-06) | MG | 130 | $35.00 |
| 9 | Furnishing & spreading topsoil (203-07) | CY | 2,691 | $16.00 |
| 10 | Filter sock (12 inch) (209-03.21) | LF | 8,150 | $5.25 |
| 11 | Sediment removal (209-05) | CY | 222 | $30.00 |
| 12 | Temporary silt fence (with backing) (209-08.02) | LF | 480 | $4.00 |
| 13 | Temporary silt fence (without backing) (209-08.03) | LF | 9,840 | $2.00 |
| 14 | Rock check dam (209-08.07) | EACH | 20 | $900.00 |
| 15 | Enhanced rock check dam (209-08.08) | EACH | 7 | $1,000.00 |
| 16 | Sandbags (209-09.01) | BAG | 125 | $10.00 |
| 17 | Polyethylene sheeting (10 mil.) (209-20.04) | SY | 1,000 | $5.00 |
| 18 | Mineral aggregate, type A base, grading D (303-01) | TON | 21,671 | $48.00 |
| 19 | Mineral aggregate, type B base, grading (D) (303-02) | TON | 200 | $51.00 |
| 20 | Mineral aggregate (size 57) (303-10.01) | TON | 207 | $58.00 |
| 21 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01) | TON | 2,694 | $147.00 |
| 22 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08) | TON | 2,486 | $151.00 |
| 23 | Treated permeable base (313-03) | SY | 505 | $61.00 |
| 24 | Bituminous material for prime coat (PC) (402-01) | TON | 32 | $300.00 |
| 25 | Aggregate for cover material (PC) (402-02) | TON | 110 | $5.00 |
| 26 | Bituminous material for tack coat (TC) (403-01) | TON | 19 | $500.00 |
| 27 | Saw cutting asphalt pavement (407-20.05) | LF | 730 | $10.00 |
| 28 | Acs mix(PG70-22) grading D (411-02.10) | TON | 1,388 | $175.00 |
| 29 | Cold planing bituminous pavement (415-01.02) | SY | 175 | $91.00 |
| 30 | Portland cement concrete pavement (plain) 8" (501-01.01) | SY | 505 | $225.00 |
| 31 | Sawing concrete pavement (full depth) (502-04.01) | LF | 690 | $25.00 |
| 32 | Load transfer dowels (502-04.02) | EACH | 301 | $25.00 |
| 33 | Transverse tie-bars (502-04.03) | EACH | 100 | $30.00 |
| 34 | 18" concrete pipe culvert (class IV) trenchless (607-03.10) | LF | 129 | $1,100.00 |
| 35 | 18" concrete pipe culvert (class V) trenchless (607-03.11) | LF | 96 | $1,100.00 |
| 36 | 18" pipe culvert (side drain) (607-39.02) | LF | 116 | $110.00 |
| 37 | 24" pipe culvert (side drain) (607-39.03) | LF | 264 | $130.00 |
| 38 | Reinforced concrete pipe arch (22" X 13") (607-57.01) | LF | 120 | $150.00 |
| 39 | Reinforced concrete pipe arch (29" X 18") (607-57.02) | LF | 72 | $180.00 |
| 40 | Class A concrete (pipe endwalls) (611-07.01) | CY | 10.84 | $3,000.00 |
| 41 | Steel bar reinforcement (pipe endwalls) (611-07.02) | LB | 930 | $4.50 |
| 42 | 18IN endwall (side drain) (611-07.31) | EACH | 8 | $4,500.00 |
| 43 | 24IN endwall (side drain) (611-07.32) | EACH | 30 | $7,000.00 |
| 44 | 18IN endwall (cross drain) 4:1 (611-07.55) | EACH | 2 | $3,600.00 |
| 45 | 15" temporary drainage pipe (621-03.01) | LF | 16 | $66.00 |
| 46 | 18" temporary drainage pipe (621-03.02) | LF | 220 | $88.00 |
| 47 | High-visibility construction fence (707-08.11) | LF | 665 | $2.50 |
| 48 | Markers (concrete R.O.W. posts) (708-02.01) | EACH | 8 | $350.00 |
| 49 | Machined rip-rap (class A-3) (709-05.05) | TON | 550 | $56.00 |
| 50 | Machined rip-rap (class A-1) (709-05.06) | TON | 1,741 | $54.00 |
| 51 | Traffic control (712-01) | LS | 1 | $104,000 |
| 52 | Flexible drums (channelizing) (712-04.01) | EACH | 655 | $45.00 |
| 53 | Warning lights (type A) (712-05.01) | EACH | 30 | $25.00 |
| 54 | Warning lights (type C) (712-05.03) | EACH | 82 | $25.00 |
| 55 | Signs (construction) (712-06) | SF | 188 | $7.50 |
| 56 | Arrow board (type C) (712-08.03) | EACH | 2 | $1,350.00 |
| 57 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 17,910 | $2.00 |
| 58 | Removable pavement marking(channelizing striping) (712-09.03) | SY | 68 | $40.00 |
| 59 | Removable pavement marking (stop line) (712-09.04) | LF | 108 | $30.00 |
| 60 | Removable pavement marking (6" line) (712-09.08) | LF | 11,940 | $2.00 |
| 61 | Flexible type II object marker (713-02.16) | EACH | 82 | $65.00 |
| 62 | "U" section steel posts (713-11.01) | LB | 565 | $5.00 |
| 63 | Flat sheet aluminum signs (0.100" thick) (713-13.03) | SF | 38 | $15.00 |
| 64 | Removal & relocation of sign & support (713-15.02) | EACH | 6 | $250.00 |
| 65 | Changeable message sign unit (713-16.01) | EACH | 4 | $5,900.00 |
| 66 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 12 | $100.00 |
| 67 | Plastic pavement marking(channelization striping) (716-02.04) | SY | 39 | $40.00 |
| 68 | Plastic pavement marking (stop line) (716-02.05) | LF | 122 | $30.00 |
| 69 | Plastic word pavement marking (RXR) (716-03.02) | EACH | 2 | $1,500.00 |
| 70 | Plastic word pavement marking (stop ahead) (716-03.03) | EACH | 2 | $1,500.00 |
| 71 | Plastic pavement marking (yield line) (716-04.12) | SF | 63 | $38.00 |
| 72 | Painted pavement marking (4" line) (716-05.01) | LM | 2.85 | $2,950.00 |
| 73 | Painted pavement marking (8" barrier line) (716-05.02) | LF | 11,940 | $2.00 |
| 74 | Painted pavement marking (6" line) (716-05.20) | LM | 2.26 | $2,950.00 |
| 75 | Painted pavement markings(8" line) (716-05.49) | LM | 0.09 | $10,560 |
| 76 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 0.36 | $15,000 |
| 77 | Spray thermo PVMT MRKNG (60 mil) (6IN line) (716-13.02) | LM | 0.33 | $10,500 |
| 78 | Mobilization (717-01) | LS | 1 | $185,000 |
| 79 | Geotextile (type III)(erosion control) (740-10.03) | SY | 4,305 | $4.60 |
| 80 | Temporary seeding (with mulch) (801-01.07) | UNIT | 176 | $35.00 |
| 81 | Water (seeding & sodding) (801-03) | MG | 200 | $30.00 |
| 82 | Seed (supplemental application) (801-07) | LB | 21 | $6.00 |
| 83 | Fertilizer (supplemental application) (801-08) | TON | 2 | $1,200.00 |
| 84 | Sodding (new sod) (803-01) | SY | 17,829 | $4.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of June 26, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.