TDOT contract CNZ182 bid tabulation
The grading, drainage, construction of a concrete i-beam bridge, and paving on u.s. 79 (s.r. 76) for industrial access support serving project mallard (l.m. 1.07 - l.m. 2.05). Let by Tennessee DOT on June 27, 2025, Crockett County. 3 bids received; low bid $17,854,046 by Hal Coffey Contracting LLC.
- Owner
- Tennessee DOT
- Letting
- 27 JUN 2025
- Pay items
- 166
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Hal Coffey Contracting LLC | $17,854,046 | Low |
| 2 | Delta Contracting Company, LLC | $18,319,031 | +3.0% |
| 3 | Ford Construction Company | $21,367,676 | +20% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Hal Coffey Contracting LLC | 2. Delta Contracting Company, LLC | 3. Ford Construction Company |
|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $185,000 | $165,000 | $190,000 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $700,000 | $155,279 | $250,000 |
| 3 | Removal of structures and obstructions (202-01) | LS | 1 | $2,500.00 | $25,000 | $90,000 |
| 4 | Removal of asphalt pavement (202-03.01) | SY | 9,365 | $5.50 | $9.00 | $6.00 |
| 5 | Removal of structures (exist. BR. ID no. 17SR0760001) (202-04.04) | LS | 1 | $250,000 | $50,000 | $10,000 |
| 6 | Road & drainage excavation (unclassified) (203-01) | CY | 104,003 | $2.10 | $5.50 | $8.00 |
| 7 | Road & drainage excavation (stream mitigation) (203-01.13) | CY | 32,960 | $14.00 | $8.00 | $10.60 |
| 8 | Borrow excavation (unclassified) (203-03) | CY | 276,423 | $6.25 | $6.98 | $10.50 |
| 9 | Select granular material (203-03.10) | TON | 40,903 | $2.50 | $35.00 | $37.00 |
| 10 | Water (203-06) | MG | 2,210 | $5.50 | $30.00 | $35.00 |
| 11 | Furnishing & spreading topsoil (203-07) | CY | 811 | $8.00 | $9.00 | $30.00 |
| 12 | Settlement plate / monitoring device (203-10.05) | EACH | 2 | $5,500.00 | $5,000.00 | $5,000.00 |
| 13 | Foundation fill material (204-08) | CY | 599 | $90.00 | $99.00 | $85.00 |
| 14 | Stream mitigation-log vanes (209-03.34) | LF | 60 | $89.00 | $270.00 | $100.00 |
| 15 | Stream mitigation-log drop structure (209-03.35) | LF | 1,250 | $147.00 | $130.00 | $70.00 |
| 16 | Stream mitigation – wood toe W/reinforced earth (209-03.67) | LF | 1,272 | $72.00 | $95.00 | $100.00 |
| 17 | Protected area marker (white with decal) (209-03.99) | EACH | 45 | $200.00 | $125.00 | $200.00 |
| 18 | Sediment removal (209-05) | CY | 1,078 | $7.50 | $9.00 | $16.00 |
| 19 | Temporary silt fence (with backing) (209-08.02) | LF | 857 | $5.50 | $5.50 | $5.50 |
| 20 | Temporary silt fence (without backing) (209-08.03) | LF | 3,952 | $1.90 | $1.90 | $1.90 |
| 21 | Enhanced silt fence check (V-ditch) (209-08.05) | EACH | 2 | $750.00 | $750.00 | $750.00 |
| 22 | Enhanced rock check dam (209-08.08) | EACH | 9 | $650.00 | $1,200.00 | $1,100.00 |
| 23 | Sandbags (209-09.01) | BAG | 300 | $3.50 | $6.00 | $8.00 |
| 24 | Sediment filter bag (15' X 15') (209-09.03) | EACH | 2 | $550.00 | $400.00 | $1,400.00 |
| 25 | Curb inlet protection (type 4) (209-09.43) | EACH | 24 | $450.00 | $450.00 | $450.00 |
| 26 | Polyethylene sheeting (6 mil. minimum) (209-20.03) | SY | 500 | $4.00 | $3.00 | $6.00 |
| 27 | Catch basin protection (type A) (209-40.30) | EACH | 2 | $600.00 | $850.00 | $600.00 |
| 28 | Catch basin protection (type D) (209-40.33) | EACH | 8 | $600.00 | $600.00 | $600.00 |
| 29 | Catch basin protection (type E) (209-40.34) | EACH | 3 | $600.00 | $600.00 | $600.00 |
| 30 | Catch basin filter assembly(type 1) (209-40.41) | EACH | 1 | $900.00 | $900.00 | $900.00 |
| 31 | Catch basin filter assembly(type 3) (209-40.43) | EACH | 1 | $900.00 | $900.00 | $900.00 |
| 32 | Catch basin filter assembly(type 4) (209-40.44) | EACH | 4 | $900.00 | $900.00 | $900.00 |
| 33 | Catch basin filter assembly(type 6) (209-40.46) | EACH | 15 | $900.00 | $900.00 | $900.00 |
| 34 | Catch basin filter assembly(type 7) (209-40.47) | EACH | 4 | $900.00 | $900.00 | $900.00 |
| 35 | Temporary diversion channel (209-65.03) | LF | 737 | $25.00 | $15.00 | $100.00 |
| 36 | Mineral aggregate, type A base, grading D (303-01) | TON | 28,483 | $35.00 | $42.00 | $40.00 |
| 37 | Granular backfill (roadway) (303-01.01) | TON | 15,976 | $59.00 | $42.00 | $43.00 |
| 38 | Mineral aggregate, type B base, grading (D) (303-02) | TON | 500 | $45.00 | $42.00 | $43.00 |
| 39 | Mineral aggregate (size 57) (303-10.01) | TON | 9,483 | $15.00 | $60.00 | $56.00 |
| 40 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01) | TON | 3,416 | $112.00 | $126.00 | $112.00 |
| 41 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 3,806 | $118.00 | $129.00 | $118.00 |
| 42 | Bituminous material for prime coat (PC) (402-01) | TON | 45 | $200.00 | $300.00 | $200.00 |
| 43 | Aggregate for cover material (PC) (402-02) | TON | 160 | $5.00 | $25.00 | $5.00 |
| 44 | Bituminous material for tack coat (TC) (403-01) | TON | 17 | $965.00 | $300.00 | $965.00 |
| 45 | Saw cutting asphalt pavement (407-20.05) | LF | 440 | $5.00 | $6.00 | $13.00 |
| 46 | Acs mix(PG64-22) grading D (411-01.10) | TON | 2,121 | $167.00 | $164.00 | $167.00 |
| 47 | Scoring shoulders (non-continuous) (16IN width) (411-12.02) | LM | 0.75 | $11,000 | $7,600.00 | $11,750 |
| 48 | Class A concrete (roadway) (604-01.01) | CY | 1,447 | $1,050.00 | $1,050.00 | $1,350.00 |
| 49 | Steel bar reinforcement (roadway) (604-01.02) | LB | 205,347 | $1.65 | $1.15 | $1.70 |
| 50 | Class A concrete (box bridges) (604-02.01) | CY | 3,187 | $855.00 | $625.00 | $950.00 |
| 51 | Steel bar reinforcement (box bridges) (604-02.02) | LB | 342,141 | $1.65 | $1.65 | $1.80 |
| 52 | 18" concrete pipe culvert (class III) (607-03.02) | LF | 1,137 | $65.00 | $77.00 | $105.00 |
| 53 | 24" concrete pipe culvert (class III) (607-05.02) | LF | 841 | $80.00 | $100.00 | $130.00 |
| 54 | 30" concrete pipe culvert (class III) (607-06.02) | LF | 203 | $110.00 | $125.00 | $140.00 |
| 55 | 36" concrete pipe culvert (class III) (607-07.02) | LF | 43 | $135.00 | $160.00 | $150.00 |
| 56 | 42" concrete pipe culvert (class III) (607-08.02) | LF | 82 | $150.00 | $200.00 | $155.00 |
| 57 | 54" concrete pipe culvert (class III) (607-10.02) | LF | 98 | $255.00 | $300.00 | $215.00 |
| 58 | Manholes, > 12' - 16' depth (611-01.04) | EACH | 1 | $18,000 | $11,000 | $19,000 |
| 59 | Rework manhole (611-01.21) | EACH | 3 | $3,500.00 | $2,500.00 | $8,000.00 |
| 60 | Junction box (see plans) (611-02.16) | EACH | 1 | $22,000 | $16,000 | $25,000 |
| 61 | Class A concrete (pipe endwalls) (611-07.01) | CY | 10 | $1,500.00 | $2,000.00 | $1,900.00 |
| 62 | Steel bar reinforcement (pipe endwalls) (611-07.02) | LB | 405 | $5.00 | $2.50 | $3.50 |
| 63 | 24IN endwall (side drain) (611-07.32) | EACH | 1 | $6,000.00 | $7,000.00 | $5,500.00 |
| 64 | 30IN endwall (side drain) (611-07.33) | EACH | 1 | $12,000 | $13,000 | $8,800.00 |
| 65 | 18IN endwall (cross drain) 6:1 (611-07.56) | EACH | 4 | $2,800.00 | $4,000.00 | $2,000.00 |
| 66 | 24IN endwall (cross drain) 3:1 (611-07.57) | EACH | 6 | $2,800.00 | $4,000.00 | $2,200.00 |
| 67 | 36IN endwall (cross drain) 6:1 (611-07.65) | EACH | 1 | $12,000 | $6,500.00 | $5,500.00 |
| 68 | Rework catchbasin (611-09.02) | EACH | 1 | $4,700.00 | $3,000.00 | $6,500.00 |
| 69 | Catch basins, type 10, 0' - 4' depth (611-10.01) | EACH | 1 | $5,500.00 | $4,500.00 | $6,200.00 |
| 70 | Catch basins, type 12, 0' - 4' depth (611-12.01) | EACH | 2 | $5,800.00 | $5,700.00 | $6,400.00 |
| 71 | Catch basins, type 12, > 4' - 8' depth (611-12.02) | EACH | 12 | $7,500.00 | $6,000.00 | $7,200.00 |
| 72 | Catch basins, type 14, > 4' - 8' depth (611-14.02) | EACH | 4 | $10,500 | $11,000 | $10,000 |
| 73 | Mobilization (prefabricated vertical drains) (627-01.01) | LS | 1 | $120,000 | $71,000 | $70,000 |
| 74 | Prefabricated vertical drain (627-01.02) | LF | 35,682 | $2.10 | $2.10 | $1.82 |
| 75 | Drainage layer material (627-01.03) | CY | 6,935 | $48.00 | $30.00 | $58.00 |
| 76 | Concrete sidewalk (4 ") (701-01.01) | SF | 22,520 | $5.00 | $7.85 | $5.00 |
| 77 | Concrete curb ramp (701-02.03) | SF | 1,120 | $17.05 | $30.00 | $17.05 |
| 78 | Concrete combined curb & gutter (702-03) | CY | 285 | $365.75 | $510.00 | $365.75 |
| 79 | Portland cement concrete ditch paving (703-01) | CY | 94 | $500.00 | $650.00 | $1,000.00 |
| 80 | Earth pad for type 38 GR end treatment (705-04.09) | EACH | 4 | $975.00 | $975.00 | $975.00 |
| 81 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 413 | $32.75 | $32.75 | $32.75 |
| 82 | Tangent energy absorbing term MASH TL-3 (705-06.20) | EACH | 4 | $3,350.00 | $3,350.00 | $3,350.00 |
| 83 | Thrie beam bridge transition MASH TL-3 (705-06.25) | EACH | 4 | $3,100.00 | $3,100.00 | $3,100.00 |
| 84 | High-visibility construction fence (707-08.11) | LF | 518 | $3.50 | $3.50 | $3.50 |
| 85 | Markers (concrete R.O.W. posts) (708-02.01) | EACH | 37 | $375.00 | $300.00 | $375.00 |
| 86 | Machined rip-rap (class A-3) (709-05.05) | TON | 786 | $49.00 | $60.00 | $65.00 |
| 87 | Machined rip-rap (class A-1) (709-05.06) | TON | 754 | $49.00 | $60.00 | $65.00 |
| 88 | Machined rip-rap (class A-2) (709-05.07) | TON | 178 | $49.00 | $60.00 | $65.00 |
| 89 | Machined rip-rap (class B) (709-05.08) | TON | 826 | $49.00 | $60.00 | $65.00 |
| 90 | Traffic control (712-01) | LS | 1 | $155,000 | $42,000 | $50,000 |
| 91 | Interconnected portable barrier rail (712-02.02) | LF | 487 | $45.00 | $36.00 | $35.00 |
| 92 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 4 | $9,500.00 | $9,200.00 | $9,483.00 |
| 93 | Flexible drums (channelizing) (712-04.01) | EACH | 40 | $35.00 | $35.00 | $35.00 |
| 94 | Warning lights (type A) (712-05.01) | EACH | 40 | $25.00 | $25.00 | $25.00 |
| 95 | Warning lights (type C) (712-05.03) | EACH | 40 | $25.00 | $25.00 | $25.00 |
| 96 | Signs (construction) (712-06) | SF | 775 | $7.35 | $7.35 | $7.35 |
| 97 | Temporary barricades (type III) (712-07.03) | LF | 240 | $15.00 | $15.00 | $15.00 |
| 98 | Arrow board (type C) (712-08.03) | EACH | 3 | $1,250.00 | $1,250.00 | $1,250.00 |
| 99 | Removable pavement marking (stop line) (712-09.04) | LF | 13 | $40.00 | $40.00 | $40.00 |
| 100 | Removable pavement marking (4" line) (712-09.09) | LF | 911 | $6.00 | $6.00 | $6.00 |
| 101 | Sign post delineation enhancement (713-02.21) | LF | 77 | $5.50 | $6.00 | $5.50 |
| 102 | "U" section steel posts (713-11.01) | LB | 408 | $4.50 | $4.00 | $4.50 |
| 103 | Perforated/knockout square tube post (713-11.02) | LB | 1,148 | $5.00 | $4.10 | $5.00 |
| 104 | Flat sheet aluminum signs (0.080" thick) (713-13.02) | SF | 277 | $14.50 | $14.70 | $14.50 |
| 105 | Flat sheet aluminum signs (0.100" thick) (713-13.03) | SF | 8 | $15.00 | $16.00 | $15.00 |
| 106 | Removal of signs, posts and footings (713-15) | LS | 1 | $1,250.00 | $813.00 | $1,250.00 |
| 107 | Changeable message sign unit (713-16.01) | EACH | 6 | $5,900.00 | $6,000.00 | $5,900.00 |
| 108 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 103 | $62.00 | $62.00 | $62.00 |
| 109 | Plastic pavement marking (cross-walk) (716-02.03) | LF | 180 | $35.00 | $35.00 | $35.00 |
| 110 | Plastic pavement marking(channelization striping) (716-02.04) | SY | 77 | $48.00 | $48.00 | $48.00 |
| 111 | Plastic pavement marking (stop line) (716-02.05) | LF | 155 | $40.00 | $40.00 | $40.00 |
| 112 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 9 | $300.00 | $300.00 | $300.00 |
| 113 | Plastic pavement marking (longitudinal cross-walk) (716-02.09) | LF | 54 | $58.00 | $58.00 | $58.00 |
| 114 | Plastic word pavement marking (RXR) (716-03.02) | EACH | 1 | $2,000.00 | $2,000.00 | $2,000.00 |
| 115 | Plastic pavement marking (straight-turn arrow) (716-04.01) | EACH | 5 | $700.00 | $700.00 | $700.00 |
| 116 | Painted pavement marking (4" line) (716-05.01) | LM | 1.38 | $3,100.00 | $3,100.00 | $3,100.00 |
| 117 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 3.82 | $9,500.00 | $9,500.00 | $9,500.00 |
| 118 | Mobilization (717-01) | LS | 1 | $550,000 | $776,923 | $450,000 |
| 119 | Geogrid reinforcement type 2 (740-07.04) | SY | 2,118 | $5.50 | $8.50 | $10.00 |
| 120 | Geotextile (type III)(erosion control) (740-10.03) | SY | 2,034 | $2.50 | $3.00 | $5.00 |
| 121 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 17,017 | $1.50 | $3.50 | $5.00 |
| 122 | Temporary sediment tube 24IN (740-11.05) | LF | 518 | $8.50 | $8.50 | $8.50 |
| 123 | Seeding (with mulch) (801-01) | UNIT | 43 | $45.00 | $45.00 | $45.00 |
| 124 | Grass seed mix (ripzn/FLPL) W/mulch (801-01.35) | UNIT | 6 | $50.00 | $50.00 | $50.00 |
| 125 | Seeding (without mulch) (801-02) | UNIT | 95 | $40.00 | $40.00 | $40.00 |
| 126 | Temporary seeding (without mulch) (801-02.08) | UNIT | 95 | $35.00 | $35.00 | $35.00 |
| 127 | Water (seeding & sodding) (801-03) | MG | 715 | $20.00 | $20.00 | $20.00 |
| 128 | Seed (supplemental application) (801-07) | LB | 74 | $300.00 | $300.00 | $300.00 |
| 129 | Cuttings: salix nigra (18IN-24IN length) (802-02.30) | EACH | 140 | $8.00 | $8.00 | $8.00 |
| 130 | Cuttings: salix sericea (18IN-24IN) (802-02.31) | EACH | 140 | $8.00 | $8.00 | $8.00 |
| 131 | Cuttings: cornus amomum (18IN-24IN) (802-02.32) | EACH | 140 | $8.00 | $8.00 | $8.00 |
| 132 | Cuttings: sambucus canadensis (18IN-24IN) (802-02.33) | EACH | 140 | $8.00 | $8.00 | $8.00 |
| 133 | Acer negundo (box elder seedlng B.R.) (802-12.01) | EACH | 510 | $8.00 | $8.00 | $8.00 |
| 134 | Betula nigra (river birch seedlng B.R.) (802-12.07) | EACH | 420 | $8.00 | $8.00 | $8.00 |
| 135 | Diospyros virginiana (persimmon seedlng B.R.) (802-12.14) | EACH | 510 | $8.00 | $8.00 | $8.00 |
| 136 | Fraxinus pennsylvanica (green ash seedlng B.R.) (802-12.16) | EACH | 420 | $8.00 | $8.00 | $8.00 |
| 137 | Juglans nigra (black walnut seedlng B.R.) (802-12.17) | EACH | 90 | $8.00 | $8.00 | $8.00 |
| 138 | Liriodendron tulipifera (tulip poplar seedlng B.R.) (802-12.19) | EACH | 90 | $8.00 | $8.00 | $8.00 |
| 139 | Platanus occidentalis (sycamore seedlng B.R.) (802-12.26) | EACH | 420 | $8.00 | $8.00 | $8.00 |
| 140 | Quercus phellos (willow oak seedlng B.R.) (802-12.38) | EACH | 510 | $8.00 | $8.00 | $8.00 |
| 141 | Carpinus caroliniana (american hornbeam seedling B.R.) (802-12.45) | EACH | 230 | $8.00 | $8.00 | $8.00 |
| 142 | Cornus amomum (silky dogwood SDLNG bare root) (802-13.54) | EACH | 140 | $8.00 | $8.00 | $8.00 |
| 143 | Hamamelis virginiana (witch hazel SDLNG bare root) (802-13.55) | EACH | 90 | $8.00 | $8.00 | $8.00 |
| 144 | Lindera benzoin (spicebush SDLNG bare root) (802-13.59) | EACH | 140 | $8.00 | $8.00 | $8.00 |
| 145 | Sodding (new sod) (803-01) | SY | 78,082 | $5.00 | $4.00 | $4.00 |
| 146 | Erosion control blanket (type II) (805-12.02) | SY | 30,725 | $2.00 | $1.60 | $1.60 |
| 147 | 700 gram coir fiber erosion blanket (805-12.08) | SY | 4,000 | $7.50 | $7.50 | $7.50 |
| 148 | CPM project schedule (108-03) | LS | 1 | $195,000 | $56,950 | $70,000 |
| 149 | Dry excavation (bridges) (204-02.01) | CY | 408 | $35.00 | $40.00 | $16.00 |
| 150 | Granular backfill (bridges) (303-01.02) | TON | 36 | $105.00 | $125.00 | $60.00 |
| 151 | Epoxy coated reinforcing steel (604-02.03) | LB | 70,607 | $1.75 | $1.80 | $1.73 |
| 152 | Class A concrete (bridges) (604-03.01) | CY | 330 | $1,100.00 | $1,100.00 | $1,460.00 |
| 153 | Steel bar reinforcement (bridges) (604-03.02) | LB | 58,532 | $1.75 | $1.69 | $1.55 |
| 154 | Pavement @ bridge ends (604-03.04) | SY | 204 | $650.00 | $450.00 | $405.00 |
| 155 | Class D concrete (bridge deck) (604-03.09) | CY | 235 | $1,250.00 | $1,500.00 | $1,275.00 |
| 156 | Applied texture finish (new structures) (604-04.01) | SY | 1,153 | $12.95 | $13.99 | $13.99 |
| 157 | Bridge deck grooving (mechanical) (604-05.31) | SY | 1,050 | $3.42 | $7.40 | $7.40 |
| 158 | Test piles (precast concrete, size 1) (606-09.01) | LF | 230 | $300.00 | $200.00 | $145.00 |
| 159 | Loading test (precast concrete, size 1) (606-09.02) | EACH | 1 | $15,000 | $5,000.00 | $9,600.00 |
| 160 | Precast concrete piles (size 1) (606-09.03) | LF | 3,070 | $85.00 | $100.00 | $117.00 |
| 161 | Pile anchorage system (seismic) (606-12.01) | EACH | 70 | $550.00 | $300.00 | $465.00 |
| 162 | Prestressed concrete I-beam (type III) (615-01.03) | LF | 998 | $475.00 | $350.00 | $400.00 |
| 163 | Conc parapet single slope (STD-1-1SS) (620-05.01) | LF | 472 | $175.00 | $160.00 | $130.00 |
| 164 | Chain-link fence (bridges) (707-07.01) | SF | 775 | $32.00 | $32.00 | $32.00 |
| 165 | 6" perforated pipe with vertical drain system (710-09.01) | LF | 146 | $35.00 | $50.00 | $30.00 |
| 166 | 6" pipe underdrain (710-09.02) | LF | 32 | $35.00 | $25.00 | $20.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of June 27, 2025. Compiled by Mirage Metrics.