FDOT contract T7601 bid tabulation

SR 60 FROM W OF BEN T DAVIS BEACH ENTRACE TO E OF BAYPORT DR. Let by Florida DOT on February 25, 2026, Hillsborough, District 7. 6 bids received; low bid $7,094,361 by Preferred Materials Inc..

Owner
Florida DOT
Letting
25 FEB 2026
Pay items
187
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Preferred Materials Inc.$7,094,361Low
2Hubbard Construction Company$7,635,829+8.0%
3C.W. Roberts Contracting, Inc.$7,731,926+9.0%
4Ajax Paving Industries of Florida LLC$8,592,066+21%
5Superior Asphalt, Inc.$8,738,001+23%
6Watson Civil Construction, Inc.$9,196,161+30%
FDOT contract T7601: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Preferred Materials Inc.2. Hubbard Construction Company3. C.W. Roberts Contracting, Inc.4. Ajax Paving Industries of Florida LLC5. Superior Asphalt, Inc.6. Watson Civil Construction, Inc.
0005Mobilization (0101-1)LS1$518,000$388,864$616,615$504,000$577,119$910,000
0010Maintenance of traffic (0102-1)DA1$359,000$517,167$338,980$725,000$572,600$350,000
0015Pedestrian or bicycle special detour (0102-4-1)SY1$10,000$10,112$9,644.31$16,682$10,375$15,000
0020Traffic control officer (0102-14)HR384$87.34$101.47$91.40$125.00$110.00$135.00
0025Work zone sign (0102-60)ED12,242$0.23$0.24$0.23$0.23$0.25$0.35
0030Temporary barrier, F&I, anchored (0102-71-15)LF578$15.00$43.55$46.69$45.95$41.10$40.00
0035Temporary barrier, relocate, anchored (0102-71-25)LF129$8.00$18.31$21.34$21.01$18.80$20.00
0040Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED29,044$0.10$0.10$0.10$0.10$0.15$0.15
0045Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD47,106$0.04$0.05$0.04$0.04$0.05$0.10
0050Arrow board / advance warning arrow panel (0102-76)ED454$5.46$5.72$5.43$5.57$5.90$8.00
0055Temporary crash cushion, redirective option (0102-89-1)LO5$873.43$915.69$1,067.18$890.60$940.00$1,200.00
0060Portable changeable message sign, temporary (0102-99)ED663$10.92$11.45$10.86$11.13$11.75$15.00
0065Temporary signalization and maintenance, intersection (0102-104)ED660$27.29$18.22$17.42$18.08$7.50$25.00
0070Temporary traffic detection and maintenance, intersection (0102-107-1)ED660$26.20$25.05$23.95$24.86$14.15$35.00
0075Existing ITS maintenance (0102-112)DA220$300.24$337.10$322.27$334.47$142.70$330.00
0080Type III barricade (0102-115)ED510$0.33$0.34$0.33$0.33$0.35$0.45
0085Artificial coverings /rolled erosion control products (0104-1)SY54$9.16$9.60$9.16$60.62$6.45$11.00
0090Sediment barrier (0104-10-3)LF2,652$2.77$2.91$2.77$10.00$1.45$3.00
0095Inlet protection system (0104-18)EACH26$203.41$213.25$203.38$150.29$146.75$325.00
0100Litter removal (0107-1)ACRE129.75$57.86$56.12$54.99$56.94$57.50$100.00
0105Mowing (0107-2)ACRE103.30$112.45$114.60$112.30$116.26$117.55$125.00
0110Clearing & grubbing (0110-1-1)ACRE1$84,351$88,433$76,697$86,550$56,315$155,004
0115Removal of existing concrete (0110-4-10)SY289$47.43$49.72$47.42$95.29$51.00$30.00
0120Regular excavation (0120-1)CY40.50$34.81$36.49$34.80$418.40$37.50$280.00
0125Embankment (0120-6)CY51.50$61.88$64.88$61.87$329.03$66.50$200.00
0130Optional base, base group 15 (0285-715)SY55$135.10$124.89$128.14$278.25$149.35$200.00
0135Milling existing asphalt pavement, 3" avg depth (0327-70-4)SY16,384$2.89$3.77$4.42$5.50$3.55$3.75
0140Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY30,522$2.11$4.76$5.04$5.02$4.00$4.45
0145Milling existing asphalt pavement, 4" avg depth (0327-70-7)SY4,034$5.38$5.76$6.76$8.32$5.55$6.15
0150Milling existing asphalt pavement, 3/4" avg depth (0327-70-19)SY6,842$2.79$3.21$3.03$2.81$2.90$3.25
0155Milling existing asphalt pavement, 3 3/4" avg depth (0327-70-20)SY69,424$2.43$2.96$5.88$5.16$3.85$4.40
0160Superpave asphaltic conc, traffic E (0334-1-15)TN10,543.10$111.57$121.21$115.64$139.46$159.00$175.00
0165Asphalt concrete friction course,traffic E, FC-12.5, PG (0337-7-88)TN10,506.70$158.61$161.09$163.07$165.81$187.05$198.00
0170Miscellaneous asphalt (0339-1)TN2.90$558.41$417.18$382.91$1,350.91$526.50$550.00
0175Inlets, curb, type 7, <10' (0425-1471)EACH3$11,700$12,267$11,699$15,986$12,600$14,000
0180Inlets, curb, type 7, partial (0425-1475)EACH1$11,086$11,622$11,084$6,948.37$11,920$6,000.00
0185Manholes, P-8, <10' (0425-2-61)EACH3$10,910$11,438$10,909$13,535$11,735$10,000
0190Manhole, adjust (0425-5)EACH6$1,355.10$1,420.68$372.03$234.22$1,460.00$1,500.00
0195Valve boxes, adjust (0425-6)EACH18$762.61$799.52$259.58$144.88$820.00$1,000.00
0200Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF85$178.80$187.45$178.78$783.13$192.25$250.00
0205Pipe culvert,optional material,round, 24"S/CD (0430-175124)LF35$246.45$258.37$246.42$911.53$265.00$300.00
0210Straight concrete endwalls, single, 0 degrees, round (0430-548100)EACH1$14,356$15,051$14,354$25,911$15,440$10,000
0215Mitered end section, optional round, 24" SD (0430-984129)EACH1$3,660.12$3,837.24$3,659.65$5,481.16$3,935.00$3,200.00
0220Pedestrian/ bicycle railing, aluminum only,42" type 1 (0515-2311)LF86$130.24$98.44$128.27$96.85$102.15$100.00
0225Bollards (0519-78)EACH7$1,326.56$1,390.76$1,326.39$1,620.19$1,540.00$5,500.00
0230Concrete curb & gutter, type F (0520-1-10)LF60$46.66$48.92$46.66$85.87$50.25$110.00
0235Traffic separator concrete- type I, 4' wide (0520-5-11)LF36$89.96$94.32$89.95$200.00$238.50$350.00
0240Concrete traffic separator, special- variable width (0520-70)SY203$167.74$175.86$167.72$133.75$302.00$425.00
0245Concrete sidewalk and driveways, 4" thick (0522-1)SY36$86.79$90.99$86.77$198.66$93.35$165.00
0250Concrete sidewalk and driveways, 6" thick (0522-2)SY135$115.73$121.33$115.71$118.10$124.45$185.00
0255Detectable warnings (0527-2)SF311$28.95$30.36$28.95$23.38$25.50$75.00
0260Riprap, rubble, F&I, ditch lining (0530-3-4)TN5.60$198.03$207.61$198.00$1,889.27$213.00$650.00
0265Bedding stone (0530-74)TN4$194.51$203.92$194.97$2,655.58$209.00$800.00
0270Guardrail -roadway, general (0536-1-1)LF80$37.87$28.62$40.11$30.91$29.35$30.00
0275Guardrail removal (0536-73)LF80$11.18$3.43$11.84$3.71$3.50$4.00
0280Guardrail end treatment- parallel approach terminal (0536-85-24)EACH1$4,136.36$4,349.55$4,380.03$4,697.81$4,465.00$4,500.00
0285Performance turf, sod (0570-1-2)SY4,829$4.06$3.35$4.50$6.74$8.10$8.00
0290Conduit, furnish & install, open trench (0630-2-11)LF14$25.11$27.33$26.13$27.12$63.00$26.00
0295Conduit, furnish & install, directional bore (0630-2-12)LF52$39.30$41.00$39.19$40.68$102.75$38.00
0300Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH1$1,709.98$1,445.18$1,381.60$1,433.91$1,620.00$1,350.00
0305Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1)EACH11$3,532.08$2,744.60$2,623.85$2,723.19$2,755.00$2,500.00
0310Traffic monitoring site speed/classification unit, furnish & install, volume speed and classification (0695-3-11)AS1$18,934$12,558$12,005$12,460$10,550$12,000
0315Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12)EACH11$2,757.84$1,999.80$1,911.82$1,984.20$2,920.00$1,850.00
0320Traffic monitoring site cabinet, F&I, type 3, 2 pane back, pedestal mount (0695-7162)EACH1$6,765.32$7,151.88$6,837.26$7,096.10$7,845.00$6,600.00
0325Raised pavement marker, type B (0706-1-3)EACH4,093$3.82$3.99$4.34$4.52$4.10$4.40
0330Painted pavement markings, standard, white, solid, 6" (0710-11101)GM8.42$1,855.81$1,935.79$1,522.21$1,581.08$1,995.00$1,500.00
0335Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102)GM0.68$2,462.02$2,568.14$1,622.04$1,694.02$2,660.00$1,650.00
0340Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF1,844$1.64$1.71$1.09$1.13$1.75$1.10
0345Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124)LF1,337$1.75$1.82$1.63$1.69$1.90$1.65
0350Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF1,917$1.86$1.94$2.17$2.26$2.00$2.15
0355Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM5.91$534.97$558.03$870.37$903.48$575.00$825.00
0360Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM0.75$705.90$736.31$875.82$903.48$763.00$820.00
0365Painted pavement markings, standard, white, message or symbol (0710-11160)EACH16$38.21$39.86$70.60$73.41$41.10$68.00
0370Painted pavement markings, standard, white, arrows (0710-11170)EACH108$32.75$34.17$43.45$45.17$41.10$42.00
0375Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM5.53$1,853.01$1,932.87$1,520.86$1,581.08$1,995.00$1,500.00
0380Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224)LF185$1.75$1.82$1.63$1.69$1.90$1.65
0385Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241)GM0.20$677.59$706.78$873.27$903.48$765.00$800.00
0390High friction surface course (0908-333100)SY7,283$25.31$38.58$32.13$30.06$27.25$35.00
0395Initial contingency amount, DO not bid (0999-25)LS1$84,000$84,000$84,000$84,000$84,000$84,000
0400Initial contingency amount, DO not bid (0999-25)LS1$8,000.00$8,000.00$8,000.00$8,000.00$8,000.00$8,000.00
0405Raised rumble strip set- permanent (0546-71-1)EACH13$1,754.49$1,830.11$1,086.13$1,129.34$1,885.00$1,100.00
0410Ground-in rumble strips, 8" sinusoidal (0546-72-3)GM3.72$5,113.14$3,673.42$4,861.22$2,456.82$2,230.00$2,750.00
0415Prestressed concrete pole, complete pole removal- pole 30' and greater (0641-2-80)EACH2$5,786.45$14,858$14,205$14,743$18,235$14,200
0420Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH28$600.48$626.36$510.48$612.29$645.00$500.00
0425Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH1$2,292.74$2,391.56$2,932.55$2,337.83$2,465.00$3,000.00
0430Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113)EACH1$2,729.45$2,847.09$3,258.39$2,783.14$2,935.00$3,300.00
0435Single column ground sign assembly, F&I ground mount, SF sheeting area for back to back signs (0700-1114)EACH1$3,493.70$3,644.27$3,801.45$3,562.41$3,760.00$3,800.00
0440Single column ground sign assembly, relocate (0700-1500)EACH2$272.95$284.71$434.45$278.31$295.00$425.00
0445Single column ground sign assembly, remove (0700-1600)EACH11$70.97$74.02$38.01$72.36$76.35$36.50
0450Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114)EACH2$9,007.21$9,395.41$8,580.43$9,184.35$9,685.00$8,200.00
0455Multi-column ground sign assembly, F&I ground mount, 100.0 SF (0700-2115)EACH2$11,464$11,958$16,292$11,689$12,330$16,500
0460Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH112$300.24$313.18$325.84$306.14$323.00$325.00
0465Sign panel, furnish & install ground mount, 12-20 SF (0700-3102)EACH10$627.78$654.83$543.07$640.12$675.00$550.00
0470Sign panel, furnish & install ground mount, 21-30 SF (0700-3103)EACH3$1,091.78$1,138.83$977.52$1,113.25$1,175.00$950.00
0475Sign panel, remove, UP to 12 SF (0700-3601)EACH108$38.21$39.86$38.01$38.96$41.10$75.00
0480Sign panel, remove, 12-20 SF (0700-3602)EACH9$49.13$51.25$38.01$50.10$52.85$100.00
0485Sign panel, remove, 21-30 SF (0700-3603)EACH3$54.59$56.94$271.53$55.66$58.70$500.00
0490Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH13$125.56$130.97$135.77$128.02$135.00$135.00
0495Enhanced hwy sign assembly, solar powered, F&I ground mount, W/highlighted sign <12 UP to 12 SF of static panels (0700-142141)EACH12$6,550.69$6,833.02$6,299.56$10,431$7,045.00$10,000
0500Enhanced highway sign solar powered, F&I ground mount, highlighted sign 12-20 SF (0700-142150)EACH2$7,642.48$7,971.85$7,059.85$10,689$8,220.00$10,000
0505Profiled thermoplastic,standard- concrete surfaces, white, solid,6" (0701-17101)GM0.02$18,196$18,980$22,628$28,234$23,480$23,000
0510Tubular marker, 36" white post (0704-1-3)EACH85$174.69$182.21$217.23$178.12$187.85$225.00
0515Tubular marker, 36" yellow (0704-1-4)EACH26$174.69$182.21$217.23$178.12$187.85$225.00
0520Object marker, type 1 (0705-10-1)EACH7$218.36$227.77$380.15$222.65$235.00$375.00
0525Object marker, type 4 (0705-10-4)EACH3$218.35$227.77$380.15$222.65$235.00$375.00
0530Raised pavement marker, type B (0706-1-3)EACH2,064$3.82$3.99$4.34$4.52$4.10$4.15
0535Painted pavement markings, surface (0710-90)LS1$40,737$42,492$48,876$50,820$50,600$43,000
0540Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102)GM0.68$6,417.57$6,694.16$7,028.84$7,340.74$6,930.00$9.25
0545Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF1,583$3.28$3.42$3.80$3.95$3.55$3.65
0550Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF1,337$4.91$5.12$5.43$5.65$5.30$5.15
0555Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF1,917$6.55$6.83$6.52$6.78$7.00$6.25
0560Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.24$2,706.86$2,823.55$3,096.82$3,388.03$2,935.00$3,100.00
0565Thermoplastic, standard, message or symbol (0711-11160)EACH16$116.82$121.86$217.23$225.87$125.65$207.00
0570Thermoplastic, standard, arrow (0711-11170)EACH108$65.51$68.33$86.89$90.35$70.45$83.00
0575Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF185$4.91$5.12$5.43$5.65$5.30$5.25
0580Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.20$2,605.98$2,718.34$3,274.77$3,388.03$2,935.00$3,000.00
0585Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM6.80$4,831.57$5,039.80$5,443.42$5,646.72$5,200.00$5,200.00
0590Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM5.91$1,208.60$1,260.69$3,263.90$3,388.03$1,300.00$3,100.00
0595Thermoplastic, standard other surfaces, white, 6", 6-10 dotted managed lane marking (0711-16171)GM0.45$2,729.47$2,847.07$3,258.40$3,388.03$2,935.00$3,100.00
0600Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM5.16$4,832.54$5,040.81$5,428.55$5,646.72$5,200.00$5,200.00
0605Permanent tape, white, solid, 6" for concrete bridges (0713-103101)GM0.05$33,976$35,440$34,664$33,880$42,930$26,500
0610Permanent tape, white, solid, 8" exit lane at interchange on concrete pavement (0713-103102)GM0.05$45,301$47,254$40,441$39,527$57,240$30,600
0615Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181)GM0.09$9,284.65$9,684.88$11,367$11,293$10,735$10,000
0620Permanent tape, yellow, solid, for concrete bridges (0713-103201)GM0.05$33,976$35,440$34,664$33,880$42,930$27,000
0625Conduit, furnish & install, open trench (0630-2-11)LF202$11.19$27.33$26.13$27.12$34.15$26.00
0630Conduit, furnish & install, directional bore (0630-2-12)LF97$33.63$41.00$39.19$40.68$35.00$37.50
0635Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH6$1,709.98$1,857.44$1,775.73$1,842.95$2,780.00$1,700.00
0640Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF720$3.00$2.28$2.18$2.26$3.15$2.15
0645Lighting conductors, F&I, no.1/0 3/0 (0 to 000) (0715-1-15)LF728$6.39$4.56$4.35$4.52$7.95$4.25
0650Load center, F&I, secondary voltage (0715-7-11)EACH2$24,288$20,682$19,773$20,521$26,810$19,000
0655Load center, remove, voltage (0715-7-41)EACH2$1,637.67$874.64$836.15$867.80$1,650.00$800.00
0660Light pole complete, F&I, standard pole standard foundation, 50' mounting height, 0' arm length (0715-61500)EACH2$12,738$13,721$13,117$13,614$15,955$12,500
0665Light pole complete, F&I, standard pole standard foundation, 50' mounting height, 10' arm length (0715-61521)EACH5$12,932$13,948$13,335$13,840$15,800$13,500
0670Light pole complete, remove pole and foundation (0715-69000)EACH2$1,045.93$1,209.44$1,156.24$1,200.01$1,650.00$1,100.00
0675Light pole complete, remove pole, foundation remains (0715-69001)EACH1$567.73$494.25$472.52$490.40$1,235.00$450.00
0680Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH7$935.60$714.05$682.64$708.48$850.00$650.00
0685Itsfm location documentation- intersection (0611-2-1)EACH2$2,942.36$3,308.32$3,162.78$3,282.51$3,845.00$3,000.00
0690Conduit, furnish & install, open trench (0630-2-11)LF2,191$14.41$27.33$26.13$27.12$24.00$25.00
0695Conduit, furnish & install, directional bore (0630-2-12)LF2,283$29.88$41.00$39.19$40.68$38.00$38.00
0700Conduit, furnish & install, aboveground (0630-2-14)LF46$43.67$48.97$46.82$48.59$68.00$44.00
0705Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI2$11,992$9,719.97$9,292.35$9,644.15$13,960$8,800.00
0710Signal cable- repair/replace/other, furnish & install (0632-7-2)LF243$8.19$6.83$6.53$6.78$9.00$6.50
0715Signal cable, remove- intersection (0632-7-6)PI2$1,091.79$1,445.19$1,381.60$1,433.91$1,235.00$1,350.00
0720Fiber optic cable, F&I, underground,2-12 fibers (0633-1121)LF211$4.51$4.56$4.35$4.52$5.90$4.25
0725Fiber optic connection, install, termination (0633-2-32)EACH24$90.07$101.36$96.90$100.57$118.00$95.00
0730Fiber optic connection hardware, F&I, buffer tube fan out kit (0633-3-14)EACH2$102.08$115.03$109.96$114.13$133.50$110.00
0735Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16)EACH2$3,320.66$3,734.25$3,569.96$3,705.12$4,340.00$3,600.00
0740Fiber optic cable locator (0633-6)DA220$222.18$249.41$238.43$247.46$290.00$230.00
0745Span wire assembly, F&I, two point, box or drop box (0634-4153)PI1$15,129$11,271$10,775$11,183$12,570$10,500
0750Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH13$1,709.98$1,490.74$1,425.15$1,479.11$1,575.00$1,400.00
0755Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH2$2,891.14$3,055.50$2,921.08$3,031.66$2,785.00$2,850.00
0760Pull & splice box, F&I, 17" X 30" cover size (0635-2-14)EACH16$2,149.76$1,888.19$1,805.12$1,873.46$1,870.00$1,700.00
0765Electrical power service, remove underground (0639-1620)AS1$873.43$349.62$334.24$346.90$825.00$315.00
0770Electrical service wire, & install (0639-2-1)LF3,926$14.72$6.83$6.53$6.78$13.15$6.50
0775Electrical service disconnect, F&I, pole mount (0639-3-11)EACH2$2,943.99$1,957.66$1,871.53$1,942.39$1,620.00$1,850.00
0780Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60)EACH1$420.33$175.39$167.67$174.01$415.00$160.00
0785Prestressed concrete pole, type P-II pedestal (0641-2-11)EACH1$3,251.32$1,915.53$1,831.25$1,900.58$3,585.00$1,800.00
0790Aluminum signals pole, (0646-1-11)EACH7$3,221.74$3,435.87$3,284.71$3,409.07$3,600.00$3,150.00
0795Aluminum signals pole, remove (0646-1-60)EACH5$573.19$440.73$421.34$437.29$620.00$400.00
0800Steel strain pole, F&I, type PS- VIII (0649-1-15)EACH4$64,243$70,500$67,398$69,950$80,815$64,000
0805Steel strain pole, remove, deep foundation removal, bolt on attachment (0649-1-65)EACH2$13,647$18,545$17,729$18,400$20,900$17,000
0810Steel mast arm assembly, and install, double arm 70'-50' (0649-21-18)EACH1$115,262$145,248$138,858$144,115$134,700$135,000
0815Steel mast arm assembly, remove, deep foundation- bolt on attachment (0649-26-5)EACH1$16,868$17,555$16,783$17,418$19,665$16,000
0820Vehicular traffic signal, furnish & install aluminum, 1 section, 1 way (0650-1-11)AS3$1,217.50$1,059.12$1,012.52$1,050.86$1,185.00$950.00
0825Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14)AS28$1,742.45$2,039.66$1,949.92$2,023.75$2,500.00$1,900.00
0830Vehicular traffic signal, furnish & install aluminum, 5 section straight, 1 way (0650-1-18)AS1$2,554.15$2,711.56$2,592.28$2,690.42$3,030.00$2,500.00
0835Vehicular traffic signal, remove- poles to remain (0650-1-60)AS3$245.65$273.32$261.30$271.19$205.00$250.00
0840Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS7$1,203.64$970.29$927.60$962.72$1,120.00$900.00
0845Vehicle detection system- microwave, furnish & install cabinet equipment (0660-3-11)EACH2$10,978$12,762$12,200$12,662$12,150$12,000
0850Vehicle detection system- microwave, furnish & install, above ground equipment (0660-3-12)EACH5$12,888$14,848$14,195$14,732$14,065$14,000
0855Vehicle detection system- furnish & install cabinet equipment (0660-4-11)EACH1$26,842$29,119$27,838$28,892$30,450$27,000
0860Vehicle detection system- furnish & install above ground equipment (0660-4-12)EACH2$9,224.27$11,720$11,204$11,628$6,700.00$10,600
0865Vehicle detection system- remove cabinet equipment (0660-4-61)EACH1$1,664.97$349.62$334.24$346.90$205.00$325.00
0870Pedestrian detector, furnish & install, standard (0665-1-11)EACH7$382.84$435.04$415.90$431.64$600.00$400.00
0875Traffic controller assembly, F&I, NEMA W/standard lock, 2 preemption (0670-5162)AS2$52,567$60,497$57,836$60,025$67,250$56,000
0880Traffic controller assembly, remove controller with (0670-5600)AS2$1,637.67$437.31$418.08$433.90$1,650.00$400.00
0885Traffic controller, modify (0671-2-40)EACH1$4,913.02$437.32$418.08$433.90$1,250.00$400.00
0890Traffic signal controller cabinet, adjust/modify (0676-1500)EACH1$4,694.67$1,711.67$1,636.37$1,698.32$2,525.00$1,600.00
0895Small equipment enclosure, furnish and install, greater than 10"W X 13"H X 11" D (0676-3-11)EACH2$3,559.21$10,466$10,005$10,384$7,180.00$9,450.00
0900Managed field ethernet switch, furnish & install (0684-1-1)EACH2$4,981.15$5,193.09$4,964.63$5,152.59$2,735.00$4,600.00
0905Uninterruptible power supply, furnish and install, line interactive with cabinet (0685-1-13)EACH2$17,086$8,576.58$8,199.26$8,509.68$16,200$7,700.00
0910Remote power management rpmu, furnish and install (0685-2-1)EACH2$1,341.42$1,076.20$1,028.86$1,067.81$960.00$970.00
0915Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH1$1,029.03$908.79$868.81$901.70$1,125.00$820.00
0920Overhead static sign furnish & install, cantilever, 40 FT (0700-4113)EACH2$77,551$93,914$89,783$93,182$140,000$86,000
0925Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22)EACH7$5,659.69$7,303.36$6,982.06$7,246.39$7,385.00$6,700.00
0930Internally illuminated sign, remove (0700-5-60)EACH1$436.71$456.67$436.58$453.11$415.00$410.00
0935Enhanced highway sign AC powered, F&I overhead W/2 beacons, 101-200 SF of static sign panels (0700-141326)EACH2$32,617$10,604$10,137$10,521$10,280$9,600.00
FDOT contract T7601: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of February 25, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy