TDOT contract CN261074 bid tabulation
The construction of a concrete box beam bridge on s.r. 33 over south fork sycamore creek (l.m. 20.56), including grading, drainage, and paving. Let by Tennessee DOT on October 2, 2026, Claiborne County. 5 bids received; low bid $2,643,606 by Southern Constructors, Inc..
- Owner
- Tennessee DOT
- Letting
- 02 OCT 2026
- Pay items
- 122
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Southern Constructors, Inc. | $2,643,606 | Low |
| 2 | Charles Blalock & Sons, Inc. | $2,993,828 | +13% |
| 3 | Jones Bros. Contractors, LLC | $3,329,043 | +26% |
| 4 | Whaley Construction, LLC | $3,498,103 | +32% |
| 5 | King General Contractors, Inc. | $3,682,691 | +39% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Southern Constructors, Inc. | 2. Charles Blalock & Sons, Inc. | 3. Jones Bros. Contractors, LLC | 4. Whaley Construction, LLC | 5. King General Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $40,000 | $27,171 | $30,000 | $28,466 | $42,463 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $28,000 | $155,500 | $162,000 | $200,000 | $71,446 |
| 3 | Removal of pipe (EX. 18" CMP, sta. 98+93.54 to 101+20.00) (202-01.13) | LF | 54 | $38.00 | $55.49 | $50.00 | $50.00 | $45.83 |
| 4 | Removal of pipe (EX. 24" CMP, sta. 20+21.05) (202-01.14) | LF | 20 | $68.00 | $149.82 | $50.00 | $60.00 | $45.83 |
| 5 | Removal of structures (CB1, sta. 100+19) (202-04.01) | LS | 1 | $600.00 | $599.25 | $1,500.00 | $2,050.00 | $3,370.08 |
| 6 | Removal of buildings tract no.4 (202-06.01) | LS | 1 | $3,000.00 | $4,874.82 | $100.00 | $4,110.00 | $7,414.18 |
| 7 | Removal of buildings (tract no. 6, 6A) (202-06.02) | LS | 1 | $9,000.00 | $4,874.82 | $100.00 | $15,300 | $9,436.22 |
| 8 | Removal of buildings (tract no. 8, 9) (202-06.03) | LS | 1 | $4,000.00 | $4,874.82 | $100.00 | $6,720.00 | $8,088.19 |
| 9 | RD & DRNG excv (acid producing- off site disposal) (203-01.07) | CY | 2,602 | $100.00 | $110.00 | $150.00 | $167.00 | $218.65 |
| 10 | Borrow excavation (offsite soil) (203-02.05) | CY | 182 | $90.00 | $48.00 | $85.00 | $60.00 | $55.27 |
| 11 | Borrow excavation (unclassified) (203-03) | CY | 678 | $75.00 | $48.00 | $85.00 | $45.00 | $53.79 |
| 12 | Water (203-06) | MG | 2 | $350.00 | $200.00 | $1.00 | $100.00 | $1,213.23 |
| 13 | Furnishing & spreading topsoil (203-07) | CY | 282.70 | $115.00 | $50.00 | $65.00 | $67.00 | $61.07 |
| 14 | Compacted clay (203-15.03) | CY | 13 | $270.00 | $500.00 | $120.00 | $165.00 | $229.17 |
| 15 | Channel substrate (203-20.01) | CY | 25 | $600.00 | $200.00 | $500.00 | $178.00 | $152.33 |
| 16 | Backfill material (flowable fill) (204-08.01) | CY | 47 | $500.00 | $5.00 | $400.00 | $682.00 | $407.11 |
| 17 | Brooming & degrassing shoulders (208-01.05) | LM | 0.21 | $2,000.00 | $3,528.00 | $40,000 | $5,000.00 | $9,166.62 |
| 18 | Ditch (riprap, sand & plastic sheeting) (208-02.01) | LF | 62 | $13.00 | $170.00 | $65.00 | $133.00 | $114.58 |
| 19 | Stream mitigation - live brush layering (209-03.42) | LF | 56 | $270.00 | $270.00 | $150.00 | $353.00 | $80.88 |
| 20 | Stream mitigation – wood toe W/reinforced earth (209-03.67) | LF | 56 | $255.00 | $270.00 | $250.00 | $902.00 | $337.01 |
| 21 | Protected area marker (white with decal) (209-03.99) | EACH | 18 | $140.00 | $270.00 | $275.00 | $350.00 | $289.83 |
| 22 | Sediment removal (209-05) | CY | 54 | $50.00 | $5.00 | $45.00 | $41.00 | $32.35 |
| 23 | Temporary silt fence (with backing) (209-08.02) | LF | 592 | $6.00 | $5.00 | $5.25 | $6.00 | $7.08 |
| 24 | Enhanced rock check dam (209-08.08) | EACH | 4 | $1,150.00 | $1,260.00 | $1,000.00 | $2,500.00 | $1,348.03 |
| 25 | Sediment filter bag (15' X 15') (209-09.03) | EACH | 2 | $800.00 | $1,400.00 | $700.00 | $2,500.00 | $943.62 |
| 26 | Temporary in stream diversion (209-65.04) | LF | 118 | $225.00 | $250.00 | $500.00 | $160.00 | $283.09 |
| 27 | Mineral aggregate, type A base, grading D (303-01) | TON | 1,067 | $55.00 | $80.00 | $88.00 | $56.00 | $78.19 |
| 28 | Mineral aggregate (size 57) (303-10.01) | TON | 81 | $70.00 | $80.00 | $85.00 | $57.00 | $84.93 |
| 29 | Mineral aggregate (size 57) (303-10.04) | TON | 329 | $60.00 | $80.00 | $100.00 | $57.00 | $84.93 |
| 30 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01) | TON | 36 | $400.00 | $375.90 | $358.00 | $394.00 | $350.49 |
| 31 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 48 | $398.00 | $371.70 | $354.00 | $389.00 | $350.49 |
| 32 | Bituminous material for tack coat (TC) (403-01) | TON | 1 | $1,250.00 | $1,155.00 | $1,100.00 | $1,210.00 | $1,314.33 |
| 33 | Acs mix (PG64-22) grading E shoulder (411-01.07) | TON | 18 | $950.00 | $882.00 | $840.00 | $924.00 | $370.71 |
| 34 | Acs mix(PG64-22) grading D (411-01.10) | TON | 120 | $300.00 | $273.00 | $260.00 | $286.00 | $370.71 |
| 35 | Scoring for rumble stripe (non-continuous) (8IN width) (411-12.03) | LM | 0.20 | $2,200.00 | $2,100.00 | $45,350 | $2,200.00 | $8,088.19 |
| 36 | Cold planing bituminous pavement (415-01.01) | TON | 102 | $160.00 | $147.00 | $140.00 | $154.00 | $51.23 |
| 37 | 48" concrete pipe culvert (class III) (607-09.02) | LF | 90 | $640.00 | $400.00 | $330.00 | $360.00 | $500.12 |
| 38 | 18" pipe culvert (side drain) (607-39.02) | LF | 163 | $140.00 | $165.00 | $85.00 | $87.00 | $175.24 |
| 39 | 18IN endwall (cross drain) 3:1 (611-07.54) | EACH | 8 | $2,300.00 | $4,500.00 | $2,500.00 | $1,572.00 | $3,747.53 |
| 40 | 48IN endwall (cross drain) 3:1 (611-07.69) | EACH | 4 | $8,800.00 | $12,000 | $8,000.00 | $3,530.00 | $8,088.19 |
| 41 | Metal beam guard fence (705-01.04) | LF | 70 | $80.00 | $80.00 | $72.50 | $88.00 | $121.32 |
| 42 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 244 | $31.00 | $30.00 | $28.00 | $32.00 | $38.08 |
| 43 | GR terminal (in-inline) MASH TL-3 (705-06.11) | EACH | 1 | $1,200.00 | $1,150.00 | $1,080.00 | $1,546.00 | $1,597.42 |
| 44 | Tangent energy absorbing term MASH TL-3 (705-06.20) | EACH | 2 | $3,800.00 | $3,600.00 | $3,380.00 | $3,520.00 | $4,448.51 |
| 45 | Thrie beam bridge transition MASH TL-3 (705-06.25) | EACH | 1 | $3,350.00 | $3,200.00 | $2,975.00 | $3,685.00 | $3,774.49 |
| 46 | Thrie beam bridge transition MASH TL-2 (705-06.26) | EACH | 1 | $2,800.00 | $2,600.00 | $2,425.00 | $2,200.00 | $2,224.25 |
| 47 | GR terminal (energy absorbing) MASH TL-2 (705-06.30) | EACH | 1 | $3,200.00 | $3,100.00 | $2,880.00 | $2,970.00 | $4,044.10 |
| 48 | Guardrail removed (706-01) | LF | 401 | $4.00 | $3.25 | $3.00 | $3.00 | $2.02 |
| 49 | Radius rail (706-06.03) | LF | 32 | $42.00 | $40.00 | $38.00 | $41.00 | $52.57 |
| 50 | Rounded end element (706-10.26) | EACH | 25 | $142.00 | $140.00 | $127.00 | $200.00 | $148.28 |
| 51 | High-visibility construction fence (707-08.11) | LF | 660 | $4.00 | $2.50 | $3.00 | $5.00 | $4.04 |
| 52 | Machined rip-rap (class A-3) (709-05.05) | TON | 100 | $95.00 | $80.00 | $90.00 | $62.00 | $87.62 |
| 53 | Machined rip-rap (class A-1) (709-05.06) | TON | 808 | $78.00 | $80.00 | $90.00 | $61.00 | $87.62 |
| 54 | Machined rip-rap (class B) (709-05.08) | TON | 443 | $61.00 | $80.00 | $90.00 | $60.00 | $98.41 |
| 55 | Rock riffles (709-05.81) | LS | 1 | $4,400.00 | $70,000 | $15,000 | $100,000 | $32,892 |
| 56 | Traffic control (712-01) | LS | 1 | $22,000 | $45,000 | $100,000 | $50,450 | $88,296 |
| 57 | Portable barrier rail (MASH TL-3) (712-02.10) | LF | 330 | $81.00 | $100.00 | $70.00 | $125.00 | $113.23 |
| 58 | Portable barrier rail, reduced deflection (MASH TL-3) (712-02.12) | LF | 120 | $142.00 | $175.00 | $150.00 | $125.00 | $149.63 |
| 59 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 6 | $6,900.00 | $5,600.00 | $6,250.00 | $7,480.00 | $9,611.47 |
| 60 | Flexible drums (channelizing) (712-04.01) | EACH | 52 | $30.00 | $30.00 | $25.00 | $28.00 | $33.70 |
| 61 | Barrier rail delineator (712-04.50) | EACH | 10 | $35.00 | $16.00 | $8.00 | $9.00 | $10.78 |
| 62 | Signs (construction) (712-06) | SF | 761 | $15.00 | $8.00 | $7.90 | $9.00 | $10.65 |
| 63 | Temporary barricades (type III) (712-07.03) | LF | 24 | $18.00 | $30.00 | $15.00 | $17.00 | $20.22 |
| 64 | Removable pavement marking (stop line) (712-09.04) | LF | 24 | $15.00 | $30.00 | $25.00 | $28.00 | $29.66 |
| 65 | Removable pavement marking (6" line) (712-09.08) | LF | 1,036 | $3.50 | $3.50 | $3.00 | $4.00 | $4.92 |
| 66 | Removable black-out tape (8IN) (712-09.31) | LF | 1,036 | $3.50 | $4.00 | $3.50 | $4.00 | $5.39 |
| 67 | Perforated/knockout square tube post (713-11.02) | LB | 99 | $5.00 | $5.00 | $4.50 | $5.00 | $6.07 |
| 68 | P post slip base (713-11.21) | EACH | 2 | $570.00 | $400.00 | $515.00 | $567.00 | $694.24 |
| 69 | Flat sheet aluminum signs (0.080" thick) (713-13.02) | SF | 3 | $15.00 | $14.00 | $13.75 | $16.00 | $18.54 |
| 70 | Flat sheet aluminum signs (0.100" thick) (713-13.03) | SF | 18 | $16.00 | $17.00 | $14.65 | $17.00 | $19.75 |
| 71 | Removal of signs, posts and footings (713-15) | LS | 1 | $400.00 | $250.00 | $300.00 | $330.00 | $404.41 |
| 72 | Changeable message sign unit (713-16.01) | EACH | 4 | $8,000.00 | $5,750.00 | $7,000.00 | $7,700.00 | $9,436.22 |
| 73 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 6 | $115.00 | $105.00 | $100.00 | $110.00 | $134.80 |
| 74 | Removal of snowplowable reflective marker (716-01.30) | EACH | 6 | $30.00 | $30.00 | $25.00 | $28.00 | $67.40 |
| 75 | Plastic pavement marking (stop line) (716-02.05) | LF | 15 | $17.00 | $16.00 | $15.00 | $17.00 | $26.96 |
| 76 | Painted pavement marking (4" line) (716-05.01) | LM | 0.56 | $2,200.00 | $2,100.00 | $2,000.00 | $2,200.00 | $4,718.11 |
| 77 | Painted pavement marking (8" barrier line) (716-05.02) | LF | 1,250 | $1.20 | $1.10 | $1.00 | $2.00 | $1.35 |
| 78 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 0.56 | $13,000 | $12,600 | $12,000 | $13,200 | $13,480 |
| 79 | Mobilization (717-01) | LS | 1 | $200,000 | $265,000 | $330,000 | $375,110 | $326,224 |
| 80 | Temporary traffic signal system (730-40.02) | LS | 1 | $95,000 | $94,376 | $155,000 | $94,710 | $137,836 |
| 81 | Geogrid reinforcement type 2 (740-07.04) | SY | 436 | $13.00 | $20.00 | $10.00 | $23.00 | $8.63 |
| 82 | Geotextile (type III)(erosion control) (740-10.03) | SY | 1,339 | $12.00 | $3.00 | $5.00 | $23.00 | $7.41 |
| 83 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 218 | $13.00 | $10.00 | $5.00 | $23.00 | $8.09 |
| 84 | Seeding (with mulch) (801-01) | UNIT | 1 | $560.00 | $105.00 | $500.00 | $220.00 | $674.02 |
| 85 | Temporary seeding (with mulch) (801-01.07) | UNIT | 31 | $60.00 | $42.00 | $55.00 | $99.00 | $74.14 |
| 86 | Seeding (special mixture) with mulch (801-01.08) | UNIT | 21 | $110.00 | $157.50 | $100.00 | $242.00 | $134.80 |
| 87 | Grass seed mix (ripzn/FLPL) W/mulch (801-01.35) | UNIT | 21 | $150.00 | $157.50 | $135.00 | $242.00 | $181.98 |
| 88 | Seeding (without mulch) (801-02) | UNIT | 31 | $45.00 | $31.50 | $40.00 | $66.00 | $53.92 |
| 89 | Water (seeding & sodding) (801-03) | MG | 3 | $130.00 | $262.50 | $120.00 | $110.00 | $161.76 |
| 90 | Cuttings: salix nigra (18IN-24IN length) (802-02.30) | EACH | 45 | $11.00 | $8.40 | $10.00 | $6.00 | $13.48 |
| 91 | Cuttings: salix sericea (18IN-24IN) (802-02.31) | EACH | 45 | $11.00 | $8.40 | $10.00 | $17.00 | $13.48 |
| 92 | Cuttings: cornus amomum (18IN-24IN) (802-02.32) | EACH | 45 | $22.00 | $8.40 | $20.00 | $6.00 | $26.96 |
| 93 | Cuttings: sambucus canadensis (18IN-24IN) (802-02.33) | EACH | 45 | $11.00 | $8.40 | $10.00 | $6.00 | $13.48 |
| 94 | Betula nigra (river birch seedlng B.R.) (802-12.07) | EACH | 22 | $11.00 | $8.40 | $10.00 | $28.00 | $13.48 |
| 95 | Cornus florida (flowering dogwood seedlng B.R.) (802-12.12) | EACH | 14 | $40.00 | $8.40 | $35.00 | $28.00 | $47.18 |
| 96 | Platanus occidentalis (sycamore seedlng B.R.) (802-12.26) | EACH | 22 | $11.00 | $8.40 | $10.00 | $28.00 | $13.48 |
| 97 | Quercus nigra (water oak seedlng B.R.) (802-12.35) | EACH | 22 | $11.00 | $8.40 | $10.00 | $28.00 | $13.48 |
| 98 | Quercus palustris (pin oak seedlng B.R.) (802-12.37) | EACH | 14 | $11.00 | $8.40 | $10.00 | $28.00 | $13.48 |
| 99 | Carya laciniosa (shellbark hickory seedling B.R.) (802-12.55) | EACH | 22 | $11.00 | $8.40 | $10.00 | $28.00 | $13.48 |
| 100 | Physocarpus opulifolius (ninebark) 2-5FT C.G. (802-13.15) | EACH | 46 | $11.00 | $15.75 | $10.00 | $88.00 | $13.48 |
| 101 | Ilex opaca (american holly SDLNG bare root) (802-13.57) | EACH | 22 | $11.00 | $8.40 | $10.00 | $28.00 | $13.48 |
| 102 | Lindera benzoin (spicebush SDLNG bare root) (802-13.59) | EACH | 46 | $11.00 | $8.40 | $10.00 | $28.00 | $13.48 |
| 103 | Ilex verticillata (CMMN winterberry SDLNG B.R.) (802-13.62) | EACH | 46 | $11.00 | $8.40 | $10.00 | $28.00 | $13.48 |
| 104 | Erosion control blanket (type III) (805-12.03) | SY | 1,696 | $2.75 | $1.31 | $2.50 | $3.00 | $3.37 |
| 105 | 700 gram coir fiber erosion blanket (805-12.08) | SY | 335 | $10.00 | $5.25 | $8.75 | $10.00 | $11.80 |
| 106 | Removal of structures (exist. bridge no. 13SR0330009) (202-04.01) | LS | 1 | $70,000 | $50,000 | $200,000 | $165,955 | $182,793 |
| 107 | Core drilling for piles(rock) (204-14) | LF | 130 | $680.00 | $310.00 | $600.00 | $357.00 | $563.48 |
| 108 | Core drilling for piles(soil) (204-15) | LF | 146 | $370.00 | $70.00 | $200.00 | $97.00 | $368.01 |
| 109 | Granular backfill (bridges) (303-01.02) | TON | 82 | $75.00 | $75.00 | $80.00 | $58.00 | $144.24 |
| 110 | Epoxy coated reinforcing steel (604-02.03) | LB | 19,249 | $2.50 | $2.30 | $2.25 | $3.08 | $2.90 |
| 111 | Class A concrete (bridges) (604-03.01) | CY | 69 | $1,050.00 | $3,500.00 | $2,500.00 | $2,346.00 | $1,523.28 |
| 112 | Steel bar reinforcement (bridges) (604-03.02) | LB | 8,858 | $2.40 | $1.60 | $2.00 | $2.92 | $2.56 |
| 113 | Pavement @ bridge ends (604-03.04) | SY | 260 | $420.00 | $450.00 | $550.00 | $657.00 | $450.24 |
| 114 | Class D concrete (bridge deck) (604-03.09) | CY | 110 | $1,800.00 | $1,975.00 | $1,750.00 | $1,927.00 | $1,610.90 |
| 115 | Applied texture finish (new structures) (604-04.01) | SY | 337 | $20.00 | $20.00 | $18.00 | $20.00 | $19.95 |
| 116 | Three star state emblem (604-04.41) | EACH | 1 | $1,500.00 | $2,000.00 | $700.00 | $1,070.00 | $2,696.06 |
| 117 | Steel piles (10 inch) (606-02.03) | LF | 276 | $155.00 | $240.00 | $75.00 | $219.00 | $276.35 |
| 118 | Prestressed concrete box beam (27" X 36") (615-02.04) | LF | 469 | $550.00 | $540.00 | $500.00 | $529.00 | $799.38 |
| 119 | Concrete railing (620-06) | LF | 199 | $260.00 | $500.00 | $250.00 | $357.00 | $262.87 |
| 120 | Temporary shoring (621-05.02) | LS | 1 | $60,000 | $5,000.00 | $50,000 | $72,880 | $142,891 |
| 121 | 6" perforated pipe with vertical drain system (710-09.01) | LF | 131 | $45.00 | $100.00 | $60.00 | $45.00 | $29.66 |
| 122 | 6" pipe underdrain (710-09.02) | LF | 50 | $45.00 | $150.00 | $10.00 | $50.00 | $21.57 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of October 2, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.