TDOT contract CN261074 bid tabulation

The construction of a concrete box beam bridge on s.r. 33 over south fork sycamore creek (l.m. 20.56), including grading, drainage, and paving. Let by Tennessee DOT on October 2, 2026, Claiborne County. 5 bids received; low bid $2,643,606 by Southern Constructors, Inc..

Owner
Tennessee DOT
Letting
02 OCT 2026
Pay items
122
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Southern Constructors, Inc.$2,643,606Low
2Charles Blalock & Sons, Inc.$2,993,828+13%
3Jones Bros. Contractors, LLC$3,329,043+26%
4Whaley Construction, LLC$3,498,103+32%
5King General Contractors, Inc.$3,682,691+39%
TDOT contract CN261074: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Southern Constructors, Inc.2. Charles Blalock & Sons, Inc.3. Jones Bros. Contractors, LLC4. Whaley Construction, LLC5. King General Contractors, Inc.
1Construction stakes, lines and grades (105-01)LS1$40,000$27,171$30,000$28,466$42,463
2Clearing and grubbing (201-01)LS1$28,000$155,500$162,000$200,000$71,446
3Removal of pipe (EX. 18" CMP, sta. 98+93.54 to 101+20.00) (202-01.13)LF54$38.00$55.49$50.00$50.00$45.83
4Removal of pipe (EX. 24" CMP, sta. 20+21.05) (202-01.14)LF20$68.00$149.82$50.00$60.00$45.83
5Removal of structures (CB1, sta. 100+19) (202-04.01)LS1$600.00$599.25$1,500.00$2,050.00$3,370.08
6Removal of buildings tract no.4 (202-06.01)LS1$3,000.00$4,874.82$100.00$4,110.00$7,414.18
7Removal of buildings (tract no. 6, 6A) (202-06.02)LS1$9,000.00$4,874.82$100.00$15,300$9,436.22
8Removal of buildings (tract no. 8, 9) (202-06.03)LS1$4,000.00$4,874.82$100.00$6,720.00$8,088.19
9RD & DRNG excv (acid producing- off site disposal) (203-01.07)CY2,602$100.00$110.00$150.00$167.00$218.65
10Borrow excavation (offsite soil) (203-02.05)CY182$90.00$48.00$85.00$60.00$55.27
11Borrow excavation (unclassified) (203-03)CY678$75.00$48.00$85.00$45.00$53.79
12Water (203-06)MG2$350.00$200.00$1.00$100.00$1,213.23
13Furnishing & spreading topsoil (203-07)CY282.70$115.00$50.00$65.00$67.00$61.07
14Compacted clay (203-15.03)CY13$270.00$500.00$120.00$165.00$229.17
15Channel substrate (203-20.01)CY25$600.00$200.00$500.00$178.00$152.33
16Backfill material (flowable fill) (204-08.01)CY47$500.00$5.00$400.00$682.00$407.11
17Brooming & degrassing shoulders (208-01.05)LM0.21$2,000.00$3,528.00$40,000$5,000.00$9,166.62
18Ditch (riprap, sand & plastic sheeting) (208-02.01)LF62$13.00$170.00$65.00$133.00$114.58
19Stream mitigation - live brush layering (209-03.42)LF56$270.00$270.00$150.00$353.00$80.88
20Stream mitigation – wood toe W/reinforced earth (209-03.67)LF56$255.00$270.00$250.00$902.00$337.01
21Protected area marker (white with decal) (209-03.99)EACH18$140.00$270.00$275.00$350.00$289.83
22Sediment removal (209-05)CY54$50.00$5.00$45.00$41.00$32.35
23Temporary silt fence (with backing) (209-08.02)LF592$6.00$5.00$5.25$6.00$7.08
24Enhanced rock check dam (209-08.08)EACH4$1,150.00$1,260.00$1,000.00$2,500.00$1,348.03
25Sediment filter bag (15' X 15') (209-09.03)EACH2$800.00$1,400.00$700.00$2,500.00$943.62
26Temporary in stream diversion (209-65.04)LF118$225.00$250.00$500.00$160.00$283.09
27Mineral aggregate, type A base, grading D (303-01)TON1,067$55.00$80.00$88.00$56.00$78.19
28Mineral aggregate (size 57) (303-10.01)TON81$70.00$80.00$85.00$57.00$84.93
29Mineral aggregate (size 57) (303-10.04)TON329$60.00$80.00$100.00$57.00$84.93
30Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01)TON36$400.00$375.90$358.00$394.00$350.49
31Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON48$398.00$371.70$354.00$389.00$350.49
32Bituminous material for tack coat (TC) (403-01)TON1$1,250.00$1,155.00$1,100.00$1,210.00$1,314.33
33Acs mix (PG64-22) grading E shoulder (411-01.07)TON18$950.00$882.00$840.00$924.00$370.71
34Acs mix(PG64-22) grading D (411-01.10)TON120$300.00$273.00$260.00$286.00$370.71
35Scoring for rumble stripe (non-continuous) (8IN width) (411-12.03)LM0.20$2,200.00$2,100.00$45,350$2,200.00$8,088.19
36Cold planing bituminous pavement (415-01.01)TON102$160.00$147.00$140.00$154.00$51.23
3748" concrete pipe culvert (class III) (607-09.02)LF90$640.00$400.00$330.00$360.00$500.12
3818" pipe culvert (side drain) (607-39.02)LF163$140.00$165.00$85.00$87.00$175.24
3918IN endwall (cross drain) 3:1 (611-07.54)EACH8$2,300.00$4,500.00$2,500.00$1,572.00$3,747.53
4048IN endwall (cross drain) 3:1 (611-07.69)EACH4$8,800.00$12,000$8,000.00$3,530.00$8,088.19
41Metal beam guard fence (705-01.04)LF70$80.00$80.00$72.50$88.00$121.32
42W beam GR (type 2) MASH TL-3 (705-06.01)LF244$31.00$30.00$28.00$32.00$38.08
43GR terminal (in-inline) MASH TL-3 (705-06.11)EACH1$1,200.00$1,150.00$1,080.00$1,546.00$1,597.42
44Tangent energy absorbing term MASH TL-3 (705-06.20)EACH2$3,800.00$3,600.00$3,380.00$3,520.00$4,448.51
45Thrie beam bridge transition MASH TL-3 (705-06.25)EACH1$3,350.00$3,200.00$2,975.00$3,685.00$3,774.49
46Thrie beam bridge transition MASH TL-2 (705-06.26)EACH1$2,800.00$2,600.00$2,425.00$2,200.00$2,224.25
47GR terminal (energy absorbing) MASH TL-2 (705-06.30)EACH1$3,200.00$3,100.00$2,880.00$2,970.00$4,044.10
48Guardrail removed (706-01)LF401$4.00$3.25$3.00$3.00$2.02
49Radius rail (706-06.03)LF32$42.00$40.00$38.00$41.00$52.57
50Rounded end element (706-10.26)EACH25$142.00$140.00$127.00$200.00$148.28
51High-visibility construction fence (707-08.11)LF660$4.00$2.50$3.00$5.00$4.04
52Machined rip-rap (class A-3) (709-05.05)TON100$95.00$80.00$90.00$62.00$87.62
53Machined rip-rap (class A-1) (709-05.06)TON808$78.00$80.00$90.00$61.00$87.62
54Machined rip-rap (class B) (709-05.08)TON443$61.00$80.00$90.00$60.00$98.41
55Rock riffles (709-05.81)LS1$4,400.00$70,000$15,000$100,000$32,892
56Traffic control (712-01)LS1$22,000$45,000$100,000$50,450$88,296
57Portable barrier rail (MASH TL-3) (712-02.10)LF330$81.00$100.00$70.00$125.00$113.23
58Portable barrier rail, reduced deflection (MASH TL-3) (712-02.12)LF120$142.00$175.00$150.00$125.00$149.63
59Temporary work zone crash cushion (MASH TL-3) (712-02.60)EACH6$6,900.00$5,600.00$6,250.00$7,480.00$9,611.47
60Flexible drums (channelizing) (712-04.01)EACH52$30.00$30.00$25.00$28.00$33.70
61Barrier rail delineator (712-04.50)EACH10$35.00$16.00$8.00$9.00$10.78
62Signs (construction) (712-06)SF761$15.00$8.00$7.90$9.00$10.65
63Temporary barricades (type III) (712-07.03)LF24$18.00$30.00$15.00$17.00$20.22
64Removable pavement marking (stop line) (712-09.04)LF24$15.00$30.00$25.00$28.00$29.66
65Removable pavement marking (6" line) (712-09.08)LF1,036$3.50$3.50$3.00$4.00$4.92
66Removable black-out tape (8IN) (712-09.31)LF1,036$3.50$4.00$3.50$4.00$5.39
67Perforated/knockout square tube post (713-11.02)LB99$5.00$5.00$4.50$5.00$6.07
68P post slip base (713-11.21)EACH2$570.00$400.00$515.00$567.00$694.24
69Flat sheet aluminum signs (0.080" thick) (713-13.02)SF3$15.00$14.00$13.75$16.00$18.54
70Flat sheet aluminum signs (0.100" thick) (713-13.03)SF18$16.00$17.00$14.65$17.00$19.75
71Removal of signs, posts and footings (713-15)LS1$400.00$250.00$300.00$330.00$404.41
72Changeable message sign unit (713-16.01)EACH4$8,000.00$5,750.00$7,000.00$7,700.00$9,436.22
73Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21)EACH6$115.00$105.00$100.00$110.00$134.80
74Removal of snowplowable reflective marker (716-01.30)EACH6$30.00$30.00$25.00$28.00$67.40
75Plastic pavement marking (stop line) (716-02.05)LF15$17.00$16.00$15.00$17.00$26.96
76Painted pavement marking (4" line) (716-05.01)LM0.56$2,200.00$2,100.00$2,000.00$2,200.00$4,718.11
77Painted pavement marking (8" barrier line) (716-05.02)LF1,250$1.20$1.10$1.00$2.00$1.35
78Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM0.56$13,000$12,600$12,000$13,200$13,480
79Mobilization (717-01)LS1$200,000$265,000$330,000$375,110$326,224
80Temporary traffic signal system (730-40.02)LS1$95,000$94,376$155,000$94,710$137,836
81Geogrid reinforcement type 2 (740-07.04)SY436$13.00$20.00$10.00$23.00$8.63
82Geotextile (type III)(erosion control) (740-10.03)SY1,339$12.00$3.00$5.00$23.00$7.41
83Geotextile (type IV)(stabilization) (740-10.04)SY218$13.00$10.00$5.00$23.00$8.09
84Seeding (with mulch) (801-01)UNIT1$560.00$105.00$500.00$220.00$674.02
85Temporary seeding (with mulch) (801-01.07)UNIT31$60.00$42.00$55.00$99.00$74.14
86Seeding (special mixture) with mulch (801-01.08)UNIT21$110.00$157.50$100.00$242.00$134.80
87Grass seed mix (ripzn/FLPL) W/mulch (801-01.35)UNIT21$150.00$157.50$135.00$242.00$181.98
88Seeding (without mulch) (801-02)UNIT31$45.00$31.50$40.00$66.00$53.92
89Water (seeding & sodding) (801-03)MG3$130.00$262.50$120.00$110.00$161.76
90Cuttings: salix nigra (18IN-24IN length) (802-02.30)EACH45$11.00$8.40$10.00$6.00$13.48
91Cuttings: salix sericea (18IN-24IN) (802-02.31)EACH45$11.00$8.40$10.00$17.00$13.48
92Cuttings: cornus amomum (18IN-24IN) (802-02.32)EACH45$22.00$8.40$20.00$6.00$26.96
93Cuttings: sambucus canadensis (18IN-24IN) (802-02.33)EACH45$11.00$8.40$10.00$6.00$13.48
94Betula nigra (river birch seedlng B.R.) (802-12.07)EACH22$11.00$8.40$10.00$28.00$13.48
95Cornus florida (flowering dogwood seedlng B.R.) (802-12.12)EACH14$40.00$8.40$35.00$28.00$47.18
96Platanus occidentalis (sycamore seedlng B.R.) (802-12.26)EACH22$11.00$8.40$10.00$28.00$13.48
97Quercus nigra (water oak seedlng B.R.) (802-12.35)EACH22$11.00$8.40$10.00$28.00$13.48
98Quercus palustris (pin oak seedlng B.R.) (802-12.37)EACH14$11.00$8.40$10.00$28.00$13.48
99Carya laciniosa (shellbark hickory seedling B.R.) (802-12.55)EACH22$11.00$8.40$10.00$28.00$13.48
100Physocarpus opulifolius (ninebark) 2-5FT C.G. (802-13.15)EACH46$11.00$15.75$10.00$88.00$13.48
101Ilex opaca (american holly SDLNG bare root) (802-13.57)EACH22$11.00$8.40$10.00$28.00$13.48
102Lindera benzoin (spicebush SDLNG bare root) (802-13.59)EACH46$11.00$8.40$10.00$28.00$13.48
103Ilex verticillata (CMMN winterberry SDLNG B.R.) (802-13.62)EACH46$11.00$8.40$10.00$28.00$13.48
104Erosion control blanket (type III) (805-12.03)SY1,696$2.75$1.31$2.50$3.00$3.37
105700 gram coir fiber erosion blanket (805-12.08)SY335$10.00$5.25$8.75$10.00$11.80
106Removal of structures (exist. bridge no. 13SR0330009) (202-04.01)LS1$70,000$50,000$200,000$165,955$182,793
107Core drilling for piles(rock) (204-14)LF130$680.00$310.00$600.00$357.00$563.48
108Core drilling for piles(soil) (204-15)LF146$370.00$70.00$200.00$97.00$368.01
109Granular backfill (bridges) (303-01.02)TON82$75.00$75.00$80.00$58.00$144.24
110Epoxy coated reinforcing steel (604-02.03)LB19,249$2.50$2.30$2.25$3.08$2.90
111Class A concrete (bridges) (604-03.01)CY69$1,050.00$3,500.00$2,500.00$2,346.00$1,523.28
112Steel bar reinforcement (bridges) (604-03.02)LB8,858$2.40$1.60$2.00$2.92$2.56
113Pavement @ bridge ends (604-03.04)SY260$420.00$450.00$550.00$657.00$450.24
114Class D concrete (bridge deck) (604-03.09)CY110$1,800.00$1,975.00$1,750.00$1,927.00$1,610.90
115Applied texture finish (new structures) (604-04.01)SY337$20.00$20.00$18.00$20.00$19.95
116Three star state emblem (604-04.41)EACH1$1,500.00$2,000.00$700.00$1,070.00$2,696.06
117Steel piles (10 inch) (606-02.03)LF276$155.00$240.00$75.00$219.00$276.35
118Prestressed concrete box beam (27" X 36") (615-02.04)LF469$550.00$540.00$500.00$529.00$799.38
119Concrete railing (620-06)LF199$260.00$500.00$250.00$357.00$262.87
120Temporary shoring (621-05.02)LS1$60,000$5,000.00$50,000$72,880$142,891
1216" perforated pipe with vertical drain system (710-09.01)LF131$45.00$100.00$60.00$45.00$29.66
1226" pipe underdrain (710-09.02)LF50$45.00$150.00$10.00$50.00$21.57
TDOT contract CN261074: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of October 2, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way