TDOT contract CNZ101 bid tabulation
The grading, drainage, signals, and paving on u.s. 41 (s.r. 1) from near jefferson pike (l.m. 3.38) to near s.r. 266 (sam ridley parkway) (l.m. 4.10) in smyrna. Let by Tennessee DOT on March 21, 2025, Rutherford County. 5 bids received; low bid $6,095,040 by Capital City Construction Services, LLC.
- Owner
- Tennessee DOT
- Letting
- 21 MAR 2025
- Pay items
- 136
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Capital City Construction Services, LLC | $6,095,040 | Low |
| 2 | Cleary Construction, Inc. | $6,325,075 | +4.0% |
| 3 | Civil Constructors, LLC | $6,509,521 | +7.0% |
| 4 | Vulcan Construction Materials, LLC | $6,747,921 | +11% |
| 5 | Wiregrass Construction Company, Inc | $6,775,300 | +11% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Capital City Construction Services, LLC | 2. Cleary Construction, Inc. | 3. Civil Constructors, LLC | 4. Vulcan Construction Materials, LLC | 5. Wiregrass Construction Company, Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $50,000 | $125,000 | $35,330 | $135,000 | $35,047 |
| 2 | Trainee (109-10.01) | HR | 1,180 | $0.80 | $0.80 | $0.80 | $0.80 | $0.80 |
| 3 | Clearing and grubbing (201-01) | LS | 1 | $8,148.57 | $108,000 | $8,880.00 | $48,200 | $7,510.14 |
| 4 | Removal of structures and obstructions (202-01.50) | EACH | 2 | $16,297 | $11,250 | $5,010.00 | $4,300.00 | $10,014 |
| 5 | Removal of asphalt pavement (202-03.01) | SY | 5,862 | $13.42 | $17.15 | $8.70 | $18.90 | $4.53 |
| 6 | Road & drainage excavation (unclassified) (203-01) | CY | 15,761 | $43.66 | $24.65 | $42.00 | $54.10 | $38.81 |
| 7 | Placing and spreading topsoil (203-04) | CY | 2,063 | $38.12 | $27.00 | $25.20 | $22.80 | $30.29 |
| 8 | Water (203-06) | MG | 153 | $28.57 | $50.00 | $23.90 | $5.00 | $19.06 |
| 9 | Sediment removal (209-05) | CY | 1,430 | $23.91 | $32.00 | $27.90 | $5.00 | $20.78 |
| 10 | Temporary silt fence (with backing) (209-08.02) | LF | 752 | $6.21 | $6.60 | $6.90 | $6.05 | $3.05 |
| 11 | Temporary silt fence (without backing) (209-08.03) | LF | 14,600 | $2.63 | $2.80 | $2.90 | $2.55 | $1.22 |
| 12 | Rock check dam (209-08.07) | EACH | 7 | $926.32 | $1,000.00 | $1,030.00 | $900.00 | $265.36 |
| 13 | Enhanced rock check dam (209-08.08) | EACH | 11 | $926.32 | $1,000.00 | $1,030.00 | $900.00 | $315.43 |
| 14 | Sandbags (209-09.01) | BAG | 500 | $7.14 | $5.60 | $11.40 | $7.15 | $3.15 |
| 15 | Catch basin filter assembly(type 1) (209-40.41) | EACH | 2 | $768.42 | $820.00 | $851.00 | $747.00 | $225.81 |
| 16 | Catch basin filter assembly(type 4) (209-40.44) | EACH | 2 | $1,031.58 | $1,100.00 | $1,140.00 | $1,000.00 | $285.39 |
| 17 | Temporary diversion channel (209-65.03) | LF | 450 | $24.97 | $21.00 | $8.90 | $19.70 | $50.07 |
| 18 | Mineral aggregate, type A base, grading D (303-01) | TON | 10,350 | $42.59 | $31.00 | $40.00 | $33.70 | $49.92 |
| 19 | Mineral aggregate (size 57) (303-10.01) | TON | 30 | $47.82 | $50.00 | $90.50 | $57.60 | $660.23 |
| 20 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 220 | $266.32 | $287.00 | $204.00 | $175.00 | $200.00 |
| 21 | Asp. conc. mix(PG70-22) (BPMB-HM) GR. A-S (307-01.21) | TON | 212 | $313.68 | $338.00 | $204.00 | $175.00 | $205.00 |
| 22 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01) | TON | 360 | $252.63 | $270.00 | $204.00 | $175.00 | $162.00 |
| 23 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08) | TON | 652 | $205.26 | $221.00 | $204.00 | $175.00 | $168.00 |
| 24 | Asphalt concrete mix (PG82-22) (BPMB-HM) grading A (307-04.01) | TON | 401 | $273.68 | $295.00 | $204.00 | $175.00 | $215.00 |
| 25 | Treated permeable base (313-03) | SY | 5,047 | $40.16 | $43.00 | $35.00 | $30.00 | $34.00 |
| 26 | Bituminous material for prime coat (PC) (402-01) | TON | 9 | $1,578.95 | $1,700.00 | $1,170.00 | $1,000.00 | $1,000.00 |
| 27 | Aggregate for cover material (PC) (402-02) | TON | 35 | $157.89 | $170.00 | $35.00 | $30.00 | $170.00 |
| 28 | Bituminous material for tack coat (TC) (403-01) | TON | 18 | $1,263.16 | $1,350.00 | $1,170.00 | $1,000.00 | $970.00 |
| 29 | Saw cutting asphalt pavement (407-20.05) | LF | 2,464 | $11.56 | $6.75 | $7.90 | $7.15 | $10.01 |
| 30 | Acs mix (PG64-22) grading E shoulder (411-01.07) | TON | 296 | $200.00 | $215.00 | $204.00 | $175.00 | $260.00 |
| 31 | Acs mix(PG64-22) grading D (411-01.10) | TON | 128 | $331.58 | $357.00 | $204.00 | $175.00 | $290.00 |
| 32 | Acs mix(PG70-22) grading D (411-02.10) | TON | 2,215 | $144.21 | $155.00 | $204.00 | $175.00 | $195.00 |
| 33 | Cold planing bituminous pavement (415-01.01) | TON | 2,109 | $25.79 | $27.80 | $52.50 | $45.00 | $32.00 |
| 34 | Portland cement concrete pavement (plain) 9" (501-01.02) | SY | 4,588 | $142.94 | $145.00 | $170.00 | $173.00 | $197.27 |
| 35 | Class A concrete (island - 6") (604-09.10) | CY | 34 | $964.28 | $795.00 | $699.00 | $614.00 | $600.81 |
| 36 | 18" concrete pipe culvert (class III) (607-03.02) | LF | 139 | $151.72 | $150.00 | $216.00 | $238.00 | $222.22 |
| 37 | 30" concrete pipe culvert (class III) (607-06.02) | LF | 11 | $319.96 | $361.00 | $1,120.00 | $530.00 | $289.62 |
| 38 | Reinforced concrete pipe arch (36" X 23") (607-57.03) | LF | 78 | $258.14 | $361.00 | $228.00 | $300.00 | $194.26 |
| 39 | 18IN endwall (cross drain) 6:1 (611-07.56) | EACH | 3 | $6,040.89 | $4,300.00 | $6,240.00 | $2,300.00 | $7,905.81 |
| 40 | 30IN endwall (cross drain) 6:1 (611-07.62) | EACH | 1 | $11,283 | $8,500.00 | $13,040 | $5,870.00 | $13,009 |
| 41 | 36IN endwall (cross drain) 6:1 (611-07.65) | EACH | 2 | $14,145 | $10,000 | $14,450 | $7,600.00 | $14,354 |
| 42 | Catch basins, type 31, > 4' - 8' depth (611-31.02) | EACH | 2 | $26,110 | $19,900 | $20,130 | $19,400 | $15,452 |
| 43 | Catch basins, type 42, 0' - 4' depth (611-42.01) | EACH | 1 | $26,110 | $6,100.00 | $7,020.00 | $5,730.00 | $5,559.24 |
| 44 | Concrete curb (702-01) | CY | 12 | $866.31 | $1,070.00 | $874.00 | $823.00 | $1,001.35 |
| 45 | Metal beam guard fence (705-01.04) | LF | 40 | $125.34 | $124.00 | $139.00 | $133.00 | $150.20 |
| 46 | Portable barrier rail delineator (705-04.50) | EACH | 257 | $10.53 | $17.00 | $17.50 | $13.20 | $14.52 |
| 47 | GR terminaltrailing end (type 13) MASH TL-3 (705-06.10) | EACH | 1 | $1,827.37 | $2,000.00 | $2,020.00 | $1,840.00 | $1,802.43 |
| 48 | Tangent energy absorbing term MASH TL-3 (705-06.20) | EACH | 1 | $5,110.53 | $4,000.00 | $5,660.00 | $4,090.00 | $3,504.73 |
| 49 | Self restoring crash cushn wide (MASH TL-3) (705-20.72) | EACH | 4 | $47,368 | $58,150 | $52,440 | $46,000 | $51,330 |
| 50 | Machined rip-rap (class A-3) (709-05.05) | TON | 550 | $88.76 | $60.00 | $67.50 | $47.90 | $77.48 |
| 51 | Machined rip-rap (class A-1) (709-05.06) | TON | 191 | $105.38 | $60.00 | $70.50 | $47.90 | $83.03 |
| 52 | Machined rip-rap (class B) (709-05.08) | TON | 7 | $199.47 | $60.00 | $126.00 | $100.00 | $245.76 |
| 53 | Aggregate underdrains (with pipe) (710-02) | LF | 3,665 | $11.68 | $12.60 | $12.90 | $11.40 | $60.31 |
| 54 | Lateral underdrain (710-05) | LF | 860 | $11.16 | $12.00 | $12.40 | $10.80 | $103.49 |
| 55 | Lateral underdrain endwall (4:1) (710-06.13) | EACH | 4 | $1,052.63 | $1,375.00 | $1,280.00 | $1,240.00 | $2,995.55 |
| 56 | Lateral underdrain endwall (6:1) (710-06.15) | EACH | 22 | $1,052.63 | $1,550.00 | $1,280.00 | $1,400.00 | $851.47 |
| 57 | 51IN single slope concrete barrier wall (711-05.71) | LF | 628 | $251.85 | $230.00 | $251.00 | $232.00 | $205.28 |
| 58 | Traffic control (712-01) | LS | 1 | $157,737 | $225,000 | $80,580 | $212,000 | $197,567 |
| 59 | Interconnected portable barrier rail (712-02.02) | LF | 5,140 | $51.87 | $52.30 | $96.50 | $110.00 | $38.46 |
| 60 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 13 | $9,165.26 | $17,400 | $8,740.00 | $31,100 | $8,761.82 |
| 61 | Flexible drums (channelizing) (712-04.01) | EACH | 339 | $32.63 | $34.85 | $36.00 | $50.00 | $37.55 |
| 62 | Barrier rail delineator (712-04.50) | EACH | 257 | $10.53 | $11.25 | $11.70 | $15.00 | $14.02 |
| 63 | Signs (construction) (712-06) | SF | 1,142 | $7.89 | $8.50 | $8.70 | $10.50 | $7.66 |
| 64 | Temporary barricades (type III) (712-07.03) | LF | 19 | $31.58 | $34.00 | $35.00 | $25.00 | $21.03 |
| 65 | Arrow board (type C) (712-08.03) | EACH | 2 | $1,157.89 | $1,230.00 | $1,280.00 | $1,250.00 | $2,202.98 |
| 66 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 5,583 | $4.21 | $5.00 | $5.80 | $5.10 | $5.01 |
| 67 | Removable pavement marking (6" line) (712-09.08) | LF | 5,560 | $3.68 | $3.00 | $4.65 | $4.10 | $4.01 |
| 68 | Class A concrete (foundation for sign supports) (713-01.01) | CY | 7 | $593.68 | $340.00 | $787.00 | $675.00 | $300.41 |
| 69 | Steel bar reinforcement(foundation for sign supports) (713-01.02) | LB | 1,320 | $3.88 | $1.15 | $4.10 | $3.50 | $1.00 |
| 70 | Square tube sign support (713-11.05) | LB | 2,590 | $8.23 | $7.40 | $6.40 | $5.50 | $6.51 |
| 71 | P post slip base (713-11.21) | EACH | 53 | $525.26 | $400.00 | $524.00 | $450.00 | $350.47 |
| 72 | Flat sheet aluminum signs (0.100" thick) (713-13.03) | SF | 494 | $13.93 | $27.00 | $20.10 | $17.25 | $24.03 |
| 73 | Removal of signs, posts and footings (713-15) | LS | 1 | $2,256.84 | $2,250.00 | $2,040.00 | $1,750.00 | $2,002.70 |
| 74 | Removal & relocation of sign & support (713-15.02) | EACH | 1 | $1,870.53 | $900.00 | $1,280.00 | $1,100.00 | $801.08 |
| 75 | Suspended flat sheet aluminum sign (0.080" thick) (713-15.07) | EACH | 9 | $631.58 | $675.00 | $1,110.00 | $575.00 | $120.16 |
| 76 | Changeable message sign unit (713-16.01) | EACH | 2 | $6,263.16 | $6,700.00 | $6,930.00 | $6,000.00 | $8,461.42 |
| 77 | Pull boxes (type C) (714-05.04) | EACH | 9 | $1,157.89 | $1,260.00 | $1,340.00 | $1,180.00 | $1,151.55 |
| 78 | Cable (2/C #6 AWG) (714-06.08) | LF | 1,200 | $3.68 | $4.00 | $5.00 | $4.40 | $4.31 |
| 79 | Luminaires (250 watt) (714-09.03) | EACH | 5 | $1,768.42 | $1,925.00 | $1,950.00 | $1,710.00 | $1,677.26 |
| 80 | Raised PVMT markers (BI-directional) (2 color lens) (716-01.13) | EACH | 75 | $42.11 | $5.90 | $23.30 | $20.50 | $20.03 |
| 81 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 4 | $52.63 | $41.00 | $58.50 | $51.10 | $50.07 |
| 82 | Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22) | EACH | 150 | $52.63 | $40.00 | $58.50 | $51.10 | $50.07 |
| 83 | Removal of snowplowable reflective marker (716-01.30) | EACH | 150 | $10.53 | $21.00 | $17.50 | $15.30 | $15.02 |
| 84 | Plastic pavement marking(channelization striping) (716-02.04) | SY | 425 | $36.84 | $41.00 | $41.00 | $35.80 | $35.05 |
| 85 | Plastic pavement marking (stop line) (716-02.05) | LF | 290 | $21.05 | $23.50 | $23.30 | $20.50 | $20.03 |
| 86 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 13 | $236.84 | $235.00 | $233.00 | $205.00 | $200.27 |
| 87 | Plastic pavement marking (24" barrier line) (716-02.07) | LF | 79 | $21.05 | $21.00 | $16.30 | $14.30 | $14.02 |
| 88 | Plastic pavement marking (8" dotted line) (716-02.08) | LF | 510 | $3.16 | $3.00 | $4.65 | $4.10 | $4.01 |
| 89 | Plastic pavement marking (6" dotted line) (716-02.11) | LF | 465 | $3.16 | $1.75 | $3.50 | $3.05 | $3.00 |
| 90 | Plastic pavement marking (8IN line) (716-02.12) | LM | 1 | $10,526 | $9,400.00 | $17,480 | $15,300 | $15,020 |
| 91 | Plastic word pavement marking (only) (716-03.01) | EACH | 4 | $394.74 | $470.00 | $524.00 | $460.00 | $450.61 |
| 92 | Plastic pavement marking (wrong way arrow) (716-04.06) | EACH | 2 | $315.79 | $120.00 | $466.00 | $409.00 | $400.54 |
| 93 | Plastic pavement marking (exit only arrow) (716-04.07) | EACH | 1 | $473.68 | $410.00 | $466.00 | $409.00 | $400.54 |
| 94 | Plastic pavement marking (yield line) (716-04.12) | SF | 45 | $31.58 | $53.00 | $41.00 | $35.80 | $35.05 |
| 95 | Plastic pavement marking (lane reduction arrow) (716-04.14) | EACH | 2 | $578.95 | $705.00 | $757.00 | $665.00 | $650.88 |
| 96 | Painted pavement markings(8" line) (716-05.50) | LF | 160 | $0.79 | $4.50 | $2.35 | $2.05 | $2.00 |
| 97 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 4 | $10,526 | $8,800.00 | $9,320.00 | $8,180.00 | $8,010.81 |
| 98 | Mobilization (717-01) | LS | 1 | $149,530 | $315,000 | $258,610 | $175,000 | $650,000 |
| 99 | Signal head assembly (130 A3 with backplate) (730-02.03) | EACH | 4 | $1,326.32 | $1,445.00 | $1,700.00 | $1,490.00 | $1,461.97 |
| 100 | Signal head assembly (130 with backplate) (730-02.09) | EACH | 13 | $1,326.32 | $1,445.00 | $1,640.00 | $1,440.00 | $1,411.91 |
| 101 | Signal head assembly (130 A2 with backplate) (730-02.11) | EACH | 3 | $1,326.32 | $1,445.00 | $1,700.00 | $1,490.00 | $1,461.97 |
| 102 | Signal head assembly (150 A2H with backplate) (730-02.17) | EACH | 1 | $2,273.68 | $2,475.00 | $2,630.00 | $2,310.00 | $2,258.05 |
| 103 | Install pull box (type B) (730-03.21) | EACH | 9 | $1,157.89 | $1,260.00 | $1,400.00 | $1,230.00 | $1,206.63 |
| 104 | Install pull box (fiber optic-type B) (730-03.24) | EACH | 3 | $3,010.53 | $3,275.00 | $5,150.00 | $4,520.00 | $4,425.97 |
| 105 | Fiber optic splice fusion (730-03.33) | EACH | 12 | $526.32 | $575.00 | $146.00 | $128.00 | $125.17 |
| 106 | Fiber splice enclosure (N lowery ST (SR 1) (730-03.36) | EACH | 3 | $2,378.95 | $2,590.00 | $1,450.00 | $1,270.00 | $1,241.68 |
| 107 | Network switch (type A) (730-03.40) | EACH | 3 | $10,789 | $11,740 | $11,220 | $9,850.00 | $9,643.01 |
| 108 | Fiber optic drop cable (12F) (730-03.54) | LF | 150 | $2.37 | $2.60 | $3.60 | $3.15 | $3.10 |
| 109 | Fiber optic drop panel (N lowery ST (SR 1) (730-03.57) | EACH | 3 | $1,578.95 | $1,720.00 | $2,180.00 | $1,910.00 | $1,872.53 |
| 110 | Electrical service connection (730-05.01) | EACH | 3 | $9,473.68 | $10,300 | $9,490.00 | $8,330.00 | $8,151.00 |
| 111 | Signal cable - 5 conductor (730-08.02) | LF | 800 | $2.37 | $2.60 | $2.70 | $2.35 | $2.30 |
| 112 | Signal cable - 7 conductor (730-08.03) | LF | 3,400 | $2.63 | $2.85 | $2.80 | $2.45 | $2.40 |
| 113 | Conduit 2" diameter (PVC schedule 40) (730-12.02) | LF | 300 | $29.47 | $32.00 | $46.50 | $40.90 | $40.05 |
| 114 | Conduit 3" diameter (PVC schedule 40) (730-12.03) | LF | 300 | $31.58 | $34.30 | $50.00 | $44.00 | $43.06 |
| 115 | Conduit 2" diameter (directional bore) (730-12.23) | LF | 640 | $86.32 | $94.00 | $99.00 | $86.90 | $85.11 |
| 116 | Conduit 3" diameter (directional bore) (730-12.24) | LF | 640 | $89.47 | $97.00 | $104.00 | $91.00 | $89.12 |
| 117 | Vehicle detector (radar - stopline) (730-13.08) | EACH | 9 | $15,000 | $16,320 | $11,940 | $10,500 | $10,264 |
| 118 | Vehicle detector (radar - advance) (730-13.09) | EACH | 6 | $12,895 | $14,030 | $13,050 | $11,500 | $11,215 |
| 119 | Cabinet (atc) (730-15.07) | EACH | 3 | $7,368.42 | $8,015.00 | $29,020 | $25,500 | $24,934 |
| 120 | Controller (econolite cobalt C) (730-16.14) | EACH | 3 | $25,537 | $27,800 | $6,980.00 | $6,130.00 | $5,998.09 |
| 121 | Cantilever signal support (2 @ 55' & 60') (730-25.09) | EACH | 2 | $54,905 | $59,730 | $64,620 | $56,700 | $55,525 |
| 122 | Cantilever signal support (2 @ 55' & 65') (730-25.10) | EACH | 1 | $62,779 | $68,300 | $72,190 | $63,400 | $62,034 |
| 123 | Cantilever signal support (1 arm @ 65') (730-25.13) | EACH | 1 | $42,779 | $46,540 | $50,980 | $44,700 | $43,809 |
| 124 | Cantilever signal support (1 arm @ 70') (730-25.14) | EACH | 2 | $43,432 | $47,250 | $51,920 | $45,600 | $44,610 |
| 125 | Battery back-UP system (730-35.06) | EACH | 3 | $10,789 | $11,740 | $11,290 | $9,910.00 | $9,698.09 |
| 126 | Geotextile (type III)(erosion control) (740-10.03) | SY | 1,347 | $3.43 | $5.00 | $3.75 | $3.35 | $1.70 |
| 127 | Temporary sediment tube 18IN (740-11.03) | LF | 1,278 | $4.53 | $4.90 | $5.00 | $4.40 | $5.27 |
| 128 | Seeding (with mulch) (801-01) | UNIT | 57 | $64.21 | $56.00 | $71.00 | $51.10 | $69.09 |
| 129 | Crown vetch mixture (with mulch) (801-01.02) | UNIT | 2 | $168.42 | $170.00 | $186.00 | $153.00 | $173.59 |
| 130 | Seeding (without mulch) (801-02) | UNIT | 2 | $126.32 | $113.50 | $140.00 | $102.00 | $35.05 |
| 131 | Water (seeding & sodding) (801-03) | MG | 78 | $168.42 | $57.00 | $186.00 | $51.10 | $98.13 |
| 132 | Sodding (new sod) (803-01) | SY | 6,394 | $6.32 | $6.00 | $7.00 | $5.35 | $5.96 |
| 133 | Turf reinforcement mat (class I) (805-01.01) | SY | 1,416 | $4.79 | $5.15 | $5.30 | $4.60 | $4.66 |
| 134 | 8IN dip slip joint water line (795-01.06) | LF | 57 | $197.09 | $330.00 | $461.00 | $340.00 | $125.00 |
| 135 | Connect to 8IN water line (795-06.05) | EACH | 2 | $5,617.14 | $5,520.00 | $7,300.00 | $3,170.00 | $3,800.00 |
| 136 | DI fittings (795-13.01) | LB | 480 | $23.40 | $14.00 | $8.30 | $28.70 | $15.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of March 21, 2025. Compiled by Mirage Metrics.