TDOT contract CNZ193 bid tabulation

The interchange improvement on i-24 at medical center parkway (l.m. 12.74 - l.m. 13.34), including grading, drainage, paving with portland cement concrete, retaining wall, its, signals, and lighting. Let by Tennessee DOT on June 27, 2025, Rutherford County. 4 bids received; low bid $6,599,647 by Capital City Construction Services, LLC.

Owner
Tennessee DOT
Letting
27 JUN 2025
Pay items
154
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Capital City Construction Services, LLC$6,599,647Low
2Civil Constructors, LLC$6,821,837+3.0%
3Bell & Associates Construction, LLC$7,056,523+7.0%
4MasTec Civil, LLC$7,215,420+9.0%
TDOT contract CNZ193: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Capital City Construction Services, LLC2. Civil Constructors, LLC3. Bell & Associates Construction, LLC4. MasTec Civil, LLC
1Construction stakes, lines and grades (105-01)LS1$110,000$62,730$42,895$160,000
2Trainee (109-10.01)HR1,180$0.80$0.80$0.80$0.80
3Clearing and grubbing (201-01)LS1$87,588$66,110$98,257$260,000
4Removal of structures and obstructions (202-01)LS1$32,594$48,710$91,828$350,000
5Removal of pipe (24" at sta. 321+08) (202-01.13)LF19$214.44$115.00$156.09$90.00
6Removal of rigid pavement, sidewalk, etc. (202-03)SY647$45.77$35.00$60.13$20.00
7Road & drainage excavation (unclassified) (203-01)CY3,055$36.77$72.00$56.91$17.00
8Borrow excavation (unclassified) (203-03)CY6,571$79.07$27.00$49.68$30.00
9Furnishing & spreading topsoil (203-07)CY767$45.00$77.00$67.62$43.00
10Sediment removal (209-05)CY35$88.40$25.00$50.85$22.00
11Curb inlet protection (type 4) (209-09.43)EACH14$140.00$155.00$303.79$312.00
12Catch basin protection (type D) (209-40.33)EACH8$165.00$756.00$320.36$315.00
13Catch basin filter assembly(type 6) (209-40.46)EACH4$980.00$687.00$762.23$780.00
14Mineral aggregate, type A base, grading D (303-01)TON2,667$47.72$52.00$52.45$49.00
15Mineral aggregate (size 57) (303-10.01)TON22$44.68$55.00$74.85$87.00
16Treated permeable base (313-03)SY5,651$36.12$44.00$37.28$39.00
17Bituminous material for tack coat (TC) (403-01)TON2.60$1,925.00$1,510.00$1,325.62$1,300.00
18Acs mix(PG70-22) grading D (411-02.10)TON321$256.00$221.00$193.32$200.00
19Cold planing bituminous pavement (415-01.02)SY6,175$4.05$5.00$4.42$4.00
20Portland cement concrete pavement (plain) 10" (501-01.03)SY5,111$149.89$202.00$170.64$170.00
21Sawing concrete pavement (full depth) (502-04.01)LF2,689$6.00$25.20$3.31$4.50
22Load transfer dowels (502-04.02)EACH2,172$10.00$4.55$3.98$4.00
23Transverse tie-bars (502-04.03)EACH517$10.00$45.50$39.77$39.00
24Grinding concrete pavement (503-01)SY350$25.00$78.00$22.09$59.00
25Class A concrete (roadway) (604-01.01)CY15$750.00$1,760.00$1,596.17$512.00
26Applied texture finish (new structures) (604-04.01)SY776$14.00$7.90$24.86$12.50
27Retaining wall (no. 1) (604-07.01)SF9,541$137.50$147.00$216.82$155.00
2818" concrete pipe culvert (class III) (607-03.02)LF10$265.06$925.00$372.32$320.00
2942" concrete pipe culvert (class III) (607-08.02)LF38$371.71$897.00$639.01$360.00
30Class A concrete (pipe endwalls) (611-07.01)CY7$1,500.00$859.00$2,582.09$3,000.00
31Steel bar reinforcement (pipe endwalls) (611-07.02)LB154$2.50$8.90$7.94$3.20
3218IN endwall (cross drain) 4:1 (611-07.55)EACH1$4,025.29$4,170.00$4,757.98$5,500.00
33Catch basins, type 12, > 4' - 8' depth (611-12.02)EACH3$10,078$11,320$11,969$5,500.00
34Conc parapet single slope (STD-1-1SS) (620-05.01)LF821$98.00$152.00$123.03$123.00
35Concrete sidewalk (4 ") (701-01.01)SF1,226$10.00$12.50$11.58$12.00
36Concrete curb ramp (701-02.03)SF511$30.00$36.00$34.73$35.00
37Concrete combined curb & gutter (702-03)CY54$650.00$812.00$752.40$707.00
38Guardrail delineation enhancement (705-04.21)LF82$3.06$3.85$3.38$8.00
39W beam GR (type 2) MASH TL-3 (705-06.01)LF245$42.79$54.00$47.27$35.00
40Thrie beam bridge transition MASH TL-3 (705-06.25)EACH4$2,375.00$2,990.00$2,623.61$3,600.00
41GR terminal (in-inline) MASH TL-3 (705-06.11)EACH2$1,063.00$1,340.00$1,174.28$1,600.00
42Guardrail removed (706-01)LF587$1.00$2.20$1.10$1.00
43Radius rail (706-06.03)LF37$49.10$62.00$54.24$36.00
44Chain link fence (6 foot) (707-01.11)LF495$20.00$39.00$35.35$23.00
45End & corner post assembly(chain-link fence 6') (707-01.12)EACH3$500.00$315.00$497.11$380.00
46Removal of fence (removal of existing R.O.W. fence along tract 7) (707-06.05)LS1$5,704.00$4,180.00$6,296.67$5,200.00
47Markers (concrete R.O.W. posts) (708-02.01)EACH3$1,185.48$1,480.00$359.02$355.00
48Machined rip-rap (class A-1) (709-05.06)TON663$94.86$59.50$67.43$94.00
49Machined rip-rap (class B) (709-05.08)TON327$95.51$78.00$78.27$137.00
50Filter cloth underdrain (with pipe) (710-04)LF2,029$12.90$18.90$16.57$15.00
51Lateral underdrain (710-05)LF400$11.20$15.10$13.26$12.50
52Lateral underdrain endwall (3:1) (710-06.12)EACH10$1,428.57$1,510.00$1,325.62$2,200.00
53Removal & disposal of concrete median barrier (711-05.01)LF821$49.63$69.50$72.63$70.00
5451IN single slope concrete barrier wall (711-05.71)LF76$425.00$315.00$516.87$340.00
55Traffic control (712-01)LS1$199,850$194,410$70,269$300,000
56Interconnected portable barrier rail (712-02.02)LF3,621$49.28$65.00$28.08$62.00
57Temporary work zone crash cushion (MASH TL-3) (712-02.60)EACH4$8,500.00$8,190.00$7,180.42$7,000.00
58Flexible drums (channelizing) (712-04.01)EACH100$32.50$41.00$35.90$35.00
59Barrier rail delineator (712-04.50)EACH91$10.00$12.60$11.05$10.00
60Warning lights (type A) (712-05.01)EACH2$20.00$25.20$22.10$23.00
61Signs (construction) (712-06)SF648$7.50$9.50$8.29$8.50
62Temporary barricades (type III) (712-07.03)LF24$19.00$24.00$20.99$21.00
63Arrow board (type C) (712-08.03)EACH2$1,100.00$1,390.00$1,215.15$1,250.00
64Removable pavement marking (8" barrier line) (712-09.02)LF400$5.00$7.60$6.63$5.50
65Steel overhead sign structure (span 84'-2") (713-09.01)EACH1$145,403$183,270$150,983$150,000
66Steel overhead sign structure (span 64'-3") (713-09.02)EACH1$125,835$158,600$130,692$145,000
67Perforated/knockout square tube post (713-11.02)LB2,410$5.30$6.70$5.94$5.00
68Flat sheet aluminum signs (0.080" thick) (713-13.02)SF128$13.23$16.70$14.82$22.00
69Flat sheet aluminum signs (0.100" thick) (713-13.03)SF440$14.35$18.10$16.07$22.00
70Extruded aluminum panel signs (713-14)SF928$28.43$36.00$31.84$34.00
71Removal of signs, posts and footings (713-15)LS1$1,625.00$2,050.00$1,820.16$7,500.00
72Changeable message sign unit (713-16.01)EACH2$5,750.00$7,250.00$6,351.91$6,000.00
73Signs (R10-11A) (713-16.21)EACH6$135.00$630.00$607.57$240.00
74Signs (R10-12) (713-16.22)EACH1$135.00$630.00$607.57$252.00
75Structural LIGHTING1 (714-01.20)LS1$19,700$25,210$22,094$25,000
76Jacked or bored conduit (714-03)LF310$41.00$13.50$11.79$11.75
77Direct burial conduit (2" PVC, schedule 40) (714-03.01)LF2,590$24.00$16.30$14.24$14.00
78Pull boxes (type C) (714-05.04)EACH4$1,550.00$3,530.00$3,093.10$3,080.00
79Cable (1/C # 6 AWG) (714-06.05)LF11,000$2.20$3.15$2.77$2.75
80Cable (#6 solid copper soft drawn) (714-06.08)LF965$2.20$2.00$1.75$1.75
81Cable (#6 copper soft drawn bare) (714-06.09)LF2,850$2.10$2.00$1.75$1.75
82Light standards (45' M.H., aluminium) (714-08.09)EACH11$5,450.00$3,530.00$3,093.10$3,100.00
83Light standards (45' M.H., aluminium) (714-08.10)EACH4$5,600.00$3,150.00$2,761.70$3,000.00
84Foundation (only) for light standard (714-08.20)EACH11$5,890.00$2,520.00$3,461.28$2,500.00
85Removal of light standard & foundation (714-08.32)EACH9$870.00$630.00$552.34$500.00
86Removal of existing cobra head luminaire (714-08.33)EACH57$134.00$189.00$165.70$160.00
87Luminaires (72W LED) (714-09.09)EACH6$820.00$1,890.00$1,657.02$1,600.00
88Luminaires (175W LED) (714-09.10)EACH72$860.00$756.00$662.81$630.00
89Modify exist control center(CC1 and CC2) (714-12.11)EACH2$1,650.00$1,260.00$1,104.68$1,050.00
90Electrical connection (see footnote on plans) (714-25.01)LS1$2,065.00$1,890.00$1,657.02$1,640.00
91Electrical connection (and reconnection) (714-25.02)LS1$6,055.00$1,890.00$1,657.02$1,630.00
92Locating utilities (714-40)LS1$34,700$44,110$11,047$5,250.00
93Snowplowable raised pavement markers (BI-dir)(2 color) (716-01.23)EACH78$50.00$126.00$110.47$38.00
94Plastic pavement marking(channelization striping) (716-02.04)SY476$35.00$38.00$33.14$39.00
95Plastic pavement marking (stop line) (716-02.05)LF84$30.00$25.20$22.09$20.00
96Plastic pavement marking (turn lane arrow) (716-02.06)EACH26$225.00$252.00$220.94$169.00
97Plastic pavement marking (8" dotted line) (716-02.08)LF62$3.00$5.00$4.42$2.25
98Plastic pavement marking (longitudinal cross-walk) (716-02.09)LF108$35.00$50.50$44.19$45.00
99Painted pavement marking (4" line) (716-05.01)LM3$1,100.00$3,150.00$2,761.70$1,015.00
100Removal of pavement marking (stop line) (716-08.05)LF150$12.00$12.60$11.05$9.00
101Removal of pavement marking (turn lane arrow) (716-08.06)EACH31$75.00$126.00$110.47$112.50
102Removal of pavement marking (line) (716-08.20)LM3$5,500.00$7,560.00$6,628.07$5,600.00
103Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM2$10,000$11,340$9,942.11$7,800.00
104Enhanced flatline thermo PVMT MRKNG (8IN barrier line) (716-12.03)LF902$2.50$3.15$2.76$2.20
105Enhanced flatline thermo PVMT MRKNG (6IN dotted line) (716-12.05)LF882$2.00$3.80$3.31$1.50
106Mobilization (717-01)LS1$324,984$306,200$529,239$718,000
107Pull box (type D) (725-20.44)EACH1$5,890.00$5,670.00$4,971.06$4,900.00
108Pull box (type E) (725-20.45)EACH3$6,970.00$6,300.00$5,523.40$5,250.00
109Conduit bank (type 4) (725-22.24)LF1,790$40.00$27.50$24.06$23.00
110Conduit bank bored (type 4) (725-22.34)LF400$78.00$49.50$43.22$43.00
111ITS cable marker (725-23.01)EACH4$240.00$315.00$276.17$270.00
112Fiber optic cable (72 F) (725-23.10)LF2,240$4.90$3.15$2.76$2.60
113Fiber optic cable (144F) (725-23.16)LF2,240$5.70$3.80$3.31$3.20
114Fiber optic closure (72 F ) (725-23.25)EACH2$1,155.00$3,150.00$2,761.70$2,700.00
115Fiber optic closure (description) (725-23.27)EACH2$1,155.00$3,150.00$2,761.70$2,700.00
116Fiber optic splice fusion (725-23.28)EACH432$108.00$1.25$1.10$1.00
117As-built plans (725-24.55)LS1$9,740.00$12,600$5,523.40$2,700.00
118Remove & relocate existing traffic signal equipment (730-01.01)EACH2$1,920.00$3,150.00$2,761.70$10,400
119Removal of signal equipment (730-01.02)EACH2$3,845.00$11,970$10,494$1,200.00
120Signal head assembly (130 with backplate) (730-02.09)EACH11$1,510.00$1,390.00$1,215.15$1,400.00
121Signal head assembly (150 A2H with backplate) (730-02.17)EACH1$1,895.00$1,640.00$1,436.08$1,100.00
122Signal head assembly (130 A3L with backplate) (730-02.30)EACH6$1,780.00$1,390.00$1,215.15$1,100.00
123Signal head assembly (130 A3L pole mounted) (730-02.31)EACH3$1,555.00$1,390.00$1,215.15$1,100.00
124Signal head assembly (130 A3R with backplate) (730-02.32)EACH4$1,575.00$1,390.00$1,215.15$1,100.00
125Signal head assembly (130 A3R pole mounted) (730-02.33)EACH2$1,555.00$1,390.00$1,215.15$1,100.00
126Install pull box (type B) (730-03.21)EACH20$1,255.00$2,270.00$1,988.42$1,980.00
127Signal cable - 5 conductor (730-08.02)LF10,830$2.40$2.10$1.83$1.85
128Signal cable - 7 conductor (730-08.03)LF2,855$2.70$2.55$2.23$2.25
129Conduit 2" diameter (PVC schedule 40) (730-12.02)LF1,160$25.00$20.10$17.61$17.50
130Conduit 3" diameter (directional bore) (730-12.24)LF2,310$27.00$12.80$11.25$11.20
131Vehicle detector (stop line radar) (730-13.09)EACH6$10,550$8,820.00$7,732.75$7,600.00
132Vehicle detector (radar - advance) (730-13.13)EACH2$11,700$8,820.00$7,732.76$7,500.00
133Modify cabinet (integrate APS, signal & radar equipment) (730-15.11)EACH2$2,535.00$3,150.00$2,761.70$2,700.00
134Pedestal pole (type A) (730-23.28)EACH9$3,095.00$5,040.00$4,418.72$4,200.00
135Pedestal pole (type B) (730-23.29)EACH5$2,635.00$5,670.00$4,971.06$4,900.00
136Cantilever signal support (2 @ 20' & 45') (730-23.55)EACH1$33,900$28,040$23,209$26,000
137Cantilever signal support (1 arm @ 30') (730-23.64)EACH1$24,500$20,170$16,875$20,000
138Cantilever signal support (1 arm @ 35') (730-23.72)EACH1$22,050$23,320$19,512$25,000
139Cantilever signal support (1 arm @ 50') (730-25.01)EACH1$28,650$30,250$25,312$30,000
140Cantilever signal support (2 @ 50' & 60') (730-25.04)EACH1$46,950$38,440$32,688$35,000
141Cantilever signal support (1 arm @ 70') (730-25.14)EACH1$46,050$32,140$28,231$40,000
142Countdown pedestrian signal (730-26.05)EACH2$1,765.00$945.00$828.51$800.00
143Pedestrian pushbutton post (730-26.06)EACH1$2,515.00$3,150.00$2,761.70$2,600.00
144Pedestrian pushbutton with 15IN sign (730-26.09)EACH2$675.00$1,580.00$1,380.85$1,300.00
145Countdown ped SGNL head W/audible pushbutton & 15IN sign (730-26.11)EACH10$1,765.00$2,520.00$2,209.36$2,100.00
146Road side unit (rsu) (730-35.50)EACH2$12,200$11,970$10,494$10,300
147Geotextile (type III)(erosion control) (740-10.03)SY223$3.26$7.50$13.11$7.00
148Temporary sediment tube 12IN (740-11.02)LF4,983$3.70$3.15$3.76$4.00
149Temporary sediment tube 20IN (740-11.04)LF1,389$4.50$3.80$4.31$4.20
150Seeding (with mulch) (801-01)UNIT123$58.00$58.50$51.06$51.00
151Water (seeding & sodding) (801-03)MG902$175.00$63.00$55.23$50.00
152Sodding (new sod) (803-01)SY901$6.00$8.69$7.62$7.50
153Erosion control blanket (type I) (805-12.01)SY9,800$1.40$1.25$1.10$1.10
154Project mowing (806-02.03)CYCL4$3,000.00$6,300.00$3,001.85$3,000.00
TDOT contract CNZ193: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of June 27, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy