TDOT contract CNZ213 bid tabulation

The construction of a concrete box beam bridge on s.r. 70 over the norfolk southern railroad (l.m. 6.19), including grading, drainage, retaining wall, and paving. Let by Tennessee DOT on August 15, 2025, Hawkins County. 2 bids received; low bid $9,392,609 by Southern Constructors, Inc..

Owner
Tennessee DOT
Letting
15 AUG 2025
Pay items
164
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Southern Constructors, Inc.$9,392,609Low
2Summers-Taylor, Inc.$11,260,165+20%
TDOT contract CNZ213: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Southern Constructors, Inc.2. Summers-Taylor, Inc.
1Construction stakes, lines and grades (105-01)LS1$100,000$40,200
2Trainee (109-10.01)HR1,180$0.80$0.80
3Clearing and grubbing (201-01)LS1$75,000$110,700
4Removal of pipe (15" CMP side drain, sta. 113+57) (202-02.01)LF30$50.00$105.00
5Road & drainage excavation (unclassified) (203-01)CY6,289$30.00$58.50
6Borrow excavation (unclassified) (203-03)CY3,415$55.00$42.00
7Placing and spreading topsoil (203-04)CY1,197$35.00$52.00
8Water (203-06)MG37$150.00$15.00
9Furnishing & spreading topsoil (203-07)CY94$75.00$129.00
10Construction of haul road (203-50)LS1$450,000$1,502,000
11Brooming & degrassing shoulders (208-01.05)LM1$1,500.00$5,980.00
1218" temporary slope drain (209-02.07)LF102$100.00$50.50
13Filter sock (18 inch) (209-03.22)LF318$22.00$19.00
14Sediment removal (209-05)CY62$100.00$48.50
15Temporary silt fence (with backing) (209-08.02)LF8,115$7.00$5.90
16Temporary silt fence (without backing) (209-08.03)LF983$7.00$4.70
17Rock check dam (209-08.07)EACH6$1,500.00$928.00
18Enhanced rock check dam (209-08.08)EACH9$2,000.00$1,500.00
19Sandbags (209-09.01)BAG200$30.00$11.50
20Curb inlet protection (type 4) (209-09.43)EACH5$1,000.00$544.00
21Polyethylene sheeting (6 mil. minimum) (209-20.03)SY20$35.00$38.50
22Mineral aggregate, type A base, grading D (303-01)TON8,218$65.00$73.50
23Mineral aggregate (size 57) (303-10.01)TON698$65.00$113.00
24Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01)TON740$200.00$197.00
25Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON590$210.00$238.00
26Asp. conc. mix(PG64-22) (BPMB-HM) GR. A-S (307-01.20)TON697$200.00$195.00
27Bituminous material for prime coat (PC) (402-01)TON10$1,450.00$1,170.00
28Aggregate for cover material (PC) (402-02)TON33$175.00$116.00
29Bituminous material for tack coat (TC) (403-01)TON8$1,650.00$1,420.00
30Saw cutting asphalt pavement (407-20.05)LF1,580$15.00$9.80
31Acs mix (PG64-22) grading E shoulder (411-01.07)TON148$225.00$272.00
32Acs mix(PG64-22) grading D (411-01.10)TON400$230.00$230.00
33Scoring shoulders (non-continuous) (16IN width) (411-12.02)LM0.70$1,200.00$13,250
34Cold planing bituminous pavement (415-01.01)TON610$100.00$43.00
35Retaining wall (SR-70 sta. 118+03.82 to sta. 126+84.42) (604-07.01)SF5,301$165.00$201.00
3618" concrete pipe culvert (class III) (607-03.02)LF72$300.00$394.00
3718" pipe culvert (side drain) (607-39.02)LF24$275.00$230.00
38Class A concrete (pipe endwalls) (611-07.01)CY3$2,500.00$2,640.00
39Steel bar reinforcement (pipe endwalls) (611-07.02)LB135$3.00$4.00
4018IN endwall (side drain) (611-07.31)EACH2$6,000.00$6,340.00
41Catch basins, type 51, > 4' - 8' depth (611-51.02)EACH4$9,500.00$12,900
42Catch basins, type 52, > 4FT - 8FT depth (611-52.02)EACH1$25,000$28,700
4342" temporary drainage pipe (621-03.06)LF85$250.00$237.00
44Temporary shoring (621-05.01)SF5,000$50.00$52.00
45Portland cement concrete ditch paving (703-01)CY1$5,000.00$5,670.00
46W beam GR (type 2) MASH TL-3 (705-06.01)LF1,363$28.00$34.00
47GR terminal (in-inline) MASH TL-3 (705-06.11)EACH6$1,500.00$1,270.00
48Tangent energy absorbing term MASH TL-3 (705-06.20)EACH1$4,000.00$3,490.00
49Thrie beam bridge transition MASH TL-3 (705-06.25)EACH4$4,000.00$2,860.00
50GR terminal (energy absorbing) MASH TL-2 (705-06.30)EACH2$3,500.00$3,700.00
51Radius rail (706-06.03)LF194$45.00$42.50
52Rounded end element (706-10.26)EACH3$500.00$159.00
53Stock fence gate (haul road) (707-03.03)EACH3$3,000.00$2,330.00
54High-visibility construction fence (707-08.11)LF2,138$7.50$4.45
55Markers (concrete R.O.W. posts) (708-02.01)EACH11$500.00$318.00
56Rubble stone rip-rap (grouted) (709-02.01)CY73$450.00$785.00
57Machined rip-rap (class A-3) (709-05.05)TON100$85.00$136.00
58Machined rip-rap (class A-1) (709-05.06)TON412$85.00$101.00
59Aggregate underdrains (with pipe) (710-02)LF1,250$30.00$25.50
60Lateral underdrain (710-05)LF176$75.00$62.50
61Lateral underdrain endwall (2:1) (710-06.11)EACH3$1,500.00$2,830.00
626" perforated plastic pipe (710-10.02)LF911$15.00$38.50
63Traffic control (712-01)LS1$150,000$92,500
64Interconnected portable barrier rail (712-02.02)LF500$50.00$89.00
65Temporary work zone crash cushion (MASH TL-3) (712-02.60)EACH4$10,500$8,470.00
66Flexible drums (channelizing) (712-04.01)EACH10$55.00$40.00
67Warning lights (type A) (712-05.01)EACH18$55.00$32.00
68Signs (construction) (712-06)SF1,408$15.00$14.00
69Temporary barricades (type III) (712-07.03)LF132$50.00$11.50
70Removable pavement marking (stop line) (712-09.04)LF51$25.00$26.00
71Class A concrete (foundation for sign supports) (713-01.01)CY0.12$1,500.00$105.00
72Steel bar reinforcement(foundation for sign supports) (713-01.02)LB25$5.00$1.05
73Sign post delineation enhancement (713-02.21)LF24$20.00$6.40
74"U" section steel posts (713-11.01)LB100$10.00$5.30
75Perforated/knockout square tube post (713-11.02)LB140$12.00$5.30
76U post slip base (713-11.22)EACH1$500.00$571.00
77Flat sheet aluminum signs (0.080" thick) (713-13.02)SF43$20.00$18.50
78Flat sheet aluminum signs (0.100" thick) (713-13.03)SF8$25.00$19.50
79Removal of signs, posts and footings (713-15)LS1$3,000.00$318.00
80Changeable message sign unit (713-16.01)EACH4$12,000$11,200
81Barrier mounted sign support (perf/knockout) (713-30.10)EACH1$600.00$1,270.00
82Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21)EACH21$110.00$65.50
83Removal of snowplowable reflective marker (716-01.30)EACH21$55.00$19.50
84Painted pavement marking (4" line) (716-05.01)LM2.80$1,500.00$3,260.00
85Painted pavement marking (stop line) (716-05.05)LF71$15.00$10.00
86Contrast pavement marking 6" (716-09.86)LM0.20$42,000$61,660
87Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM1.30$8,200.00$11,400
88Spray thermo PVMT MRKNG (60 mil) (6IN line) (716-13.02)LM0.20$8,500.00$5,500.00
89Mobilization (717-01)LS1$950,000$640,000
90Geogrid reinforcement type 2 (740-07.04)SY1,013$10.00$6.30
91Geotextile (type III)(erosion control) (740-10.03)SY873$10.00$8.40
92Geotextile (type IV)(stabilization) (740-10.04)SY611$10.00$10.50
93Temporary sediment tube 20IN (740-11.04)LF6,027$10.00$4.70
94Seeding (with mulch) (801-01)UNIT46$150.00$111.00
95Temporary seeding (with mulch) (801-01.07)UNIT436$75.00$43.50
96Natve seed MX final stablizatn of slopes (801-01.38)UNIT24$175.00$174.00
97Seeding (without mulch) (801-02)UNIT130$45.00$38.00
98Water (seeding & sodding) (801-03)MG80$225.00$218.00
99Seed (supplemental application) (801-07)LB35$100.00$65.50
100Fertilizer (supplemental application) (801-08)TON3$2,200.00$2,290.00
101Sodding (new sod) (803-01)SY2,542$12.00$11.00
102Turf reinforcement mat (class III) (805-01.03)SY521$12.00$11.00
103Erosion control blanket (type II) (805-12.02)SY11,016$2.00$1.50
104Project mowing (806-02.03)CYCL4$5,000.00$1,480.00
105Removal of asbestos (existing BR. no. 37-SR070-06.19) (202-01.05)LS1$50,000$26,500
106Removal of structures (existing BR. no. 37-SR070-06.19) (202-04.01)LS1$200,000$237,000
107Dry excavation (bridges) (204-02.01)CY554$85.00$218.00
108Core drilling for piles(rock) (204-14)LF464$400.00$689.00
109Core drilling for piles(soil) (204-15)LF240$400.00$215.00
110Granular backfill (bridges) (303-01.02)TON30$90.00$197.00
111Epoxy coated reinforcing steel (604-02.03)LB110,364$2.25$2.20
112Class A concrete (bridges) (604-03.01)CY351$1,300.00$2,200.00
113Steel bar reinforcement (bridges) (604-03.02)LB77,248$2.25$3.05
114Pavement @ bridge ends (604-03.04)SY228$500.00$877.00
115Class D concrete (bridge deck) (604-03.09)CY266$1,600.00$1,730.00
116Applied texture finish (new structures) (604-04.01)SY1,238$22.00$19.00
117Three star state emblem (604-04.41)EACH7$2,500.00$4,050.00
118Bridge deck grooving (mechanical) (604-05.31)SY1,090$12.00$6.30
119Steel piles (12 inch) (606-03.03)LF1,381$200.00$205.00
120Pile tips (steel piles, 12 inch) (606-03.06)EACH83$500.00$253.00
121Prestressed concrete box beam (33" X 48") (615-02.11)LF1,122$675.00$800.00
122Conc parapet single slope (STD-1-1SS) (620-05.01)LF1,321$175.00$210.00
123Chain-link fence (bridges) (707-07.01)SF2,702$35.00$29.50
124Reinforced concrete slope pavement (709-04)CY100$1,500.00$975.00
1256" perforated pipe with vertical drain system (710-09.01)LF126$70.00$58.00
1266" pipe underdrain (710-09.02)LF44$70.00$50.00
127Guy marker (E3-10) (760-15.17)EACH5$125.00$136.00
128Pole 45FT class 2 wood (790-04.02)EACH7$2,500.00$2,720.00
129Pole 45FT class 3 wood (790-04.03)EACH2$2,500.00$2,720.00
130Pole 50FT class 1 wood (790-05.01)EACH1$3,800.00$4,080.00
1311PH primary tap 15KV (790-21.09)EACH1$500.00$477.00
1323PH crossarm DBL prim sup LRG cond 15KV (790-25.11)EACH5$2,500.00$2,270.00
1333PH crossarm dde LRG cond 15KV (790-25.24)EACH5$3,000.00$2,540.00
1343PH crossarm double small angle 15KV (790-25.42)EACH3$2,500.00$2,270.00
135Down guy - through bolt type (790-32.01)EACH8$550.00$376.00
136OH guy hvy const -through bolt type (790-32.21)EACH2$1,250.00$659.00
137Transfer capacitor bank (790-36.02)EACH1$10,000$9,970.00
138OH cond 3/0 6/1 acsr pigeon (790-40.05)LF1,452$4.00$2.70
139OH cond 336.4 19 aac tulip (790-40.42)LF403$5.00$3.90
140OH cond 556.5 19 aac dahlia (790-40.46)LF1,209$8.00$7.70
141OH cond 795 37 aac arbutus (790-40.49)LF4,356$8.00$6.60
142Cutout knife switch, SNGL loadbreak 15KV (790-58.03)EACH1$2,200.00$2,270.00
143Pole ground rod type (790-68.01)EACH10$500.00$437.00
144Anchor power screw (790-72.01)EACH5$1,500.00$1,360.00
145Fiber tangent assembly (790-74.31)EACH6$550.00$474.00
146Fiber double deadend assembly (790-74.33)EACH7$1,250.00$1,220.00
147Remove wire (790-98.01)LF7,950$3.00$2.10
148Remove poles (790-98.02)EACH9$1,000.00$1,040.00
149Remove framing/associated apparatus (790-98.03)EACH20$500.00$464.00
1502IN mdpe gas main (791-02.02)LF153$60.00$58.00
1516IN mdpe gas main (791-02.05)LF390$75.00$127.00
152HDD 2IN PE pipe - unconsolidated (791-04.02)LF100$70.00$101.00
153HDD 6IN PE pipe - unconsolidated (791-04.05)LF60$100.00$164.00
154Connect to 2IN EX. PE main (791-06.02)EACH2$3,500.00$7,620.00
155Connect to 6IN EX. PE main (791-06.04)EACH2$5,000.00$13,200
156Pole 40FT class 4 wood (793-01.12)EACH1$5,500.00$2,720.00
157Anchor 1IN (793-01.41)EACH10$1,500.00$1,020.00
158Aerial splice closure (793-04.07)EACH1$1,200.00$1,130.00
159Transfer aerial cable (793-04.08)EACH9$400.00$287.00
160Dig splice pit 80 C.F. (793-12.01)EACH2$1,250.00$3,060.00
1611 duct formation @ 36IN depth (793-13.12)LF30$110.00$151.00
162Remove poles all sizes (793-98.04)EACH2$1,100.00$1,040.00
163Remove anchor (any size) (793-98.08)EACH3$300.00$227.00
164Remove down guy (793-98.09)EACH3$100.00$54.50
TDOT contract CNZ213: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of August 15, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy