TDOT contract CNZ267 bid tabulation
The construction of a concrete box beam bridge on s.r. 320 (east brainerd road) over the csx railroad (l.m. 0.86) in chattanooga, including grading, drainage, retaining wall, and paving. Let by Tennessee DOT on October 3, 2025, Hamilton County. 2 bids received; low bid $10,219,956 by Dement Construction Group, LLC.
- Owner
- Tennessee DOT
- Letting
- 03 OCT 2025
- Pay items
- 219
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Dement Construction Group, LLC | $10,219,956 | Low |
| 2 | Wright Brothers Civil Construction, LLC | $11,514,449 | +13% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Dement Construction Group, LLC | 2. Wright Brothers Civil Construction, LLC |
|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $100,000 | $61,000 |
| 2 | CPM project schedule (108-03) | LS | 1 | $50,000 | $10,000 |
| 3 | Trainee (109-10.01) | HR | 1,100 | $0.80 | $0.80 |
| 4 | Clearing and grubbing (201-01) | LS | 1 | $468,000 | $445,000 |
| 5 | Removal of structures and obstructions (202-01.50) | EACH | 1 | $1,500.00 | $770.00 |
| 6 | Removal of pipe (18" RCP, sta. 50+49 benham drive) (202-02.01) | LF | 105 | $25.00 | $25.00 |
| 7 | Removal of rigid pavement, sidewalk, etc. (202-03) | SY | 465 | $15.00 | $8.45 |
| 8 | Removal of asphalt pavement (202-03.01) | SY | 1,610 | $15.00 | $7.25 |
| 9 | Removal of curb (concrete curb) (202-08.10) | LF | 1,695 | $10.00 | $12.50 |
| 10 | Road & drainage excavation (unclassified) (203-01) | CY | 5,017 | $40.00 | $34.00 |
| 11 | Borrow excavation (graded solid rock) (203-02.01) | TON | 350 | $100.00 | $67.25 |
| 12 | Borrow excavation (unclassified) (203-03) | CY | 4,820 | $50.00 | $38.00 |
| 13 | Placing and spreading topsoil (203-04) | CY | 483 | $25.00 | $12.10 |
| 14 | Water (203-06) | MG | 16 | $25.00 | $25.80 |
| 15 | Furnishing & spreading topsoil (203-07) | CY | 1,002 | $56.00 | $11.65 |
| 16 | Waste material (203-10.15) | CY | 207 | $200.00 | $143.00 |
| 17 | Construction of haul road (203-50) | LS | 1 | $80,000 | $365,500 |
| 18 | 10" temporary slope drain (209-02.04) | LF | 71 | $14.00 | $33.00 |
| 19 | Sediment removal (209-05) | CY | 116 | $30.00 | $34.00 |
| 20 | Temporary silt fence (with backing) (209-08.02) | LF | 3,532 | $5.00 | $5.65 |
| 21 | Rock check dam (209-08.07) | EACH | 3 | $800.00 | $900.00 |
| 22 | Enhanced rock check dam (209-08.08) | EACH | 5 | $1,000.00 | $1,100.00 |
| 23 | Curb inlet protection (type 4) (209-09.43) | EACH | 17 | $375.50 | $424.00 |
| 24 | Catch basin protection (type D) (209-40.33) | EACH | 13 | $425.50 | $480.00 |
| 25 | Mineral aggregate, type A base, grading D (303-01) | TON | 2,692 | $31.30 | $59.00 |
| 26 | Mineral aggregate (size 57) (303-10.04) | TON | 346 | $70.00 | $112.00 |
| 27 | Mineral aggregate (size 4) (303-10.07) | TON | 70 | $100.00 | $66.00 |
| 28 | Asp. conc. mix(PG70-22) (BPMB-HM) GR. A-S (307-01.21) | TON | 453 | $210.00 | $148.00 |
| 29 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01) | TON | 490 | $202.50 | $148.00 |
| 30 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08) | TON | 446 | $215.50 | $200.00 |
| 31 | Bituminous material for prime coat (PC) (402-01) | TON | 4 | $2,200.00 | $1,175.00 |
| 32 | Aggregate for cover material (PC) (402-02) | TON | 15 | $500.00 | $300.00 |
| 33 | Bituminous material for tack coat (TC) (403-01) | TON | 5 | $850.00 | $830.00 |
| 34 | Saw cutting asphalt pavement (407-20.05) | LF | 766 | $25.00 | $11.00 |
| 35 | Acs mix(PG70-22) grading D (411-02.10) | TON | 239 | $296.00 | $216.00 |
| 36 | Cold planing bituminous pavement (415-01.02) | SY | 731 | $42.25 | $29.00 |
| 37 | Concrete pavement removal (502-03.13) | SY | 152 | $25.00 | $16.65 |
| 38 | Sawing concrete pavement (full depth) (502-04.01) | LF | 147 | $30.00 | $16.70 |
| 39 | Retaining wall (wall C) (604-07.01) | SF | 3,355 | $175.00 | $233.00 |
| 40 | 18" concrete pipe culvert (class III) (607-03.02) | LF | 1,155 | $120.00 | $113.00 |
| 41 | Class A concrete (pipe endwalls) (611-07.01) | CY | 1 | $2,500.00 | $4,200.00 |
| 42 | Steel bar reinforcement (pipe endwalls) (611-07.02) | LB | 45 | $15.00 | $13.00 |
| 43 | Adjustment of existing catchbasin (611-09.01) | EACH | 1 | $1,000.00 | $2,600.00 |
| 44 | Catch basins, type 12, 0' - 4' depth (611-12.01) | EACH | 4 | $5,000.00 | $7,300.00 |
| 45 | Catch basins, type 12, > 4' - 8' depth (611-12.02) | EACH | 4 | $6,000.00 | $8,300.00 |
| 46 | Catch basins, type 12, > 12' - 16' depth (611-12.04) | EACH | 2 | $9,000.00 | $8,900.00 |
| 47 | Catch basins, type 14, > 4' - 8' depth (611-14.02) | EACH | 2 | $6,000.00 | $10,500 |
| 48 | Concrete sidewalk (4 ") (701-01.01) | SF | 9,316 | $7.85 | $8.75 |
| 49 | Concrete driveway (701-02) | SF | 1,391 | $12.00 | $13.40 |
| 50 | Concrete curb ramp (701-02.03) | SF | 207 | $28.00 | $31.40 |
| 51 | Concrete curb (702-01) | CY | 2 | $760.00 | $850.00 |
| 52 | Concrete combined curb & gutter (702-03) | CY | 112 | $520.00 | $580.00 |
| 53 | GR terminaltrailing end (type 13) MASH TL-3 (705-06.10) | EACH | 2 | $1,350.00 | $1,500.00 |
| 54 | Tangent energy absorbing term MASH TL-3 (705-06.20) | EACH | 1 | $3,350.00 | $3,800.00 |
| 55 | Thrie beam bridge transition MASH TL-3 (705-06.25) | EACH | 4 | $3,850.00 | $4,300.00 |
| 56 | Thrie beam 38IN vehicle & pedestrian safety rail MASH TL-3 (705-06.27) | LF | 890 | $44.50 | $50.25 |
| 57 | GR terminal (energy absorbing) MASH TL-2 (705-06.30) | EACH | 1 | $3,050.00 | $3,400.00 |
| 58 | Guardrail removed (706-01) | LF | 1,293 | $1.50 | $1.70 |
| 59 | Chain-link fence (6 foot) (vinyl coated) (707-02.11) | LF | 190 | $23.00 | $26.40 |
| 60 | End & corner post assemblies (6' vinyl coated) (707-02.12) | EACH | 5 | $400.00 | $459.00 |
| 61 | Removal of fence (various) (707-06.01) | LF | 795 | $6.00 | $7.00 |
| 62 | Markers (concrete R.O.W. posts) (708-02.01) | EACH | 11 | $600.00 | $344.00 |
| 63 | Machined rip-rap (class A-3) (709-05.05) | TON | 100 | $100.00 | $72.75 |
| 64 | Machined rip-rap (class A-1) (709-05.06) | TON | 18 | $100.00 | $81.00 |
| 65 | Aggregate underdrains (with pipe) (710-02) | LF | 1,755 | $20.00 | $16.00 |
| 66 | Traffic control (712-01) | LS | 1 | $251,850 | $100,000 |
| 67 | Interconnected portable barrier rail (712-02.02) | LF | 2,240 | $30.00 | $33.50 |
| 68 | Bridge mounted interconnected portable barrier rail (712-02.47) | LF | 440 | $60.00 | $50.00 |
| 69 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 10 | $7,950.00 | $8,975.00 |
| 70 | Flexible drums (channelizing) (712-04.01) | EACH | 50 | $31.00 | $50.75 |
| 71 | Barrier rail delineator (712-04.50) | EACH | 268 | $10.00 | $16.35 |
| 72 | Warning lights (type A) (712-05.01) | EACH | 76 | $20.00 | $42.00 |
| 73 | Signs (construction) (712-06) | SF | 911 | $7.50 | $9.25 |
| 74 | Temporary barricades (type II) (712-07.02) | LF | 12 | $15.50 | $22.60 |
| 75 | Temporary barricades (type III) (712-07.03) | LF | 144 | $28.00 | $20.30 |
| 76 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 424 | $3.65 | $4.10 |
| 77 | Removable pavement marking (6" line) (712-09.08) | LF | 1,029 | $3.15 | $3.55 |
| 78 | Class A concrete (foundation for sign supports) (713-01.01) | CY | 2 | $605.70 | $730.00 |
| 79 | Steel bar reinforcement(foundation for sign supports) (713-01.02) | LB | 271 | $8.06 | $3.90 |
| 80 | Sign post delineation enhancement (713-02.21) | LF | 12 | $10.45 | $6.50 |
| 81 | Steel I-beams & WF-beams(breakaway) sign support (713-06) | LB | 493 | $10.03 | $8.50 |
| 82 | "U" section steel posts (713-11.01) | LB | 38 | $8.10 | $7.00 |
| 83 | Perforated/knockout square tube post (713-11.02) | LB | 85 | $8.64 | $7.00 |
| 84 | Flat sheet aluminum signs (0.100" thick) (713-13.03) | SF | 32 | $21.48 | $18.65 |
| 85 | Extruded aluminum panel signs (713-14) | SF | 40 | $37.89 | $31.60 |
| 86 | Removal of signs, posts and footings (713-15) | LS | 1 | $679.95 | $560.00 |
| 87 | Changeable message sign unit (713-16.01) | EACH | 3 | $8,700.00 | $11,300 |
| 88 | Remove and replace sign (existing street name signs) (713-16.50) | EACH | 2 | $315.45 | $282.00 |
| 89 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 21 | $100.00 | $113.00 |
| 90 | Removal of snowplowable reflective marker (716-01.30) | EACH | 15 | $30.00 | $33.90 |
| 91 | Plastic pavement marking(channelization striping) (716-02.04) | SY | 5 | $30.00 | $33.90 |
| 92 | Plastic pavement marking (stop line) (716-02.05) | LF | 23 | $15.00 | $17.00 |
| 93 | Plastic pavement marking (longitudinal cross-walk) (716-02.09) | LF | 76 | $25.00 | $28.20 |
| 94 | Painted pavement marking (8" barrier line) (716-05.02) | LF | 2,305 | $0.50 | $0.55 |
| 95 | Painted pavement marking (6" line) (716-05.20) | LM | 1.71 | $1,750.00 | $2,000.00 |
| 96 | Hydroblast removal of pavement marking (line) (716-08.30) | LM | 1.13 | $4,750.00 | $5,400.00 |
| 97 | Contrast pavement marking 6" (716-09.83) | LF | 847 | $14.00 | $15.80 |
| 98 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 0.81 | $10,000 | $11,300 |
| 99 | Mobilization (717-01) | LS | 1 | $950,000 | $1,150,000 |
| 100 | Geogrid reinforcement type 2 (740-07.04) | SY | 524 | $20.00 | $8.15 |
| 101 | Geotextile (type III)(erosion control) (740-10.03) | SY | 223 | $6.00 | $3.90 |
| 102 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 762 | $5.00 | $4.30 |
| 103 | Temporary sediment tube 12IN (740-11.02) | LF | 1,616 | $4.85 | $5.45 |
| 104 | Seeding (with mulch) (801-01) | UNIT | 7 | $75.00 | $84.75 |
| 105 | Temporary seeding (with mulch) (801-01.07) | UNIT | 160 | $35.50 | $40.10 |
| 106 | Seeding (without mulch) (801-02) | UNIT | 45 | $31.52 | $35.60 |
| 107 | Water (seeding & sodding) (801-03) | MG | 9 | $250.00 | $282.00 |
| 108 | Sodding (new sod) (803-01) | SY | 4,325 | $6.25 | $7.00 |
| 109 | Turf reinforcement mat (class I) (805-01.01) | SY | 392 | $5.00 | $5.60 |
| 110 | Erosion control blanket (type II) (805-12.02) | SY | 3,581 | $1.25 | $1.40 |
| 111 | Removal of structures (BR. no. 33-SR320-0.86) (202-04.01) | LS | 1 | $125,000 | $345,000 |
| 112 | Dry excavation (bridges) (204-02.01) | CY | 2,024 | $25.00 | $62.75 |
| 113 | Granular backfill (bridges) (303-01.02) | TON | 1,985 | $55.00 | $107.00 |
| 114 | Epoxy coated reinforcing steel (604-02.03) | LB | 92,655 | $1.60 | $1.85 |
| 115 | Class A concrete (bridges) (604-03.01) | CY | 897 | $900.00 | $1,035.00 |
| 116 | Steel bar reinforcement (bridges) (604-03.02) | LB | 165,612 | $1.50 | $1.45 |
| 117 | Pavement @ bridge ends (604-03.04) | SY | 262 | $650.00 | $403.00 |
| 118 | Class D concrete (bridge deck) (604-03.09) | CY | 247 | $1,250.00 | $2,200.00 |
| 119 | Applied texture finish (new structures) (604-04.01) | SY | 1,413 | $12.99 | $27.20 |
| 120 | Three star state emblem (604-04.41) | EACH | 4 | $1,350.00 | $3,600.00 |
| 121 | Bridge deck grooving (mechanical) (604-05.31) | SY | 825 | $7.74 | $8.75 |
| 122 | Steel piles (12 inch) (606-03.03) | LF | 3,249 | $95.00 | $90.50 |
| 123 | Pile tips (steel piles, 12 inch) (606-03.06) | EACH | 191 | $315.00 | $164.00 |
| 124 | Deck drains (grate type 2) (610-10.45) | EACH | 4 | $2,000.00 | $4,150.00 |
| 125 | Prestressed concrete box beam (24" X 36") (615-02.19) | LF | 1,412 | $450.00 | $485.00 |
| 126 | Bridge deck crack sealing (617-02) | LF | 211 | $5.00 | $10.00 |
| 127 | Sealant (HMWM) (617-05) | GAL | 3 | $300.00 | $262.00 |
| 128 | Concrete parapet with structural tubing (620-05) | LF | 677 | $300.00 | $384.00 |
| 129 | Temporary shoring (621-05.01) | SF | 1,200 | $125.00 | $88.50 |
| 130 | Chain-link fence (bridges) (707-07.01) | SF | 1,168 | $28.00 | $32.00 |
| 131 | Reinforced concrete slope pavement (709-04) | CY | 31 | $1,500.00 | $1,700.00 |
| 132 | 6" perforated pipe with vertical drain system (710-09.01) | LF | 135 | $50.00 | $53.75 |
| 133 | 6" pipe underdrain (710-09.02) | LF | 50 | $20.00 | $28.10 |
| 134 | Concrete sidewalk (4 ") (701-01.01) | SF | 75 | $10.00 | $21.50 |
| 135 | Concrete combined curb & gutter (702-03) | CY | 1 | $1,000.00 | $1,800.00 |
| 136 | Pole 40FT class 4 wood (790-03.03) | EACH | 1 | $1,231.25 | $1,400.00 |
| 137 | Pole 45FT class 4 wood (790-04.04) | EACH | 1 | $1,342.50 | $1,515.00 |
| 138 | Pole 50FT class 2 wood (790-05.02) | EACH | 3 | $1,825.00 | $2,050.00 |
| 139 | Pole 50FT class H2 metal (790-05.08) | EACH | 1 | $6,653.75 | $7,500.00 |
| 140 | Pole 55FT class 1 wood (790-06.01) | EACH | 1 | $2,060.00 | $2,300.00 |
| 141 | Pole 60FT class 1 wood (790-07.01) | EACH | 3 | $2,400.00 | $2,700.00 |
| 142 | Pole 65FT class H4 metal (790-08.06) | EACH | 1 | $10,749 | $12,100 |
| 143 | Pole 85FT class H4 metal (790-12.07) | EACH | 2 | $17,875 | $20,200 |
| 144 | 1PH deadend 15KV (790-21.08) | EACH | 1 | $410.21 | $463.00 |
| 145 | 1PH primary tap 15KV (790-21.09) | EACH | 1 | $514.43 | $580.00 |
| 146 | 2PH crossarm const deadend (SGL) 15KV (790-23.07) | EACH | 2 | $1,276.58 | $1,400.00 |
| 147 | 3PH crossarm DBL LRG cond 15KV (790-25.07) | EACH | 2 | $1,672.66 | $1,900.00 |
| 148 | 3PH crossarm SGL LRG cond 15KV (790-25.08) | EACH | 2 | $994.78 | $1,100.00 |
| 149 | 3PH crossarm dde LRG cond 15KV (790-25.24) | EACH | 1 | $2,122.95 | $2,400.00 |
| 150 | 3PH crossarm dde 10FT arms LRG cond 15KV (790-25.27) | EACH | 2 | $2,535.58 | $2,900.00 |
| 151 | 3PH crossarm DBL 10FT LRG cond 15KV (790-25.30) | EACH | 1 | $1,745.94 | $2,000.00 |
| 152 | Secondary conductor 6 AL duplex (790-30.06) | LF | 481 | $1.96 | $2.20 |
| 153 | Service assembly-pole type (790-31.02) | EACH | 9 | $134.30 | $152.00 |
| 154 | Service conductor 1/0 AL qplex (790-31.20) | LF | 62 | $7.71 | $8.70 |
| 155 | Down guy - through bolt type heavy duty (790-32.02) | EACH | 3 | $629.06 | $710.00 |
| 156 | Down guy - insulated (790-32.06) | EACH | 3 | $615.20 | $690.00 |
| 157 | OH guy - through bolt type (790-32.07) | EACH | 4 | $1,241.88 | $1,400.00 |
| 158 | Guy guard (790-32.23) | EACH | 6 | $14.75 | $16.60 |
| 159 | Screw type anchor 23,000LB (F1-5D-P) (790-33.31) | EACH | 6 | $649.19 | $730.00 |
| 160 | Transfer light (790-36.06) | EACH | 1 | $356.25 | $400.00 |
| 161 | Transfer existing 3PH transformer/recloser (790-36.12) | EACH | 1 | $5,400.38 | $6,100.00 |
| 162 | Transfer conductor (790-36.14) | EACH | 9 | $117.50 | $133.00 |
| 163 | OH cond 1/0 6/1 acsr raven (790-40.03) | LF | 796 | $3.51 | $4.00 |
| 164 | OH cond 4/0 7 aac oxlip (790-40.39) | LF | 4,468 | $4.33 | $5.00 |
| 165 | 1PH primary riser W/ 3IN conduit (790-43.53) | EACH | 1 | $2,281.66 | $2,600.00 |
| 166 | 1PH transformer conv W/xarm MTD fuse & LA (790-46.03) | EACH | 1 | $1,001.50 | $1,100.00 |
| 167 | 1PH fuse cutout xarm mount 15KV (790-60.01) | EACH | 5 | $490.15 | $550.00 |
| 168 | Sec MTG 3PH 120/208 V (4 wire GRD wye) (790-64.12) | EACH | 1 | $1,596.38 | $1,800.00 |
| 169 | Lightning arrester arm MTD 9 KV (790-65.03) | EACH | 3 | $331.40 | $374.00 |
| 170 | Pole ground rod type (790-68.01) | EACH | 4 | $267.96 | $302.00 |
| 171 | Pole ground plate type (790-68.02) | EACH | 5 | $250.83 | $283.00 |
| 172 | Ground-ground rod for ST pole (790-69.11) | EACH | 4 | $209.91 | $237.00 |
| 173 | Arm pin (790-69.32) | EACH | 18 | $66.50 | $75.00 |
| 174 | Extension link - epoxy -8FT (790-69.41) | EACH | 4 | $145.56 | $164.00 |
| 175 | DBL arm line post ins no ohgw 46KV max (790-71.04) | EACH | 2 | $2,442.75 | $2,800.00 |
| 176 | Fiber tangent assembly (790-74.31) | EACH | 5 | $183.46 | $207.00 |
| 177 | Fiber deadend assembly (790-74.32) | EACH | 1 | $796.61 | $900.00 |
| 178 | Fiber double deadend assembly (790-74.33) | EACH | 2 | $1,406.06 | $1,575.00 |
| 179 | Remove wire (790-98.01) | LF | 6,326 | $2.25 | $2.55 |
| 180 | Remove poles (790-98.02) | EACH | 9 | $550.00 | $620.00 |
| 181 | Remove framing/associated apparatus (790-98.03) | EACH | 60 | $400.00 | $452.00 |
| 182 | Tree and brush removal off row (790-98.20) | LS | 1 | $15,000 | $27,800 |
| 183 | 2IN mdpe gas main (791-02.02) | LF | 195 | $123.00 | $139.00 |
| 184 | 6IN mdpe gas main (791-02.05) | LF | 1,080 | $210.00 | $237.00 |
| 185 | HDD 6IN PE pipe - unconsolidated (791-04.05) | LF | 400 | $1,050.00 | $1,175.00 |
| 186 | Bore/jack ___in - steel casing pipe - uncon. (791-05.14) | LF | 300 | $2,300.00 | $2,595.00 |
| 187 | Connect to __in EX. PE main (791-06.09) | EACH | 1 | $6,000.00 | $6,800.00 |
| 188 | Connect to 6IN EX. STL main (791-06.12) | EACH | 2 | $51,000 | $57,600 |
| 189 | 6IN PE gas valve assembly (791-07.03) | EACH | 2 | $2,150.00 | $2,400.00 |
| 190 | Pole 35FT class 2 wood (793-01.05) | EACH | 1 | $3,510.00 | $780.00 |
| 191 | Pole 40FT class 4 wood (793-01.12) | EACH | 2 | $4,030.00 | $780.00 |
| 192 | Anchor 1IN (793-01.41) | EACH | 9 | $807.00 | $510.00 |
| 193 | Handhole 30INX48IN (793-11.20) | EACH | 1 | $6,240.00 | $2,050.00 |
| 194 | Dig splice pit (15 LF) (793-12.21) | EACH | 2 | $910.00 | $660.00 |
| 195 | 2 duct formation @ 36IN depth (793-13.17) | LF | 150 | $73.50 | $60.00 |
| 196 | Concrete encasement per duct (793-14.02) | LF | 300 | $16.50 | $13.00 |
| 197 | 4IN core drill into manhole (793-14.10) | EACH | 2 | $472.00 | $339.00 |
| 198 | 1 1/4IN innerduct (793-14.12) | LF | 450 | $4.30 | $1.40 |
| 199 | MH(retire/remove/gravel backfill) (793-16.01) | EACH | 3 | $1,485.00 | $1,675.00 |
| 200 | Restore asphalt (793-97.01) | SY | 100 | $500.00 | $150.00 |
| 201 | Remove poles all sizes (793-98.04) | EACH | 10 | $654.00 | $254.00 |
| 202 | Communication assembly (bond) (798-05.27) | EACH | 4 | $5,285.00 | $5,950.00 |
| 203 | Communication assembly (CSC) (798-05.29) | EACH | 5 | $5,600.00 | $6,300.00 |
| 204 | Communication assembly (dde) (798-05.32) | EACH | 2 | $5,250.00 | $5,925.00 |
| 205 | Communication assembly (DE) (798-05.33) | EACH | 6 | $4,844.00 | $5,450.00 |
| 206 | Communication assembly (E1-2) (798-05.34) | EACH | 7 | $4,294.00 | $4,825.00 |
| 207 | Communication assembly (E2-2) (798-05.35) | EACH | 3 | $6,605.00 | $7,450.00 |
| 208 | Communication assembly (F2&F3) (798-05.37) | EACH | 1 | $8,807.00 | $9,925.00 |
| 209 | Communication assembly (loop) (798-05.52) | EACH | 1 | $910.00 | $1,025.00 |
| 210 | Communication assembly (SVC) (798-05.54) | EACH | 8 | $11,124 | $12,600 |
| 211 | 5/16" HS steel strand (798-05.59) | LF | 1,378 | $19.15 | $21.60 |
| 212 | 18”/15 deg fiberglass standoff bracket (798-06.90) | EACH | 1 | $1,904.00 | $2,125.00 |
| 213 | Riser (798-08.01) | EACH | 2 | $2,996.00 | $3,400.00 |
| 214 | Transfer communication assy (SVC) (798-08.04) | EACH | 1 | $7,416.00 | $8,375.00 |
| 215 | Transfer fiberoptic cable (798-08.06) | EACH | 18 | $3,708.00 | $4,200.00 |
| 216 | Transfer SVC drop (798-08.07) | EACH | 8 | $4,368.00 | $4,925.00 |
| 217 | Remove steel strand (798-09.01) | LF | 1,402 | $4.40 | $5.00 |
| 218 | Remove poles, guys, anchors (798-09.03) | EACH | 4 | $1,750.00 | $1,975.00 |
| 219 | Remove strand pole framing (798-09.08) | EACH | 25 | $700.00 | $790.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of October 3, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.