TDOT contract CNZ903 bid tabulation

The construction of a concrete box beam or welded plate girder bridge on s.r. 107 (unicoi drive) over north indian creek (l.m. 5.22) in erwin, including grading, drainage, and paving. Let by Tennessee DOT on August 15, 2025, Unicoi County. 2 bids received; low bid $7,979,553 by Summers-Taylor, Inc..

Owner
Tennessee DOT
Letting
15 AUG 2025
Pay items
248
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Summers-Taylor, Inc.$7,979,553Low
2Southern Constructors, Inc.$8,631,874+8.0%
TDOT contract CNZ903: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Summers-Taylor, Inc.2. Southern Constructors, Inc.
1Construction stakes, lines and grades (105-01)LS1$53,100$80,000
2Trainee (109-10.01)HR1,180$0.80$0.80
3Clearing and grubbing (201-01)LS1$75,000$90,000
4Removal of structures and obstructions (202-01.50)EACH3$2,000.00$3,100.00
5Removal of pipe (12" ,sta. 216+08.31) (202-02.01)LF41$147.00$190.00
6Removal of pipe (18" ,sta. 215+11.35) (202-02.02)LF104$108.00$120.00
7Removal of pipe (18" ,sta. 214+26.31) (202-02.03)LF60$100.00$140.00
8Removal of pipe (12" ,sta. 212+91.74) (202-02.04)LF203$95.00$165.00
9Removal of pipe (15" ,sta. 212+67.83) (202-02.05)LF140$104.00$165.00
10Removal of pipe (15",sta. 211+96.85) (202-02.06)LF14$104.00$340.00
11Removal of asphalt pavement (202-03.01)SY1,314$18.50$15.00
12Road & drainage excavation (unclassified) (203-01)CY1,910$122.00$72.00
13Borrow excavation (graded solid rock) (203-02.01)TON523$100.00$125.00
14Placing and spreading topsoil (203-04)CY105$77.50$71.00
15Water (203-06)MG22$119.00$300.00
16Furnishing & spreading topsoil (203-07)CY46$105.00$130.00
17Construction of haul road (203-50)LS1$305,000$150,000
18Backfill material (flowable fill) (204-08.01)CY2$514.00$3,100.00
19Sediment removal (209-05)CY67$40.00$60.00
20Temporary silt fence (with backing) (209-08.02)LF582$11.00$12.00
21Temporary silt fence (without backing) (209-08.03)LF514$3.00$7.00
22Rock check dam (209-08.07)EACH4$826.00$1,300.00
23Enhanced rock check dam (209-08.08)EACH6$1,550.00$2,000.00
24Sediment filter bag (15' X 15') (209-09.03)EACH1$3,430.00$1,300.00
25Curb inlet protection (type 4) (209-09.43)EACH13$370.00$1,100.00
26Catch basin protection (type A) (209-40.30)EACH4$740.00$2,300.00
27Catch basin protection (type D) (209-40.33)EACH1$342.00$700.00
28Temporary diversion channel (209-65.03)LF122$132.00$2,700.00
29Mineral aggregate, type A base, grading D (303-01)TON2,807$78.00$90.00
30Granular backfill (roadway) (303-01.01)TON15$129.00$120.00
31Mineral aggregate (size 57) (303-10.01)TON22$135.00$95.00
32Mineral aggregate (size ) (303-10.04)TON532$115.00$110.00
33Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01)TON512$235.00$260.00
34Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON452$295.00$330.00
35Bituminous material for prime coat (PC) (402-01)TON5$1,500.00$1,650.00
36Bituminous material for tack coat (TC) (403-01)TON2.50$1,350.00$1,500.00
37Acs mix (PG64-22) grading E shoulder (411-01.07)TON24$482.00$550.00
38Acs mix(PG64-22) grading D (411-01.10)TON278$335.00$390.00
39Cold planing bituminous pavement (415-01.01)TON41$195.00$220.00
4018" concrete pipe culvert (class III) (607-03.02)LF541$266.00$380.00
4124" concrete pipe culvert (class III) (607-05.02)LF54$337.00$560.00
4230" concrete pipe culvert (class III) (607-06.02)LF78$374.00$590.00
43Manholes, > 4' - 8' depth (611-01.02)EACH1$9,500.00$7,600.00
44Class A concrete (pipe endwalls) (611-07.01)CY2$3,640.00$2,600.00
45Steel bar reinforcement (pipe endwalls) (611-07.02)LB93$2.85$8.00
46Catch basins, type 12, 0' - 4' depth (611-12.01)EACH3$7,460.00$7,300.00
47Catch basins, type 12, > 4' - 8' depth (611-12.02)EACH3$8,590.00$8,300.00
48Catch basins, type 14, > 4' - 8' depth (611-14.02)EACH5$14,700$11,500
49Catch basins, type 25, 0' - 4' depth (611-25.01)EACH1$9,220.00$11,200
50Catch basins, type 25, > 4' - 8' depth (611-25.02)EACH1$9,640.00$16,000
51Catch basins, type 42, 0' - 4' depth (611-42.01)EACH1$6,660.00$9,500.00
52Concrete median pavement (701-03)CY27$822.00$950.00
53Concrete curb (702-01)CY14$588.00$1,600.00
54Concrete combined curb & gutter (702-03)CY46$611.00$1,750.00
55W beam GR (type 2) MASH TL-3 (705-06.01)LF113$34.50$35.00
56GR terminal (in-inline) MASH TL-3 (705-06.11)EACH1$1,730.00$1,800.00
57Tangent energy absorbing term MASH TL-3 (705-06.20)EACH3$4,040.00$4,000.00
58Thrie beam bridge transition MASH TL-3 (705-06.25)EACH4$4,500.00$4,800.00
59Guardrail removed (706-01)LF142$4.60$5.00
60Radius rail (706-06.03)LF38$46.00$50.00
61Rounded end element (706-10.26)EACH1$577.00$650.00
62Markers (concrete R.O.W. posts) (708-02.01)EACH10$695.00$380.00
63Machined rip-rap (class A-3) (709-05.05)TON50$139.00$145.00
64Machined rip-rap (class B) (709-05.08)TON28$144.00$95.00
65Machined rip-rap (class C) (709-05.09)TON1,335$92.00$110.00
66Traffic control (712-01)LS1$95,000$100,000
67Portable barrier rail, reduced deflection (MASH TL-3) (712-02.12)LF465$125.00$190.00
68Temporary work zone crash cushion (MASH TL-3) (712-02.60)EACH6$5,740.00$11,000
69Flexible drums (channelizing) (712-04.01)EACH100$44.50$50.00
70Barrier rail delineator (712-04.50)EACH10$39.00$38.00
71Warning lights (type A) (712-05.01)EACH50$39.00$33.00
72Signs (construction) (712-06)SF1,486$15.00$15.00
73Temporary barricades (type III) (712-07.03)LF77$30.00$22.00
74Removable pavement marking (8" barrier line) (712-09.02)LF1,406$4.55$4.00
75Removable pavement marking (stop line) (712-09.04)LF48$23.00$25.00
76Removable pavement marking (6" line) (712-09.08)LF840$3.70$3.80
77Removable black-out tape (6") (712-09.30)LF1,500$3.70$3.90
78Class A concrete (foundation for sign supports) (713-01.01)CY2$875.00$800.00
79Steel bar reinforcement(foundation for sign supports) (713-01.02)LB225$4.00$4.00
80Sign post delineation enhancement (713-02.21)LF6$9.10$8.00
81Perforated/knockout square tube post (713-11.02)LB1,257$5.70$6.00
82Square tube sign support (713-11.05)LB233$9.10$8.00
83P post slip base (713-11.21)EACH9$739.00$700.00
84Flat sheet aluminum signs (0.080" thick) (713-13.02)SF140$15.00$18.00
85Flat sheet aluminum signs (0.100" thick) (713-13.03)SF45$16.00$20.00
86Removal of signs, posts and footings (713-15)LS1$2,500.00$1,200.00
87Changeable message sign unit (713-16.01)EACH2$10,400$11,000
88Plastic pavement marking (stop line) (716-02.05)LF31$17.00$20.00
89Painted pavement marking (6" line) (716-05.20)LM0.80$2,845.00$3,300.00
90Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM0.80$8,550.00$10,000
91Mobilization (717-01)LS1$425,000$600,000
92Temporary traffic signal system (730-40.02)LS1$100,600$170,000
93Geogrid reinforcement type 2 (740-07.04)SY800$6.30$12.00
94Geotextile (type III)(erosion control) (740-10.03)SY875$7.30$10.00
95Geotextile (type IV)(stabilization) (740-10.04)SY1,105$7.50$14.00
96Temporary sediment tube 12IN (740-11.02)LF425$4.50$12.00
97Temporary seeding (with mulch) (801-01.07)UNIT8$85.50$135.00
98Natve seed MX final stablizatn of slopes (801-01.38)UNIT8$114.00$230.00
99Seeding (without mulch) (801-02)UNIT4$91.00$100.00
100Water (seeding & sodding) (801-03)MG5$79.50$300.00
101Sodding (new sod) (803-01)SY472$11.50$18.00
102Erosion control blanket (type II) (805-12.02)SY451$2.85$5.00
103Project mowing (806-02.03)CYCL6$2,670.00$6,000.00
104Removal of asbestos (202-01.02)LS1$35,000$25,000
105Removal of structures (EX. BR. no. 86-SR107-05.22) (202-04.01)LS1$375,000$300,000
106Dry excavation (bridges) (204-02.01)CY176$86.00$72.00
107Granular backfill (bridges) (303-01.02)TON30$130.00$100.00
108Pavement @ bridge ends (604-03.04)SY230$754.00$520.00
109Bridge deck grooving (mechanical) (604-05.31)SY776$5.50$12.00
110Conc parapet single slope (STD-1-1SS) (620-05.01)LF289$298.00$320.00
1116" perforated pipe with vertical drain system (710-09.01)LF124$100.00$85.00
1126" pipe underdrain (710-09.02)LF28$87.00$85.00
113Wet excavation (bridges) (204-03.01)CY94$110.00
114Foundation preparation(PR no. 1 ,sta. 210+80.00) (204-10.01)LS1$30,000
115Core drilling for piles(soil) (204-15)LF904$700.00
116Epoxy coated reinforcing steel (604-02.03)LB48,378$1.80
117Class A concrete (bridges) (604-03.01)CY154$1,600.00
118Steel bar reinforcement (bridges) (604-03.02)LB26,409$2.40
119Class D concrete (bridge deck) (604-03.09)CY155$1,800.00
120Applied texture finish (new structures) (604-04.01)SY582$25.00
121Steel piles (12 inch) (606-03.03)LF1,176$250.00
122Pile tips (steel piles, 12 inch) (606-03.06)EACH40$280.00
123Prestressed concrete box beam (33" X 36") (615-02.05)LF578$650.00
124Core drilling for piles(soil) (204-15)LF585$725.00
125Steel structures (35-inch web, welded plate girder) (602-04.01)LS1$950,000
126Bearing device (abutments) (602-10.60)EACH10$3,300.00
127Epoxy coated reinforcing steel (604-02.03)LB37,373$3.60
128Class A concrete (bridges) (604-03.01)CY50$3,100.00
129Steel bar reinforcement (bridges) (604-03.02)LB9,934$3.40
130Class D concrete (bridge deck) (604-03.09)CY196$1,670.00
131Applied texture finish (new structures) (604-04.01)SY351$48.00
132Steel piles (12 inch) (606-03.03)LF612$200.00
133Pile tips (steel piles, 12 inch) (606-03.06)EACH18$400.00
134Removal of asphalt pavement (202-03.03)CY160$86.00$65.00
135Erosion control (209-99.91)LS1$33,000$15,000
136Saw cutting asphalt pavement (407-20.05)LF855$15.50$13.00
137Pole 45FT class 2 metal (790-04.07)EACH5$4,600.00$6,000.00
138Pole 50FT class 2 wood (790-05.02)EACH1$3,300.00$4,300.00
139Pole 50FT class 2 metal (790-05.06)EACH2$7,000.00$9,000.00
140Pole 55 FT class 2 metal (790-06.06)EACH1$9,500.00$12,000
141Pole 60FT class H5 metal (790-07.18)EACH1$16,200$21,000
142Pole(35FT class 4 metal) (790-20.01)EACH2$12,300$16,000
143Pole(55FT class H5 metal) (790-20.08)EACH1$16,200$21,000
144Top existing pole (790-20.30)EACH13$84.50$95.00
1451PH primary tap 15KV (790-21.09)EACH1$508.00$590.00
1461PH crossarm deadend 15KV (790-21.11)EACH1$774.00$900.00
1471PH crossarm dde 15KV (790-21.12)EACH1$774.00$900.00
1483PH crossarm DBL 15KV (790-25.06)EACH2$2,800.00$3,500.00
1493PH crossarm DBL 10FT prim sup 15KV (790-25.12)EACH4$2,800.00$3,500.00
1503PH crossarm deadend SGL 15KV (790-25.21)EACH1$1,800.00$2,200.00
1513PH crossarm dde 15KV (790-25.23)EACH4$3,700.00$4,700.00
152Service assembly-pole type (790-31.02)EACH9$229.00$260.00
153Service conductor 6 AL duplex (790-31.04)LF61$1.50$2.00
154Service conductor 2 AL triplex (790-31.11)LF549$4.40$5.00
155Down guy - through bolt ST PL (790-32.03)EACH14$479.00$550.00
156OH guy - through bolt type (790-32.07)EACH7$602.00$680.00
157Guy guard (790-32.23)EACH10$37.50$43.00
158Plate type anchor 10,000LB-12,000LB (790-33.06)EACH2$895.00$1,000.00
159Screw type anchor 15,000LB (790-33.25)EACH4$895.00$1,000.00
160Screw type anchor 28,000LB (790-33.26)EACH9$1,150.00$1,450.00
161Screw type anchor 32,000LB (790-33.27)EACH3$1,160.00$1,460.00
162Transfer - light assembly (790-36.10)EACH2$404.00$450.00
163Transfer existing 1PH transformer/recloser (790-36.11)EACH7$1,020.00$1,300.00
164Transfer street light (790-36.13)EACH1$340.00$440.00
165Transfer conductor (790-36.14)EACH52$310.00$400.00
166Transfer framing/associated apparatus (790-36.15)EACH16$410.00$520.00
167OH cond 4 7/1 acsr swanate (790-40.01)LF160$2.80$3.00
168OH cond 1/0 6/1 acsr raven (790-40.03)LF2,208$3.00$3.50
169OH cond 4/0 6/1 acsr penguin (790-40.06)LF6,624$3.10$4.00
170UG sec cond 1/0 AL TPLX (790-41.46)LF200$4.40$5.50
1712IN dia PVC pipe (790-42.08)LF230$22.00$28.00
1722 duct bank @ 36IN-48IN depth (790-42.17)LF130$80.00$100.00
173Secondary pullbox large (790-43.46)EACH2$3,300.00$4,200.00
174Secondary riser W/ 2IN conduit (790-43.50)EACH2$2,300.00$2,900.00
175Pole ground rod type (790-68.01)EACH13$520.00$680.00
176Miscellaneous assemblies (790-68.10)EACH25$400.00$500.00
177Dead end shoe (790-68.11)EACH12$111.00$130.00
178Extension link - epoxy -8FT (790-69.41)EACH2$139.00$160.00
179Street light (70W LED) (790-70.20)EACH2$1,150.00$1,300.00
180Guy factory formed with thimble clevis (790-72.07)EACH9$312.00$350.00
181108-144 fiber(installation only) (790-74.20)LF4,219$0.90$1.00
182288-432 fiber(installation only) (790-74.22)LF2,016$0.90$1.00
183Fiber tangent assembly (790-74.31)EACH10$346.00$400.00
184Fiber deadend assembly (790-74.32)EACH46$200.00$250.00
185Fiber storage double loop (790-74.35)EACH12$200.00$248.00
186Remove wire (790-98.01)LF15,376$1.75$2.00
187Remove poles (790-98.02)EACH13$462.00$540.00
188Remove framing/associated apparatus (790-98.03)EACH192$364.00$420.00
189Tree and brush removal off row (790-98.20)LS1$6,930.00$8,000.00
1906IN steel gas main (791-01.05)LF531$228.00$260.00
1912IN mdpe gas main (791-02.02)LF215$193.00$220.00
192HDD 2IN PE pipe - unconsolidated (791-04.02)LF245$410.00$460.00
193Bore/jack 12IN - steel casing pipe - rock (791-05.21)LF80$1,250.00$1,700.00
194Connect to 2IN EX. PE main (791-06.02)EACH2$7,610.00$8,500.00
195Connect to 6IN EX. STL main (791-06.12)EACH2$23,400$27,000
196Connect to 6IN EX. STL main W/ stopple (791-06.33)EACH2$56,200$64,000
1972IN PE hot tap connection (791-06.51)EACH1$17,000$19,000
1982IN PE gas valve assembly (791-07.01)EACH3$3,280.00$3,800.00
1996IN steel gas valve assembly (791-07.11)EACH2$14,600$17,000
2001IN PE service pipe (791-08.08)LF10$211.00$240.00
2013-wire cathodic protection station (791-09.02)EACH2$2,930.00$3,400.00
202Restore asphalt (791-09.05)SY200$195.00$80.00
203Retire in place 6IN serv cut & plug (791-10.06)EACH2$5,000.00$6,300.00
204Pole 35FT class 5 wood (793-01.08)EACH6$2,500.00$6,000.00
205Anchor 3/4IN (793-01.40)EACH9$725.00$1,100.00
206Guy wire 6.6M or 1/4IN (793-02.07)EACH2$200.00$420.00
207Guy wire 10M or 3/8IN (793-02.08)EACH10$220.00$480.00
208Overhead guy wire (10M) (793-02.93)LF3$620.00$950.00
20925 pair group aerial splice (793-03.01)EACH158$320.00$440.00
2106M strand (793-03.02)LF1,130$3.60$4.00
21110M strand (793-03.03)LF1,750$4.70$5.00
21250 pair cable (793-03.12)LF50$6.60$18.00
213200 paircable (793-03.16)LF905$9.10$25.00
214400 pair cable (793-03.18)LF740$11.00$45.00
215600 pair cable (793-03.19)LF305$13.50$60.00
216Relash/delash cable (793-04.01)LF3,977$6.20$7.00
2172 pair aerial drop (793-04.02)LF1,610$5.10$7.00
218Ready access closure (793-04.06)EACH5$492.00$1,100.00
219Aerial splice closure (793-04.07)EACH5$492.00$1,100.00
220Transfer aerial cable (793-04.08)EACH22$559.09$700.00
221Buried riser guard (793-11.13)EACH4$615.00$700.00
222600 pair UG cable (793-12.08)LF300$13.50$60.00
2232 duct formation @ 36IN depth (793-13.17)LF200$53.50$80.00
224Sand encasement per duct (793-14.01)LF400$6.30$13.00
225Remove aerial cable and wire (793-98.01)LF6,875$3.55$4.00
226Remove poles all sizes (793-98.04)EACH12$820.00$850.00
227Remove anchor (any size) (793-98.08)EACH11$74.50$100.00
2284IN dip restrained joint water line (795-01.01)LF10$1,330.00$280.00
2298IN dip restrained joint water line (795-01.05)LF740$256.00$200.00
23012IN dip restrained joint water line (795-01.09)LF310$437.00$320.00
2312IN PVC casing pipe open cut (795-05.91)LF115$91.00$120.00
232Connect to 6IN water line (795-06.04)EACH1$2,440.00$6,800.00
233Cut and cap 4IN water line (795-06.32)EACH2$2,400.00$350.00
2344IN X 4IN tapping sleeve and valve (795-07.01)EACH2$7,680.00$10,000
23512IN X 12IN tapping sleeve and valve (795-07.15)EACH2$16,100$25,000
236Insertion valve (4IN) (795-07.30)EACH1$18,300$3,200.00
237Insertion valve (12IN) (795-07.34)EACH2$26,700$9,000.00
2388IN gate valve assembly (795-08.05)EACH2$6,260.00$5,000.00
239Relocate/reconnect service assembly (795-09.09)EACH3$2,800.00$2,700.00
240Sample tap (795-09.10)EACH1$2,110.00$16,000
241TI of 2IN HDPE casing for service pipe-uncon (795-09.24)LF155$276.00$220.00
2423/4IN copper service pipe (795-09.28)LF270$55.50$220.00
2432IN blow-off assembly (795-10.31)EACH1$5,000.00$3,200.00
244Blow-off assembly (795-11.01)EACH1$6,130.00$4,400.00
245Retire in place existing water main (795-11.12)LF1,111$32.50$15.00
246Remove exisitng valve (795-12.07)EACH2$1,120.00$800.00
247Creek crossing (#1) (795-13.05)LS1$123,100$70,000
248Reconnect service assembly (795-20.01)EACH2$1,190.00$1,100.00
TDOT contract CNZ903: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of August 15, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy