TDOT contract CN261015 bid tabulation
The grading, drainage, construction of a concrete box bridge, and paving on a s.i.a. route from u.s. 441 (s.r. 71) to sawmill road, serving norris industrial park. Let by Tennessee DOT on March 20, 2026, Anderson County. 5 bids received; low bid $4,422,359 by Whaley Construction, LLC.
- Owner
- Tennessee DOT
- Letting
- 20 MAR 2026
- Pay items
- 93
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Whaley Construction, LLC | $4,422,359 | Low |
| 2 | Charles Blalock & Sons, Inc. | $4,769,083 | +8.0% |
| 3 | Southern Constructors, Inc. | $5,378,616 | +22% |
| 4 | Adams Contracting, LLC | $5,623,703 | +27% |
| 5 | King General Contractors, Inc. | $6,672,968 | +51% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Whaley Construction, LLC | 2. Charles Blalock & Sons, Inc. | 3. Southern Constructors, Inc. | 4. Adams Contracting, LLC | 5. King General Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $28,063 | $30,000 | $70,000 | $75,000 | $74,142 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $185,000 | $215,000 | $78,000 | $200,000 | $215,685 |
| 3 | Removal of pipe (24" CMP, sta 53+30 sawmill RD.) (202-02.01) | LF | 79 | $62.00 | $70.41 | $70.00 | $25.00 | $107.84 |
| 4 | Removal of pipe (12" CMP, sta 45+47 sawmill RD.) (202-02.02) | LF | 29 | $52.00 | $191.81 | $45.00 | $25.00 | $97.06 |
| 5 | Removal of pipe (12" CMP, sta 52+95 sawmill RD.) (202-02.03) | LF | 21 | $58.00 | $264.88 | $35.00 | $25.00 | $97.06 |
| 6 | Road & drainage excavation (unclassified) (203-01) | CY | 32,348 | $18.52 | $17.88 | $35.00 | $25.00 | $36.40 |
| 7 | Borrow excavation (graded solid rock) (203-02.01) | TON | 6,330 | $46.89 | $40.00 | $47.00 | $45.00 | $70.10 |
| 8 | Borrow excavation (unclassified) (203-03) | CY | 14,765 | $28.25 | $16.00 | $32.00 | $60.00 | $53.92 |
| 9 | Placing and spreading topsoil (203-04) | CY | 2,184 | $12.23 | $14.89 | $65.00 | $20.00 | $24.26 |
| 10 | Water (203-06) | MG | 373 | $65.00 | $11.41 | $200.00 | $25.00 | $53.92 |
| 11 | Furnishing & spreading topsoil (203-07) | CY | 175.98 | $45.00 | $89.07 | $105.00 | $90.00 | $99.75 |
| 12 | Channel excavation (unclassified) (203-08) | CY | 100 | $55.50 | $101.18 | $65.00 | $75.00 | $53.92 |
| 13 | Channel substrate (203-20.01) | CY | 165 | $150.00 | $125.01 | $105.00 | $85.00 | $53.92 |
| 14 | Culvert excavation (unclassified) (204-01) | CY | 335 | $61.19 | $88.73 | $65.00 | $75.00 | $53.92 |
| 15 | Foundation fill material (204-08) | CY | 55 | $100.91 | $500.18 | $130.00 | $90.00 | $110.54 |
| 16 | Brooming & degrassing shoulders (208-01.05) | LM | 0.40 | $3,251.00 | $15,489 | $2,000.00 | $2,500.00 | $4,044.10 |
| 17 | 18" temporary slope drain (209-02.07) | LF | 136 | $32.00 | $38.50 | $55.00 | $55.00 | $74.14 |
| 18 | Stream mitigation-coconut fiber rolls (209-03.31) | LF | 593 | $20.35 | $11.00 | $28.00 | $22.00 | $21.57 |
| 19 | Sediment removal (209-05) | CY | 165 | $5.00 | $15.76 | $55.00 | $10.00 | $13.48 |
| 20 | Temporary silt fence (with backing) (209-08.02) | LF | 2,590 | $5.28 | $4.95 | $6.50 | $5.25 | $6.74 |
| 21 | Temporary silt fence (without backing) (209-08.03) | LF | 1,180 | $3.08 | $2.20 | $4.00 | $3.00 | $5.39 |
| 22 | Rock check dam (209-08.07) | EACH | 31 | $650.00 | $660.00 | $900.00 | $800.00 | $700.98 |
| 23 | Enhanced rock check dam (209-08.08) | EACH | 21 | $750.00 | $1,100.00 | $1,400.00 | $1,300.00 | $727.94 |
| 24 | Sediment filter bag (15' X 15') (209-09.03) | EACH | 4 | $2,550.00 | $1,692.84 | $1,000.00 | $1,000.00 | $943.62 |
| 25 | Temporary diversion channel (209-65.03) | LF | 818 | $101.47 | $102.68 | $150.00 | $90.00 | $80.88 |
| 26 | Temporary in stream diversion (209-65.04) | LF | 170 | $152.23 | $209.58 | $260.00 | $175.00 | $134.80 |
| 27 | Mineral aggregate, type A base, grading D (303-01) | TON | 4,222 | $46.20 | $46.20 | $52.00 | $50.00 | $62.01 |
| 28 | Granular backfill (roadway) (303-01.01) | TON | 1,635 | $52.00 | $63.81 | $60.00 | $50.00 | $99.75 |
| 29 | Mineral aggregate (size 57) (303-10.01) | TON | 116 | $51.85 | $60.27 | $65.00 | $60.00 | $107.84 |
| 30 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01) | TON | 789 | $136.50 | $151.80 | $145.00 | $142.00 | $188.72 |
| 31 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 517 | $150.15 | $162.80 | $160.00 | $156.00 | $202.20 |
| 32 | Bituminous material for prime coat (PC) (402-01) | TON | 8 | $1,018.50 | $1,441.00 | $1,000.00 | $1,060.00 | $1,765.92 |
| 33 | Aggregate for cover material (PC) (402-02) | TON | 24 | $154.35 | $85.80 | $150.00 | $160.00 | $107.84 |
| 34 | Bituminous material for tack coat (TC) (403-01) | TON | 5 | $932.40 | $1,111.00 | $900.00 | $965.00 | $1,361.51 |
| 35 | Acs mix(PG64-22) grading D (411-01.10) | TON | 637 | $168.00 | $184.80 | $180.00 | $174.00 | $229.17 |
| 36 | Cold planing bituminous pavement (415-01.01) | TON | 188 | $63.00 | $85.80 | $68.00 | $65.00 | $107.84 |
| 37 | Class A concrete (roadway) (604-01.01) | CY | 277 | $1,335.56 | $2,006.31 | $1,400.00 | $1,475.00 | $1,765.92 |
| 38 | Steel bar reinforcement (roadway) (604-01.02) | LB | 41,184 | $2.63 | $3.37 | $1.75 | $1.75 | $4.72 |
| 39 | 24" concrete pipe culvert (class III) (607-05.02) | LF | 132 | $158.25 | $205.15 | $190.00 | $135.00 | $118.63 |
| 40 | 18" pipe culvert (side drain) (607-39.02) | LF | 80 | $98.00 | $104.84 | $140.00 | $100.00 | $101.10 |
| 41 | Class A concrete (pipe endwalls) (611-07.01) | CY | 6 | $2,291.67 | $3,293.43 | $900.00 | $2,350.00 | $2,453.42 |
| 42 | Steel bar reinforcement (pipe endwalls) (611-07.02) | LB | 210 | $5.14 | $9.25 | $7.00 | $5.00 | $5.39 |
| 43 | 18IN endwall (side drain) (611-07.31) | EACH | 3 | $7,120.00 | $8,343.61 | $4,600.00 | $4,800.00 | $9,436.22 |
| 44 | 24IN endwall (side drain) (611-07.32) | EACH | 1 | $8,010.00 | $10,445 | $6,700.00 | $6,400.00 | $11,189 |
| 45 | 24IN endwall (cross drain) 4:1 (611-07.58) | EACH | 1 | $4,376.00 | $5,027.81 | $3,400.00 | $3,000.00 | $7,953.39 |
| 46 | Catch basin, 60IN round,> 4FT-8FT depth (611-60.10) | EACH | 2 | $7,452.00 | $6,859.47 | $9,500.00 | $8,000.00 | $8,492.60 |
| 47 | Manhole structure, 48IN round,> 4FT-8FT depth (611-62.01) | EACH | 1 | $7,356.00 | $5,753.03 | $15,000 | $6,340.00 | $5,122.52 |
| 48 | 24" temporary drainage pipe (621-03.03) | LF | 275 | $119.00 | $114.29 | $48.00 | $60.00 | $66.05 |
| 49 | Metal beam guard fence (705-01.04) | LF | 54 | $83.60 | $83.60 | $84.00 | $100.00 | $121.32 |
| 50 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 1,931 | $27.50 | $27.50 | $27.00 | $32.00 | $37.74 |
| 51 | GR terminal (in-inline) MASH TL-3 (705-06.11) | EACH | 7 | $1,430.00 | $1,430.00 | $1,400.00 | $1,450.00 | $2,426.46 |
| 52 | GR terminal (energy absorbing) MASH TL-2 (705-06.30) | EACH | 3 | $2,970.00 | $2,970.00 | $3,000.00 | $3,500.00 | $4,044.10 |
| 53 | Radius rail (706-06.03) | LF | 329 | $36.30 | $36.30 | $38.00 | $37.00 | $60.66 |
| 54 | Rounded end element (706-10.26) | EACH | 7 | $198.00 | $198.00 | $200.00 | $185.00 | $471.81 |
| 55 | High-visibility construction fence (707-08.11) | LF | 678 | $3.41 | $2.04 | $3.00 | $2.60 | $4.38 |
| 56 | Machined rip-rap (class A-3) (709-05.05) | TON | 150 | $68.23 | $67.60 | $75.00 | $65.00 | $110.54 |
| 57 | Machined rip-rap (class A-1) (709-05.06) | TON | 1,218 | $53.60 | $67.60 | $72.00 | $70.00 | $114.58 |
| 58 | Machined rip-rap (class B) (709-05.08) | TON | 55.50 | $52.12 | $67.60 | $64.00 | $75.00 | $114.58 |
| 59 | Machined rip-rap (class C) (709-05.09) | TON | 345 | $51.27 | $67.60 | $60.00 | $90.00 | $114.58 |
| 60 | Machined rip-rap (grouted) (709-05.10) | CY | 329 | $173.26 | $147.60 | $310.00 | $225.00 | $310.05 |
| 61 | Traffic control (712-01) | LS | 1 | $98,550 | $35,000 | $30,000 | $85,000 | $47,181 |
| 62 | Portable barrier rail, reduced deflection (MASH TL-3) (712-02.12) | LF | 400 | $152.00 | $201.28 | $130.00 | $90.00 | $87.62 |
| 63 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 6 | $7,560.00 | $6,050.00 | $8,000.00 | $8,200.00 | $9,705.83 |
| 64 | Flexible drums (channelizing) (712-04.01) | EACH | 156 | $43.58 | $46.11 | $50.00 | $45.00 | $55.94 |
| 65 | Barrier rail delineator (712-04.50) | EACH | 20 | $5.25 | $5.56 | $30.00 | $5.25 | $6.74 |
| 66 | Warning lights (type A) (712-05.01) | EACH | 79 | $27.30 | $28.89 | $30.00 | $27.00 | $35.05 |
| 67 | Signs (construction) (712-06) | SF | 1,626.88 | $7.62 | $8.06 | $15.00 | $8.00 | $9.77 |
| 68 | Temporary barricades (type III) (712-07.03) | LF | 216 | $15.40 | $15.56 | $18.00 | $15.00 | $24.26 |
| 69 | Removable pavement marking (stop line) (712-09.04) | LF | 21 | $26.40 | $26.40 | $15.00 | $26.00 | $40.44 |
| 70 | Removable pavement marking (6" line) (712-09.08) | LF | 1 | $4.95 | $4.95 | $3.50 | $4.75 | $67.40 |
| 71 | Steel hollow square post (breakaway) sign supports (713-05) | LB | 458 | $1.10 | $1.11 | $2.00 | $1.10 | $1.35 |
| 72 | Perforated/knockout square tube post (713-11.02) | LB | 460 | $11.03 | $11.67 | $13.00 | $11.00 | $14.15 |
| 73 | P post slip base (713-11.21) | EACH | 11 | $577.50 | $611.11 | $650.00 | $575.00 | $741.42 |
| 74 | Flat sheet aluminum signs (0.080" thick) (713-13.02) | SF | 94 | $13.65 | $14.44 | $15.00 | $14.00 | $17.52 |
| 75 | Plastic pavement marking (stop line) (716-02.05) | LF | 50 | $16.50 | $16.50 | $25.00 | $16.00 | $43.14 |
| 76 | Plastic pavement marking (transverse shoulder) (716-04.04) | LF | 235 | $6.33 | $6.33 | $18.00 | $6.00 | $33.70 |
| 77 | Painted pavement marking (6" line) (716-05.20) | LM | 0.40 | $2,200.00 | $2,200.00 | $3,300.00 | $2,200.00 | $3,774.49 |
| 78 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 0.90 | $9,350.00 | $9,350.00 | $12,000 | $9,000.00 | $6,066.14 |
| 79 | Mobilization (717-01) | LS | 1 | $204,605 | $266,000 | $300,000 | $550,000 | $323,528 |
| 80 | Temporary traffic signal system (730-40.02) | LS | 1 | $66,885 | $80,000 | $80,000 | $65,000 | $111,887 |
| 81 | Geotextile (type III)(erosion control) (740-10.03) | SY | 3,395 | $5.10 | $2.59 | $8.00 | $2.00 | $5.39 |
| 82 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 4,109 | $4.95 | $4.98 | $10.00 | $2.50 | $6.07 |
| 83 | Temporary sediment tube 12IN (740-11.02) | LF | 1,426 | $3.85 | $3.30 | $5.00 | $4.50 | $8.09 |
| 84 | Temporary seeding (with mulch) (801-01.07) | UNIT | 100 | $41.80 | $33.00 | $50.00 | $42.00 | $60.66 |
| 85 | Natve seed MX final stablizatn of slopes (801-01.38) | UNIT | 42 | $132.00 | $82.50 | $125.00 | $105.00 | $87.62 |
| 86 | Seeding (without mulch) (801-02) | UNIT | 108 | $44.00 | $24.75 | $45.00 | $38.00 | $80.88 |
| 87 | Water (seeding & sodding) (801-03) | MG | 10 | $110.00 | $137.50 | $120.00 | $105.00 | $188.72 |
| 88 | Erosion control blanket (type II) (805-12.02) | SY | 10,869 | $1.10 | $1.38 | $1.50 | $1.25 | $4.04 |
| 89 | Culvert excavation (unclassified) (204-01) | CY | 630 | $58.95 | $80.94 | $65.00 | $75.00 | $49.88 |
| 90 | Foundation fill material (204-08) | CY | 60 | $102.67 | $120.53 | $130.00 | $90.00 | $242.65 |
| 91 | Granular backfill (roadway) (303-01.01) | TON | 656 | $59.44 | $74.86 | $60.00 | $50.00 | $102.45 |
| 92 | Class A concrete (box bridges) (604-02.01) | CY | 242 | $1,336.60 | $2,061.66 | $1,400.00 | $1,950.00 | $1,765.92 |
| 93 | Steel bar reinforcement (box bridges) (604-02.02) | LB | 44,390 | $2.64 | $2.51 | $1.70 | $1.75 | $4.72 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of March 20, 2026. Compiled by Mirage Metrics.