TDOT contract CN261015 bid tabulation

The grading, drainage, construction of a concrete box bridge, and paving on a s.i.a. route from u.s. 441 (s.r. 71) to sawmill road, serving norris industrial park. Let by Tennessee DOT on March 20, 2026, Anderson County. 5 bids received; low bid $4,422,359 by Whaley Construction, LLC.

Owner
Tennessee DOT
Letting
20 MAR 2026
Pay items
93
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Whaley Construction, LLC$4,422,359Low
2Charles Blalock & Sons, Inc.$4,769,083+8.0%
3Southern Constructors, Inc.$5,378,616+22%
4Adams Contracting, LLC$5,623,703+27%
5King General Contractors, Inc.$6,672,968+51%
TDOT contract CN261015: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Whaley Construction, LLC2. Charles Blalock & Sons, Inc.3. Southern Constructors, Inc.4. Adams Contracting, LLC5. King General Contractors, Inc.
1Construction stakes, lines and grades (105-01)LS1$28,063$30,000$70,000$75,000$74,142
2Clearing and grubbing (201-01)LS1$185,000$215,000$78,000$200,000$215,685
3Removal of pipe (24" CMP, sta 53+30 sawmill RD.) (202-02.01)LF79$62.00$70.41$70.00$25.00$107.84
4Removal of pipe (12" CMP, sta 45+47 sawmill RD.) (202-02.02)LF29$52.00$191.81$45.00$25.00$97.06
5Removal of pipe (12" CMP, sta 52+95 sawmill RD.) (202-02.03)LF21$58.00$264.88$35.00$25.00$97.06
6Road & drainage excavation (unclassified) (203-01)CY32,348$18.52$17.88$35.00$25.00$36.40
7Borrow excavation (graded solid rock) (203-02.01)TON6,330$46.89$40.00$47.00$45.00$70.10
8Borrow excavation (unclassified) (203-03)CY14,765$28.25$16.00$32.00$60.00$53.92
9Placing and spreading topsoil (203-04)CY2,184$12.23$14.89$65.00$20.00$24.26
10Water (203-06)MG373$65.00$11.41$200.00$25.00$53.92
11Furnishing & spreading topsoil (203-07)CY175.98$45.00$89.07$105.00$90.00$99.75
12Channel excavation (unclassified) (203-08)CY100$55.50$101.18$65.00$75.00$53.92
13Channel substrate (203-20.01)CY165$150.00$125.01$105.00$85.00$53.92
14Culvert excavation (unclassified) (204-01)CY335$61.19$88.73$65.00$75.00$53.92
15Foundation fill material (204-08)CY55$100.91$500.18$130.00$90.00$110.54
16Brooming & degrassing shoulders (208-01.05)LM0.40$3,251.00$15,489$2,000.00$2,500.00$4,044.10
1718" temporary slope drain (209-02.07)LF136$32.00$38.50$55.00$55.00$74.14
18Stream mitigation-coconut fiber rolls (209-03.31)LF593$20.35$11.00$28.00$22.00$21.57
19Sediment removal (209-05)CY165$5.00$15.76$55.00$10.00$13.48
20Temporary silt fence (with backing) (209-08.02)LF2,590$5.28$4.95$6.50$5.25$6.74
21Temporary silt fence (without backing) (209-08.03)LF1,180$3.08$2.20$4.00$3.00$5.39
22Rock check dam (209-08.07)EACH31$650.00$660.00$900.00$800.00$700.98
23Enhanced rock check dam (209-08.08)EACH21$750.00$1,100.00$1,400.00$1,300.00$727.94
24Sediment filter bag (15' X 15') (209-09.03)EACH4$2,550.00$1,692.84$1,000.00$1,000.00$943.62
25Temporary diversion channel (209-65.03)LF818$101.47$102.68$150.00$90.00$80.88
26Temporary in stream diversion (209-65.04)LF170$152.23$209.58$260.00$175.00$134.80
27Mineral aggregate, type A base, grading D (303-01)TON4,222$46.20$46.20$52.00$50.00$62.01
28Granular backfill (roadway) (303-01.01)TON1,635$52.00$63.81$60.00$50.00$99.75
29Mineral aggregate (size 57) (303-10.01)TON116$51.85$60.27$65.00$60.00$107.84
30Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01)TON789$136.50$151.80$145.00$142.00$188.72
31Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON517$150.15$162.80$160.00$156.00$202.20
32Bituminous material for prime coat (PC) (402-01)TON8$1,018.50$1,441.00$1,000.00$1,060.00$1,765.92
33Aggregate for cover material (PC) (402-02)TON24$154.35$85.80$150.00$160.00$107.84
34Bituminous material for tack coat (TC) (403-01)TON5$932.40$1,111.00$900.00$965.00$1,361.51
35Acs mix(PG64-22) grading D (411-01.10)TON637$168.00$184.80$180.00$174.00$229.17
36Cold planing bituminous pavement (415-01.01)TON188$63.00$85.80$68.00$65.00$107.84
37Class A concrete (roadway) (604-01.01)CY277$1,335.56$2,006.31$1,400.00$1,475.00$1,765.92
38Steel bar reinforcement (roadway) (604-01.02)LB41,184$2.63$3.37$1.75$1.75$4.72
3924" concrete pipe culvert (class III) (607-05.02)LF132$158.25$205.15$190.00$135.00$118.63
4018" pipe culvert (side drain) (607-39.02)LF80$98.00$104.84$140.00$100.00$101.10
41Class A concrete (pipe endwalls) (611-07.01)CY6$2,291.67$3,293.43$900.00$2,350.00$2,453.42
42Steel bar reinforcement (pipe endwalls) (611-07.02)LB210$5.14$9.25$7.00$5.00$5.39
4318IN endwall (side drain) (611-07.31)EACH3$7,120.00$8,343.61$4,600.00$4,800.00$9,436.22
4424IN endwall (side drain) (611-07.32)EACH1$8,010.00$10,445$6,700.00$6,400.00$11,189
4524IN endwall (cross drain) 4:1 (611-07.58)EACH1$4,376.00$5,027.81$3,400.00$3,000.00$7,953.39
46Catch basin, 60IN round,> 4FT-8FT depth (611-60.10)EACH2$7,452.00$6,859.47$9,500.00$8,000.00$8,492.60
47Manhole structure, 48IN round,> 4FT-8FT depth (611-62.01)EACH1$7,356.00$5,753.03$15,000$6,340.00$5,122.52
4824" temporary drainage pipe (621-03.03)LF275$119.00$114.29$48.00$60.00$66.05
49Metal beam guard fence (705-01.04)LF54$83.60$83.60$84.00$100.00$121.32
50W beam GR (type 2) MASH TL-3 (705-06.01)LF1,931$27.50$27.50$27.00$32.00$37.74
51GR terminal (in-inline) MASH TL-3 (705-06.11)EACH7$1,430.00$1,430.00$1,400.00$1,450.00$2,426.46
52GR terminal (energy absorbing) MASH TL-2 (705-06.30)EACH3$2,970.00$2,970.00$3,000.00$3,500.00$4,044.10
53Radius rail (706-06.03)LF329$36.30$36.30$38.00$37.00$60.66
54Rounded end element (706-10.26)EACH7$198.00$198.00$200.00$185.00$471.81
55High-visibility construction fence (707-08.11)LF678$3.41$2.04$3.00$2.60$4.38
56Machined rip-rap (class A-3) (709-05.05)TON150$68.23$67.60$75.00$65.00$110.54
57Machined rip-rap (class A-1) (709-05.06)TON1,218$53.60$67.60$72.00$70.00$114.58
58Machined rip-rap (class B) (709-05.08)TON55.50$52.12$67.60$64.00$75.00$114.58
59Machined rip-rap (class C) (709-05.09)TON345$51.27$67.60$60.00$90.00$114.58
60Machined rip-rap (grouted) (709-05.10)CY329$173.26$147.60$310.00$225.00$310.05
61Traffic control (712-01)LS1$98,550$35,000$30,000$85,000$47,181
62Portable barrier rail, reduced deflection (MASH TL-3) (712-02.12)LF400$152.00$201.28$130.00$90.00$87.62
63Temporary work zone crash cushion (MASH TL-3) (712-02.60)EACH6$7,560.00$6,050.00$8,000.00$8,200.00$9,705.83
64Flexible drums (channelizing) (712-04.01)EACH156$43.58$46.11$50.00$45.00$55.94
65Barrier rail delineator (712-04.50)EACH20$5.25$5.56$30.00$5.25$6.74
66Warning lights (type A) (712-05.01)EACH79$27.30$28.89$30.00$27.00$35.05
67Signs (construction) (712-06)SF1,626.88$7.62$8.06$15.00$8.00$9.77
68Temporary barricades (type III) (712-07.03)LF216$15.40$15.56$18.00$15.00$24.26
69Removable pavement marking (stop line) (712-09.04)LF21$26.40$26.40$15.00$26.00$40.44
70Removable pavement marking (6" line) (712-09.08)LF1$4.95$4.95$3.50$4.75$67.40
71Steel hollow square post (breakaway) sign supports (713-05)LB458$1.10$1.11$2.00$1.10$1.35
72Perforated/knockout square tube post (713-11.02)LB460$11.03$11.67$13.00$11.00$14.15
73P post slip base (713-11.21)EACH11$577.50$611.11$650.00$575.00$741.42
74Flat sheet aluminum signs (0.080" thick) (713-13.02)SF94$13.65$14.44$15.00$14.00$17.52
75Plastic pavement marking (stop line) (716-02.05)LF50$16.50$16.50$25.00$16.00$43.14
76Plastic pavement marking (transverse shoulder) (716-04.04)LF235$6.33$6.33$18.00$6.00$33.70
77Painted pavement marking (6" line) (716-05.20)LM0.40$2,200.00$2,200.00$3,300.00$2,200.00$3,774.49
78Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM0.90$9,350.00$9,350.00$12,000$9,000.00$6,066.14
79Mobilization (717-01)LS1$204,605$266,000$300,000$550,000$323,528
80Temporary traffic signal system (730-40.02)LS1$66,885$80,000$80,000$65,000$111,887
81Geotextile (type III)(erosion control) (740-10.03)SY3,395$5.10$2.59$8.00$2.00$5.39
82Geotextile (type IV)(stabilization) (740-10.04)SY4,109$4.95$4.98$10.00$2.50$6.07
83Temporary sediment tube 12IN (740-11.02)LF1,426$3.85$3.30$5.00$4.50$8.09
84Temporary seeding (with mulch) (801-01.07)UNIT100$41.80$33.00$50.00$42.00$60.66
85Natve seed MX final stablizatn of slopes (801-01.38)UNIT42$132.00$82.50$125.00$105.00$87.62
86Seeding (without mulch) (801-02)UNIT108$44.00$24.75$45.00$38.00$80.88
87Water (seeding & sodding) (801-03)MG10$110.00$137.50$120.00$105.00$188.72
88Erosion control blanket (type II) (805-12.02)SY10,869$1.10$1.38$1.50$1.25$4.04
89Culvert excavation (unclassified) (204-01)CY630$58.95$80.94$65.00$75.00$49.88
90Foundation fill material (204-08)CY60$102.67$120.53$130.00$90.00$242.65
91Granular backfill (roadway) (303-01.01)TON656$59.44$74.86$60.00$50.00$102.45
92Class A concrete (box bridges) (604-02.01)CY242$1,336.60$2,061.66$1,400.00$1,950.00$1,765.92
93Steel bar reinforcement (box bridges) (604-02.02)LB44,390$2.64$2.51$1.70$1.75$4.72
TDOT contract CN261015: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of March 20, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy