TDOT contract CN261064 bid tabulation

The grading, drainage, construction of bridges and a retaining wall, signals, and paving on a s.i.a. route serving eastman chemical company. Let by Tennessee DOT on October 2, 2026, Sullivan County. 1 bid received; low bid $23,131,389 by Summers-Taylor, Inc..

Owner
Tennessee DOT
Letting
02 OCT 2026
Pay items
274
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Summers-Taylor, Inc.$23,131,389Low
TDOT contract CN261064: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Summers-Taylor, Inc.
1Construction stakes, lines and grades (105-01)LS1$194,700
2Clearing and grubbing (201-01)LS1$245,679
3Removal of pipe (see plans sheet 2F1) (202-01.13)LF713$33.71
4Removal of structures and obstructions (202-01.50)EACH16$954.74
5Removal of rigid pavement, sidewalk, etc. (202-03)SY600$11.36
6Removal of curb (existing roundabout) (202-08.10)LF800$8.52
7Removal of curb and gutter (existing roundabout) (202-08.15)LF1,500$5.12
8Road & drainage excavation (unclassified) (203-01)CY88,915$15.45
9Borrow excavation (graded solid rock) (203-02.01)TON42,423$47.08
10Borrow excavation (unclassified) (203-03)CY10,138$16.75
11Placing and spreading topsoil (203-04)CY9,185$28.33
12Water (203-06)MG520$13.76
13Construction of haul road (203-50)LS1$900,000
14Culvert excavation (unclassified) (204-01)CY200$53.98
15Backfill material (flowable fill) (204-08.01)CY125$472.30
16Brooming & degrassing shoulders (208-01.05)LM0.36$11,382
1718" temporary slope drain (209-02.07)LF200$80.99
18Sediment removal (209-05)CY650$40.65
19Temporary silt fence (with backing) (209-08.02)LF19,000$6.52
20Rock check dam (209-08.07)EACH100$740.70
21Enhanced rock check dam (209-08.08)EACH12$1,359.63
22Sediment filter bag (15' X 15') (209-09.03)EACH4$3,358.50
23Catch basin filter assembly(type 6) (209-40.46)EACH53$896.71
24Catch basin filter assembly(type 7) (209-40.47)EACH6$944.85
25Temporary in stream diversion (209-65.04)LF370$65.46
26Mineral aggregate, type A base, grading D (303-01)TON20,000$45.19
27Granular backfill (roadway) (303-01.01)TON900$69.08
28Mineral aggregate (size 57) (303-10.01)TON100$92.15
29Mineral aggregate (size 4) (303-10.07)TON4,551$60.96
30Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01)TON5,000$165.00
31Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON3,800$175.00
32Bituminous material for tack coat (TC) (403-01)TON30$1,350.00
33Acs mix(PG64-22) grading D (411-01.10)TON2,700$199.50
34Cold planing bituminous pavement (415-01.02)SY6,000$12.00
35Portland cement concrete pavement (plain) 8" (501-01.01)SY280$158.22
36Class A concrete (roadway) (604-01.01)CY76$1,878.96
37Steel bar reinforcement (roadway) (604-01.02)LB16,700$0.92
38Retaining wall (R1, sta. 113+18.00 to sta. 118+60.00 RT riverport road) (604-07.01)SF2,200$301.04
3918" concrete pipe culvert (class III) (607-03.02)LF4,447$126.88
4030" concrete pipe culvert (class III) (607-06.02)LF44$220.68
4136" concrete pipe culvert (class III) (607-07.02)LF238$241.91
42Class A concrete (pipe endwalls) (611-07.01)CY20$2,404.94
43Steel bar reinforcement (pipe endwalls) (611-07.02)LB1,200$1.47
4430IN endwall (cross drain) 4:1 (611-07.61)EACH1$11,335
45Catch basins, type 12, 0' - 4' depth (611-12.01)EACH26$6,858.49
46Catch basins, type 12, > 4' - 8' depth (611-12.02)EACH26$7,416.50
47Catch basins, type 12, > 8' - 12' depth (611-12.03)EACH1$11,575
48Catch basins, type 14, > 4' - 8' depth (611-14.02)EACH6$13,239
4972" temporary drainage pipe (621-03.11)LF780$228.77
50Concrete sidewalk (4 ") (701-01.01)SF5,000$15.41
51Concrete curb ramp (retrofit) (701-02.01)SF150$43.92
52Concrete curb ramp (701-02.03)SF1,000$45.69
53Concrete median pavement (701-03)CY30$1,046.71
54Concrete curb (702-01)CY60$767.62
55Concrete combined curb & gutter (702-03)CY1,200$495.70
56Earth pad for type 38 GR end treatment (705-04.09)EACH2$1,266.12
57W beam GR (type 2) MASH TL-3 (705-06.01)LF2,539$35.45
58W beam GR (type 2) MASH TL-3 (long post) (705-06.02)LF395$41.78
59GR terminal (in-inline) MASH TL-3 (705-06.11)EACH2$1,424.39
60Tangent energy absorbing term MASH TL-3 (705-06.20)EACH10$4,463.09
61Thrie beam bridge transition MASH TL-3 (705-06.25)EACH8$3,931.31
62Guardrail removed (706-01)LF590$3.80
63Radius rail (706-06.03)LF100$44.31
64Chain link fence (6 foot) (707-01.11)LF600$36.18
65Gate - chain-link fence-6 foot (tract 18 access control) (707-01.13)EACH2$2,584.46
66Removal of fence (tracts 4 & 18) (707-06.01)LF1,910$12.92
67Removal of gate (tract 4 sta. 54+30 LT.) (707-06.02)EACH1$646.11
68High-visibility construction fence (707-08.11)LF1,910$3.39
69Machined rip-rap (class A-3) (709-05.05)TON101$87.69
70Machined rip-rap (class A-1) (709-05.06)TON130$180.07
71Machined rip-rap (class B) (709-05.08)TON2,359$73.83
72Machined rip-rap (class C) (709-05.09)TON225$79.57
73Traffic control (712-01)LS1$150,000
74Interconnected portable barrier rail (712-02.02)LF3,100$70.00
75Temporary work zone crash cushion (MASH TL-3) (712-02.60)EACH6$20,839
76Flexible drums (channelizing) (712-04.01)EACH200$41.27
77Barrier rail delineator (712-04.50)EACH40$19.42
78Warning lights (type A) (712-05.01)EACH100$38.52
79Signs (construction) (712-06)SF513$11.35
80Temporary barricades (type III) (712-07.03)LF400$13.76
81Removable pavement marking (8" barrier line) (712-09.02)LF1,800$4.75
82Sign post delineation enhancement (713-02.21)LF42$10.03
83"U" section steel posts (713-11.01)LB350$5.01
84Perforated/knockout square tube post (713-11.02)LB1,000$11.91
85Flat sheet aluminum signs (0.080" thick) (713-13.02)SF400$24.13
86Street name sign (rigid 0.100IN thick (713-14.21)SF72$43.87
87Removal of signs, posts and footings (713-15)LS1$2,506.93
88Metal barricade (type III) (713-15.35)EACH4$1,190.79
89Changeable message sign unit (713-16.01)EACH2$11,030
90Signs (R10-12A, (30"X36") (713-16.20)EACH2$313.37
91Remove conductor (714-01.69)LF1,575$1.90
92Jacked or bored conduit (714-03)LF220$206.47
93Direct burial conduit (2" PVC, schedule 40) (714-03.01)LF6,125$17.09
94Direct burial conduit (3" PVC, schedule 40) (714-03.02)LF1,940$23.42
95Pull boxes (type C) (714-05.04)EACH22$1,133.18
96Foundation for light standards - roadway (post top) (714-08.28)EACH23$2,494.26
97Removal of light standard & foundation (714-08.32)EACH5$734.35
98LED luminaires (relocate existing) (714-09.47)EACH1$5,134.13
99Plastic pavement marking(channelization striping) (716-02.04)SY17$37.98
100Plastic pavement marking (stop line) (716-02.05)LF200$14.56
101Plastic pavement marking (turn lane arrow) (716-02.06)EACH14$234.23
102Plastic pavement marking (8" dotted line) (716-02.08)LF740$3.48
103Plastic pavement marking (longitudinal cross-walk) (716-02.09)LF250$37.35
104Plastic pavement marking (straight-turn arrow) (716-04.01)EACH6$265.89
105Plastic pavement marking (yield line) (716-04.12)SF80$24.69
106Painted pavement marking (6" line) (716-05.20)LM3$2,215.71
107Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM8$8,166.50
108Mobilization (717-01)LS1$850,000
109Signal head assembly (130 with backplate) (730-02.09)EACH9$1,880.19
110Signal head assembly (140 A4F with backplate) (730-02.59)EACH2$2,456.28
111Install pull box (type B) (730-03.21)EACH4$1,525.68
112Electrical service connection (730-05.01)EACH1$10,091
113Signal cable - 5 conductor (730-08.02)LF600$4.56
114Signal cable - 7 conductor (730-08.03)LF1,675$5.57
115Signal cable - 9 conductor (730-08.04)LF150$8.86
116Conduit 2" diameter (directional bore) (730-12.23)LF675$81.03
117Conduit 2" diameter (PVC schedule 80) (730-12.26)LF125$30.39
118Conduit 3" diameter (PVC schedule 80) (730-12.27)LF20$45.58
119Vehicle detector (video) (730-13.02)EACH4$14,244
120Cabinet (TS2, type 1 (base mounted) (730-15.07)EACH1$35,388
121Controller (atc) (730-16.04)EACH1$8,660.28
122Install modem (730-17.01)EACH1$4,836.59
123Pedestal pole (type A) (730-23.28)EACH1$5,229.09
124Cantilever signal support (1 arm @ 30') (730-23.64)EACH1$40,453
125Cantilever signal support (1 arm @ 40') (730-23.80)EACH1$41,149
126Cantilever signal support (1 arm @ 55') (730-25.07)EACH1$52,164
127Cantilever signal support (1 arm @ 60') (730-25.11)EACH1$57,419
128Pedestrian pushbutton post (730-26.06)EACH1$3,196.97
129Countdown ped SGNL head W/audible pushbutton & 15IN sign (730-26.11)EACH4$2,437.29
130Battery back-UP system (730-35.06)EACH1$12,851
131Temporary traffic signal system (730-40.02)LS1$51,378
132Geotextile (type III)(erosion control) (740-10.03)SY8,622$7.75
133Geotextile (type IV)(stabilization) (740-10.04)SY15,541$7.97
134Temporary sediment tube 18IN (740-11.03)LF646$13.77
135Seeding (with mulch) (801-01)UNIT100$76.74
136Temporary seeding (with mulch) (801-01.07)UNIT500$38.37
137Special wetland seed mixture (801-01.36)UNIT6$402.90
138Seeding (without mulch) (801-02)UNIT400$35.17
139Water (seeding & sodding) (801-03)MG100$191.86
140Seed (supplemental application) (801-07)LB300$6.40
141Sodding (new sod) (803-01)SY19,930$7.03
142Turf reinforcement mat (class I) (805-01.01)SY5,000$5.88
143Erosion control blanket (type II) (805-12.02)SY32,000$1.15
144Dry excavation (bridges) (204-02.01)CY381$26.23
145Wet excavation (bridges) (204-03.01)CY201$63.80
146Rock excavation (bridges) (204-04.01)CY52$326.99
147Rock drilling (bridges) (204-05)LF108$59.04
148Foundation preparation(bent no.1, sta. 36+25.00) (204-10.01)LS1$34,711
149Foundation preparation(pier no.1, sta. 73+15.70) (204-10.02)LS1$97,946
150Foundation preparation(bent no.2, sta. 37+05.50) (204-10.03)LS1$66,118
151Foundation preparation(pier no.2, sta. 73+75.70) (204-10.04)LS1$122,763
152Core drilling for piles(rock) (204-14)LF200$672.13
153Granular backfill (bridges) (303-01.02)TON141$102.23
154Epoxy coated reinforcing steel (604-02.03)LB213,888$1.83
155Class A concrete (bridges) (604-03.01)CY694$2,033.29
156Steel bar reinforcement (bridges) (604-03.02)LB120,375$1.97
157Pavement @ bridge ends (604-03.04)SY444$497.45
158Class DS concrete (604-03.32)CY523$1,751.94
159Applied texture finish (new structures) (604-04.01)SY1,813$16.92
160Bridge deck grooving (mechanical) (604-05.31)SY1,767$7.56
161Steel piles (12 inch) (606-03.03)LF500$186.42
162Pile tips (steel piles, 12 inch) (606-03.06)EACH19$189.75
163Deck drains (grate drains type 2) (610-10.45)EACH6$3,434.69
164Prestressed concrete I-beam (type III) (615-01.03)LF868$471.79
165Prestressed concrete box beam (27" X 48") (615-02.10)LF986$630.23
166Standard concrete classic parapet rail (620-05.02)LF823$425.09
1676" perforated pipe with vertical drain system (710-09.01)LF236$40.80
1686" pipe underdrain (710-09.02)LF84$29.55
169Pole 45FT class 2 wood (790-04.02)EACH2$2,665.19
170Pole 45FT class 3 wood (790-04.03)EACH5$2,495.00
171Pole 55FT class 1 wood (790-06.01)EACH4$3,538.82
172Pole 55FT class 2 wood (790-06.02)EACH2$3,381.73
1733PH crossarm 25KV (790-26.01)EACH1$1,646.65
1743PH crossarm DBL SM angle 25KV (790-26.12)EACH4$2,392.55
1753PH crossarm DBL 10FT SM angle 25KV (790-26.14)EACH1$2,808.27
1763PH xarm DBL 10FT LRG cond SM angle 25KV (790-26.15)EACH3$2,862.10
1773PH crossarm dde 25KV (790-26.25)EACH4$3,398.34
1783PH crossarm DBL dde 25KV (790-26.27)EACH2$4,093.64
179Service assembly-pole type (790-31.02)EACH6$238.27
180Service conductor 2 AL triplex (790-31.11)LF78$7.41
181Down guy - through bolt type (790-32.01)EACH13$400.33
182Down guy - insulated (790-32.06)EACH13$519.16
183OH guy - through bolt type (790-32.07)EACH1$739.54
184Guy guard (790-32.23)EACH11$25.57
185Overhead guy light construction - preform (790-32.27)EACH1$715.65
186Screw type anchor 23,000LB (F1-5D-P) (790-33.31)EACH11$807.91
187Transfer - light assembly (790-36.10)EACH1$489.63
188Switch-900A-underslung (three phase) (790-36.21)EACH1$5,655.76
189OH cond 2 7/1 acsr sparate (790-40.02)LF1,370$3.33
190OH cond 1/0 6/1 acsr raven (790-40.03)LF4,110$4.16
191OH cond 4/0 6/1 acsr penguin (790-40.06)LF883$5.64
192OH cond 556.5 19 aac dahlia (790-40.46)LF2,649$9.46
193UG pri cond 4/0 AL 25KV (790-41.16)LF2,121$23.71
1944IN dia PVC pipe (790-42.10)LF3,868$18.57
1954 duct bank @ 36IN-48IN depth (790-42.19)LF1,040$52.66
196Deadbreak elbow 600A 25KV (790-43.29)EACH12$1,237.87
197Primary pullbox (790-43.47)EACH4$10,184
1983PH transformer pad - ground sleeve (790-51.07)EACH1$7,507.11
1991PH fuse cutout xarm mount 25KV (790-61.01)EACH1$946.22
200Pole ground rod type (790-68.01)EACH8$443.97
201SGL phase mounting bracket - fiberglass (790-68.13)EACH1$297.19
202Arm pin (790-69.32)EACH9$238.52
203Remove wire (790-98.01)LF12,384$2.86
204Remove poles (790-98.02)EACH13$761.08
205Remove framing/associated apparatus (790-98.03)EACH68$475.67
206<=2 in PE temp. by-pass for tie-in (791-02.27)LS1$21,936
2074IN HDPE gas main (791-03.04)LF297$94.01
208HDD 2IN PE pipe - rock (791-04.11)LF764$188.02
209HDD 4IN PE pipe - rock (791-04.13)LF66$431.19
210Connect to 2IN EX. PE main (791-06.02)EACH2$4,888.51
211Connect to 4IN EX. PE main (791-06.03)EACH2$6,894.04
2124IN PE gas valve assembly (791-07.02)EACH1$2,506.93
213Retire gas main (791-10.10)LS1$6,016.62
214Anchor 3/4IN (793-01.40)EACH4$814.75
215Guy wire 10M or 3/8IN (793-02.08)EACH9$188.02
216Install guy guard (793-02.99)EACH9$46.38
21725 pair group aerial splice (793-03.01)EACH28$250.69
21810M strand (793-03.03)LF745$4.07
21950 pair cable (793-03.12)LF815$12.53
220Install strand bond (793-03.40)EACH9$37.60
221Relash/delash cable (793-04.01)LF200$5.01
222Ready access closure (793-04.06)EACH6$564.06
223Transfer aerial cable (793-04.08)EACH17$407.38
224Underground splice closure (793-04.12)EACH4$1,880.19
22548 fiber(material only) (793-07.04)LF1,500$1.88
22612-96 fiber(installation only) (793-07.16)LF1,500$5.01
227Fiber optic maintenance loop (793-07.23)EACH4$313.37
228Single fiber optic cable splice (793-07.25)EACH120$94.01
229Fiber(48) aerial pressurized splice closure (793-07.73)EACH2$1,065.45
230Test bare fiber (793-07.99)EACH96$25.07
231Expose existing cable/conduit (all depths) (793-10.20)LF60$125.35
232Buried riser guard (793-11.13)EACH4$376.04
233Composite handhole 5FTX3FTX3FT (793-11.17)EACH2$3,133.66
234Handhole 30INX48IN (793-11.20)EACH2$2,757.62
235Remove handhole (793-11.31)EACH3$501.39
236Rearrangement existing cable (793-12.02)EACH10$2,256.23
237200 pair UG cable (793-12.05)LF1,060$25.07
23825 pair group UG splice (793-13.06)EACH17$250.69
2391 duct formation @ 36IN depth (793-13.12)LF230$50.14
2402 duct formation @ 36IN depth (793-13.17)LF900$62.67
241Sand encasement per duct (793-14.01)LF660$10.03
242Concrete encasement per duct (793-14.02)LF1,370$37.60
243Bridge conduit hanger system (793-14.09)LS1$333,316
2441 1/4IN innerduct (793-14.12)LF2,760$3.76
245Laterally adjust conduit bank (793-14.41)LF60$125.35
246Remove conduit/duct bank from existing cable (793-80.01)LF8$125.35
247Remove aerial cable and wire (793-98.01)LF6,300$2.51
248Remove poles all sizes (793-98.04)EACH10$752.08
249Retire buried facilities in place (793-98.05)LF530$1.88
250Remove anchor (any size) (793-98.08)EACH4$125.35
251Remove down guy (793-98.09)EACH7$94.01
25212IN dip restrained joint water line (795-01.09)LF520$252.63
25316IN dip restrained joint water line (795-01.13)LF320$330.21
254Connect to 12IN water line (795-06.07)EACH2$20,440
255Connect to 16IN water line (795-06.09)EACH2$22,098
256Cut and cap 12IN water line (795-06.37)EACH2$7,211.39
257Cut and cap 16IN water line (795-06.39)EACH2$8,137.13
25812IN gate valve assembly (795-08.09)EACH2$8,157.08
25916IN butterfly valve assembly (795-08.13)EACH2$10,578
260Removal of existing line 4" OD or greater (795-12.35)LF630$65.54
26130IN steel casing pipe open cut method (795-15.10)LF115$552.88
2623IN HDPE force main (797-02.05)LF460$87.23
26318IN dip gravity sewer 12FT-18FT depth (797-05.19)LF233$365.75
26418IN dip gravity sewer >18FT depth (797-05.20)LF125$920.13
2658IN PVC gravity sewer 0FT-6FT depth (797-05.51)LF70$242.84
266Open cut 36IN steel casing pipe (797-06.95)LF310$695.09
26748IN manhole 4FT-6FT depth (797-07.02)EACH2$6,180.42
26860IN manhole 12FT-14FT depth (797-07.17)EACH1$14,824
26960IN manhole 24FT-28FT depth (797-07.21)EACH1$43,963
270Manhole drop connection assembly (797-07.56)EACH1$6,240.05
271Remove sewer manhole (797-07.80)EACH2$5,092.88
272Connect to 3IN force main (797-10.15)EACH1$5,841.68
273Retirein place existing sewer 15IN-24IN (797-11.32)LF417$75.95
274By-pass pumping (797-11.38)LS1$116,575
TDOT contract CN261064: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of October 2, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy