TDOT contract CN262058 bid tabulation

The grading, drainage, construction of concrete bulb-tee bridges, and paving on u.s. 127 (s.r. 28) from near potato farm road to near lowe road (l.m. 22.68 - l.m. 29.18). Let by Tennessee DOT on August 14, 2026, Cumberland County. 6 bids received; low bid $69,978,616 by Charles Blalock & Sons, Inc..

Owner
Tennessee DOT
Letting
14 AUG 2026
Pay items
373
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Charles Blalock & Sons, Inc.$69,978,616Low
2Jones Bros. Contractors, LLC$72,994,551+4.0%
3Cleary Construction, Inc.$76,566,329+9.0%
4Rogers Group, Inc.$79,329,807+13%
5MasTec Civil, LLC$94,362,358+35%
6AIS Infrastructure, LLC$122,993,339+76%
TDOT contract CN262058: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Charles Blalock & Sons, Inc.2. Jones Bros. Contractors, LLC3. Cleary Construction, Inc.4. Rogers Group, Inc.5. MasTec Civil, LLC6. AIS Infrastructure, LLC
1Construction stakes, lines and grades (105-01)LS1$464,822$500,000$795,000$1,609,453$900,000$663,392
2CPM project schedule (108-03)LS1$78,750$200,000$190,000$626,437$60,000$1,851,656
3Trainee (109-10.01)HR6,320$0.80$0.80$0.80$0.80$0.80$0.80
4Clearing and grubbing (201-01)LS1$1,892,436$1,975,000$2,750,000$3,369,570$5,000,000$3,831,534
5Removal of structures and obstructions (202-01)LS1$116,275$200,000$592,000$2,342,746$1,500,000$3,748,846
6Removal of rigid pavement, sidewalk, etc. (202-03)SY100$125.48$25.00$32.00$26.91$65.00$64.50
7Removal of asphalt pavement (202-03.01)SY30,087$0.60$5.00$4.25$1.00$5.50$6.58
8Road & drainage excavation (unclassified) (203-01)CY955,503$9.84$11.56$9.90$10.80$17.50$19.73
9Borrow excavation (graded solid rock) (203-02.01)TON72,359$23.56$20.50$22.50$20.25$21.00$32.56
10Placing and spreading topsoil (203-04)CY81,233$0.70$5.00$9.65$16.81$10.00$17.97
11Undercutting (203-05)CY23,306$10.04$13.00$9.00$19.16$14.00$23.39
12Water (203-06)MG943$109.83$1.00$40.00$9.30$27.50$12.66
13Channel excavation (unclassified) (203-08)CY1,637$34.82$20.00$21.00$15.08$64.00$34.49
14Channel substrate (203-20.01)CY276$96.09$150.00$40.00$77.37$132.00$220.93
15Construction of haul road (203-50)LS1$222,158$700,000$118,500$281,254$1,200,000$1,326,259
16Foundation fill material (204-08)CY233$100.83$105.00$127.00$65.67$121.00$89.38
1718" temporary slope drain (209-02.07)LF1,466$29.17$28.00$20.00$92.89$29.00$64.93
1824" temporary slope drain (209-02.08)LF1,737$43.41$40.00$33.00$108.94$47.00$77.78
1930" temporary slope drain (209-02.09)LF675$70.72$55.00$46.00$130.76$78.00$83.96
2048" temporary slope drain (209-02.12)LF112$152.93$115.00$114.00$209.89$165.00$183.44
21Filter sock (24 inch) (209-03.23)LF180$12.60$12.00$13.50$9.90$5.40$12.21
22Sediment removal (209-05)CY4,699$12.14$10.00$25.00$44.58$11.00$24.66
23Temporary silt fence (with backing) (209-08.02)LF129,857$4.46$4.25$4.75$5.21$4.60$6.70
24Temporary silt fence (without backing) (209-08.03)LF13,055$1.84$1.75$2.00$2.61$3.00$3.86
25Rock check dam (209-08.07)EACH706$761.25$835.00$815.00$625.16$920.00$964.62
26Enhanced rock check dam (209-08.08)EACH142$997.50$975.00$1,070.00$897.51$1,090.00$1,387.69
27Sandbags (209-09.01)BAG2,000$12.60$10.00$12.00$15.67$8.00$17.82
28Sediment filter bag (15' X 15') (209-09.03)EACH14$3,009.36$650.00$940.00$677.39$230.00$745.61
29Polyethylene sheeting (6 mil. minimum) (209-20.03)SY400$3.94$5.00$3.60$1.00$3.45$9.44
30Temporary diversion channel (209-65.03)LF1,690$23.83$21.00$17.00$52.90$34.00$49.77
31Mineral aggregate, type A base, grading D (303-01)TON228,411$30.50$31.50$31.30$30.50$35.00$37.03
32Granular backfill (roadway) (303-01.01)TON3,227$51.85$40.00$48.00$35.58$44.00$37.44
33Mineral aggregate (size 57) (303-10.01)TON2,854$47.73$50.00$49.00$54.17$51.00$63.79
34Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01)TON4,380$99.75$95.00$105.00$95.00$104.00$115.33
35Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON9,511$121.80$116.00$128.00$116.00$127.00$140.82
36Asp. conc. mix(PG70-22) (BPMB-HM) GR. A-S (307-01.21)TON14,422$97.13$92.50$102.00$92.50$102.00$112.29
37Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01)TON15,460$92.93$88.50$98.00$88.50$97.00$107.44
38Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08)TON10,177$111.83$106.50$118.00$106.50$117.00$129.29
39Bituminous material for tack coat (TC) (403-01)TON142$1,050.00$1,000.00$1,105.00$1,000.00$1,100.00$1,213.97
40Saw cutting asphalt pavement (407-20.05)LF1,150$11.65$5.00$8.85$1.88$9.00$6.07
41Acs mix (PG64-22) grading E shoulder (411-01.07)TON5,488$106.31$101.25$112.00$101.25$110.00$122.91
42Acs mix(PG64-22) grading D (411-01.10)TON5,513$177.45$169.00$187.00$169.00$184.00$205.16
43Acs mix(PG70-22) grading D (411-02.10)TON7,793$153.30$146.00$162.00$146.00$160.00$177.24
44Scoring shoulders (non-continuous) (16IN width) (411-12.02)LM10.90$759.49$1,915.00$680.00$793.77$1,145.00$1,282.97
45Scoring for centerline rumble (4IN width-24IN spacing) (411-12.05)LM3$759.49$1,915.00$3,000.00$793.77$1,400.00$1,282.96
46Class A concrete (roadway) (604-01.01)CY638$2,529.61$1,325.00$1,775.00$2,757.29$1,800.00$2,663.34
47Steel bar reinforcement (roadway) (604-01.02)LB145,380$0.22$1.50$1.75$0.02$0.11$2.03
4818" concrete pipe culvert (class III) (607-03.02)LF1,035$103.86$75.00$94.00$118.92$89.00$116.98
4924" concrete pipe culvert (class III) (607-05.02)LF799$136.93$90.00$103.00$143.38$105.00$139.54
5024" concrete pipe culvert (class IV) (607-05.03)LF100$142.82$100.00$140.00$167.65$104.00$140.21
5130" concrete pipe culvert (class III) (607-06.02)LF310$173.14$115.00$131.00$176.13$138.00$160.99
5236" concrete pipe culvert (class III) (607-07.02)LF212$196.97$135.00$220.00$174.37$173.00$184.24
5342" concrete pipe culvert (class III) (607-08.02)LF215$288.71$200.00$250.00$238.75$271.00$358.92
5448" concrete pipe culvert (class III) (607-09.02)LF149$477.97$320.00$328.00$344.18$355.00$360.37
5518" pipe culvert (side drain) (607-39.02)LF3,760$101.79$95.00$80.00$125.84$88.00$99.17
5624" pipe culvert (side drain) (607-39.03)LF615$135.57$115.00$100.00$111.82$114.00$116.03
5730" pipe culvert (side drain) (607-39.04)LF169$166.07$125.00$123.00$173.76$146.00$133.86
5836" pipe culvert (side drain) (607-39.05)LF182$223.81$180.00$145.00$169.21$164.00$152.65
59Reinforced concrete pipe arch (22" X 13") (607-57.01)LF43$521.31$160.00$130.00$140.27$150.00$210.86
60Reinforced concrete pipe arch (29" X 18") (607-57.02)LF16$954.23$170.00$153.00$177.86$188.00$232.77
61Reinforced concrete pipe arch (18" X 11") (607-57.09)LF45$497.38$165.00$120.00$123.46$130.00$156.62
62Manholes, > 12' - 16' depth (611-01.04)EACH1$11,266$7,500.00$6,500.00$8,593.66$9,200.00$13,724
63Spring drain box, type 2A (611-02.02)EACH1$7,061.82$6,400.00$6,220.00$7,383.10$9,600.00$5,130.52
64Class A concrete (pipe endwalls) (611-07.01)CY54$1,575.00$1,800.00$1,950.00$2,605.64$1,200.00$1,881.19
65Steel bar reinforcement (pipe endwalls) (611-07.02)LB1,916$3.15$3.25$6.00$0.01$1.72$2.14
6618IN endwall (side drain) (611-07.31)EACH232$3,626.02$4,600.00$3,350.00$4,068.88$3,800.00$5,171.56
6724IN endwall (side drain) (611-07.32)EACH50$5,241.88$6,000.00$4,410.00$3,593.63$3,900.00$6,528.22
6830IN endwall (side drain) (611-07.33)EACH12$9,767.31$14,100$10,400$13,247$12,900$16,046
6936IN endwall (side drain) (611-07.34)EACH4$12,770$17,400$12,500$16,384$15,200$12,285
7018IN endwall (cross drain) 3:1 (611-07.54)EACH16$2,669.59$1,700.00$1,700.00$1,719.88$3,800.00$2,652.26
7118IN endwall (cross drain) 4:1 (611-07.55)EACH3$2,991.61$2,000.00$1,960.00$1,993.61$4,100.00$2,951.68
7218IN endwall (cross drain) 6:1 (611-07.56)EACH3$5,359.00$2,500.00$2,460.00$2,544.88$4,600.00$3,592.67
7324IN endwall (cross drain) 3:1 (611-07.57)EACH5$4,259.17$2,500.00$2,200.00$2,287.78$4,500.00$3,311.45
7424IN endwall (cross drain) 4:1 (611-07.58)EACH11$4,761.77$2,900.00$2,600.00$2,715.35$4,900.00$3,778.76
7524IN endwall (cross drain) 6:1 (611-07.59)EACH7$6,149.18$4,500.00$3,400.00$3,870.15$6,100.00$5,068.76
7630IN endwall (cross drain) 3:1 (611-07.60)EACH3$6,874.68$5,600.00$3,180.00$3,928.03$6,700.00$5,456.00
7730IN endwall (cross drain) 4:1 (611-07.61)EACH1$6,800.99$6,500.00$4,600.00$4,840.41$7,600.00$6,427.41
7830IN endwall (cross drain) 6:1 (611-07.62)EACH2$8,983.26$8,500.00$5,850.00$6,635.15$9,300.00$8,466.59
7936IN endwall (cross drain) 6:1 (611-07.65)EACH2$12,770$11,100$7,310.00$16,175$12,000$10,693
8042IN endwall (cross drain) 3:1 (611-07.66)EACH4$9,567.67$9,500.00$6,050.00$11,460$9,000.00$12,481
8142IN endwall (cross drain) 6:1 (611-07.68)EACH2$11,776$12,000$9,325.00$21,792$13,000$15,053
8248IN endwall (cross drain) 3:1 (611-07.69)EACH2$10,759$11,700$7,100.00$19,629$11,000$20,120
8348IN endwall (cross drain) 4:1 (611-07.70)EACH2$12,653$13,600$11,565$26,365$12,500$24,364
8418" temporary drainage pipe (621-03.02)LF160$59.14$48.00$50.00$85.08$67.00$72.85
8524" temporary drainage pipe (621-03.03)LF20$112.06$58.00$63.00$343.10$195.00$873.68
8636" temporary drainage pipe (621-03.05)LF146$103.70$100.00$91.00$153.84$112.00$180.38
8742" temporary drainage pipe (621-03.06)LF460$129.24$118.00$130.00$184.43$127.00$169.28
88Earth pad for type 38 GR end treatment (705-04.09)EACH18$632.32$600.00$665.00$648.32$1,100.00$1,533.59
89Portable barrier rail delineator (705-04.50)EACH1,258$13.13$12.50$13.30$13.23$8.00$15.64
90W beam GR (type 2) MASH TL-3 (705-06.01)LF3,600$28.45$27.00$30.00$29.17$29.00$34.51
91GR terminaltrailing end (type 13) MASH TL-3 (705-06.10)EACH8$1,844.27$1,750.00$1,940.00$1,890.93$1,880.00$1,789.19
92GR terminal (in-inline) MASH TL-3 (705-06.11)EACH8$1,580.80$1,500.00$1,660.00$1,620.80$1,200.00$1,661.39
93Tangent energy absorbing term MASH TL-3 (705-06.20)EACH18$2,898.14$2,750.00$3,045.00$2,971.46$3,600.00$4,345.18
94Thrie beam bridge transition MASH TL-3 (705-06.25)EACH8$3,161.60$3,000.00$3,320.00$3,241.60$3,700.00$3,578.38
95Radius rail (706-06.03)LF225$34.25$32.50$36.00$35.12$32.00$57.51
96Rounded end element (706-10.26)EACH8$210.77$200.00$222.00$216.11$110.00$351.45
97Chain link fence (6 foot) (707-01.11)LF16,378$16.64$15.85$17.50$22.52$18.00$19.24
98End & corner post assembly(chain-link fence 6') (707-01.12)EACH54$341.25$325.00$360.00$261.86$365.00$394.54
99Stock fence (707-03.01)LF22,570$7.35$7.00$8.00$12.83$8.00$8.50
100End, braced line, corner post assembly(stock fence) (707-03.02)EACH223$236.25$225.00$250.00$244.84$252.00$273.14
101Drive gate (stock fence) (description) (707-03.20)EACH3$2,100.00$2,000.00$2,215.00$2,199.65$2,250.00$2,427.94
102Water crossing (707-04)LF360$6.30$6.00$6.70$10.47$6.70$7.28
103Water gate (707-05)SF525$33.60$32.00$35.50$31.42$36.00$38.85
104Removal of fence (chain link, wooden, and woven wire) (707-06.05)LS1$13,256$20,000$32,850$28,805$35,000$41,174
105High-visibility construction fence (707-08.11)LF24,110$1.84$1.75$2.00$2.54$3.40$3.75
106Markers (concrete R.O.W. posts) (708-02.01)EACH208$325.50$340.00$645.00$643.90$350.00$307.31
107Rubble stone rip-rap (709-01.01)CY3$1,376.30$215.00$72.00$329.04$337.00$10,924
108Machined rip-rap (class A-3) (709-05.05)TON727$49.35$55.00$46.50$45.30$74.00$125.18
109Machined rip-rap (class A-1) (709-05.06)TON14,469$50.63$55.00$46.50$37.38$54.00$104.04
110Machined rip-rap (class B) (709-05.08)TON9,795$52.76$55.00$48.50$40.78$57.00$103.05
111Machined rip-rap (class C) (709-05.09)TON7,029$52.76$55.00$48.50$41.18$55.00$97.05
112Gabions (ditch lining) (709-10.01)CY1,939$257.58$170.00$164.00$313.98$335.00$349.59
113Aggregate underdrains (with pipe) (710-02)LF60,782$13.80$7.68$14.35$14.16$14.50$15.97
114Lateral underdrain (710-05)LF9,310$13.27$16.00$13.80$13.61$14.00$15.35
115Lateral underdrain endwall (3:1) (710-06.12)EACH6$1,327.23$900.00$1,385.00$1,361.14$1,395.00$1,535.43
116Lateral underdrain endwall (4:1) (710-06.13)EACH67$1,327.23$900.00$1,385.00$1,361.14$1,395.00$1,535.43
117Lateral underdrain endwall (6:1) (710-06.15)EACH229$1,327.23$1,210.00$1,385.00$1,361.14$1,395.00$1,535.43
118Traffic control (712-01)LS1$175,642$250,000$495,000$803,469$1,000,000$1,971,328
119Interconnected portable barrier rail (712-02.02)LF9,930$30.07$42.00$13.90$41.84$76.00$85.91
120Temporary work zone crash cushion (MASH TL-3) (712-02.60)EACH14$7,612.50$13,000$7,630.00$12,098$16,000$19,518
121Flexible drums (channelizing) (712-04.01)EACH753$49.35$47.00$39.00$49.74$52.00$58.82
122Barrier rail delineator (712-04.50)EACH500$13.13$12.50$13.30$33.76$13.75$38.44
123Warning lights (type A) (712-05.01)EACH124$21.00$20.00$44.30$21.17$22.00$25.03
124Signs (construction) (712-06)SF1,385$7.77$7.40$8.85$7.83$8.00$9.26
125Temporary barricades (type III) (712-07.03)LF660$17.85$17.00$20.00$17.99$18.00$21.28
126Removable pavement marking (8" barrier line) (712-09.02)LF12,875$3.41$3.25$3.60$3.37$6.00$6.37
127Class A concrete (foundation for sign supports) (713-01.01)CY8$210.00$200.00$222.00$218.00$220.00$250.30
128Steel bar reinforcement(foundation for sign supports) (713-01.02)LB1,569$1.58$1.50$1.65$1.64$1.65$1.88
129Delineator (mile marker) & steel post (713-02.04)EACH6$131.25$125.00$138.50$136.25$137.50$156.44
130Sign post delineation enhancement (713-02.21)LF561$3.41$3.25$3.60$3.54$4.00$4.07
131Perforated/knockout square tube post (713-11.02)LB4,708$4.20$4.00$4.45$4.36$4.40$5.01
132P post slip base (713-11.21)EACH74$556.50$530.00$590.00$577.70$583.00$663.30
133Flat sheet aluminum signs (0.080" thick) (713-13.02)SF293$15.49$14.75$16.30$16.08$16.00$18.46
134Flat sheet aluminum signs (0.100" thick) (713-13.03)SF518$16.28$15.50$17.20$16.90$17.00$18.77
135Street name sign (rigid 0.100IN thick (713-14.21)SF57$18.90$18.00$20.00$19.62$20.00$22.53
136Removal of signs, posts and footings (713-15)LS1$525.00$500.00$555.00$545.00$550.00$625.76
137Changeable message sign unit (713-16.01)EACH8$12,600$12,000$13,300$12,699$13,200$15,018
138Temporary raised pavement marker,yellow (716-01.07)EACH170$13.13$12.50$14.00$12.96$13.00$14.57
139Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21)EACH623$46.73$44.50$50.00$46.14$57.00$63.13
140Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22)EACH18$46.73$44.50$50.00$46.14$57.00$63.13
141Plastic pavement marking(channelization striping) (716-02.04)SY120$31.24$29.75$33.00$30.85$34.00$37.63
142Plastic pavement marking (stop line) (716-02.05)LF1,295$12.86$12.25$13.60$12.70$21.00$22.76
143Plastic pavement marking (turn lane arrow) (716-02.06)EACH3$194.25$185.00$205.00$191.82$330.00$364.19
144Plastic pavement marking (8" dotted line) (716-02.08)LF720$3.36$3.20$3.55$3.32$3.30$3.64
145Plastic pavement marking (8IN line) (716-02.12)LM1$10,500$10,000$11,000$10,369$14,300$15,782
146Painted pavement marking (4" line) (716-05.01)LM16.03$918.75$875.00$970.00$907.26$1,760.00$1,942.35
147Painted pavement marking (stop line) (716-05.05)LF40$5.51$5.25$5.85$5.44$7.70$8.50
148Removal of pavement marking (stop line) (716-08.05)LF40$3.15$3.00$3.35$3.11$8.80$9.71
149Removal of pavement marking (line) (716-08.20)LM2.03$2,546.25$2,425.00$2,685.00$2,514.42$3,850.00$4,248.89
150Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM24.50$6,903.75$6,575.00$7,300.00$6,817.45$9,020.00$9,954.55
151Spray thermo PVMT MRKNG (60 mil) (4IN line) (716-13.01)LM5.60$3,018.75$2,875.00$3,200.00$2,981.01$5,225.00$5,766.35
152Mobilization (717-01)LS1$1,748,827$5,000,000$3,000,000$2,275,697$9,500,000$10,962,708
153Field office (type 2) (722-01.02)LS1$108,792$230,000$135,000$242,189$350,000$1,332,685
154Geogrid reinforcement type 2 (740-07.04)SY6,460$2.92$5.00$5.70$3.53$9.35$6.24
155Geotextile (type III)(erosion control) (740-10.03)SY22,298$2.47$2.00$2.75$4.35$2.30$5.00
156Geotextile (type IV)(stabilization) (740-10.04)SY77,656$3.91$2.75$3.60$2.73$3.80$6.15
157Temporary sediment tube 20IN (740-11.04)LF1,748$3.52$3.35$3.75$3.91$4.60$5.10
158Seeding (with mulch) (801-01)UNIT3,224$40.43$38.50$43.24$46.90$38.50$61.91
159Crown vetch mixture (with mulch) (801-01.02)UNIT333$49.88$47.50$53.40$101.61$39.60$63.13
160Temporary seeding (with mulch) (801-01.07)UNIT2,831$28.88$27.50$31.00$38.30$29.70$32.78
161Special wetland seed mixture (801-01.36)UNIT30$183.75$175.00$200.00$78.16$143.00$382.40
162Natve seed MX final stablizatn of slopes (801-01.38)UNIT318$105.00$100.00$112.50$53.15$83.60$168.13
163Seeding (without mulch) (801-02)UNIT437$23.10$22.00$24.75$30.74$33.00$31.14
164Water (seeding & sodding) (801-03)MG2,596$52.50$50.00$56.25$83.37$55.00$72.84
165Sodding (new sod) (803-01)SY90,102$6.30$6.00$6.74$6.04$6.50$6.56
166Turf reinforcement mat (class I) (805-01.01)SY20,222$3.41$3.25$3.65$4.17$4.00$5.23
167Erosion control blanket (type II) (805-12.02)SY114,134$1.21$1.15$1.30$1.04$0.95$1.15
168Project mowing (806-02.03)CYCL10$4,499.28$3,500.00$7,200.00$4,735.35$19,450$48,559
169Dry excavation (bridges) (204-02.01)CY508$50.00$38.00$55.40$51.33$17.00$57.02
170Wet excavation (bridges) (204-03.01)CY100$100.00$80.00$110.80$102.65$17.00$57.02
171Rock excavation (bridges) (204-04.01)CY33$550.00$110.00$610.00$564.58$283.00$114.04
172Rock drilling (bridges) (204-05)LF24$110.00$75.00$120.00$112.92$98.00$505.82
173Core drilling and sampling (204-05.01)LF201$130.00$115.00$105.00$97.52$135.00$182.10
174Foundation preparation(pier no. 1, sta 1339+01.10) (204-10.01)LS1$40,000$25,000$44,300$41,060$12,620$23,361
175Core drilling for piles(rock) (204-14)LF433$294.00$625.00$325.00$301.79$575.00$943.60
176Core drilling for piles(soil) (204-15)LF34$63.00$625.00$70.00$64.67$589.00$314.53
177Granular backfill (bridges) (303-01.02)TON119$60.00$65.00$66.50$61.59$108.00$174.77
178Epoxy coated reinforcing steel (604-02.03)LB269,789$1.85$1.50$2.05$1.90$1.50$2.21
179Class A concrete (bridges) (604-03.01)CY728$2,000.00$1,200.00$2,215.00$2,053.01$1,500.00$3,081.11
180Steel bar reinforcement (bridges) (604-03.02)LB122,071$1.70$1.50$1.90$1.75$1.45$2.33
181Pavement @ bridge ends (604-03.04)SY504$380.00$450.00$420.00$390.07$400.00$717.79
182Class DS concrete (604-03.32)CY857$1,295.00$1,250.00$1,435.00$1,329.32$1,556.00$2,252.33
183Applied texture finish (new structures) (604-04.01)SY3,413$18.00$15.00$20.00$18.48$23.00$44.43
184Three star state emblem (604-04.41)EACH8$850.00$2,000.00$940.00$872.53$1,158.00$1,998.50
185Bridge deck grooving (mechanical) (604-05.31)SY3,288$4.20$5.00$4.65$4.31$9.00$9.71
186Steel piles (12 inch) (606-03.03)LF519$115.00$130.00$127.50$118.05$121.00$420.39
187Prestressed concrete bulb tee beam (6" web)(BT-54) (615-01.10)LF795$540.00$600.00$600.00$554.31$561.00$822.08
188Prestressed concrete bulb tee beam (6" web)(BT-72) (615-01.12)LF2,354$560.00$600.00$620.00$574.84$631.00$701.97
189Conc parapet single slope (STD-1-1SS) (620-05.01)LF1,265$120.00$115.00$133.00$123.22$161.00$132.37
190Camera inspection - drilled shaft (dry) (625-01.10)EACH3$2,150.00$1,500.00$2,380.00$2,207.73$2,750.00$2,185.14
191Camera inspection - drilled shaft (underwater) (625-01.11)EACH3$2,150.00$2,000.00$2,380.00$2,207.73$2,750.00$2,185.14
192Drilled shaft-soil (6'- 0" dia.) (625-02.01)VF20$550.00$1,600.00$610.00$564.77$1,735.00$1,965.84
193Drilled shaft-rock (5'- 6" dia.) (625-02.13)VF60$1,400.00$2,200.00$1,550.00$1,437.59$2,192.00$5,827.89
194Drilled shaft-rock (6'- 0" dia.) (625-02.14)VF75$2,000.00$2,200.00$2,215.00$2,053.70$2,182.00$6,221.06
195Drilled shaft casing-permanent (6'- 0" inside dia.) (625-02.25)VF105$930.00$781.00$1,030.00$954.97$925.00$1,449.61
196Drilled shaft (SH-SCC) concrete (625-02.40)CY162$700.00$700.00$775.00$718.80$855.00$1,179.50
197Drilled shaft reinforcing steel (625-02.44)LB42,355$1.75$1.50$2.00$1.80$1.50$2.38
1986" perforated pipe with vertical drain system (710-09.01)LF314$45.00$70.00$50.00$46.21$15.00$72.84
1996" pipe underdrain (710-09.02)LF130$30.00$20.00$33.00$30.81$14.00$25.93
200Pole 30FT class 6 wood (790-01.05)EACH3$578.48$546.25$605.00$565.73$607.00$1,994.92
201Pole 35FT class 5 wood (790-02.04)EACH3$750.57$708.75$785.00$734.02$787.00$2,234.07
202Pole 40FT class 4 wood (790-03.03)EACH7$1,086.80$1,026.25$1,135.00$1,062.84$1,140.00$2,478.34
203Pole 45FT class 3 wood (790-04.03)EACH34$1,368.76$1,292.50$1,430.00$1,338.58$1,450.00$2,830.22
204Pole 45FT class 4 wood (790-04.04)EACH2$1,266.83$1,196.25$1,325.00$1,238.90$1,330.00$2,648.31
205Pole 50FT class 2 wood (790-05.02)EACH6$1,711.61$1,616.25$1,800.00$1,673.88$1,800.00$3,596.82
206Pole 55FT class 2 wood (790-06.02)EACH1$1,817.51$1,716.25$1,900.00$1,777.43$1,907.00$4,067.88
207Pole 60FT class H2 metal (790-07.08)EACH97$8,089.96$8,941.25$8,450.00$7,911.60$9,950.00$10,714
208Pole 65FT class H2 metal (790-08.04)EACH32$8,909.58$9,818.75$9,300.00$8,713.15$10,100$11,848
209Pole 70FT class H2 metal (790-09.05)EACH3$10,055$10,498$10,500$9,833.08$11,650$13,197
210Pole 75FT class H2 metal (790-10.05)EACH2$11,874$11,213$12,400$11,612$12,500$14,396
2111PH SGL primary support 25KV (790-22.01)EACH7$534.58$504.80$560.00$522.80$560.00$378.60
2121PH DBL primary support 25KV (790-22.02)EACH4$598.80$565.44$625.00$585.60$630.00$489.87
2131PH DBL PTS angle 25KV (790-22.07)EACH7$635.39$599.99$665.00$621.38$667.00$706.36
2141PH dde angle 25KV (790-22.11)EACH10$702.39$663.26$735.00$686.91$740.00$670.86
2151PH dead end 25KV (790-22.13)EACH19$538.61$508.60$560.00$526.73$565.00$436.74
2161PH dead end tap W/ extension 25KV (790-22.15)EACH52$531.02$501.43$555.00$519.31$560.00$475.51
2171PH dde tangent 25KV (790-22.16)EACH14$751.40$709.54$785.00$734.84$790.00$1,103.09
2182PH crossarm SGL 25KV (790-24.01)EACH1$897.17$847.19$935.00$877.39$945.00$1,297.13
2192PH dead end crossarm 25KV (790-24.08)EACH1$1,273.81$1,202.84$1,330.00$1,245.73$1,350.00$2,199.77
2203PH crossarm 25KV (790-26.01)EACH1$948.44$895.60$990.00$927.54$995.00$1,191.30
2213PH crossarm SGL LRG cond 25KV (790-26.03)EACH75$1,071.38$1,011.69$1,120.00$1,047.76$1,120.00$1,371.75
2223PH crossarm SGL FBRGLS DBL prim sup 25KV (790-26.06)EACH42$1,909.02$1,802.66$1,995.00$1,866.93$2,000.00$2,503.42
2233PH xarm DBL 10FT LRG cond SM angle 25KV (790-26.15)EACH7$2,281.63$2,154.51$2,385.00$2,231.33$2,390.00$3,443.32
2243PH crossarm dead end 25KV (790-26.26)EACH16$1,687.74$1,593.71$1,750.00$1,650.53$1,770.00$2,528.63
2253PH DBL 10FT xarm dde 25KV (790-26.28)EACH7$2,592.71$2,448.26$2,700.00$2,535.55$2,720.00$4,807.03
226Secondary conductor 6 AL duplex (790-30.06)LF30$2.82$2.66$3.00$2.75$2.95$3.53
227Secondary conductor 2 AL triplex (790-30.13)LF1,205$4.49$4.24$4.70$4.39$4.70$6.54
228Service assembly-house type (790-31.01)EACH1$121.36$114.60$127.00$118.69$127.00$138.82
229Service assembly-pole type (790-31.02)EACH65$158.90$150.05$165.00$155.40$166.00$149.53
230Down guy - through bolt type (790-32.01)EACH5$406.61$383.96$425.00$397.65$426.00$437.11
231Down guy - insulated (790-32.06)EACH176$438.14$413.73$460.00$428.48$460.00$463.52
232OH guy - through bolt type (790-32.07)EACH10$544.47$514.13$570.00$532.46$571.00$685.85
233OH guy - through bolt type heavy duty (790-32.08)EACH8$520.38$491.39$545.00$508.91$545.00$631.80
234Guy guard (790-32.23)EACH184$26.21$24.75$27.00$25.63$27.50$34.33
235Rock anchor guy bolt type (790-33.18)EACH180$671.12$633.73$700.00$656.32$704.00$1,392.70
236OH cond 2 7/1 acsr sparate (790-40.02)LF40$3.08$2.91$3.25$3.01$3.50$2.99
237OH cond 1/0 6/1 acsr raven (790-40.03)LF30,606$3.43$3.24$3.60$3.36$3.60$3.72
238OH cond 336.4 19 aac tulip (790-40.42)LF27,505$5.30$5.00$5.55$5.18$5.50$6.95
239OH cond 795 37 aac arbutus (790-40.49)LF82,516$7.82$8.44$8.15$7.64$9.35$10.36
240UG pri cond 1/0 AL 25KV (790-41.13)LF360$16.34$15.43$17.00$15.98$17.15$21.02
241UG sec cond 2/0 AL TPLX (790-41.47)LF320$6.97$6.58$7.30$6.81$7.30$12.58
2423IN dia PVC pipe (790-42.09)LF160$194.15$183.33$202.00$189.87$204.00$17.15
243Loadbreak junction 3 PT 200A 25KV (790-43.21)EACH4$5,763.89$5,442.76$6,000.00$5,636.81$6,050.00$3,784.75
244Loadbreak junction 4 PT 200A 25KV (790-43.22)EACH1$8,020.77$7,573.90$8,400.00$7,843.94$8,415.00$5,234.44
245Secondary riser W/ 3IN conduit (790-43.51)EACH9$935.41$883.26$980.00$914.78$980.00$1,717.69
2461PH primary riser W/ 3IN conduit (790-43.53)EACH4$2,658.51$2,510.39$2,775.00$2,599.89$2,790.00$2,765.19
2473PH primary riser W/ 6IN conduit (790-43.58)EACH1$6,208.76$5,862.84$6,485.00$6,071.87$6,515.00$8,050.56
2481PH transformer conv W/pole MTD fuse & LA (790-46.02)EACH19$546.51$516.06$570.00$534.46$574.00$1,553.94
2491PH transformer conv W/xarm MTD fuse & LA (790-46.03)EACH38$475.08$448.61$495.00$464.60$500.00$1,484.81
2501PH transformer pad (790-50.03)EACH1$14,187$13,397$14,800$13,874$14,885$11,616
25110KVA 1PH OH xformer 7.2KV 120/240 (790-52.03)EACH15$436.84$412.50$455.00$427.21$460.00$785.85
25215KVA 1PH OH xformer 7.2KV 120/240 (790-52.04)EACH3$463.31$437.50$485.00$453.10$487.00$785.84
25315KVA 1PH OH xformer 7.2KV dual voltage (790-52.05)EACH28$463.31$437.50$485.00$453.10$487.00$785.85
25425KVA 1PH OH xformer 7.2KV dual voltage (790-52.08)EACH11$473.90$447.50$495.00$463.45$500.00$982.31
255Goab switch 25KV (790-59.06)EACH1$11,468$10,829$12,000$11,215$12,000$15,002
2561PH fuse cutout BRKT mount 15KV (790-60.02)EACH19$545.87$515.46$570.00$533.84$572.00$845.20
2571PH fuse cutout xarm mount 25KV (790-61.01)EACH13$368.73$348.19$385.00$360.60$385.00$570.42
2581PH sectionalizers or recloser 25KV (790-61.03)EACH1$1,382.72$1,305.69$1,450.00$1,352.24$1,450.00$2,089.97
2593PH sectlr or recl W/ bypass SW 25KV (790-61.10)EACH4$6,519.93$6,156.68$6,810.00$6,376.19$6,850.00$8,351.69
2601PH hydr recl 280A cont 5000A int 15KV (790-62.06)EACH1$913.38$862.50$950.00$893.24$960.00$1,571.70
261Sec MTG 1PH 120/240 volts residential (790-64.02)EACH4$926.63$875.00$970.00$906.20$972.00$1,622.85
262Lightning arrester arm MTD 18 KV (790-65.05)EACH13$356.25$336.40$375.00$348.39$375.00$403.82
2633PH regulator platform mount (790-65.11)EACH1$28,353$26,773$30,000$27,728$29,800$25,837
2641PH 500A regulator 25KV (790-67.07)EACH3$1,125.19$1,062.50$1,175.00$1,100.38$1,200.00$4,911.57
265Pole ground rod type (790-68.01)EACH137$177.17$167.30$185.00$173.26$186.00$423.46
266Pole ground wrap type (790-68.03)EACH5$248.17$234.34$260.00$242.70$260.00$499.09
267Pole ground W/ PLTFM for air break SWCH (790-68.08)EACH1$957.55$904.20$1,000.00$936.43$1,005.00$1,785.23
268GND-assy GND rod with aluminum (790-69.09)EACH44$263.69$249.00$275.00$257.88$275.00$499.30
269Stick pin (790-69.31)EACH7$126.48$119.43$132.00$123.69$133.00$181.01
270Flood light (790-70.10)EACH1$1,252.41$1,182.63$1,300.00$1,224.80$1,315.00$1,297.50
271Street light (400W MV) (790-70.20)EACH1$1,198.63$1,131.85$1,250.00$1,172.20$1,260.00$1,245.46
272Street light (70W LED) (790-70.21)EACH3$662.39$625.48$690.00$647.78$695.00$726.49
273Guy factory formed with thimble clevis (790-72.07)EACH3$363.66$343.40$380.00$355.64$382.00$315.68
274Remove wire (790-98.01)LF156,911$2.38$2.25$2.50$2.33$2.50$2.75
275Remove poles (790-98.02)EACH249$688.35$650.00$720.00$673.17$722.00$982.31
276Remove framing/associated apparatus (790-98.03)EACH1,345$423.60$400.00$442.00$414.26$445.00$392.92
277<2IN HDPE gas main (791-03.01)LF1,818$40.30$38.00$72.00$66.73$94.00$78.91
2782IN HDPE gas main (791-03.02)LF9,400$49.85$47.00$72.00$66.73$94.00$78.91
2794IN HDPE gas main (791-03.04)LF522$76.36$72.00$88.50$82.13$108.00$97.12
2808IN HDPE gas main (791-03.06)LF22,083$117.73$111.00$134.00$124.22$81.00$146.89
281HDD <2IN PE pipe - unconsolidated (791-04.01)LF178$97.58$92.00$166.00$153.99$132.00$182.10
282HDD 2IN PE pipe - unconsolidated (791-04.02)LF1,106$97.58$92.00$182.50$169.39$132.00$200.30
283HDD 4IN PE pipe - unconsolidated (791-04.04)LF105$222.73$210.00$194.00$179.66$308.00$212.44
284HDD 8IN PE pipe - unconsolidated (791-04.06)LF770$275.76$260.00$332.00$307.99$462.00$364.19
285Connect to 8IN EX. PE main (791-06.05)EACH12$4,772.73$4,500.00$6,635.00$6,159.72$13,750$7,283.82
2862IN PE hot tap connection (791-06.51)EACH18$3,818.18$3,600.00$2,210.00$2,053.24$7,480.00$2,427.94
2874IN PE hot tap connection (791-06.52)EACH1$6,575.76$6,200.00$3,870.00$3,593.17$15,950$4,248.89
2888IN PE gas valve assembly (791-07.04)EACH1$4,454.54$4,200.00$4,420.00$4,106.48$7,480.00$4,855.87
289Reconnect service assembly (791-08.40)EACH47$2,333.33$2,200.00$1,770.00$1,642.59$1,320.00$1,942.35
290Gas main removal (791-08.41)LF4,228$29.70$28.00$11.00$10.27$33.00$12.14
291Pole 30FT class 4 wood (793-01.01)EACH1$874.13$2,544.68$3,320.00$862.62$3,900.00$5,945.98
292Pole 40FT class 4 wood (793-01.12)EACH1$1,173.38$2,745.48$3,600.00$1,157.93$4,185.00$6,193.73
293Anchor 3/4IN (793-01.40)EACH63$531.56$586.48$775.00$524.56$1,085.00$1,362.62
294Anchor 1IN (793-01.41)EACH39$511.88$686.54$885.00$505.14$1,239.00$1,486.49
295Guy wire 10M or 3/8IN (793-02.08)EACH129$149.63$239.99$310.00$147.66$365.00$569.82
296Overhead guy wire (10M or 3/8IN) (793-02.92)EACH5$267.75$576.49$725.00$264.22$878.00$569.82
297Install guy guard (793-02.99)EACH124$29.61$59.44$89.00$29.22$138.00$247.75
29810M strand (793-03.03)LF67,314$3.62$3.05$3.75$3.57$4.80$5.95
299Install strand bond (793-03.40)EACH101$36.54$39.82$61.00$36.06$143.00$154.84
300Relash/delash cable (793-04.01)LF13,396$2.13$2.50$3.10$2.10$3.60$4.95
3012 pair aerial drop (793-04.02)LF1,210$4.10$2.67$3.35$4.04$4.10$7.43
302Aerial splice closure (793-04.07)EACH74$945.00$665.57$860.00$932.56$1,010.00$8,448.24
303Aerial splice closure (3M) (793-04.13)EACH11$1,787.63$806.18$860.00$1,764.09$1,228.00$9,686.98
30412 fiber (material only) (793-07.01)LF8,228$1.01$0.61$0.75$0.99$1.00$3.72
30524 fiber(material only) (793-07.02)LF8,846$1.35$0.69$0.85$1.34$1.10$3.96
30648 fiber(material only) (793-07.04)LF7,210$1.88$0.82$1.00$1.85$1.30$4.21
30796 fiber(material only) (793-07.05)LF42,064$2.74$1.54$1.85$2.70$2.40$4.46
308144 fiber(material only) (793-07.07)LF39,480$3.35$2.27$2.70$3.31$3.70$5.33
309216 fiber(material only) (793-07.09)LF2,500$4.65$2.15$2.60$4.59$3.50$5.57
310288 fiber(material only) (793-07.10)LF31,290$5.51$2.62$3.15$5.44$4.20$5.70
31112-96 fiber(installation only) (793-07.16)LF66,348$1.69$2.35$2.90$1.67$3.55$3.96
312108-144 fiber(installation only) (793-07.17)LF39,480$2.01$2.35$2.90$1.98$3.55$3.96
313192-216 fiber(installation only) (793-07.18)LF2,500$2.32$2.78$3.40$2.29$4.20$3.96
314288-432 fiber(installation only) (793-07.19)LF31,290$2.64$2.78$3.40$2.60$4.20$3.96
315Single fiber optic cable splice (793-07.25)EACH1,818$33.23$30.40$44.00$32.79$47.00$99.10
316Hot splice existing fiber cables (793-07.41)EACH6,603$39.53$30.40$39.00$39.01$47.00$148.65
317Rearrange fiber drop (793-07.83)LF14$48.83$185.04$228.00$48.18$286.00$74.32
318Install fiber storage bracket (793-07.90)EACH153$149.63$199.90$255.00$147.66$306.00$792.80
319Rearrange existing fiber storage bracket (793-07.91)EACH11$101.59$79.65$105.00$100.25$306.00$768.02
320Buried riser guard (793-11.13)EACH16$248.06$339.55$395.00$244.80$467.00$768.02
3212 pair buried drop (793-11.14)LF1,500$8.51$4.60$5.60$8.39$7.00$37.16
322Enter existing handhole (793-11.32)EACH3$889.88$318.63$400.00$878.16$1,222.00$1,015.77
323Rearrange existing splice case (793-11.50)EACH23$551.25$216.72$275.00$543.99$332.00$1,560.82
324Rearrangement existing cable (793-12.02)EACH5$425.25$1,274.52$1,660.00$419.65$1,950.00$1,981.99
3252 duct formation @ 36IN depth (793-13.17)LF600$61.74$48.79$72.00$60.93$89.00$198.20
3264 duct formation @ 36IN depth (793-13.27)LF120$86.47$72.12$122.00$85.33$107.00$247.75
327Transfer cable attachment (793-15.01)EACH88$146.79$283.81$385.00$144.86$247.00$991.00
328Directional bore 3IN/flex sleeve (793-16.03)LF300$49.30$90.00$73.00$48.65$82.00$322.07
329Directional bore 1.25IN/flex sleeve (793-16.45)LF60$34.10$70.00$71.00$33.66$73.00$260.14
330Remove aerial cable and wire (793-98.01)LF51,510$1.26$1.27$1.60$1.24$2.00$3.72
331Remove poles all sizes (793-98.04)EACH111$126.00$318.63$415.00$124.34$488.00$743.25
332Remove pedestals (793-98.06)EACH1$189.00$79.65$110.00$186.51$130.00$743.24
333Remove underground to overhead riser (793-98.07)EACH12$94.50$79.65$110.00$93.26$123.00$371.62
334Remove anchor (any size) (793-98.08)EACH64$50.40$79.65$110.00$49.74$123.00$371.62
335Remove down guy (793-98.09)EACH87$37.80$79.65$110.00$37.30$120.00$371.62
336Remove fiber storage bracket (793-98.10)EACH34$50.40$79.65$110.00$49.74$120.00$371.62
337Trim utility right-of-way (793-98.21)LF356$6.30$8.95$11.00$6.22$14.00$148.65
3386IN HDPE water line (795-02.04)LF3,400$84.00$80.00$50.00$82.15$59.00$84.29
3396IN HDPE water line (HDD) (795-02.32)LF620$278.25$265.00$288.00$272.12$207.00$315.63
3404IN PVC water line (795-03.04)LF3,140$52.50$50.00$77.00$51.34$57.00$84.98
3416IN PVC water line (795-03.05)LF56,122$80.85$65.00$102.00$73.93$56.70$111.69
34210IN PVC water line (795-03.07)LF475$94.50$90.00$72.00$92.42$74.00$78.91
343HDD 2IN HDPE carrier pipe-uncon (795-05.01)LF450$157.50$150.00$163.00$154.03$95.00$178.45
344Bore/jack 10IN steel casing pipe-uncon. (795-05.62)LF403$808.50$750.00$500.00$770.14$715.00$1,108.37
345Connect to 2IN water line (795-06.01)EACH6$1,575.00$1,500.00$2,500.00$1,540.28$4,150.00$2,792.13
346Connect to 4IN water line (795-06.03)EACH6$2,625.00$2,500.00$3,000.00$2,567.13$3,520.00$3,277.72
347Connect to 6IN water line (795-06.04)EACH29$3,150.00$3,000.00$3,430.00$3,080.55$3,100.00$3,763.30
348Temporary tie-in (795-06.28)EACH8$2,625.00$2,500.00$1,660.00$2,567.13$3,850.00$1,820.95
349Cut/cap existing lines (all sizes) (795-06.30)EACH35$2,100.00$2,000.00$1,660.00$2,053.70$1,250.00$1,820.95
350Cut and cap service line (795-06.35)EACH24$525.00$500.00$610.00$513.43$1,100.00$667.68
3514IN X 4IN tapping sleeve and valve (795-07.01)EACH9$4,200.00$4,000.00$7,630.00$4,107.40$5,000.00$8,376.39
3526IN X 6IN tapping sleeve and valve (795-07.03)EACH25$5,775.00$5,500.00$8,850.00$5,647.68$5,300.00$9,711.75
3534IN gate valve assembly (795-08.03)EACH8$2,100.00$2,000.00$3,150.00$2,053.70$2,250.00$3,459.81
3546IN gate valve assembly (795-08.04)EACH148$2,362.50$2,250.00$3,320.00$2,310.41$2,780.00$3,641.91
3553/4IN water service meter assembly (795-09.01)EACH103$1,575.00$1,500.00$1,770.00$1,540.28$1,435.00$1,942.35
3561-1/2IN water service meter assembly (795-09.03)EACH8$5,250.00$5,000.00$6,100.00$5,134.25$3,555.00$6,676.83
357Relocate/reconnect service assembly (795-09.09)EACH13$1,050.00$1,000.00$1,000.00$1,026.85$1,690.00$1,092.57
3583/4IN pexa service pipe (795-09.60)LF1,400$26.25$25.00$27.50$25.67$29.00$30.35
3591IN auto air release valve assembly (795-10.03)EACH1$1,575.00$1,500.00$13,275$1,540.27$5,400.00$14,568
3603/4IN PRV assembly (795-10.25)EACH40$315.00$300.00$690.00$308.06$1,600.00$758.73
361Blow-off assembly (795-11.01)EACH16$3,675.00$3,500.00$6,850.00$3,593.98$3,750.00$7,405.21
362Fire hydrant assembly (795-11.02)EACH35$7,875.00$7,500.00$8,460.00$7,701.38$10,100$9,286.86
363Removal of existing line 4" OD or greater (795-12.35)LF10,000$21.00$20.00$5.55$20.54$4.40$6.07
364Bridge hanger system (795-13.04)LS1$315,000$300,000$570,000$308,055$191,000$642,392
365Creek crossing (#1) (795-13.05)LS1$31,500$60,000$24,300$61,611$34,400$26,707
366Creek crossing (#2) (795-13.06)LS1$26,250$50,000$16,600$51,343$22,900$18,210
367Creek crossing (#3) (795-13.07)LS1$21,000$40,000$16,600$41,074$22,300$18,210
368Creek crossing (#4) (795-13.08)LS1$29,400$28,000$22,100$28,752$15,400$24,279
369Creek crossing (#5) (795-13.09)LS1$29,400$28,000$24,300$28,752$18,300$26,707
370Creek crossing (#6) (795-13.10)LS1$29,400$28,000$16,600$28,752$14,400$18,210
371Restore asphalt (795-14.08)SY350$210.00$200.00$83.00$205.37$59.00$91.05
372Restore concrete (795-14.09)SY435$262.50$250.00$166.00$256.71$156.00$182.10
37310IN steel casing pipe open cut method (795-15.24)LF3,325$210.00$200.00$133.00$205.37$140.00$145.68
TDOT contract CN262058: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of August 14, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy