TDOT contract CN262058 bid tabulation
The grading, drainage, construction of concrete bulb-tee bridges, and paving on u.s. 127 (s.r. 28) from near potato farm road to near lowe road (l.m. 22.68 - l.m. 29.18). Let by Tennessee DOT on August 14, 2026, Cumberland County. 6 bids received; low bid $69,978,616 by Charles Blalock & Sons, Inc..
- Owner
- Tennessee DOT
- Letting
- 14 AUG 2026
- Pay items
- 373
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Charles Blalock & Sons, Inc. | $69,978,616 | Low |
| 2 | Jones Bros. Contractors, LLC | $72,994,551 | +4.0% |
| 3 | Cleary Construction, Inc. | $76,566,329 | +9.0% |
| 4 | Rogers Group, Inc. | $79,329,807 | +13% |
| 5 | MasTec Civil, LLC | $94,362,358 | +35% |
| 6 | AIS Infrastructure, LLC | $122,993,339 | +76% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Charles Blalock & Sons, Inc. | 2. Jones Bros. Contractors, LLC | 3. Cleary Construction, Inc. | 4. Rogers Group, Inc. | 5. MasTec Civil, LLC | 6. AIS Infrastructure, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $464,822 | $500,000 | $795,000 | $1,609,453 | $900,000 | $663,392 |
| 2 | CPM project schedule (108-03) | LS | 1 | $78,750 | $200,000 | $190,000 | $626,437 | $60,000 | $1,851,656 |
| 3 | Trainee (109-10.01) | HR | 6,320 | $0.80 | $0.80 | $0.80 | $0.80 | $0.80 | $0.80 |
| 4 | Clearing and grubbing (201-01) | LS | 1 | $1,892,436 | $1,975,000 | $2,750,000 | $3,369,570 | $5,000,000 | $3,831,534 |
| 5 | Removal of structures and obstructions (202-01) | LS | 1 | $116,275 | $200,000 | $592,000 | $2,342,746 | $1,500,000 | $3,748,846 |
| 6 | Removal of rigid pavement, sidewalk, etc. (202-03) | SY | 100 | $125.48 | $25.00 | $32.00 | $26.91 | $65.00 | $64.50 |
| 7 | Removal of asphalt pavement (202-03.01) | SY | 30,087 | $0.60 | $5.00 | $4.25 | $1.00 | $5.50 | $6.58 |
| 8 | Road & drainage excavation (unclassified) (203-01) | CY | 955,503 | $9.84 | $11.56 | $9.90 | $10.80 | $17.50 | $19.73 |
| 9 | Borrow excavation (graded solid rock) (203-02.01) | TON | 72,359 | $23.56 | $20.50 | $22.50 | $20.25 | $21.00 | $32.56 |
| 10 | Placing and spreading topsoil (203-04) | CY | 81,233 | $0.70 | $5.00 | $9.65 | $16.81 | $10.00 | $17.97 |
| 11 | Undercutting (203-05) | CY | 23,306 | $10.04 | $13.00 | $9.00 | $19.16 | $14.00 | $23.39 |
| 12 | Water (203-06) | MG | 943 | $109.83 | $1.00 | $40.00 | $9.30 | $27.50 | $12.66 |
| 13 | Channel excavation (unclassified) (203-08) | CY | 1,637 | $34.82 | $20.00 | $21.00 | $15.08 | $64.00 | $34.49 |
| 14 | Channel substrate (203-20.01) | CY | 276 | $96.09 | $150.00 | $40.00 | $77.37 | $132.00 | $220.93 |
| 15 | Construction of haul road (203-50) | LS | 1 | $222,158 | $700,000 | $118,500 | $281,254 | $1,200,000 | $1,326,259 |
| 16 | Foundation fill material (204-08) | CY | 233 | $100.83 | $105.00 | $127.00 | $65.67 | $121.00 | $89.38 |
| 17 | 18" temporary slope drain (209-02.07) | LF | 1,466 | $29.17 | $28.00 | $20.00 | $92.89 | $29.00 | $64.93 |
| 18 | 24" temporary slope drain (209-02.08) | LF | 1,737 | $43.41 | $40.00 | $33.00 | $108.94 | $47.00 | $77.78 |
| 19 | 30" temporary slope drain (209-02.09) | LF | 675 | $70.72 | $55.00 | $46.00 | $130.76 | $78.00 | $83.96 |
| 20 | 48" temporary slope drain (209-02.12) | LF | 112 | $152.93 | $115.00 | $114.00 | $209.89 | $165.00 | $183.44 |
| 21 | Filter sock (24 inch) (209-03.23) | LF | 180 | $12.60 | $12.00 | $13.50 | $9.90 | $5.40 | $12.21 |
| 22 | Sediment removal (209-05) | CY | 4,699 | $12.14 | $10.00 | $25.00 | $44.58 | $11.00 | $24.66 |
| 23 | Temporary silt fence (with backing) (209-08.02) | LF | 129,857 | $4.46 | $4.25 | $4.75 | $5.21 | $4.60 | $6.70 |
| 24 | Temporary silt fence (without backing) (209-08.03) | LF | 13,055 | $1.84 | $1.75 | $2.00 | $2.61 | $3.00 | $3.86 |
| 25 | Rock check dam (209-08.07) | EACH | 706 | $761.25 | $835.00 | $815.00 | $625.16 | $920.00 | $964.62 |
| 26 | Enhanced rock check dam (209-08.08) | EACH | 142 | $997.50 | $975.00 | $1,070.00 | $897.51 | $1,090.00 | $1,387.69 |
| 27 | Sandbags (209-09.01) | BAG | 2,000 | $12.60 | $10.00 | $12.00 | $15.67 | $8.00 | $17.82 |
| 28 | Sediment filter bag (15' X 15') (209-09.03) | EACH | 14 | $3,009.36 | $650.00 | $940.00 | $677.39 | $230.00 | $745.61 |
| 29 | Polyethylene sheeting (6 mil. minimum) (209-20.03) | SY | 400 | $3.94 | $5.00 | $3.60 | $1.00 | $3.45 | $9.44 |
| 30 | Temporary diversion channel (209-65.03) | LF | 1,690 | $23.83 | $21.00 | $17.00 | $52.90 | $34.00 | $49.77 |
| 31 | Mineral aggregate, type A base, grading D (303-01) | TON | 228,411 | $30.50 | $31.50 | $31.30 | $30.50 | $35.00 | $37.03 |
| 32 | Granular backfill (roadway) (303-01.01) | TON | 3,227 | $51.85 | $40.00 | $48.00 | $35.58 | $44.00 | $37.44 |
| 33 | Mineral aggregate (size 57) (303-10.01) | TON | 2,854 | $47.73 | $50.00 | $49.00 | $54.17 | $51.00 | $63.79 |
| 34 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01) | TON | 4,380 | $99.75 | $95.00 | $105.00 | $95.00 | $104.00 | $115.33 |
| 35 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 9,511 | $121.80 | $116.00 | $128.00 | $116.00 | $127.00 | $140.82 |
| 36 | Asp. conc. mix(PG70-22) (BPMB-HM) GR. A-S (307-01.21) | TON | 14,422 | $97.13 | $92.50 | $102.00 | $92.50 | $102.00 | $112.29 |
| 37 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01) | TON | 15,460 | $92.93 | $88.50 | $98.00 | $88.50 | $97.00 | $107.44 |
| 38 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08) | TON | 10,177 | $111.83 | $106.50 | $118.00 | $106.50 | $117.00 | $129.29 |
| 39 | Bituminous material for tack coat (TC) (403-01) | TON | 142 | $1,050.00 | $1,000.00 | $1,105.00 | $1,000.00 | $1,100.00 | $1,213.97 |
| 40 | Saw cutting asphalt pavement (407-20.05) | LF | 1,150 | $11.65 | $5.00 | $8.85 | $1.88 | $9.00 | $6.07 |
| 41 | Acs mix (PG64-22) grading E shoulder (411-01.07) | TON | 5,488 | $106.31 | $101.25 | $112.00 | $101.25 | $110.00 | $122.91 |
| 42 | Acs mix(PG64-22) grading D (411-01.10) | TON | 5,513 | $177.45 | $169.00 | $187.00 | $169.00 | $184.00 | $205.16 |
| 43 | Acs mix(PG70-22) grading D (411-02.10) | TON | 7,793 | $153.30 | $146.00 | $162.00 | $146.00 | $160.00 | $177.24 |
| 44 | Scoring shoulders (non-continuous) (16IN width) (411-12.02) | LM | 10.90 | $759.49 | $1,915.00 | $680.00 | $793.77 | $1,145.00 | $1,282.97 |
| 45 | Scoring for centerline rumble (4IN width-24IN spacing) (411-12.05) | LM | 3 | $759.49 | $1,915.00 | $3,000.00 | $793.77 | $1,400.00 | $1,282.96 |
| 46 | Class A concrete (roadway) (604-01.01) | CY | 638 | $2,529.61 | $1,325.00 | $1,775.00 | $2,757.29 | $1,800.00 | $2,663.34 |
| 47 | Steel bar reinforcement (roadway) (604-01.02) | LB | 145,380 | $0.22 | $1.50 | $1.75 | $0.02 | $0.11 | $2.03 |
| 48 | 18" concrete pipe culvert (class III) (607-03.02) | LF | 1,035 | $103.86 | $75.00 | $94.00 | $118.92 | $89.00 | $116.98 |
| 49 | 24" concrete pipe culvert (class III) (607-05.02) | LF | 799 | $136.93 | $90.00 | $103.00 | $143.38 | $105.00 | $139.54 |
| 50 | 24" concrete pipe culvert (class IV) (607-05.03) | LF | 100 | $142.82 | $100.00 | $140.00 | $167.65 | $104.00 | $140.21 |
| 51 | 30" concrete pipe culvert (class III) (607-06.02) | LF | 310 | $173.14 | $115.00 | $131.00 | $176.13 | $138.00 | $160.99 |
| 52 | 36" concrete pipe culvert (class III) (607-07.02) | LF | 212 | $196.97 | $135.00 | $220.00 | $174.37 | $173.00 | $184.24 |
| 53 | 42" concrete pipe culvert (class III) (607-08.02) | LF | 215 | $288.71 | $200.00 | $250.00 | $238.75 | $271.00 | $358.92 |
| 54 | 48" concrete pipe culvert (class III) (607-09.02) | LF | 149 | $477.97 | $320.00 | $328.00 | $344.18 | $355.00 | $360.37 |
| 55 | 18" pipe culvert (side drain) (607-39.02) | LF | 3,760 | $101.79 | $95.00 | $80.00 | $125.84 | $88.00 | $99.17 |
| 56 | 24" pipe culvert (side drain) (607-39.03) | LF | 615 | $135.57 | $115.00 | $100.00 | $111.82 | $114.00 | $116.03 |
| 57 | 30" pipe culvert (side drain) (607-39.04) | LF | 169 | $166.07 | $125.00 | $123.00 | $173.76 | $146.00 | $133.86 |
| 58 | 36" pipe culvert (side drain) (607-39.05) | LF | 182 | $223.81 | $180.00 | $145.00 | $169.21 | $164.00 | $152.65 |
| 59 | Reinforced concrete pipe arch (22" X 13") (607-57.01) | LF | 43 | $521.31 | $160.00 | $130.00 | $140.27 | $150.00 | $210.86 |
| 60 | Reinforced concrete pipe arch (29" X 18") (607-57.02) | LF | 16 | $954.23 | $170.00 | $153.00 | $177.86 | $188.00 | $232.77 |
| 61 | Reinforced concrete pipe arch (18" X 11") (607-57.09) | LF | 45 | $497.38 | $165.00 | $120.00 | $123.46 | $130.00 | $156.62 |
| 62 | Manholes, > 12' - 16' depth (611-01.04) | EACH | 1 | $11,266 | $7,500.00 | $6,500.00 | $8,593.66 | $9,200.00 | $13,724 |
| 63 | Spring drain box, type 2A (611-02.02) | EACH | 1 | $7,061.82 | $6,400.00 | $6,220.00 | $7,383.10 | $9,600.00 | $5,130.52 |
| 64 | Class A concrete (pipe endwalls) (611-07.01) | CY | 54 | $1,575.00 | $1,800.00 | $1,950.00 | $2,605.64 | $1,200.00 | $1,881.19 |
| 65 | Steel bar reinforcement (pipe endwalls) (611-07.02) | LB | 1,916 | $3.15 | $3.25 | $6.00 | $0.01 | $1.72 | $2.14 |
| 66 | 18IN endwall (side drain) (611-07.31) | EACH | 232 | $3,626.02 | $4,600.00 | $3,350.00 | $4,068.88 | $3,800.00 | $5,171.56 |
| 67 | 24IN endwall (side drain) (611-07.32) | EACH | 50 | $5,241.88 | $6,000.00 | $4,410.00 | $3,593.63 | $3,900.00 | $6,528.22 |
| 68 | 30IN endwall (side drain) (611-07.33) | EACH | 12 | $9,767.31 | $14,100 | $10,400 | $13,247 | $12,900 | $16,046 |
| 69 | 36IN endwall (side drain) (611-07.34) | EACH | 4 | $12,770 | $17,400 | $12,500 | $16,384 | $15,200 | $12,285 |
| 70 | 18IN endwall (cross drain) 3:1 (611-07.54) | EACH | 16 | $2,669.59 | $1,700.00 | $1,700.00 | $1,719.88 | $3,800.00 | $2,652.26 |
| 71 | 18IN endwall (cross drain) 4:1 (611-07.55) | EACH | 3 | $2,991.61 | $2,000.00 | $1,960.00 | $1,993.61 | $4,100.00 | $2,951.68 |
| 72 | 18IN endwall (cross drain) 6:1 (611-07.56) | EACH | 3 | $5,359.00 | $2,500.00 | $2,460.00 | $2,544.88 | $4,600.00 | $3,592.67 |
| 73 | 24IN endwall (cross drain) 3:1 (611-07.57) | EACH | 5 | $4,259.17 | $2,500.00 | $2,200.00 | $2,287.78 | $4,500.00 | $3,311.45 |
| 74 | 24IN endwall (cross drain) 4:1 (611-07.58) | EACH | 11 | $4,761.77 | $2,900.00 | $2,600.00 | $2,715.35 | $4,900.00 | $3,778.76 |
| 75 | 24IN endwall (cross drain) 6:1 (611-07.59) | EACH | 7 | $6,149.18 | $4,500.00 | $3,400.00 | $3,870.15 | $6,100.00 | $5,068.76 |
| 76 | 30IN endwall (cross drain) 3:1 (611-07.60) | EACH | 3 | $6,874.68 | $5,600.00 | $3,180.00 | $3,928.03 | $6,700.00 | $5,456.00 |
| 77 | 30IN endwall (cross drain) 4:1 (611-07.61) | EACH | 1 | $6,800.99 | $6,500.00 | $4,600.00 | $4,840.41 | $7,600.00 | $6,427.41 |
| 78 | 30IN endwall (cross drain) 6:1 (611-07.62) | EACH | 2 | $8,983.26 | $8,500.00 | $5,850.00 | $6,635.15 | $9,300.00 | $8,466.59 |
| 79 | 36IN endwall (cross drain) 6:1 (611-07.65) | EACH | 2 | $12,770 | $11,100 | $7,310.00 | $16,175 | $12,000 | $10,693 |
| 80 | 42IN endwall (cross drain) 3:1 (611-07.66) | EACH | 4 | $9,567.67 | $9,500.00 | $6,050.00 | $11,460 | $9,000.00 | $12,481 |
| 81 | 42IN endwall (cross drain) 6:1 (611-07.68) | EACH | 2 | $11,776 | $12,000 | $9,325.00 | $21,792 | $13,000 | $15,053 |
| 82 | 48IN endwall (cross drain) 3:1 (611-07.69) | EACH | 2 | $10,759 | $11,700 | $7,100.00 | $19,629 | $11,000 | $20,120 |
| 83 | 48IN endwall (cross drain) 4:1 (611-07.70) | EACH | 2 | $12,653 | $13,600 | $11,565 | $26,365 | $12,500 | $24,364 |
| 84 | 18" temporary drainage pipe (621-03.02) | LF | 160 | $59.14 | $48.00 | $50.00 | $85.08 | $67.00 | $72.85 |
| 85 | 24" temporary drainage pipe (621-03.03) | LF | 20 | $112.06 | $58.00 | $63.00 | $343.10 | $195.00 | $873.68 |
| 86 | 36" temporary drainage pipe (621-03.05) | LF | 146 | $103.70 | $100.00 | $91.00 | $153.84 | $112.00 | $180.38 |
| 87 | 42" temporary drainage pipe (621-03.06) | LF | 460 | $129.24 | $118.00 | $130.00 | $184.43 | $127.00 | $169.28 |
| 88 | Earth pad for type 38 GR end treatment (705-04.09) | EACH | 18 | $632.32 | $600.00 | $665.00 | $648.32 | $1,100.00 | $1,533.59 |
| 89 | Portable barrier rail delineator (705-04.50) | EACH | 1,258 | $13.13 | $12.50 | $13.30 | $13.23 | $8.00 | $15.64 |
| 90 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 3,600 | $28.45 | $27.00 | $30.00 | $29.17 | $29.00 | $34.51 |
| 91 | GR terminaltrailing end (type 13) MASH TL-3 (705-06.10) | EACH | 8 | $1,844.27 | $1,750.00 | $1,940.00 | $1,890.93 | $1,880.00 | $1,789.19 |
| 92 | GR terminal (in-inline) MASH TL-3 (705-06.11) | EACH | 8 | $1,580.80 | $1,500.00 | $1,660.00 | $1,620.80 | $1,200.00 | $1,661.39 |
| 93 | Tangent energy absorbing term MASH TL-3 (705-06.20) | EACH | 18 | $2,898.14 | $2,750.00 | $3,045.00 | $2,971.46 | $3,600.00 | $4,345.18 |
| 94 | Thrie beam bridge transition MASH TL-3 (705-06.25) | EACH | 8 | $3,161.60 | $3,000.00 | $3,320.00 | $3,241.60 | $3,700.00 | $3,578.38 |
| 95 | Radius rail (706-06.03) | LF | 225 | $34.25 | $32.50 | $36.00 | $35.12 | $32.00 | $57.51 |
| 96 | Rounded end element (706-10.26) | EACH | 8 | $210.77 | $200.00 | $222.00 | $216.11 | $110.00 | $351.45 |
| 97 | Chain link fence (6 foot) (707-01.11) | LF | 16,378 | $16.64 | $15.85 | $17.50 | $22.52 | $18.00 | $19.24 |
| 98 | End & corner post assembly(chain-link fence 6') (707-01.12) | EACH | 54 | $341.25 | $325.00 | $360.00 | $261.86 | $365.00 | $394.54 |
| 99 | Stock fence (707-03.01) | LF | 22,570 | $7.35 | $7.00 | $8.00 | $12.83 | $8.00 | $8.50 |
| 100 | End, braced line, corner post assembly(stock fence) (707-03.02) | EACH | 223 | $236.25 | $225.00 | $250.00 | $244.84 | $252.00 | $273.14 |
| 101 | Drive gate (stock fence) (description) (707-03.20) | EACH | 3 | $2,100.00 | $2,000.00 | $2,215.00 | $2,199.65 | $2,250.00 | $2,427.94 |
| 102 | Water crossing (707-04) | LF | 360 | $6.30 | $6.00 | $6.70 | $10.47 | $6.70 | $7.28 |
| 103 | Water gate (707-05) | SF | 525 | $33.60 | $32.00 | $35.50 | $31.42 | $36.00 | $38.85 |
| 104 | Removal of fence (chain link, wooden, and woven wire) (707-06.05) | LS | 1 | $13,256 | $20,000 | $32,850 | $28,805 | $35,000 | $41,174 |
| 105 | High-visibility construction fence (707-08.11) | LF | 24,110 | $1.84 | $1.75 | $2.00 | $2.54 | $3.40 | $3.75 |
| 106 | Markers (concrete R.O.W. posts) (708-02.01) | EACH | 208 | $325.50 | $340.00 | $645.00 | $643.90 | $350.00 | $307.31 |
| 107 | Rubble stone rip-rap (709-01.01) | CY | 3 | $1,376.30 | $215.00 | $72.00 | $329.04 | $337.00 | $10,924 |
| 108 | Machined rip-rap (class A-3) (709-05.05) | TON | 727 | $49.35 | $55.00 | $46.50 | $45.30 | $74.00 | $125.18 |
| 109 | Machined rip-rap (class A-1) (709-05.06) | TON | 14,469 | $50.63 | $55.00 | $46.50 | $37.38 | $54.00 | $104.04 |
| 110 | Machined rip-rap (class B) (709-05.08) | TON | 9,795 | $52.76 | $55.00 | $48.50 | $40.78 | $57.00 | $103.05 |
| 111 | Machined rip-rap (class C) (709-05.09) | TON | 7,029 | $52.76 | $55.00 | $48.50 | $41.18 | $55.00 | $97.05 |
| 112 | Gabions (ditch lining) (709-10.01) | CY | 1,939 | $257.58 | $170.00 | $164.00 | $313.98 | $335.00 | $349.59 |
| 113 | Aggregate underdrains (with pipe) (710-02) | LF | 60,782 | $13.80 | $7.68 | $14.35 | $14.16 | $14.50 | $15.97 |
| 114 | Lateral underdrain (710-05) | LF | 9,310 | $13.27 | $16.00 | $13.80 | $13.61 | $14.00 | $15.35 |
| 115 | Lateral underdrain endwall (3:1) (710-06.12) | EACH | 6 | $1,327.23 | $900.00 | $1,385.00 | $1,361.14 | $1,395.00 | $1,535.43 |
| 116 | Lateral underdrain endwall (4:1) (710-06.13) | EACH | 67 | $1,327.23 | $900.00 | $1,385.00 | $1,361.14 | $1,395.00 | $1,535.43 |
| 117 | Lateral underdrain endwall (6:1) (710-06.15) | EACH | 229 | $1,327.23 | $1,210.00 | $1,385.00 | $1,361.14 | $1,395.00 | $1,535.43 |
| 118 | Traffic control (712-01) | LS | 1 | $175,642 | $250,000 | $495,000 | $803,469 | $1,000,000 | $1,971,328 |
| 119 | Interconnected portable barrier rail (712-02.02) | LF | 9,930 | $30.07 | $42.00 | $13.90 | $41.84 | $76.00 | $85.91 |
| 120 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 14 | $7,612.50 | $13,000 | $7,630.00 | $12,098 | $16,000 | $19,518 |
| 121 | Flexible drums (channelizing) (712-04.01) | EACH | 753 | $49.35 | $47.00 | $39.00 | $49.74 | $52.00 | $58.82 |
| 122 | Barrier rail delineator (712-04.50) | EACH | 500 | $13.13 | $12.50 | $13.30 | $33.76 | $13.75 | $38.44 |
| 123 | Warning lights (type A) (712-05.01) | EACH | 124 | $21.00 | $20.00 | $44.30 | $21.17 | $22.00 | $25.03 |
| 124 | Signs (construction) (712-06) | SF | 1,385 | $7.77 | $7.40 | $8.85 | $7.83 | $8.00 | $9.26 |
| 125 | Temporary barricades (type III) (712-07.03) | LF | 660 | $17.85 | $17.00 | $20.00 | $17.99 | $18.00 | $21.28 |
| 126 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 12,875 | $3.41 | $3.25 | $3.60 | $3.37 | $6.00 | $6.37 |
| 127 | Class A concrete (foundation for sign supports) (713-01.01) | CY | 8 | $210.00 | $200.00 | $222.00 | $218.00 | $220.00 | $250.30 |
| 128 | Steel bar reinforcement(foundation for sign supports) (713-01.02) | LB | 1,569 | $1.58 | $1.50 | $1.65 | $1.64 | $1.65 | $1.88 |
| 129 | Delineator (mile marker) & steel post (713-02.04) | EACH | 6 | $131.25 | $125.00 | $138.50 | $136.25 | $137.50 | $156.44 |
| 130 | Sign post delineation enhancement (713-02.21) | LF | 561 | $3.41 | $3.25 | $3.60 | $3.54 | $4.00 | $4.07 |
| 131 | Perforated/knockout square tube post (713-11.02) | LB | 4,708 | $4.20 | $4.00 | $4.45 | $4.36 | $4.40 | $5.01 |
| 132 | P post slip base (713-11.21) | EACH | 74 | $556.50 | $530.00 | $590.00 | $577.70 | $583.00 | $663.30 |
| 133 | Flat sheet aluminum signs (0.080" thick) (713-13.02) | SF | 293 | $15.49 | $14.75 | $16.30 | $16.08 | $16.00 | $18.46 |
| 134 | Flat sheet aluminum signs (0.100" thick) (713-13.03) | SF | 518 | $16.28 | $15.50 | $17.20 | $16.90 | $17.00 | $18.77 |
| 135 | Street name sign (rigid 0.100IN thick (713-14.21) | SF | 57 | $18.90 | $18.00 | $20.00 | $19.62 | $20.00 | $22.53 |
| 136 | Removal of signs, posts and footings (713-15) | LS | 1 | $525.00 | $500.00 | $555.00 | $545.00 | $550.00 | $625.76 |
| 137 | Changeable message sign unit (713-16.01) | EACH | 8 | $12,600 | $12,000 | $13,300 | $12,699 | $13,200 | $15,018 |
| 138 | Temporary raised pavement marker,yellow (716-01.07) | EACH | 170 | $13.13 | $12.50 | $14.00 | $12.96 | $13.00 | $14.57 |
| 139 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 623 | $46.73 | $44.50 | $50.00 | $46.14 | $57.00 | $63.13 |
| 140 | Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22) | EACH | 18 | $46.73 | $44.50 | $50.00 | $46.14 | $57.00 | $63.13 |
| 141 | Plastic pavement marking(channelization striping) (716-02.04) | SY | 120 | $31.24 | $29.75 | $33.00 | $30.85 | $34.00 | $37.63 |
| 142 | Plastic pavement marking (stop line) (716-02.05) | LF | 1,295 | $12.86 | $12.25 | $13.60 | $12.70 | $21.00 | $22.76 |
| 143 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 3 | $194.25 | $185.00 | $205.00 | $191.82 | $330.00 | $364.19 |
| 144 | Plastic pavement marking (8" dotted line) (716-02.08) | LF | 720 | $3.36 | $3.20 | $3.55 | $3.32 | $3.30 | $3.64 |
| 145 | Plastic pavement marking (8IN line) (716-02.12) | LM | 1 | $10,500 | $10,000 | $11,000 | $10,369 | $14,300 | $15,782 |
| 146 | Painted pavement marking (4" line) (716-05.01) | LM | 16.03 | $918.75 | $875.00 | $970.00 | $907.26 | $1,760.00 | $1,942.35 |
| 147 | Painted pavement marking (stop line) (716-05.05) | LF | 40 | $5.51 | $5.25 | $5.85 | $5.44 | $7.70 | $8.50 |
| 148 | Removal of pavement marking (stop line) (716-08.05) | LF | 40 | $3.15 | $3.00 | $3.35 | $3.11 | $8.80 | $9.71 |
| 149 | Removal of pavement marking (line) (716-08.20) | LM | 2.03 | $2,546.25 | $2,425.00 | $2,685.00 | $2,514.42 | $3,850.00 | $4,248.89 |
| 150 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 24.50 | $6,903.75 | $6,575.00 | $7,300.00 | $6,817.45 | $9,020.00 | $9,954.55 |
| 151 | Spray thermo PVMT MRKNG (60 mil) (4IN line) (716-13.01) | LM | 5.60 | $3,018.75 | $2,875.00 | $3,200.00 | $2,981.01 | $5,225.00 | $5,766.35 |
| 152 | Mobilization (717-01) | LS | 1 | $1,748,827 | $5,000,000 | $3,000,000 | $2,275,697 | $9,500,000 | $10,962,708 |
| 153 | Field office (type 2) (722-01.02) | LS | 1 | $108,792 | $230,000 | $135,000 | $242,189 | $350,000 | $1,332,685 |
| 154 | Geogrid reinforcement type 2 (740-07.04) | SY | 6,460 | $2.92 | $5.00 | $5.70 | $3.53 | $9.35 | $6.24 |
| 155 | Geotextile (type III)(erosion control) (740-10.03) | SY | 22,298 | $2.47 | $2.00 | $2.75 | $4.35 | $2.30 | $5.00 |
| 156 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 77,656 | $3.91 | $2.75 | $3.60 | $2.73 | $3.80 | $6.15 |
| 157 | Temporary sediment tube 20IN (740-11.04) | LF | 1,748 | $3.52 | $3.35 | $3.75 | $3.91 | $4.60 | $5.10 |
| 158 | Seeding (with mulch) (801-01) | UNIT | 3,224 | $40.43 | $38.50 | $43.24 | $46.90 | $38.50 | $61.91 |
| 159 | Crown vetch mixture (with mulch) (801-01.02) | UNIT | 333 | $49.88 | $47.50 | $53.40 | $101.61 | $39.60 | $63.13 |
| 160 | Temporary seeding (with mulch) (801-01.07) | UNIT | 2,831 | $28.88 | $27.50 | $31.00 | $38.30 | $29.70 | $32.78 |
| 161 | Special wetland seed mixture (801-01.36) | UNIT | 30 | $183.75 | $175.00 | $200.00 | $78.16 | $143.00 | $382.40 |
| 162 | Natve seed MX final stablizatn of slopes (801-01.38) | UNIT | 318 | $105.00 | $100.00 | $112.50 | $53.15 | $83.60 | $168.13 |
| 163 | Seeding (without mulch) (801-02) | UNIT | 437 | $23.10 | $22.00 | $24.75 | $30.74 | $33.00 | $31.14 |
| 164 | Water (seeding & sodding) (801-03) | MG | 2,596 | $52.50 | $50.00 | $56.25 | $83.37 | $55.00 | $72.84 |
| 165 | Sodding (new sod) (803-01) | SY | 90,102 | $6.30 | $6.00 | $6.74 | $6.04 | $6.50 | $6.56 |
| 166 | Turf reinforcement mat (class I) (805-01.01) | SY | 20,222 | $3.41 | $3.25 | $3.65 | $4.17 | $4.00 | $5.23 |
| 167 | Erosion control blanket (type II) (805-12.02) | SY | 114,134 | $1.21 | $1.15 | $1.30 | $1.04 | $0.95 | $1.15 |
| 168 | Project mowing (806-02.03) | CYCL | 10 | $4,499.28 | $3,500.00 | $7,200.00 | $4,735.35 | $19,450 | $48,559 |
| 169 | Dry excavation (bridges) (204-02.01) | CY | 508 | $50.00 | $38.00 | $55.40 | $51.33 | $17.00 | $57.02 |
| 170 | Wet excavation (bridges) (204-03.01) | CY | 100 | $100.00 | $80.00 | $110.80 | $102.65 | $17.00 | $57.02 |
| 171 | Rock excavation (bridges) (204-04.01) | CY | 33 | $550.00 | $110.00 | $610.00 | $564.58 | $283.00 | $114.04 |
| 172 | Rock drilling (bridges) (204-05) | LF | 24 | $110.00 | $75.00 | $120.00 | $112.92 | $98.00 | $505.82 |
| 173 | Core drilling and sampling (204-05.01) | LF | 201 | $130.00 | $115.00 | $105.00 | $97.52 | $135.00 | $182.10 |
| 174 | Foundation preparation(pier no. 1, sta 1339+01.10) (204-10.01) | LS | 1 | $40,000 | $25,000 | $44,300 | $41,060 | $12,620 | $23,361 |
| 175 | Core drilling for piles(rock) (204-14) | LF | 433 | $294.00 | $625.00 | $325.00 | $301.79 | $575.00 | $943.60 |
| 176 | Core drilling for piles(soil) (204-15) | LF | 34 | $63.00 | $625.00 | $70.00 | $64.67 | $589.00 | $314.53 |
| 177 | Granular backfill (bridges) (303-01.02) | TON | 119 | $60.00 | $65.00 | $66.50 | $61.59 | $108.00 | $174.77 |
| 178 | Epoxy coated reinforcing steel (604-02.03) | LB | 269,789 | $1.85 | $1.50 | $2.05 | $1.90 | $1.50 | $2.21 |
| 179 | Class A concrete (bridges) (604-03.01) | CY | 728 | $2,000.00 | $1,200.00 | $2,215.00 | $2,053.01 | $1,500.00 | $3,081.11 |
| 180 | Steel bar reinforcement (bridges) (604-03.02) | LB | 122,071 | $1.70 | $1.50 | $1.90 | $1.75 | $1.45 | $2.33 |
| 181 | Pavement @ bridge ends (604-03.04) | SY | 504 | $380.00 | $450.00 | $420.00 | $390.07 | $400.00 | $717.79 |
| 182 | Class DS concrete (604-03.32) | CY | 857 | $1,295.00 | $1,250.00 | $1,435.00 | $1,329.32 | $1,556.00 | $2,252.33 |
| 183 | Applied texture finish (new structures) (604-04.01) | SY | 3,413 | $18.00 | $15.00 | $20.00 | $18.48 | $23.00 | $44.43 |
| 184 | Three star state emblem (604-04.41) | EACH | 8 | $850.00 | $2,000.00 | $940.00 | $872.53 | $1,158.00 | $1,998.50 |
| 185 | Bridge deck grooving (mechanical) (604-05.31) | SY | 3,288 | $4.20 | $5.00 | $4.65 | $4.31 | $9.00 | $9.71 |
| 186 | Steel piles (12 inch) (606-03.03) | LF | 519 | $115.00 | $130.00 | $127.50 | $118.05 | $121.00 | $420.39 |
| 187 | Prestressed concrete bulb tee beam (6" web)(BT-54) (615-01.10) | LF | 795 | $540.00 | $600.00 | $600.00 | $554.31 | $561.00 | $822.08 |
| 188 | Prestressed concrete bulb tee beam (6" web)(BT-72) (615-01.12) | LF | 2,354 | $560.00 | $600.00 | $620.00 | $574.84 | $631.00 | $701.97 |
| 189 | Conc parapet single slope (STD-1-1SS) (620-05.01) | LF | 1,265 | $120.00 | $115.00 | $133.00 | $123.22 | $161.00 | $132.37 |
| 190 | Camera inspection - drilled shaft (dry) (625-01.10) | EACH | 3 | $2,150.00 | $1,500.00 | $2,380.00 | $2,207.73 | $2,750.00 | $2,185.14 |
| 191 | Camera inspection - drilled shaft (underwater) (625-01.11) | EACH | 3 | $2,150.00 | $2,000.00 | $2,380.00 | $2,207.73 | $2,750.00 | $2,185.14 |
| 192 | Drilled shaft-soil (6'- 0" dia.) (625-02.01) | VF | 20 | $550.00 | $1,600.00 | $610.00 | $564.77 | $1,735.00 | $1,965.84 |
| 193 | Drilled shaft-rock (5'- 6" dia.) (625-02.13) | VF | 60 | $1,400.00 | $2,200.00 | $1,550.00 | $1,437.59 | $2,192.00 | $5,827.89 |
| 194 | Drilled shaft-rock (6'- 0" dia.) (625-02.14) | VF | 75 | $2,000.00 | $2,200.00 | $2,215.00 | $2,053.70 | $2,182.00 | $6,221.06 |
| 195 | Drilled shaft casing-permanent (6'- 0" inside dia.) (625-02.25) | VF | 105 | $930.00 | $781.00 | $1,030.00 | $954.97 | $925.00 | $1,449.61 |
| 196 | Drilled shaft (SH-SCC) concrete (625-02.40) | CY | 162 | $700.00 | $700.00 | $775.00 | $718.80 | $855.00 | $1,179.50 |
| 197 | Drilled shaft reinforcing steel (625-02.44) | LB | 42,355 | $1.75 | $1.50 | $2.00 | $1.80 | $1.50 | $2.38 |
| 198 | 6" perforated pipe with vertical drain system (710-09.01) | LF | 314 | $45.00 | $70.00 | $50.00 | $46.21 | $15.00 | $72.84 |
| 199 | 6" pipe underdrain (710-09.02) | LF | 130 | $30.00 | $20.00 | $33.00 | $30.81 | $14.00 | $25.93 |
| 200 | Pole 30FT class 6 wood (790-01.05) | EACH | 3 | $578.48 | $546.25 | $605.00 | $565.73 | $607.00 | $1,994.92 |
| 201 | Pole 35FT class 5 wood (790-02.04) | EACH | 3 | $750.57 | $708.75 | $785.00 | $734.02 | $787.00 | $2,234.07 |
| 202 | Pole 40FT class 4 wood (790-03.03) | EACH | 7 | $1,086.80 | $1,026.25 | $1,135.00 | $1,062.84 | $1,140.00 | $2,478.34 |
| 203 | Pole 45FT class 3 wood (790-04.03) | EACH | 34 | $1,368.76 | $1,292.50 | $1,430.00 | $1,338.58 | $1,450.00 | $2,830.22 |
| 204 | Pole 45FT class 4 wood (790-04.04) | EACH | 2 | $1,266.83 | $1,196.25 | $1,325.00 | $1,238.90 | $1,330.00 | $2,648.31 |
| 205 | Pole 50FT class 2 wood (790-05.02) | EACH | 6 | $1,711.61 | $1,616.25 | $1,800.00 | $1,673.88 | $1,800.00 | $3,596.82 |
| 206 | Pole 55FT class 2 wood (790-06.02) | EACH | 1 | $1,817.51 | $1,716.25 | $1,900.00 | $1,777.43 | $1,907.00 | $4,067.88 |
| 207 | Pole 60FT class H2 metal (790-07.08) | EACH | 97 | $8,089.96 | $8,941.25 | $8,450.00 | $7,911.60 | $9,950.00 | $10,714 |
| 208 | Pole 65FT class H2 metal (790-08.04) | EACH | 32 | $8,909.58 | $9,818.75 | $9,300.00 | $8,713.15 | $10,100 | $11,848 |
| 209 | Pole 70FT class H2 metal (790-09.05) | EACH | 3 | $10,055 | $10,498 | $10,500 | $9,833.08 | $11,650 | $13,197 |
| 210 | Pole 75FT class H2 metal (790-10.05) | EACH | 2 | $11,874 | $11,213 | $12,400 | $11,612 | $12,500 | $14,396 |
| 211 | 1PH SGL primary support 25KV (790-22.01) | EACH | 7 | $534.58 | $504.80 | $560.00 | $522.80 | $560.00 | $378.60 |
| 212 | 1PH DBL primary support 25KV (790-22.02) | EACH | 4 | $598.80 | $565.44 | $625.00 | $585.60 | $630.00 | $489.87 |
| 213 | 1PH DBL PTS angle 25KV (790-22.07) | EACH | 7 | $635.39 | $599.99 | $665.00 | $621.38 | $667.00 | $706.36 |
| 214 | 1PH dde angle 25KV (790-22.11) | EACH | 10 | $702.39 | $663.26 | $735.00 | $686.91 | $740.00 | $670.86 |
| 215 | 1PH dead end 25KV (790-22.13) | EACH | 19 | $538.61 | $508.60 | $560.00 | $526.73 | $565.00 | $436.74 |
| 216 | 1PH dead end tap W/ extension 25KV (790-22.15) | EACH | 52 | $531.02 | $501.43 | $555.00 | $519.31 | $560.00 | $475.51 |
| 217 | 1PH dde tangent 25KV (790-22.16) | EACH | 14 | $751.40 | $709.54 | $785.00 | $734.84 | $790.00 | $1,103.09 |
| 218 | 2PH crossarm SGL 25KV (790-24.01) | EACH | 1 | $897.17 | $847.19 | $935.00 | $877.39 | $945.00 | $1,297.13 |
| 219 | 2PH dead end crossarm 25KV (790-24.08) | EACH | 1 | $1,273.81 | $1,202.84 | $1,330.00 | $1,245.73 | $1,350.00 | $2,199.77 |
| 220 | 3PH crossarm 25KV (790-26.01) | EACH | 1 | $948.44 | $895.60 | $990.00 | $927.54 | $995.00 | $1,191.30 |
| 221 | 3PH crossarm SGL LRG cond 25KV (790-26.03) | EACH | 75 | $1,071.38 | $1,011.69 | $1,120.00 | $1,047.76 | $1,120.00 | $1,371.75 |
| 222 | 3PH crossarm SGL FBRGLS DBL prim sup 25KV (790-26.06) | EACH | 42 | $1,909.02 | $1,802.66 | $1,995.00 | $1,866.93 | $2,000.00 | $2,503.42 |
| 223 | 3PH xarm DBL 10FT LRG cond SM angle 25KV (790-26.15) | EACH | 7 | $2,281.63 | $2,154.51 | $2,385.00 | $2,231.33 | $2,390.00 | $3,443.32 |
| 224 | 3PH crossarm dead end 25KV (790-26.26) | EACH | 16 | $1,687.74 | $1,593.71 | $1,750.00 | $1,650.53 | $1,770.00 | $2,528.63 |
| 225 | 3PH DBL 10FT xarm dde 25KV (790-26.28) | EACH | 7 | $2,592.71 | $2,448.26 | $2,700.00 | $2,535.55 | $2,720.00 | $4,807.03 |
| 226 | Secondary conductor 6 AL duplex (790-30.06) | LF | 30 | $2.82 | $2.66 | $3.00 | $2.75 | $2.95 | $3.53 |
| 227 | Secondary conductor 2 AL triplex (790-30.13) | LF | 1,205 | $4.49 | $4.24 | $4.70 | $4.39 | $4.70 | $6.54 |
| 228 | Service assembly-house type (790-31.01) | EACH | 1 | $121.36 | $114.60 | $127.00 | $118.69 | $127.00 | $138.82 |
| 229 | Service assembly-pole type (790-31.02) | EACH | 65 | $158.90 | $150.05 | $165.00 | $155.40 | $166.00 | $149.53 |
| 230 | Down guy - through bolt type (790-32.01) | EACH | 5 | $406.61 | $383.96 | $425.00 | $397.65 | $426.00 | $437.11 |
| 231 | Down guy - insulated (790-32.06) | EACH | 176 | $438.14 | $413.73 | $460.00 | $428.48 | $460.00 | $463.52 |
| 232 | OH guy - through bolt type (790-32.07) | EACH | 10 | $544.47 | $514.13 | $570.00 | $532.46 | $571.00 | $685.85 |
| 233 | OH guy - through bolt type heavy duty (790-32.08) | EACH | 8 | $520.38 | $491.39 | $545.00 | $508.91 | $545.00 | $631.80 |
| 234 | Guy guard (790-32.23) | EACH | 184 | $26.21 | $24.75 | $27.00 | $25.63 | $27.50 | $34.33 |
| 235 | Rock anchor guy bolt type (790-33.18) | EACH | 180 | $671.12 | $633.73 | $700.00 | $656.32 | $704.00 | $1,392.70 |
| 236 | OH cond 2 7/1 acsr sparate (790-40.02) | LF | 40 | $3.08 | $2.91 | $3.25 | $3.01 | $3.50 | $2.99 |
| 237 | OH cond 1/0 6/1 acsr raven (790-40.03) | LF | 30,606 | $3.43 | $3.24 | $3.60 | $3.36 | $3.60 | $3.72 |
| 238 | OH cond 336.4 19 aac tulip (790-40.42) | LF | 27,505 | $5.30 | $5.00 | $5.55 | $5.18 | $5.50 | $6.95 |
| 239 | OH cond 795 37 aac arbutus (790-40.49) | LF | 82,516 | $7.82 | $8.44 | $8.15 | $7.64 | $9.35 | $10.36 |
| 240 | UG pri cond 1/0 AL 25KV (790-41.13) | LF | 360 | $16.34 | $15.43 | $17.00 | $15.98 | $17.15 | $21.02 |
| 241 | UG sec cond 2/0 AL TPLX (790-41.47) | LF | 320 | $6.97 | $6.58 | $7.30 | $6.81 | $7.30 | $12.58 |
| 242 | 3IN dia PVC pipe (790-42.09) | LF | 160 | $194.15 | $183.33 | $202.00 | $189.87 | $204.00 | $17.15 |
| 243 | Loadbreak junction 3 PT 200A 25KV (790-43.21) | EACH | 4 | $5,763.89 | $5,442.76 | $6,000.00 | $5,636.81 | $6,050.00 | $3,784.75 |
| 244 | Loadbreak junction 4 PT 200A 25KV (790-43.22) | EACH | 1 | $8,020.77 | $7,573.90 | $8,400.00 | $7,843.94 | $8,415.00 | $5,234.44 |
| 245 | Secondary riser W/ 3IN conduit (790-43.51) | EACH | 9 | $935.41 | $883.26 | $980.00 | $914.78 | $980.00 | $1,717.69 |
| 246 | 1PH primary riser W/ 3IN conduit (790-43.53) | EACH | 4 | $2,658.51 | $2,510.39 | $2,775.00 | $2,599.89 | $2,790.00 | $2,765.19 |
| 247 | 3PH primary riser W/ 6IN conduit (790-43.58) | EACH | 1 | $6,208.76 | $5,862.84 | $6,485.00 | $6,071.87 | $6,515.00 | $8,050.56 |
| 248 | 1PH transformer conv W/pole MTD fuse & LA (790-46.02) | EACH | 19 | $546.51 | $516.06 | $570.00 | $534.46 | $574.00 | $1,553.94 |
| 249 | 1PH transformer conv W/xarm MTD fuse & LA (790-46.03) | EACH | 38 | $475.08 | $448.61 | $495.00 | $464.60 | $500.00 | $1,484.81 |
| 250 | 1PH transformer pad (790-50.03) | EACH | 1 | $14,187 | $13,397 | $14,800 | $13,874 | $14,885 | $11,616 |
| 251 | 10KVA 1PH OH xformer 7.2KV 120/240 (790-52.03) | EACH | 15 | $436.84 | $412.50 | $455.00 | $427.21 | $460.00 | $785.85 |
| 252 | 15KVA 1PH OH xformer 7.2KV 120/240 (790-52.04) | EACH | 3 | $463.31 | $437.50 | $485.00 | $453.10 | $487.00 | $785.84 |
| 253 | 15KVA 1PH OH xformer 7.2KV dual voltage (790-52.05) | EACH | 28 | $463.31 | $437.50 | $485.00 | $453.10 | $487.00 | $785.85 |
| 254 | 25KVA 1PH OH xformer 7.2KV dual voltage (790-52.08) | EACH | 11 | $473.90 | $447.50 | $495.00 | $463.45 | $500.00 | $982.31 |
| 255 | Goab switch 25KV (790-59.06) | EACH | 1 | $11,468 | $10,829 | $12,000 | $11,215 | $12,000 | $15,002 |
| 256 | 1PH fuse cutout BRKT mount 15KV (790-60.02) | EACH | 19 | $545.87 | $515.46 | $570.00 | $533.84 | $572.00 | $845.20 |
| 257 | 1PH fuse cutout xarm mount 25KV (790-61.01) | EACH | 13 | $368.73 | $348.19 | $385.00 | $360.60 | $385.00 | $570.42 |
| 258 | 1PH sectionalizers or recloser 25KV (790-61.03) | EACH | 1 | $1,382.72 | $1,305.69 | $1,450.00 | $1,352.24 | $1,450.00 | $2,089.97 |
| 259 | 3PH sectlr or recl W/ bypass SW 25KV (790-61.10) | EACH | 4 | $6,519.93 | $6,156.68 | $6,810.00 | $6,376.19 | $6,850.00 | $8,351.69 |
| 260 | 1PH hydr recl 280A cont 5000A int 15KV (790-62.06) | EACH | 1 | $913.38 | $862.50 | $950.00 | $893.24 | $960.00 | $1,571.70 |
| 261 | Sec MTG 1PH 120/240 volts residential (790-64.02) | EACH | 4 | $926.63 | $875.00 | $970.00 | $906.20 | $972.00 | $1,622.85 |
| 262 | Lightning arrester arm MTD 18 KV (790-65.05) | EACH | 13 | $356.25 | $336.40 | $375.00 | $348.39 | $375.00 | $403.82 |
| 263 | 3PH regulator platform mount (790-65.11) | EACH | 1 | $28,353 | $26,773 | $30,000 | $27,728 | $29,800 | $25,837 |
| 264 | 1PH 500A regulator 25KV (790-67.07) | EACH | 3 | $1,125.19 | $1,062.50 | $1,175.00 | $1,100.38 | $1,200.00 | $4,911.57 |
| 265 | Pole ground rod type (790-68.01) | EACH | 137 | $177.17 | $167.30 | $185.00 | $173.26 | $186.00 | $423.46 |
| 266 | Pole ground wrap type (790-68.03) | EACH | 5 | $248.17 | $234.34 | $260.00 | $242.70 | $260.00 | $499.09 |
| 267 | Pole ground W/ PLTFM for air break SWCH (790-68.08) | EACH | 1 | $957.55 | $904.20 | $1,000.00 | $936.43 | $1,005.00 | $1,785.23 |
| 268 | GND-assy GND rod with aluminum (790-69.09) | EACH | 44 | $263.69 | $249.00 | $275.00 | $257.88 | $275.00 | $499.30 |
| 269 | Stick pin (790-69.31) | EACH | 7 | $126.48 | $119.43 | $132.00 | $123.69 | $133.00 | $181.01 |
| 270 | Flood light (790-70.10) | EACH | 1 | $1,252.41 | $1,182.63 | $1,300.00 | $1,224.80 | $1,315.00 | $1,297.50 |
| 271 | Street light (400W MV) (790-70.20) | EACH | 1 | $1,198.63 | $1,131.85 | $1,250.00 | $1,172.20 | $1,260.00 | $1,245.46 |
| 272 | Street light (70W LED) (790-70.21) | EACH | 3 | $662.39 | $625.48 | $690.00 | $647.78 | $695.00 | $726.49 |
| 273 | Guy factory formed with thimble clevis (790-72.07) | EACH | 3 | $363.66 | $343.40 | $380.00 | $355.64 | $382.00 | $315.68 |
| 274 | Remove wire (790-98.01) | LF | 156,911 | $2.38 | $2.25 | $2.50 | $2.33 | $2.50 | $2.75 |
| 275 | Remove poles (790-98.02) | EACH | 249 | $688.35 | $650.00 | $720.00 | $673.17 | $722.00 | $982.31 |
| 276 | Remove framing/associated apparatus (790-98.03) | EACH | 1,345 | $423.60 | $400.00 | $442.00 | $414.26 | $445.00 | $392.92 |
| 277 | <2IN HDPE gas main (791-03.01) | LF | 1,818 | $40.30 | $38.00 | $72.00 | $66.73 | $94.00 | $78.91 |
| 278 | 2IN HDPE gas main (791-03.02) | LF | 9,400 | $49.85 | $47.00 | $72.00 | $66.73 | $94.00 | $78.91 |
| 279 | 4IN HDPE gas main (791-03.04) | LF | 522 | $76.36 | $72.00 | $88.50 | $82.13 | $108.00 | $97.12 |
| 280 | 8IN HDPE gas main (791-03.06) | LF | 22,083 | $117.73 | $111.00 | $134.00 | $124.22 | $81.00 | $146.89 |
| 281 | HDD <2IN PE pipe - unconsolidated (791-04.01) | LF | 178 | $97.58 | $92.00 | $166.00 | $153.99 | $132.00 | $182.10 |
| 282 | HDD 2IN PE pipe - unconsolidated (791-04.02) | LF | 1,106 | $97.58 | $92.00 | $182.50 | $169.39 | $132.00 | $200.30 |
| 283 | HDD 4IN PE pipe - unconsolidated (791-04.04) | LF | 105 | $222.73 | $210.00 | $194.00 | $179.66 | $308.00 | $212.44 |
| 284 | HDD 8IN PE pipe - unconsolidated (791-04.06) | LF | 770 | $275.76 | $260.00 | $332.00 | $307.99 | $462.00 | $364.19 |
| 285 | Connect to 8IN EX. PE main (791-06.05) | EACH | 12 | $4,772.73 | $4,500.00 | $6,635.00 | $6,159.72 | $13,750 | $7,283.82 |
| 286 | 2IN PE hot tap connection (791-06.51) | EACH | 18 | $3,818.18 | $3,600.00 | $2,210.00 | $2,053.24 | $7,480.00 | $2,427.94 |
| 287 | 4IN PE hot tap connection (791-06.52) | EACH | 1 | $6,575.76 | $6,200.00 | $3,870.00 | $3,593.17 | $15,950 | $4,248.89 |
| 288 | 8IN PE gas valve assembly (791-07.04) | EACH | 1 | $4,454.54 | $4,200.00 | $4,420.00 | $4,106.48 | $7,480.00 | $4,855.87 |
| 289 | Reconnect service assembly (791-08.40) | EACH | 47 | $2,333.33 | $2,200.00 | $1,770.00 | $1,642.59 | $1,320.00 | $1,942.35 |
| 290 | Gas main removal (791-08.41) | LF | 4,228 | $29.70 | $28.00 | $11.00 | $10.27 | $33.00 | $12.14 |
| 291 | Pole 30FT class 4 wood (793-01.01) | EACH | 1 | $874.13 | $2,544.68 | $3,320.00 | $862.62 | $3,900.00 | $5,945.98 |
| 292 | Pole 40FT class 4 wood (793-01.12) | EACH | 1 | $1,173.38 | $2,745.48 | $3,600.00 | $1,157.93 | $4,185.00 | $6,193.73 |
| 293 | Anchor 3/4IN (793-01.40) | EACH | 63 | $531.56 | $586.48 | $775.00 | $524.56 | $1,085.00 | $1,362.62 |
| 294 | Anchor 1IN (793-01.41) | EACH | 39 | $511.88 | $686.54 | $885.00 | $505.14 | $1,239.00 | $1,486.49 |
| 295 | Guy wire 10M or 3/8IN (793-02.08) | EACH | 129 | $149.63 | $239.99 | $310.00 | $147.66 | $365.00 | $569.82 |
| 296 | Overhead guy wire (10M or 3/8IN) (793-02.92) | EACH | 5 | $267.75 | $576.49 | $725.00 | $264.22 | $878.00 | $569.82 |
| 297 | Install guy guard (793-02.99) | EACH | 124 | $29.61 | $59.44 | $89.00 | $29.22 | $138.00 | $247.75 |
| 298 | 10M strand (793-03.03) | LF | 67,314 | $3.62 | $3.05 | $3.75 | $3.57 | $4.80 | $5.95 |
| 299 | Install strand bond (793-03.40) | EACH | 101 | $36.54 | $39.82 | $61.00 | $36.06 | $143.00 | $154.84 |
| 300 | Relash/delash cable (793-04.01) | LF | 13,396 | $2.13 | $2.50 | $3.10 | $2.10 | $3.60 | $4.95 |
| 301 | 2 pair aerial drop (793-04.02) | LF | 1,210 | $4.10 | $2.67 | $3.35 | $4.04 | $4.10 | $7.43 |
| 302 | Aerial splice closure (793-04.07) | EACH | 74 | $945.00 | $665.57 | $860.00 | $932.56 | $1,010.00 | $8,448.24 |
| 303 | Aerial splice closure (3M) (793-04.13) | EACH | 11 | $1,787.63 | $806.18 | $860.00 | $1,764.09 | $1,228.00 | $9,686.98 |
| 304 | 12 fiber (material only) (793-07.01) | LF | 8,228 | $1.01 | $0.61 | $0.75 | $0.99 | $1.00 | $3.72 |
| 305 | 24 fiber(material only) (793-07.02) | LF | 8,846 | $1.35 | $0.69 | $0.85 | $1.34 | $1.10 | $3.96 |
| 306 | 48 fiber(material only) (793-07.04) | LF | 7,210 | $1.88 | $0.82 | $1.00 | $1.85 | $1.30 | $4.21 |
| 307 | 96 fiber(material only) (793-07.05) | LF | 42,064 | $2.74 | $1.54 | $1.85 | $2.70 | $2.40 | $4.46 |
| 308 | 144 fiber(material only) (793-07.07) | LF | 39,480 | $3.35 | $2.27 | $2.70 | $3.31 | $3.70 | $5.33 |
| 309 | 216 fiber(material only) (793-07.09) | LF | 2,500 | $4.65 | $2.15 | $2.60 | $4.59 | $3.50 | $5.57 |
| 310 | 288 fiber(material only) (793-07.10) | LF | 31,290 | $5.51 | $2.62 | $3.15 | $5.44 | $4.20 | $5.70 |
| 311 | 12-96 fiber(installation only) (793-07.16) | LF | 66,348 | $1.69 | $2.35 | $2.90 | $1.67 | $3.55 | $3.96 |
| 312 | 108-144 fiber(installation only) (793-07.17) | LF | 39,480 | $2.01 | $2.35 | $2.90 | $1.98 | $3.55 | $3.96 |
| 313 | 192-216 fiber(installation only) (793-07.18) | LF | 2,500 | $2.32 | $2.78 | $3.40 | $2.29 | $4.20 | $3.96 |
| 314 | 288-432 fiber(installation only) (793-07.19) | LF | 31,290 | $2.64 | $2.78 | $3.40 | $2.60 | $4.20 | $3.96 |
| 315 | Single fiber optic cable splice (793-07.25) | EACH | 1,818 | $33.23 | $30.40 | $44.00 | $32.79 | $47.00 | $99.10 |
| 316 | Hot splice existing fiber cables (793-07.41) | EACH | 6,603 | $39.53 | $30.40 | $39.00 | $39.01 | $47.00 | $148.65 |
| 317 | Rearrange fiber drop (793-07.83) | LF | 14 | $48.83 | $185.04 | $228.00 | $48.18 | $286.00 | $74.32 |
| 318 | Install fiber storage bracket (793-07.90) | EACH | 153 | $149.63 | $199.90 | $255.00 | $147.66 | $306.00 | $792.80 |
| 319 | Rearrange existing fiber storage bracket (793-07.91) | EACH | 11 | $101.59 | $79.65 | $105.00 | $100.25 | $306.00 | $768.02 |
| 320 | Buried riser guard (793-11.13) | EACH | 16 | $248.06 | $339.55 | $395.00 | $244.80 | $467.00 | $768.02 |
| 321 | 2 pair buried drop (793-11.14) | LF | 1,500 | $8.51 | $4.60 | $5.60 | $8.39 | $7.00 | $37.16 |
| 322 | Enter existing handhole (793-11.32) | EACH | 3 | $889.88 | $318.63 | $400.00 | $878.16 | $1,222.00 | $1,015.77 |
| 323 | Rearrange existing splice case (793-11.50) | EACH | 23 | $551.25 | $216.72 | $275.00 | $543.99 | $332.00 | $1,560.82 |
| 324 | Rearrangement existing cable (793-12.02) | EACH | 5 | $425.25 | $1,274.52 | $1,660.00 | $419.65 | $1,950.00 | $1,981.99 |
| 325 | 2 duct formation @ 36IN depth (793-13.17) | LF | 600 | $61.74 | $48.79 | $72.00 | $60.93 | $89.00 | $198.20 |
| 326 | 4 duct formation @ 36IN depth (793-13.27) | LF | 120 | $86.47 | $72.12 | $122.00 | $85.33 | $107.00 | $247.75 |
| 327 | Transfer cable attachment (793-15.01) | EACH | 88 | $146.79 | $283.81 | $385.00 | $144.86 | $247.00 | $991.00 |
| 328 | Directional bore 3IN/flex sleeve (793-16.03) | LF | 300 | $49.30 | $90.00 | $73.00 | $48.65 | $82.00 | $322.07 |
| 329 | Directional bore 1.25IN/flex sleeve (793-16.45) | LF | 60 | $34.10 | $70.00 | $71.00 | $33.66 | $73.00 | $260.14 |
| 330 | Remove aerial cable and wire (793-98.01) | LF | 51,510 | $1.26 | $1.27 | $1.60 | $1.24 | $2.00 | $3.72 |
| 331 | Remove poles all sizes (793-98.04) | EACH | 111 | $126.00 | $318.63 | $415.00 | $124.34 | $488.00 | $743.25 |
| 332 | Remove pedestals (793-98.06) | EACH | 1 | $189.00 | $79.65 | $110.00 | $186.51 | $130.00 | $743.24 |
| 333 | Remove underground to overhead riser (793-98.07) | EACH | 12 | $94.50 | $79.65 | $110.00 | $93.26 | $123.00 | $371.62 |
| 334 | Remove anchor (any size) (793-98.08) | EACH | 64 | $50.40 | $79.65 | $110.00 | $49.74 | $123.00 | $371.62 |
| 335 | Remove down guy (793-98.09) | EACH | 87 | $37.80 | $79.65 | $110.00 | $37.30 | $120.00 | $371.62 |
| 336 | Remove fiber storage bracket (793-98.10) | EACH | 34 | $50.40 | $79.65 | $110.00 | $49.74 | $120.00 | $371.62 |
| 337 | Trim utility right-of-way (793-98.21) | LF | 356 | $6.30 | $8.95 | $11.00 | $6.22 | $14.00 | $148.65 |
| 338 | 6IN HDPE water line (795-02.04) | LF | 3,400 | $84.00 | $80.00 | $50.00 | $82.15 | $59.00 | $84.29 |
| 339 | 6IN HDPE water line (HDD) (795-02.32) | LF | 620 | $278.25 | $265.00 | $288.00 | $272.12 | $207.00 | $315.63 |
| 340 | 4IN PVC water line (795-03.04) | LF | 3,140 | $52.50 | $50.00 | $77.00 | $51.34 | $57.00 | $84.98 |
| 341 | 6IN PVC water line (795-03.05) | LF | 56,122 | $80.85 | $65.00 | $102.00 | $73.93 | $56.70 | $111.69 |
| 342 | 10IN PVC water line (795-03.07) | LF | 475 | $94.50 | $90.00 | $72.00 | $92.42 | $74.00 | $78.91 |
| 343 | HDD 2IN HDPE carrier pipe-uncon (795-05.01) | LF | 450 | $157.50 | $150.00 | $163.00 | $154.03 | $95.00 | $178.45 |
| 344 | Bore/jack 10IN steel casing pipe-uncon. (795-05.62) | LF | 403 | $808.50 | $750.00 | $500.00 | $770.14 | $715.00 | $1,108.37 |
| 345 | Connect to 2IN water line (795-06.01) | EACH | 6 | $1,575.00 | $1,500.00 | $2,500.00 | $1,540.28 | $4,150.00 | $2,792.13 |
| 346 | Connect to 4IN water line (795-06.03) | EACH | 6 | $2,625.00 | $2,500.00 | $3,000.00 | $2,567.13 | $3,520.00 | $3,277.72 |
| 347 | Connect to 6IN water line (795-06.04) | EACH | 29 | $3,150.00 | $3,000.00 | $3,430.00 | $3,080.55 | $3,100.00 | $3,763.30 |
| 348 | Temporary tie-in (795-06.28) | EACH | 8 | $2,625.00 | $2,500.00 | $1,660.00 | $2,567.13 | $3,850.00 | $1,820.95 |
| 349 | Cut/cap existing lines (all sizes) (795-06.30) | EACH | 35 | $2,100.00 | $2,000.00 | $1,660.00 | $2,053.70 | $1,250.00 | $1,820.95 |
| 350 | Cut and cap service line (795-06.35) | EACH | 24 | $525.00 | $500.00 | $610.00 | $513.43 | $1,100.00 | $667.68 |
| 351 | 4IN X 4IN tapping sleeve and valve (795-07.01) | EACH | 9 | $4,200.00 | $4,000.00 | $7,630.00 | $4,107.40 | $5,000.00 | $8,376.39 |
| 352 | 6IN X 6IN tapping sleeve and valve (795-07.03) | EACH | 25 | $5,775.00 | $5,500.00 | $8,850.00 | $5,647.68 | $5,300.00 | $9,711.75 |
| 353 | 4IN gate valve assembly (795-08.03) | EACH | 8 | $2,100.00 | $2,000.00 | $3,150.00 | $2,053.70 | $2,250.00 | $3,459.81 |
| 354 | 6IN gate valve assembly (795-08.04) | EACH | 148 | $2,362.50 | $2,250.00 | $3,320.00 | $2,310.41 | $2,780.00 | $3,641.91 |
| 355 | 3/4IN water service meter assembly (795-09.01) | EACH | 103 | $1,575.00 | $1,500.00 | $1,770.00 | $1,540.28 | $1,435.00 | $1,942.35 |
| 356 | 1-1/2IN water service meter assembly (795-09.03) | EACH | 8 | $5,250.00 | $5,000.00 | $6,100.00 | $5,134.25 | $3,555.00 | $6,676.83 |
| 357 | Relocate/reconnect service assembly (795-09.09) | EACH | 13 | $1,050.00 | $1,000.00 | $1,000.00 | $1,026.85 | $1,690.00 | $1,092.57 |
| 358 | 3/4IN pexa service pipe (795-09.60) | LF | 1,400 | $26.25 | $25.00 | $27.50 | $25.67 | $29.00 | $30.35 |
| 359 | 1IN auto air release valve assembly (795-10.03) | EACH | 1 | $1,575.00 | $1,500.00 | $13,275 | $1,540.27 | $5,400.00 | $14,568 |
| 360 | 3/4IN PRV assembly (795-10.25) | EACH | 40 | $315.00 | $300.00 | $690.00 | $308.06 | $1,600.00 | $758.73 |
| 361 | Blow-off assembly (795-11.01) | EACH | 16 | $3,675.00 | $3,500.00 | $6,850.00 | $3,593.98 | $3,750.00 | $7,405.21 |
| 362 | Fire hydrant assembly (795-11.02) | EACH | 35 | $7,875.00 | $7,500.00 | $8,460.00 | $7,701.38 | $10,100 | $9,286.86 |
| 363 | Removal of existing line 4" OD or greater (795-12.35) | LF | 10,000 | $21.00 | $20.00 | $5.55 | $20.54 | $4.40 | $6.07 |
| 364 | Bridge hanger system (795-13.04) | LS | 1 | $315,000 | $300,000 | $570,000 | $308,055 | $191,000 | $642,392 |
| 365 | Creek crossing (#1) (795-13.05) | LS | 1 | $31,500 | $60,000 | $24,300 | $61,611 | $34,400 | $26,707 |
| 366 | Creek crossing (#2) (795-13.06) | LS | 1 | $26,250 | $50,000 | $16,600 | $51,343 | $22,900 | $18,210 |
| 367 | Creek crossing (#3) (795-13.07) | LS | 1 | $21,000 | $40,000 | $16,600 | $41,074 | $22,300 | $18,210 |
| 368 | Creek crossing (#4) (795-13.08) | LS | 1 | $29,400 | $28,000 | $22,100 | $28,752 | $15,400 | $24,279 |
| 369 | Creek crossing (#5) (795-13.09) | LS | 1 | $29,400 | $28,000 | $24,300 | $28,752 | $18,300 | $26,707 |
| 370 | Creek crossing (#6) (795-13.10) | LS | 1 | $29,400 | $28,000 | $16,600 | $28,752 | $14,400 | $18,210 |
| 371 | Restore asphalt (795-14.08) | SY | 350 | $210.00 | $200.00 | $83.00 | $205.37 | $59.00 | $91.05 |
| 372 | Restore concrete (795-14.09) | SY | 435 | $262.50 | $250.00 | $166.00 | $256.71 | $156.00 | $182.10 |
| 373 | 10IN steel casing pipe open cut method (795-15.24) | LF | 3,325 | $210.00 | $200.00 | $133.00 | $205.37 | $140.00 | $145.68 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of August 14, 2026. Compiled by Mirage Metrics.